HSE CASE
&
MANAGING HSE IN
CONTRACTS
Julius Akpong
FECRMI, FISPN, IdipNEBOSH, MASSP, GradIOSH, MCSN,
HSE CASE
OUTLINE
What is HSE Case?
Application of HSE Case
Structure
Uses of HSE case
What is HSE Case?
An HSE case is a document that
demonstrates that there are controls in place
to manage major risks associated with an
asset or activity and that those risks have
been reduced to ALARP.
It is not a management system nor the
mechanism to achieve the management of
risks to ALARP.
Application
These are usually developed for groups of assets and
activities that share the same risks and are in the same
receiving environments e.g swamp flow stations managed by
the same asset manager can share a common HSE
management system and therefore a common case to
demonstrate adequate control for major risks.
However, it is necessary to carry out separate HEMP for each
individual location before it can be stated that the hazards and
controls are similar within the group.
Application
SPDC requires that the following types of facilities, as a
minimum, have an HSE Case even if the risks are not
found to be high:
Major oil flow stations
Gas processing plants
Oil export terminals
Tank farms
Offshore production facilities
Oil and gas transmission systems.
It’s a reference document and guide for a number of
activities essential for the safe operation and
management of an asset or facility.
STRUCTURE
The HSE case is made up of 7 parts
Part 1: Management summary and introduction
Part 2: Operations HSE – MS
Part 3: Activities catalogue
Part 4: Description of operation
Part 5: Hazard analysis/ Hazard register/ Mopo
Part 6: Identified deficiencies/Remedial work plan
Part 7: Conclusions/ statement of fitness
Part 1: Management summary and
introduction
This contains the following:
Statement of the case’ objective
Statement of criteria used to measure objectives
Scope of operations or process analysed
Conclusions against objectives
Statement of how recommendations and remedial work
is to be done.
Summary of method used
Definition of HSE case owner and custodian
Review cycle
Scope and structure of 7 parts of the HSE case.
Part 2: Operations HSE – MS
Provides evidence that the corporate HSE MS is being
applied and is functioning at the installation or business
process level, it contains the following:
Operation specific HSE policy and objectives
Operations HSE organization, staff HSE responsibilities,
how resources are provided, standards and documents
used.
Hazard and effects management methods, planning
methods and procedures used, performance monitoring
methods and how corrective action is undertaken
Role and type of audits
Management review.
Part 3: Activities catalogue
The catalogue provides evidence that control of risk is
occurring through quality assurance of critical activities.
Contains the following information:
Listing of HSE critical activities and tasks
For each critical activity, identification of:
Its hazard management objectives
The methods used to achieve each objective
Management controls applied
Accountabilities
Competency requirements
interfaces
Part 4: Description of operation
This part describes the essential features of the specific
installation or process as it supports the HSE case. It
describes a simple accurate outline of the operation
including all HSE associated aspects. Contents below:
Hazard inventories and their location
Location, layout and structural details
Supporting infrastructure details
Process control systems
Protection systems
Detection systems
Shutdown systems
Emergency response systems
Lifesaving systems
Part 5: Hazard analysis/ Hazard
register/ Mopo
Contents:
Summary reports on various hazard analyses
and assessment studies undertaken with
findings
Risk determination and ALARP
demonstration
Location specific hazard register
Safety Critical operating procedures (SCOP)
Manual of permitted operations (Mopo)
Part 6: Identified deficiencies/Remedial
work plan
Contents:
Identified shortfalls
Proposed modifications
Execution plan with action parties, target completion
dates and priority assessment.
Various assessments including implementation failure
and system failure.
Part 7: Conclusions, statements of
fitness
Contents:
Adequate HSEMS
Hazards and effects managed
Risks evaluated/reduced to ALARP
General description of shortfalls and remedial
action
Fit for safe operation.
Uses of the HSE Case
Provide a systematic framework for formal management
review of HSE management in their facility.
It is a safe work reference for managers and supervisors
on specific high risk tasks and activities.
An induction guide for new workers at all levels.
A thorough guide on HSE management in contracts for
contractors and contract holders.
As a framework for conducting internal and external
audits.
As a reference for incident investigation, reporting and
follow up
Identified areas for improvement and remedial action
plans help improve management, operations and
individual attainment of targets.
MANAGING HSE IN
CONTRACTS
OUTLINE
Why manage HSE in Contracts
Front end - HSE requirements/ Activities
Tender – HSE requirements/ Activities
Evaluation phase HSE activities
Mobilization phase
Execution phase
Demobilization and close out
Why manage HSE in contracts
An Organization may decide to manage HSE in contracts
because it wants to:
Achieve high levels of HSE standards in projects
Ensure that all elements of IACR in HEMP are effectively
utilized to address all hazards to contractor’s personnel,
company employee, visitors and the general public.
Ensure that both the contractor and contract holder are
mutually aware of their minimum obligation to achieve
the above.
Ensure that the means to monitor the contract HSE
management systems are mutually defined, understood
and accepted, agreed by all parties as contractually
binding.
Project definition
The Organization draws up the policy statement on HSE
that is to be observed
Define the organisation; formal structure for planning,
communications and responsibilities on HSE issues
Define minimum competency levels and training
requirements in HSE for contract staff expected on the
project.
Develop a comprehensive listing of HSE standards and
procedures applicable to the project
Define the criteria for HSE performance monitoring
Define the basis under which internal and external HSE
auditing would be conducted.
Front end – HSE requirements and
activities
Determine the HSE impact on scope, schedule and
strategy for the contracts required
Assess HSE content of each contract
Confirm suitability of contract scope, schedule and
strategy against HSE assessments
Prepare HSE related contract documents
Prequalify potential contractors for HSE suitability
Prepare the outline contract with appropriate milestone
hold points.
Tender- HSE requirement/activities
Contractors preparation of the HSE plan
Company response to contractor’s HSE clarification
requests, copies of queries and replies should be
circulated to all contractors.
Clarification meetings might be held with contractors
individually or in groups
Site visits by contractor may also be necessary.
Evaluation phase – HSE Activities
Evaluate thoroughly each contractors HSE Plan to
ensure that it achieves the minimum acceptable
standard.
Clarify each contractor’s plan where necessary.
Establish the costs included in each bid for HSE
activities.
Evaluate and provide rating and comparison of HSE
aspects in the bids to determine acceptability on HSE
requirements.
Mobilization phase – HSE Activities
Hold kick-off meetings
Contractor commences mobilization
Review and finalize HSE plan with company
Company supervise, inspect and monitor progress
Contractor fulfils pre execution milestone requirements
Company Holds pre execution audit
Execution phase – HSE activities
Demonstration of Contractor’s line management
commitment to HSE
Reinforcement of HSE targets as defined in the HSE
plan
Provision of training as needed for specific contractor
employees
Regular checks of the contractor’s performance by
contract holder
Execution phase cont’d.
Contractor’s monitoring of the quality, condition and
integrity of his plant equipment and tools
Contractor’s holding of daily toolbox and HSE meetings
Contractor’s implementation of exercises and drills of
contingency plans with maintenance of an effective audit
trail.
Monitoring of the contractor’s accident investigation and
follow up
Performing HSE inspections/audit of contractor activities
(including contractor’s internal HSE control system)
Demobilization and closeout
Demobilization
Site restoration
Disposal of surplus material and waste, and its
documentation.
Close out
Assess the effectiveness of the plan
Identify areas unanticipated in the plan, how they were overcome
and future approach to be taken
Highlight successful positive aspects that should be used in the
future
Discuss analysis of company and contractor’s performance with
contractor’s management for means of improvement.
Provide input information on the contractor for company’s bid list to
identify actions needed in assessments for future tenders
ME
[email protected]
08039297684