RESUME HARI KE-6
MANAJEMEN PEMELIHARAAN DAN PENGOPERASIAN PEMBANGKIT
Outline Materi
- Asset Management
- WPC
- Outage Management
- Operation Management (production Mgmt & Operation Mgmt)
Asset Management Journey
- 2009 : Implementasi Asset Management
- 2013: PAS 55 Certified
- 2017: ISO 55001 Certified
- 2019: Excellent at the Basic
- 2021: Implementasi Integrated Strategic Asset Management (ISAM)
- 2025: Advance ISAM
Challenges
- Peningkatan Kinerja Operasional
- Peningkatan kapabilitas dan Tata Kelola o&M
- Alignment organisasi untuk melindungi AM.
- Implementasi teknologi dan digitalisasi
- Maintain, create & realisasi long-term-value (ROA)
- Sustainability perusahaan dan pembangkit
- Fine-tuning Pengelolaan perusahaan
Definisi Asset Management (MA)
The coordinated activity of an organization to realise value from assets.
Goal of Asset Management
Mengoptimalkan Overall Equipment Effectiveness (OEE) dan Life Cycle Cost (LCC)
- OEE = Availibility x Productivity x
7 Pilar Asset Management
1. Reliability Mgmt
2. WPC Mgmt
3. Efficiency Mgmt
4. Outage Mgmt
5. Operation Mgmt
6. Supply Chain Mgmt
7. Life Cycle Mgmt
Diagram Asset Management Transaction (AMT)
CBM: Condition Based Maintnenance contoh PdM.
Fungsi Generik Operasi, Pemeliharaan, Enjiniring
- Operation : Operate and deliver the product
- Maintenance: Preserve the asset fuction
- Engineering: Close performance gap and improve
Proses Bisnis Pembangkitan – The Big “O” Process
Stakeholder (Shareholder, Government, Customer/Buyer, Community, Employees, Suppliers)
→ Strategic Plan Longterm Plan
Bagaimana jika salah satu tidak ada?
Operation
Operation
Operation
Siklus Manajemen Reliabiity (Excellence at the Basic)
- Identifying the Right Work
- Accomplishing the Right Work
- Learning the Right Way
- Learning from the Experience
Pentingnya Tata Kelola dan Teknikal saling berkesinambungan.
Reliability Basis vs LCM
Reliability Basis
Effective Work Package
Work Plan:
- Job Scope Safety Technical Data Checklists Procedures
- Special Tools
- Estimated Time
- Clearances
- Special Skills/Multi Department
- Primary Parts
- Repair History
WPC
Definisi
is a well-defined series of processes used to effectively plan, schedule, and manage work
activities…
Maksud dan Tujuan WPC
- Adalah serangkaian proses
RELIABILITY MAINTENANCE
Oleh: Agus Aopik
BoK 2 – Manufacturing Process Reliability (TPM)
Total Productive Maintenance
BoK 2 - Autonomous Maintenance
We all responsible for our equipment
BoK 2 - Planned Maintenance
BoK 3 – Equipment Reliability - 4th Maintenance Generation
- Managing physical and economics risks.
BoK 3 – Equipment Reliability – Reliability Engineering
SUPPLY CHAIN MANAGEMENT
Oleh: Boni Muplihin
Senior Officer Demand Planning I
Model Implementasi Manajemen Aset
Adalah model yang dapat mencakup semua proses dan mekanisme tata Kelola pembangkit
baik proses utama operasi dan pemeliharaan pembangkit maupun proses pendukung lainnya
yang terintegrasikan dan selaraskan dengan proses utama sehingga menjadi satu kesatuan
atau gambaran yang utuh.
Definisi
- SCM: bagian dari mata rantai penyediaan tenaga listrik yang harus dilakukan secara
efektif.
- SCM meliputi, manajemen inventory, manajemen gudang, manajemen pengadaan dan
manajemen logistic.
Tujuan Pengelolaan SCM & Procurement
Supply Chain & Procurement as a strategic partner and digital lighthouse.
- Innovation: New tools, new skills, System-based approach
- Insight: Deep expertise and category knowledge, New Suppliers and partners
- Integrity: Ethical sourcing, focus on best outcomes for IP, Think – Act – Work
Together.
Kunci kesuksesan transformasi digital SC&Proc
Industry 4.0
1. Business – Impact Driven Solutions
• Deploy digital use cases that drive value and clear targets for productivity or
growth.
• User/Customer-back modular solutions linked to end-to-end business
processes.
• All spend categories covered by digital use cases.
2. Technology – Innovative Architecture
• Multi-speed development (Fast-concept literation, modular concept, master 2-
speed IT)
• Next-generation analytical tools
3. People – Agile DNA
• New governance, roles, and skills required.
• New ways of working: Test and learn, fall fast & tweak and break silos.
• New partnership models with ecosystems (e.g. startups, established vendors,
research Institutes)
Empat area utama transformasi SC&Pro
- Demand Planning
• Demand Forecasting
• Demand Consolidation
- Strategic Procurement
• Supplier Development/Qualification
• Category Analytics
• Sourcing Execution
- Operational Procurement
• Contract Management
• Supplier Performance Management
• Procure to pay
- Inventory/Logistics
• Inventory Planning
• Logistics
Proses Bisnis SCM
1. Pengelolaan Data kataog
2. Inventory Policy
3. Perencanaan Inventory
4. …
5. … dst s/d 15
KPI SCM
1. Kesesuaian dan Kelengkapan Data Katalog
2. Duplikasi Data Katalog
3. Service Level Material
4. Perputaran Material
5. Penurunan Level
6. Procurement ROI (Return of Investment)
7. Efisiensi Biaya di Proses Pengadaan
8. Stock Opname
9. Efektifitas Pemakaian Material Gudang
Aplikasi
- IBM Maximo
- Oracle ERP
- IP-Inventory
- IP-SCM
- I-Track
- D&B Hoovers
- Tableau
Digital Procurement
Proses Bisnis
Budget → ERP Iproc →ERP Sourcing →ERP Purchasing →
ERP Receiving: → Invoice
- Barang Expense/Jasa
- Fixed Asset
- Inventory
WorkFlow Material Exclude Procurement
Inventory Planning & Controlling Scope Work
- Target Performance
• ITO
• Saldo akhir persediaan
- Evaluasi & Monitoring
- Tools - Smart Inventory Management System with IP-ProInventory
Manajemen Pengadaan
- Unit <IDR 15 M
- Strategic Sourcing
- Unit <IDR 10 M Meleihi Wewenang
- Overseas Procurement
- Unit <IDR 5 M Head Office
- Procurement with trade finance
- Unit <IDR 1 M
payment
- Unit <IDR 500 Jt
- National Capacity
Development
Manajemen Logistik
Activities:
Managing inbound & outbound logistic
Tools:
- Kontrak payung forwarder.
- Kuota larangan terbatas impor di Soetta (15000 pcs) dan Tanjung Priok (1500 Pcs)
- Mitra utama kepabeanan di Soetta, Tanjung Priok, Juanda dan Tanjung Perak
KPI:
- Customer Leadtime
- Freight optimization
- Cost avoidance terkait dengan customs
Manajemen Gudang
Supplier
Gudang
User
Accounting
Result
- 2019 → :
Cost Saving:
LIFECYCLE MANAGEMENT (LCM)
Oleh: Lasaro Brastha Risdaniar
Senior Officer Penyaluran Energi Primer & Abu
Definisi LCM
Merupakan metode utk melakukan perencanaan jangka panjang yg sistematis, terintegrasi,
dan bersifat komprehensif dgn jalan melakukan evaluasi teknis thd kondisi peralatan
pembangkit, melakukan pemodelan dan evaluasi ekonomis, memilih action plan yang paling
optimal dan melakukan benchmark thd best practice utk mengidentifikasi peluang2 dalam
melakukan peningkatan kinerja dan optimasi biaya.
Latar Belakang LCM
- Persaingan di Industri Pembangkitan TL semakin kompetitif
- Meningkatnya tuntutan utk peningkatan reliability, availlibility, maintainability, dan
safety pembangkit serta mempertahankan dan meningkatkan Kapasitas dan kinerja
jangka panjang unutk menjaga kelangsungan perusahaan.
- Proses perencanaan HAR KIT yang dilakukan berdasarkan reliability Based
Optimization yaitu yearly basis planning.
Tujuan LCM
Untuk melakukan REN jangka panjang HAR KIT yg menoptimalkan antara unplanned
generation loss, biaya HAR, dan biaya investasi seraya meningkatkan pemenuhan thd
persyaratan keamanan dan keselamatan KIT.
Reliability Basis vs LCM
- RB memastikan keberlanjutan
fungsi dan keandalan. Same
LCM
Siklus Hidup Aset
4 elemen: akuisisi, operasi dan HAR, Cyclis refurbishment/replacement, dan ultimate end of
life.
4 Elemen dasar biaya pada siklus hidup asset:
- Akuisisi
- Operasi Rutin dan Perawatan
- Periode Overhaul Utama atau Penggantian
- Akhir Umur pakai (E)
Feasibility Study → Design → Build & In → Commissioning → Operate & Maintain →
Closure → kembali lagi ke Feasibily Study
Siklus Hidup Aset
LCM merupakan basis dari PAS55-1-2008 (British Standard dan Institute Asset
Management)
Kegiatan Utama LCM
- Planning : penyusunan baseline vision mengenal operational lifetime pembangkit,
maintenance/replacement schedule dan cost yang menjadi dasar dalam melakukan
long -term financial planning; Capital Planning; Generation Planning
- Economics: Plant valuation update; Capital Improvement cost estimating; resource
allocation; Cost accounting dan tracking; Benchmarking.
- Plant Material Condition: Aging management untuk SSC utama; Engineering review
ddan evaluasi untuk aging; Engineering Investigation
- Operation & Maintenance: Improvement thd kegiatan O&M; Modifikasi atau
Engineering Change Proposal/Management
Ruang Lingkup (1)
- Penyusunan database evaluasi teknikal utk melakukan evaluasi pengoperasian KIT
dlm jangka waktu yg panjang.
- Eval mekanisme aging dan pengaruhnya thd peralatan.
- Eval dan prediksi waktu keusangan (obsolenscence assessment) peralatan KIT.
- Assessment (Remaining Life Assessment atai RLA) kondisi peralatan KIT dgn
menekankan pada faktor keselamatan dan proses aging peralatan2 kritikal.
Ruang Lingkup (2)
- Eval kegiatan HAR yg dilakukan saat ini dan membandingkannya th
Proses LCM
LCM mengidentifikasi program HAR jangka panjang yg diperlukan utk meningkatkan
keandalan dan merupakan bagian kegaitan REN HAR dalam WPC yg diupdate setiap tahun.
Penyusunan Preliminary LCM Plan
Dimulai dari REN LCM di tingkat SSC yg terdiri dari beberapa tahapan utama yaitu:
- Pemilihan dan pengklasifikasian SSC
- Eval teknis thd SSC dan mmenentukan LCM plan alternatig
- Eval ekonomis thd LCM plan alternatif dan pemilihan LCM plan yg paling optimal/
Penyusunan LCM Master Plan di tingkat korporat
Preliminary LCM Plan yg telah disusun menjadi input dlm melakukan proses eval, optimasi
dan penyusunan LCM Master Plan…
LCM Planning
Proses LCM