Seven Seas Industries SDN BHD V Philips Electronic Supplies (M) SDN BHD & Anor (2008) 5 MLJ 157
Seven Seas Industries SDN BHD V Philips Electronic Supplies (M) SDN BHD & Anor (2008) 5 MLJ 157
[2008] 5 MLJ (M) Sdn Bhd & Anor (Sulaiman Daud JCA) 157
B
COURT OF APPEAL (PUTRAJAYA) — CIVIL APPEAL NO W–02–376
OF 2003
ZALEHA ZAHARI, KN SEGARA AND SULAIMAN DAUD JJCA
24 APRIL 2008
C
Contract — Breach — Confidentiality agreement — System devised by appellant
for assembly of loaders — Whether information on system confidential in nature
— Whether system was unique in light of usage and practice of similar trade and
industry — Whether there was breach of confidential information
D
Cases referred to
E
Chow Yee Wah & Anor v Choo Ah Pat [1978] 2 MLJ 4 (refd)
Coco v AN Clark (Engineers) Ltd [1969] RPC 41 (refd)
Eastern & Oriental Hotel (1951) Sdn Bhd v Ellarious George Fernandez & Anor
[1989] 1 MLJ 35 (refd)
F Frame v Smith (1987) 42 DLR [4th] 81 (refd)
Gan Yook Chin (P) & Anor v Lee Ing Chin @ Lee Teck Seng & Ors [2005] 2
MLJ 1 (refd)
Heilbut, Symons & Co v Buckleton [1913] AC 30 (refd)
Hospital Products Ltd v United States Surgical Corp (1984) 156 CLR 41 (refd)
G Kluang Wood Products v Hong Leong Finance [1999] 1 MLJ 193 (refd)
Lee Ing Chin @ Lee Teck Seng & Ors v Gan Yook Chin & Anor [2003] 2 MLJ
97 (refd)
Tindok Besar Estate Sdn Bhd v Tinjar Co [1979] 2 MLJ 229 (refd)
Watt v Thomas [1947] AC 484 (refd)
H
Legislation referred to
Evidence Act 1950 s 92, 92(b)
A
Sulaiman Daud JCA (delivering judgment of the court):
[1] This is an appeal against the decision of the learned judge of the High
Court dismissing the appellant’s claim against the respondents for damages B
and other declaratory reliefs arising out of an alleged repudiation of a written
agreement and an alleged wrongful appropriation and use of confidential
information.
BACKGROUND FACTS C
[2] The factual background can be stated briefly. The second respondent is
a company limited by shares with shareholding in the first respondent’s
company. The principal business of the company includes the production of D
loaders which forms integral components of compact disc based equipments.
In 1991 the second respondent subcontracted the assembly of the loaders to
a company called Singamip Industries Sdn Bhd (‘Singamip’) which had its
operation in Tampoi. At the same time it appointed one of its officers by the
name of Allan Netto (‘SP2’) to supervise the assembly at the plant. E
Subsequently in late 1992 the second respondent appointed the appellant to
replace Singamip as its subcontractor to carry out the assembly of the loaders.
After the phasing out of Singamip and until 1995, the appellant was the only
subcontractor carrying out such assembly for the respondents in this region.
F
[3] In 1993 the appellant commenced operation at its assembly plant
known as Seven Seas 1 (‘SS1’) in Desa Cemerlang, Johore which later
expanded to Seven Seas 2 (‘SS2’) in Senai. Prior to 10 January 1996 there was
no written relationship between the parties. Their relationship only evolved
out of constant and continuous dealing between them. The volume of loaders G
required to be assembled was determined at logistic meetings. So too, issues
pertaining to charges for down time and under capacity. Ultimately on
10 January 1996 the appellant and the first respondent executed a
‘subcontractor contract’ (‘the contract’) to formalise their relationship. The
annexure to the contract which formed an integral part thereof was executed H
later on 15 August 1996. In April 1996 the appellant established its third
assembly plant known as Seven Seas 3 (‘SS3’) replacing SS1 and SS2.
A [5] From the pleading it is apparent that the appellant’s causes of action
against the respondents in the present suit are for breach of contract arising
out of the said termination, and for wrongful appropriation and use by the
latter of confidential information belonging to the appellant. The issues that
arose for determination in the court below which are now pursued in this
B appeal are as follows:
(i) Whether there exist an implied term of the contract, or a collateral
agreement, as to a minimum of 50,000 loaders to be assembled per day
for the duration of the contract?
C
(ii) Whether the contract was validly terminated?
(iii) Whether the appellant has any proprietary or other right to the system
of assembly, and if so, whether the respondents have appropriated that
D right wrongfully?
[6] The learned judge found for the respondents in respect of all the
aforesaid issues. The present appeal substantially relates to the findings of fact
by the learned judge. The function of an appellate court in hearing an appeal
E on questions of fact is well established. In Watt v Thomas [1947] AC 484,
Lord Thinkerton, in a well known passage of his speech summarises the
principles to be adopted as follows: ‘(i) where a question of fact has been tried
by a judge without a jury, and there is no misdirection of himself by the
F
judge, an appellate court which is disposed to come to a different conclusion
on the printed evidence, should not do so unless it is satisfied that any
advantage enjoyed by the trial judge by reason of having seen and heard the
witnesses, could not be sufficient to explain or justify the trial judge’s
conclusion; (ii) the appellate court may take the view that, without having
G seen or heard the witnesses, it is not in a position to come to any satisfactory
conclusion on the printed evidence; and (iii) the appellate court, either
because the reasons given by the trial judge are not satisfactory, or because it
unmistakably so appears from the evidence, may be satisfied that he has not
taken proper advantage of his having seen and heard the witnesses, and the
H matter will then become at large for the appellate court’.
[7] In Gan Yook Chin (P) & Anor v Lee Ing Chin @ Lee Teck Seng & Ors
[2005] 2 MLJ 1, the Federal Court affirmed the test of ‘insufficient judicial
I appreciation of evidence’ as a ground for appellate intervention adopted by
the Court of Appeal in Lee Ing Chin @ Lee Teck Seng & Ors v Gan Yook Chin
& Anor [2003] 2 MLJ 97. In holding that such a test is consistent with the
established ‘plainly wrong test’, Steve Shim CJ (Sabah & Sarawak) said,
at p 10, as follows:
164 Malayan Law Journal [2008] 5 MLJ
In our view, the Court of Appeal in citing these cases had clearly borne in mind A
the central features of appellate intervention is to determine whether or not the
trial court had arrived at its decision or finding correctly on the basis of the relevant
law and/or the established evidence. In doing so the Court of Appeal was perfectly
entitled to examine the process of evaluation of the evidence by the trial court.
Clearly, the phrase ‘insufficient judicial appreciation of evidence’ merely related to B
such a process. This is reflected in the Court of Appeal restatement that a judge
who was required to adjudicate upon a dispute must arrive at his decision on an
issue of fact by assessing, weighing and, for good reasons, either accepting or
rejecting the whole or part of the evidence placed before him. The Court of Appeal
further reiterated the principle central to appellate intervention, ie that a decision
arrived at by a trial court without judicial appreciation of the evidence might be C
set aside on appeal …
[8] With this guiding principle in mind we will now proceed to consider
whether there was an insufficient judicial appreciation of evidence by the D
learned trial judge in coming to his finding in respect of the three identified
issues aforesaid.
[9] The claim that there was a representation as to the said volumes was set
out in para 16.2 of the statement of claim which read as follows:
16.2 It had been represented by the second defendant that at all material times F
during the said operation of the said agreement, the volume of loaders required by
the first and/or second defendants was between 50,000 and not exceeding 70,000
units per day and this volume was to be exclusively manufactured by the plaintiff.
This representation was an intrinsic element, either expressed or implied, of the
agreement and/or any collateral agreement thereto. As a result of the said
G
representation, the plaintiff agreed to the reduction of the unit price from $0.83
to RM1.48 as fixed by the second defendant giving a reasonably and legitimately
income of RM74,000 per day to the plaintiff.
[10] Learned counsel for the appellant submitted that the said oral H
representation on the volume of loaders formed an essential element in the
relationship between the parties on the basis that the written contract
document was not intended to form the entire agreement between the
parties. In other words such representation amounted to an express term of
the contract so as to constitute a collateral agreement between them. I
A matter on which a document is silent and which is not inconsistent with its
terms. Unless the additional evidence sought to be introduced falls within the
scope of any of the provisos, it should not be allowed to be introduced as it
would be to contradict, vary, add or subtract from the terms of the agreement
(per Chang Min Tat FJ in Tindok Besar Estate Sdn Bhd v Tinjar Co [1979] 2
B MLJ 229 at p 233). Such collateral contract must be viewed strictly
(see Heilbut, Symons & Co v Buckleton [1913] AC 30). No agreement would
be safe from being re-written by one party in court of law if parole evidence
which do not fall within the proviso of s 92 of the Evidence Act is admitted
C in evidence (see Tindok Besar Estate Sdn Bhd).
It is my opinion that for the oral evidence to be accepted the credibility of the
witness has to be solid. Unfortunately the evidence given are either self serving or
because of disappointment with Philips. I treat the evidence given by Jos Sanders
E (SP1) or Allan Netto on the ‘promises’ of the volume with suspect.
[13] Learned counsel for the appellant criticised the learned judge’s finding
on two main grounds. His first argument was directed to the learned judge’s
F finding on the credibility of SP1 and SP2, the appellant’s witnesses. It is
submitted that the learned judge had no basis to conclude that the relevant
witnesses as not credible. It is further submitted that the learned judge
misapplied the test in Eastern & Oriental Hotel (1951) Sdn Bhd v Ellarious
George Fernandez & Anor [1989] 1 MLJ 35 in that he failed to take into
G
consideration the objective facts concerning the nature of the relationship
between the parties and placed too much weight on the purported motives of
SP1 and SP2. His second argument is related to the learned judge’s evaluation
of the circumstantial evidence as to the relationship between the parties, the
H element of exclusivity and the establishment of SS3.
[14] We will firstly deal with the issue of credibility. It is trite law that
where the question before the appellate court relates to the credibility of
witnesses, the court has always been reluctant to differ from the judge who
I has seen and heard the witnesses, unless it can be clearly shown that he has
fallen in error. It would not be sufficient to warrant any interference merely
because the appellate court entertains doubt whether such finding is right
(see Kluang Wood Products v Hong Leong Finance [1999] 1 MLJ 193). The
appellate court is also reluctant to interfere in a case where the learned judge
166 Malayan Law Journal [2008] 5 MLJ
has announced as part of his judgment that he believes one set of witnesses A
and disbelieves the others (see Chow Yee Wah & Anor v Choo Ah Pat [1978]
2 MLJ 4).
[15] From the judgment it appears to us that the learned judge has rejected
B
the evidence of SP1 and SP2 on three main grounds. First of all he found that
SP2 and SP3 have given conflicting evidence as to how the two shareholders
of the appellant first met SP1 to start Seven Seas. He also found SP2 to have
wavered and faltered under cross-examination on the setting up of Seven Seas
by making specific reference to that part of SP2’s testimony on
C
cross-examination. Secondly, SP2, while in the employment of Philips, had
negotiated with SP1 in the setting up of Seven Seas, and as such the learned
judge found his evidence to be self serving for his own benefit and that of
SP3, his brother. Thirdly the learned judge formed the opinion that SP1 had
an axe to grind for two reasons, ie (i) he was not given a free hand to be the
D
man in Philips; and (ii) his association with Allan Netto was not well received
in Philips. Having considered the judgment as a whole we are satisfied that
the learned judge has not erred in his finding on the credibility of SP1 and
SP2 to warrant any interference by this court.
E
[16] Apart from the issue of credibility, we are also satisfied that the learned
judge has rightly considered all the relevant factors in coming to his finding
on the non-existence of the alleged oral representation or collateral
agreement. He has considered the event and the background leading to, and
the purpose for, the establishment of SS3. He also took into account the fact F
that the appellant has all the expertise at hand in the drafting of the
agreement to reflect the true intention of the parties.
[17] The learned judge also referred to Article IV.5 of the contract which
deals with the requirement of loaders. He found nothing therein which G
guarantee the volume or quantity of loaders to be assembled by the appellant
per day. The said article reads as follows:
Each month Philips will provide call-off requirement. In the first month the
volume will be fixed and in the second and third months a fluctuation within H
+/-10% will be allowed. Additionally, Philips will provide a non-binding forecasted
call-off requirement for the subsequent three months;
Philips will be legally bound by this three months call of requirement;
Philips will not be liable for any firm quantities above this three months call-off
I
requirement. This would mean the quantities could fluctuate to zero while the
agreement can remain effective;
This call-off requirements will be supplied by Philips to Seven Seas each second
week of the month according to the Philips production calendar.
Seven Seas Industries Sdn Bhd v Philips Electronic Supplies
[2008] 5 MLJ (M) Sdn Bhd & Anor (Sulaiman Daud JCA) 167
A [18] Learned counsel for the appellant argued that the said article is not
intended to define volume but a provision setting out a ‘call off ’ procedure
for the purpose of optimising resources. With respect we do not agree with
him. Even if the said clause is not intended to define volume but it is very
much related to the volume of loaders required to be assembled per day. It
B sets out the formula in determining such volume. If it is the intention of the
parties to provide for the minimum requirement of loaders to be assembled
per day we find no reason for the same to be omitted in the contract. As
mentioned earlier, the appellant has all the expertise, legal and technical, in
the drafting of the contract. Further we are of the view that the alleged oral
C terms on the minimum volume of loaders is also in disharmony, if not in
contradiction, with the express terms of the said article which specifically
provide ‘for the quantities could fluctuate to zero’.
D [19] It is to be noted that the contract also provide for under capacity claim
for the purpose of compensating the appellant for the excess labour if the
volume required is less than the order. From the evidence and other
contemporaneous documents relating to this matter, it is apparent that all
such claims by the appellant were based on orders and the call off
E requirement made at the logistic meetings. No claim was ever made on the
alleged promise of 50,000 loaders per day. The basis on which the under
capacity claim was made is in our view consistent with the procedure set out
in the said Article IV.5 as to the daily requirement of loaders by the
respondents. This further fortified our view that the parties never intended to
F specify the minimum amount of loaders required per day in the contract.
[20] With regard to the claim of exclusivity, we failed to see how such an
assurance is relevant to the claim on the alleged implied terms as to the
minimum requirement of loaders per day. It is clear from the words of the
G contract that the requirement of loaders by the respondents is not constant
but subject to ‘a non-binding forecasted call off requirement’ which could
fluctuate to zero. Further it is to be recalled that the under capacity claim
made by the appellant was never based on these figures. In any event we are
in agreement with learned counsel for the respondents that the objective
H evidence is also inconsistent with any exclusive arrangement. First, there is the
minute of Seven Seas Industries management meeting held on 15 May 1996
where it is clearly recorded that ‘Seven Seas is currently investigating and
having preliminary discussions with other customers concerning
manufacturing of other products and possible joint ventures’. Then there is
I the evidence of SP5 who confirmed that the second respondent not only
requested one floor to be reserved for them but also agreed for other
customers to use the appellant’s factory. Further it is to be noted that the
appellant did not complain of any breach of its alleged exclusive right when
the respondents’ own factory commenced operation in 1996 for the assembly
168 Malayan Law Journal [2008] 5 MLJ
of their own loaders. For the reasons aforesaid we agree with the finding of A
the learned judge that the appellant has failed to show the existence of such
oral representation or collateral agreement, or the element of exclusivity as
pleaded.
[22] The learned judge held that the contract was validly terminated
C
pursuant to Article X1 by giving six months prior notice as required therein.
He also rejected the appellant’s contention on the existence of a fiduciary
relationship between the parties to disentitle the respondents from
terminating the contract pursuant to the said article. Learned counsel for the
appellant raised two main issues which he contended to be relevant to the
D
issue of termination. First, whether there exist a fiduciary relationship
between the parties; and secondly, if such relationship existed, whether there
is implied in the contract an obligation of good faith between the parties to
render the termination clause ineffective.
E
[23] We will first deal with the issue of fiduciary relationship. The guideline
in determining the existence of a fiduciary relationship was laid down by
Wilson J in Frame v Smith (1987) 42 DLR [4th] 81, where Her Ladyship said
at p 99:
F
Relationship in which a fiduciary obligation have been imposed seem to possess
three general characteristics:
(1) the fiduciary has scope for the exercise of some discretion or power;
(2) the fiduciary can unilaterally exercise that power or discretion so as to G
affect the beneficiary’s legal interest;
(3) the beneficiary is peculiarly vulnerable to, or at the mercy of, the
fiduciary holding the discretion or power.
H
[24] In Hospital Products Ltd v United States Surgical Corp (1984) 156 CLR
41, Mason J classified the critical feature of these fiduciary relationship as
being that ‘the fiduciary undertakes or agrees to act for on behalf of or in the
interest of another person in the exercise of a power or discretion which will
affect the interests of that other person in a legal or practical way’. I
[25] Before us, learned counsel for the appellant submitted that the
relationship between the parties went beyond that of a mere
contractor-principal relationship. It is one of trust and confidence, in the
Seven Seas Industries Sdn Bhd v Philips Electronic Supplies
[2008] 5 MLJ (M) Sdn Bhd & Anor (Sulaiman Daud JCA) 169
A nature of partnership. It is asserted that the respondents have full access to the
financial information of the appellant and participated in making structural
changes at SS1 and SS2 and in the setting up of SS3. It is also submitted the
existence of the fiduciary relationship is evidenced in the unequal bargaining
position between the parties.
B
[26] Having examined the evidence on the nature and character of their
relationship, we agree with the learned judge that such relationship as
aforesaid did not give rise to a fiduciary relationship. As correctly stated by
C
learned counsel for the appellant the essence of fiduciary relationship is one
of trust and confidence between the fiduciary and the beneficiary where the
latter undertakes or agrees to act for, on behalf or in the interest of, the
beneficiary, being a person in a position of vulnerability. In the present case
there is no element of trust and confidence in the relationship between the
D parties, and no party is put in a position of vulnerability under the contract.
[27] It is true that there is a close relationship between the parties in the
carrying out of their respective functions and obligations under the contract
but it is not such giving rise to a fiduciary relationship. Their close
E relationship can be attributed to the nature of the contract and their
respective obligations thereunder. The terms of the contract stipulate that the
appellant will provide labour force, manufacturing facilities and office space,
while the respondents will provide the material required for the manufacture
of loaders. The respondents also set out the manufacturing process, and
F determine the technical and other specifications, to be complied by the
appellant. It also appears to us that the other terms of the contract are
substantially similar to other form of contracts for service with provisions on
claims for late delivery, payment and calculation of fees payable. For the
reasons aforesaid, we agree with the learned judge that the parties’
G
relationship is not based on trust and confidence. It is a mere
principal-contractor relationship.
[30] In our view the existence of the said obligation or duty again depend
on the expressed intention of the parties which is to be ascertained from the
B
terms of the contract, and on the nature of the relationship between the
parties. It is a well established principle that where the terms of a contract are
clear and free from ambiguity the court will not impose any implied terms.
In the present case the contract was terminated in accordance with the first
mode aforesaid by giving the six months prior notice which in our view is C
reasonable. Further the contract also provide for the protection of the rights
and obligations of the parties regarding delivery, warranty, payment and
confidentiality for the duration of the six months’ period. For these reasons
we agree with the learned judge that the contract was validly terminated in
accordance with the clear terms thereof. D
[31] We would add that there is also justification in the termination of the
contract. The appellant in its letter dated 4 November 1997 to the
respondents admitted that it faced manpower problem to meet substantial
volume increases apart from the problem with its contractor. Then there are E
the minutes of the meeting held on 8 November 1997 between the appellant’s
management and the representative of the respondents which showed that the
appellant was facing manpower crisis coupled with shortage of trained staff
and high turnover. These internal problems experienced by the appellant in
our view constitute reasonable grounds for the respondents to terminate the F
contract by giving the requisite six months notice. Further, we are also in
agreement with the learned counsel for the respondents that the appellant has
in fact acquiesced in the termination when it asked the respondents to leave
its premises before the expiry of the said six months period.
G
BREACH OF CONFIDENCE
H
[33] This issue centers on whether there was misuse of confidential
information concerning a system devised by the appellant for the assembly of
loaders (referred to as ‘system of assembly’). It is the appellant’s pleaded case
that it has devised a unique system of assembly allowing it to achieve a high
state of efficiency and state of control by the incorporation of several key I
features as particularised in para 8 of the statement of claim, including the use
of specially designed assembly line with anti-static conveyor belt and
anti-static immovable table, the installation of red and yellow calling lights to
alert material shortage, the installation of red pilot lamp to highlight line
Seven Seas Industries Sdn Bhd v Philips Electronic Supplies
[2008] 5 MLJ (M) Sdn Bhd & Anor (Sulaiman Daud JCA) 171
A failure, the use of bowls and plates to hold the compact discs, the
introduction of the use of stickers and the use of conveyor belts (‘the key
features’).
[34] It is the appellant’s case that such a system falls within the rubric of
B
confidential information which the respondents have copied and used in their
factory in breach of a duty of confidence. The learned judge in dismissing the
appellant’s claim referred to Coco v AN Clark (Engineers) Ltd [1969] RPC 41
which sets out the three elements to be established in order to succeed in an
C action for breach of confidence, that is to say, firstly, the information sought
to be protected has the necessary quality of confidence; secondly, the
information was communicated in circumstances importing an obligation of
confidence; and, thirdly, there must be unauthorised use of that information
to the detriment of the party communicating it. We are of the view that the
D learned judge has adopted the right approach in the determination of this
issue.
[35] Having evaluated the evidence before him, the learned judge held as
follows:
E
Allan Netto was employed by Philips to be their man at Singamip. It has always
been the arrangement that Philips would place their man at sub-contractors
premises. This practice was accepted in the plaintiff ’s factories. SS Leong was
placed in SS3 with the consent of the plaintiff. The unique system claimed by them
F was open to Philips who were at SS3 with the consent of the plaintiff. They can
see the set up in the factory. I do not recall any evidence as being led or put that
the unique system that Philips employee see every working day was confidential …
[36] The first question is whether the appellant can show that the
G
information sought to be protected has ‘the necessary quality of confidence’.
On this issue, we agree with the learned judge that information on the system
of assembly is not confidential in nature. As correctly pointed out by the
learned judge the system of assembly was opened to the respondents’
H representatives who were at SS1, SS2 and SS3 with the consent of the
appellant. It is also clear from the contract that the manufacturing process
was regulated and monitored by the respondents to ensure quality control set
by them. Under the contract the respondents were also given access to the
appellant’s factory to provide training opportunities for the appellant’s
I personnel.
[37] We are also in agreement with learned counsel for the respondents that
the appellant has failed to show that the system of assembly is unique when
judged in the light of usage and practice of similar trade and industry. The
172 Malayan Law Journal [2008] 5 MLJ
evidence clearly shows that the key features of the system as aforesaid have A
been used in the assembly industry long before the setting up of the
appellant’s assembly plant in SS1.
[38] For the reasons aforesaid, we unanimously dismissed this appeal with
costs and make further order for the deposit to be paid to the respondents B
towards the account of taxed costs.