0% found this document useful (0 votes)
135 views19 pages

NBC Land SDN BHD V Majlis Perbandaran Klang

The Court of Appeal allowed the appellant's appeal in part, finding that the appellant's claim for breach of contract was not time barred. The court found that the respondent was estopped from relying on the limitation defense based on continuous correspondence between the parties to resolve the matter. However, the court dismissed the appeals related to trespass and nuisance claims, agreeing with the High Court that the appellant failed to prove those claims. Specifically, the appellant did not prove that trespass occurred on land beyond what was leased to the respondent, nor did appellant establish trespass which was required for the nuisance claim.

Uploaded by

Siti Hawa Auni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
135 views19 pages

NBC Land SDN BHD V Majlis Perbandaran Klang

The Court of Appeal allowed the appellant's appeal in part, finding that the appellant's claim for breach of contract was not time barred. The court found that the respondent was estopped from relying on the limitation defense based on continuous correspondence between the parties to resolve the matter. However, the court dismissed the appeals related to trespass and nuisance claims, agreeing with the High Court that the appellant failed to prove those claims. Specifically, the appellant did not prove that trespass occurred on land beyond what was leased to the respondent, nor did appellant establish trespass which was required for the nuisance claim.

Uploaded by

Siti Hawa Auni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

NBC Land Sdn Bhd v Majlis Perbandaran Klang

[2021] 5 MLJ (Lau Bee Lan JCA) 717

A
NBC Land Sdn Bhd v Majlis Perbandaran Klang

COURT OF APPEAL (PUTRAJAYA) — CIVIL APPEAL


B
NO B-01(NCvC)(W)–441–08 of 2019
LAU BEE LAN, ABU BAKAR JAIS AND GUNALAN MUNIANDY JJCA
31 MAY 2021

C Civil Procedure — Limitation — Breach of contract — When cause of action


accrued — Whether appellant’s claim was time barred — Whether respondent
was estopped from relying on the defence of limitation

D Tort — Trespass to land — Whether the usage of land was with the knowledge
and consent of appellant — Whether appellant failed to prove its claim of trespass
— Whether learned judge erred in dismissing appellant’s claim for nuisance

This was an appeal by the appellant, against the decision of the High Court
E dated 8 August 2019 dismissing the appellant’s claim against the respondent
with costs, after a full trial. Golden Hope Plantations Bhd (‘Golden Hope’) was
the owner of a piece of land (‘the said land’) measuring approximately 161.36
acres in Klang. In 1997, desirous of acquiring a portion of the said land for the
purpose of a dumpsite, the state authority issued the relevant statutory notices
F under the Land Acquisition Act 1960 to Golden Hope. In response to the
notices, Golden Hope proposed that the state lease the portion of the said land
that it required instead of acquiring the whole land. The state authority agreed,
and a lease agreement was entered between Golden Hope and the respondent
of which Golden Hope leased 36 acres of the said land to the respondent for use
G as a dumpsite. The 36 acres leased to the respondent was located on Lot 77168
and part of Lot 77169 (‘the affected land’) and the lease was to expire on 22
April 2002. On 30 June 2000, the appellant purchased the said land from
Golden Hope. The sale and purchase agreement between them stipulated that
the said land was purchased on an ‘as is where is basis’. The appellant then
H issued a notice to the respondent to stop dumping rubbish on the affected land.
The respondent complied with the request. The appellant and the respondent
subsequently discovered that the actual portion of the said land used by the
respondent as a dumpsite was 39.479 acres, which was an additional 3.479
acres in excess of the 36 acres leased to the respondent under the lease
I agreement. At the appellant’s request, the respondent filled the dumpsite with
red soil and took steps to relocate some of the rubbish. At a meeting attended
by the parties’ respective representatives on 2 December 2003, the respondent
had agreed to bear 50% of the cost to rehabilitate the affected land used by the
respondent as a dumpsite. The dispute on the rehabilitation of the dumpsite
718 Malayan Law Journal [2021] 5 MLJ

continued until the appellant instituted an action on 19 June 2017 which was A
the subject matter of the present appeal. On 9 December 2016, there was a
meeting at the respondent’s premises attended by the parties’ representatives
whereby the respondent informed the appellant for the first time that the
respondent had changed its mind and that it would no longer abide by the
agreement reached between the parties on 2 December 2003. The appellant’s B
alleged causes of actions against the respondent included that: (a) the
appellant’s cause of action for breach of contract arose from the breach of
agreement reached between the appellant and the respondent on 2 December
2003; (b) the appellant’s cause of action for trespass arose from the respondent
C
allegedly trespassing into and wrongfully dumping rubbish on the additional
3.479 acres of the appellant’s land. The appellant alleged that the actual portion
of the appellant’s land used by the respondent to dump rubbish situated on Lot
77168 and part of Lot 77169 measured 39.478 acres, whereas the portion of
the land leased by Golden Hope to the respondent to be utilised as a dumpsite D
was only limited to 36 acres; and (c) the appellant’s cause of action in private
nuisance arose from the respondent’s act of trespass and coupled with its refusal
to rehabilitate the affected land, had interfered with the condition of the land
and consequently caused injury to the appellant’s right of enjoyment of its land.
The primary grounds of appeal raised by the appellant were: (a) in respect of E
the appellant’s claim for breach of contract, the learned judge erred in finding
that the appellant’s claim was time barred after having found that the
respondent had breached its contractual obligation; (b) in respect of the
appellant’s claim for trespass, the learned judge erred in finding that the
appellant failed to prove the allegation that the rubbish dumped at the site F
without the appellant’s consent after it had become the owner of the affected
land; and (c) in respect of the appellant’s claim for private nuisance against the
respondent, the learned judge erred in making no finding.

Held, allowing the appeal on limitation, and dismissing the appeal in respect of G
the claim for trespass and nuisance:
(1) The court found that there was merit when the lead counsel for the
appellant, Dato’ Sri Gopal Sri Ram submitted orally that the cause of
action against the respondent arose on 9 June 2016 where it was during
a meeting held on the said date between the respondent represented by its H
new Yang Di Pertua, YBhg. Dato’ Haji Mohammad Yasid bin Bidin,
Puan Zulina binti Yahya and Puan Haziza binti Mad Salleh that the
respondent informed the appellant for the first time that the respondent
had changed its mind to the effect that it would no longer abide by the
agreement to treat and rehabilitate the affected land. Having regard to the I
totality of the evidence available, the learned judge erred in failing to
judicially appreciate the evidence before her of which the learned justices
were satisfied that the respondent by its conduct was estopped from
relying on the defence of limitation having regard to the continuous
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan JCA) 719

A correspondence between the parties in attempting to resolve the matter.


The learned judge had erred in failing to take into account sufficiently the
common assumption upon which the parties had proceeded during the
relevant period of their relationship (see paras 15 & 18).
(2) The finding by the learned judge that there was a time frame set by the
B
parties to the agreement of 2 December 2003 on when the rehabilitation
works were to be carried out could not stand and was clearly erroneous.
Undoubtedly, the appellant’s cause of action in contract was not caught
by limitation and was well within the six years’ time bar stipulated under
s 6 of the Limitation Act (see para 19).
C
(3) The court found, based on cl 6 of the sale and purchase agreement dated
30 June 2020 and supported by the evidence of SP1, it was proved that
the usage as a dumpsite by the respondent of the land owned by Golden
Hope (prior to the sale) was with the knowledge of the appellant and with
D the consent of Golden Hope. Secondly, the appellants submission that
the portion of the said land that was leased to the respondent to be used
as a dumpsite was only 36 acres was not contradicted by the appellant,
was flawed as there was evidence shown to the contrary. The court found
that there was evidence to show that the fact of the area of 36 acres
E mentioned in cl 6 was an estimate was confirmed by SP1 in
cross-examination (see paras 28–30).
(4) Based on the evidence of SP4 and the survey reports of 2002 and 2018 it
was correctly submitted by the respondent that the appellant had failed to
prove that trespass in the form of usage in excess of 3.479 acres only
F
occurred when the appellant became the owner of the said land. The onus
was on the appellant to prove its claim in trespass which the appellant
failed to discharge. The learned judge was correct in her finding that the
appellant’s claim for trespass must fail (see paras 34–35).
G (5) The appellant’s claim in nuisance hinged on proof of trespass being
established. Since the appellant’s claim for trespass was not established,
the appellant’s claim in nuisance must necessarily fall. Nothing turned on
the fact that the learned judge made no findings on the cause of action for
nuisance as submitted by the respondent (see para 36).
H
[Bahasa Malaysia summary
Ini adalah rayuan oleh perayu, terhadapa keputusan Mahkamah Tinggi
bertarikh 8 Ogos 2019 yang menolak tuntutan perayu terhadap responden
dengan kos, selepas perbicaraan penuh. Golden Hope Plantations Berhad
I (‘Golden Hope’) adalah pemilik sebidang tanah (‘tanah tersebut’) yang
berukuran lebih kurang 161.36 ekar di Klang. Pada 1997, dengan hasrat untuk
memperoleh sebahagian tanah tersebut untuk tujuan tempat pembuangan
sampah, pihak berkuasa negeri telah mengeluarkan pemberitahuan berkanun
yang relevan di bawah Akta Pengambilan Tanah 1960 kepada Golden Hope.
720 Malayan Law Journal [2021] 5 MLJ

Sebagai tindak balas kepada pemberitahuan tersebut, Golden Hope A


mencadangkan agar pihak berkuasa negeri memajak sebahagian tanah tersebut
yang diperlukannya dan bukannya memperoleh seluruh tanah tersebut. Pihak
berkuasa negeri bersetuju, dan perjanjian pajakan dimeterai antara Golden
Hope dan responden yang mana Golden Hope menyewa 36 ekar tanah
tersebut kepada responden untuk digunakan sebagai tempat pembuangan B
sampah. 36 ekar yang dipajak kepada responden terletak atas Lot 77168 dan
sebahagian Lot 77169 (‘tanah terjejas’) dan pajakan itu luput pada 22 April
2002. Pada 30 Jun 2000, perayu telah membeli tanah tersebut daripada
Golden Hope. Perjanjian jual beli antara mereka menyatakan bahawa tanah
tersebut telah dibeli berdasarkan ‘as is where is basis’. Perayu kemudian telah C
mengeluarkan notis kepada responden untuk menghentikan pembuangan
sampah atas tanah terjejas itu. Responden mematuhi permintaan itu. Perayu
dan responden kemudian mendapati bahawa bahagian sebenar tanah tersebut
yang digunakan oleh responden sebagai tempat pembuangan sampah adalah
39,479 ekar, yang melebihi 3,479 ekar daripada 36 ekar yang dipajak kepada D
responden di bawah perjanjian pajakan itu. Atas permintaan perayu,
responden telah memenuhi tempat pembuangan sampah itu dengan tanah
merah dan mengambil langkah untuk mengalih sebahagian sampah itu. Dalam
mesyuarat yang dihadiri oleh wakil pihak masing-masing pada 2 Disember
2003, responden telah bersetuju untuk menanggung 50% daripada kos untuk E
memulihkan tanah yang terjejas yang digunakan oleh responden sebagai
tempat pembuangan sampah. Perselisihan mengenai pemulihan tempat
pembuangan sampah berlanjutan sehingga perayu memulakan tindakan pada
19 Jun 2017 yang menjadi hal perkara rayuan ini. Pada 9 Disember 2016,
terdapat mesyuarat di premis responden yang dihadiri oleh wakil pihak di F
mana responden untuk pertama kalinya memaklumkan kepada perayu bahawa
responden telah berubah fikiran dan bahawa ia tidak akan lagi mematuhi
perjanjian yang dicapai antara kedua-dua pihak pada 2 Disember 2003.
Dakwaan kausa tindakan perayu terhadap responden termasuk bahawa: (a)
kausa tindakan perayu untuk pelanggaran kontrak daripada pelanggaran G
perjanjian yang dicapai antara perayu dan responden pada 2 Disember 2003;
(b) kausa tindakan perayu untuk pencerobohan timbul daripaa dakwaan
responden menceroboh ke dan dengan salah membuang sampah atas tanah
tambahan 3,479 ekar perayu. Perayu mendakwa bahawa bahagian sebenar
tanah perayu digunakan oleh responden untuk membuang sampah terletak di H
Lot 77168 dan sebahagian di Lot 77169 berukuran 39,478 ekar, manakala
bahagian tanah yang dipajak oleh Golden Hope kepada responden untuk
digunakan sebagai tempat pembuangan sampah hanya terhad kepada 36 ekar;
dan (c) kausa tindakan perayu dalam kacau ganggu persendirian timbul
daripada tindakan responden menceroboh dan bersekali dengan I
keengganannya memulihkan tanah terjejas itu, telah mengganggu keadaan
tanah tersebut dan akhirnya menjejaskan hak perayu menikmati tanahnya.
Alasan utama rayuan yang ditimbulkan oleh perayu adalah: (a) berkaitan
tuntutan perayu untuk pelanggaran kontrak, hakim yang bijaksana terkhilaf
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan JCA) 721

A kerana mendapati bahawa tuntutan perayu telah luput had masa setelah
mendapati bahawa responden telah melanggar tanggungjawab
kontraktualnya; (b) berkaitan tuntutan peryau utuk pencerobohan, hakim
yang bijaksana terkhilad kerana mendapati perayu telah gagal membuktikan
dakwaan bahawa sampah yang dibuang di tapak itu tanpa persetujuan perayu
B selepas ia menjadi pemilik tanah terjejas itu; dan (c) berkaitan tuntutan perayu
untuk kacau ganggu persendirian terhadap responden, hakim yang bijaksana
terkhilaf kerana tidak membuat apa-apa penemuan.

Diputuskan, membenarkan rayuan berhubung had masa, dan menolak


C rayuan berkaitan tuntutan untuk pencerobohan dan kacau ganggu:
(1) Mahkamah mendapati bahawa terdapat merit apabila peguam utama
untuk perayu, Dato’ Sri Gopal Sri Ram berhujah secara lisan bahawa
kausa tindakan terhadap responden timbul pada 9 Jun 2016 semasa
D mesyuarat diadakan pada tarikh tersebut antara responden yang diwakili
oleh Yang Di Pertua barunya, iaitu YBhg. Dato’ Haji Mohammad Yasid
bin Bidin, Puan Zulina binti Yahya and Puan Haziza binti Mad Salleh
apabila responden memberitahu perayu untuk kali pertamanya bahawa
responden teah berubah fikirannya dan tidak akan mematuhi lagi
E perjanjian itu untuk memperbaiki dan memulihkan tanah terjejas itu.
Setelah mengambil kira keseluruhan keterangan yang sedia ada, hakim
yang bijaksana telah terkhilaf kerana gagal secara adil menghargai
keterangan di hadapan beliau yang mana hakim yang bijaksana telah
berpuas hati bahawa responden melalui tingkah lakunya diestopkan
F daripada bergantung kepada pembelaan had masa berdasarkan
hubungan berterusan antara pihak-pihak dalam usaha untuk
menyelesaikan perkara tersebut. Hakim yang bijaksana terkhilaf kerana
gagal mempertimbangkan sewajarnya andaian biasa yang mana
pihak-pihak telah mendahului sepankang tempoh berkaitan hubungan
G mereka (lihat perenggan 15 & 18).
(2) Penemuan oleh hakim yang bijaksana bahawa terdapat tempoh masa
yang ditetapkan oleh pihak-pihak kepada perjanjian 2 Disember 2003
mengenai bila kerja pemulihan dijalankan tidak boleh bertahan dan jelas
H tersilap. Tanpa diragui, kausa tindakan perayu dalam kontrak tidak
terbatas kepada had masa dan berada dalam had masa enam tahun seperti
dinyatakan di bawah s 6 Akta Had Masa 1953 (lihat perenggan 19).
(3) Mahkamah mendapati berdasarkan fasal 6 perjanjian jual beli bertarikh
30 Jun 2020 dan disokong oleh keterangan SP1, ia dibuktikan bahawa
I penggunaan sebagai tempat pembuangan sampah oleh responden atas
tanah tersebut yang dimiliki oleh Golden Hope (sebelum jualan) adalah
dalam pengetahuan perayu dan dengan persetujuan Golden Hope.
Keduanya, hujah perayu bahawa bahagian tanah tersebut yang dipajak
kepada responden yang digunakan sebagai tempat pembuangan sampah
722 Malayan Law Journal [2021] 5 MLJ

yang hanya 36 ekar itu tidak disangkal oleh perayu, dan cacat kerana A
terdapat keterangan yang menunjukkan sebaliknya. Mahkamah
mendapati bahawa terdapat keterangan untuk menunjukkan bahawa
fakta yang kawasan 36 ekar yang disebutkan dalam fasal 6 adalah
anggaran yang disahkan oleh SP1 dalam pemeriksaan balas (lihat
perenggan 28–30). B

(4) Berdasarkan keterangan SP4 dan laporan kajian 2002 dan 2018 ia telah
dihujahkan dengan betul oleh responden bahawa perayu telah gagal
untuk membuktikan bahawa pencerobohan dalam bentuk penggunaan
yang melebihi 3,479 ekar hanya berlaki apabila perayu menjadi pemilik C
tanah tersebut. Beban adalah terletak pada perayu untuk membuktikan
tuntutannya dalam pencerobohan yang mana perayu gagal untuk
laksanakan. Hakim yang bijaksana adalah betul dalam penemuannya
bahawa tuntutan perayu untuk pencerobohan patut gagal (lihat
perenggan 34–35). D
(5) Tuntutan kacau ganggu perayu bergantung kepada bukti pencerobohan
ditunjukkan. Oleh kerana tuntutan perayu untuk pencerobohan tidak
dibuktikan, tuntutan perayu dalam kacau ganggu semestinya gagal.
Tiada apa-apa atas fakta yang menunjukkan bahawa hakim yang E
bijaksana tidak membuat apa-apa penemuan berhubung kausa tindakan
untuk kacau ganggu sepertimana dihujahkan oleh responden (lihat
perenggan 36).]

Cases referred to F
Boustead Trading (1985) Sdn Bhd v Arab-Malaysian Merchant Bank Bhd
[1995] 3 MLJ 331, FC (refd)
Nasri v Mesah [1971] 1 MLJ 32, FC (folld)
Selvaduray v Chinniah [1939] 1 MLJ 253; [1939] 1 LNS 107, SC (refd)
Slomowitz v Vereeniging Town Council [1966] 3 CPD 317 (refd) G

Legislation referred to
Land Acquisition Act 1960
Limitation Act 1953 ss 6, 6(1)(a)
H
Local Government Act 1976

Appeal from: Civil Suit No BA-21NCVC-40-06 of 2017 (High Court,


Shah Alam)
Gopal Sri Ram (Austen Pereira, Harold Tan and Guok Ngek Seong with him) I
(Harold & Lam Partnership) for the appellant.
S Ramesh (Mohd Faiz with him) (Khairul Fadzli Amin & Co) for the respondent.
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 723

A Lau Bee Lan JCA:

INTRODUCTION

[1] This is an appeal from the appellant, NBC Land Sdn Bhd (formerly
B known as Banjaria Sdn Bhd) against the decision of the High Court dated
8 August 2019 dismissing the appellant’s claim against the respondent, Majlis
Perbandaran Klang (‘MPK’) with costs, after a full trial.

[2] Having considered the respective parties’ written submissions and the
C
oral arguments and the relevant records of appeal, we had allowed the appeal in
part on the issue of limitation and dismissed the appeal in respect of the
appellant’s claim for trespass and nuisance. These are our reasons in respect of
the said decision.
D BACKGROUND FACTS

[3] The appellant is a property development company in Klang. The


respondent, is the Municipal Council of Klang, established pursuant to the
Local Government Act 1976 (Act 171).
E
[4] The facts relevant to this appeal are gleaned from the narrative spelled
out by the learned judge in her judgment and the appellant’s chronology of
facts:
F (a) Golden Hope Plantations Bhd (‘Golden Hope’) was the owner of a piece
of land (‘the said land’) measuring approximately 161.36 acres in Klang.
In 1997, desirous of acquiring a portion of the said land for the purpose
of a dumpsite, the state authority issued the relevant statutory notices
under the Land Acquisition Act 1960 to Golden Hope. In response to
G the notices, Golden Hope proposed that the state lease the portion of the
said land that it required instead of acquiring the whole land;
(b) the state authority agreed and a lease agreement was entered between
Golden Hope and the respondent of which Golden Hope leased
H 36 acres of the said land to the respondent for use as a dumpsite. These
36 acres leased to the respondent is located on Lot 77168 and part of
Lot 77169 (‘the affected land’) and the lease was to expire on
22 April 2002;
(c) on 30 June 2000, the appellant purchased the said land from Golden
I Hope. The sale and purchase agreement between them stipulated that
the said land was purchased on an as is where is basis. The appellant then
issued a notice to the respondent to stop dumping rubbish on the
affected land and on 1 December 2000, the respondent complied with
the request;
724 Malayan Law Journal [2021] 5 MLJ

(d) the appellant and the respondent subsequently discovered that the A
actual portion of the said land used by the respondent as a dumpsite was
39.479 acres, which is an additional 3.479 acres in excess of the 36 acres
leased to the respondent under the lease agreement;
(e) via a letter of 5 January 2002 to the respondent, the appellant B
acknowledged receipt by YDP Dato’ Sharif ’s office confirming the
matters discussed during the meeting on 13 December 2001 which,
among others, are as follows:
Kami difahamkan bahawa pihak Majlis Perbandaran Klang (‘MPK’) akan
menjalankan kerja-kerja rawatan/pemulihan (rehabilitation) di atas bekas C
tapak pelupusan sampah (‘tapak tersebut’) yang terletak di atas Lot 77168
dan sebahagian Lot 77169 di mana kos-kos untuk kerja tersebut akan
ditanggung sepenuhnya oleh pihak MPK …
(f) at the appellant’s request, the respondent filled the dumpsite with red D
soil and took steps to relocate some of the rubbish. Following the
appellant’s dissatisfaction with the steps taken, another meeting was
held on 2 December 2003 at the respondent’s premises. At the meeting
attended by the parties’ respective representatives, the respondent had
agreed to bear 50% of the cost to rehabilitate the affected land used by E
the respondent as a dumpsite.
This is evident from the minutes of the meeting of 2 December 2003,
the relevant extracts are reproduced as follows:
2.2 RAWATAN PEMULIHAN DI TAPAK PELUPUSAN MPK DI JALAN
F
TELOK GONG (LAMA)
(g) …
(h) Tuan Tanah iaitu Syarikat Golden Hope Plantations telah meminta
supaya Majlis membaikpulih tanah di tapak pelupusan sampah
tersebut. G
(i) Kos bagi rawatan pemulihan bekas tapak pelupusan seluas 40 ekar ini
adalah lebih kurang RM6 juta. Syarikat Banjaria Sdn Bhd telah bersetuju
untuk berkongsi 50:50 bagi kos tersebut.
3.1 KOS RAWATAN PEMULIHAN BEKAS TAPAK PELUPUSAN H
TELOK GONG
Memandang kos bagi rawatan/pemulihan bekas tapak pelupusan sampah
seluas 40 ekar adalah lebih kurang RM6 juta, mesyuarat bersetuju supaya
pihak Syarikat Banjaria Sdn Bhd mengeluarkan kos sebanyak RM3 juta.
Jumlah ini tidak termasuk kerja-kerja landskap. Pembayaran kepada I
kontraktor hendaklah dibayar melalui akaun Majlis. Manakala RM2 juta
dibiayai oleh kerajaan Persekutuan dan RM1 juta oleh kerajaan negeri
(menggunakan peruntukan tahun 2004).
3.2 TAWARAN TENDER
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 725

A Kerja-kerja rawatan/pemulihan bekas tapak pelupusan sampah Telok


Gong akan ditawarkan secara tender oleh Majlis. (Emphasis added.)

(a) on 18 March 2004, the appellant wrote to the respondent confirming


the matters discussed during the meeting on 10 March 2004. Relevant
B extracts of the letter read as follows:
Seperti yang telah diperbincangkan dan dipersetujui di dalam mesyuarat
yang diadakan pada 10 Mac 2004 (rujukan B), kedua-dua pihak Banjaria
Sdn Bhd dan pihak Majlis Perbandaran Klang (‘MPK’) bersetuju untuk
bersama-sama menanggung kos perbelanjaan bagi rawatan bekas tapak
C pelupusan sampah di atas Lot 77168 dan sebahagian Lot 77169 dengan
nisbah 50:50 …

(b) on 15 April 2004 the respondent responded confirming the contents of


the appellant’s letter of 18 March 2004 regarding the matters discussed
D during the meeting of 10 March 2004.

[5] The dispute on the rehabilitation of the dumpsite continued until the
appellant instituted this action which is the subject matter of the appeal before
us on 19 June 2017. However, prior to this, on 9 December 2016 there was a
E meeting at the respondent’s premises attended by the parties’ representatives
whereby the respondent informed the appellant for the first time that the
respondent had changed its mind and that it would no longer abide by the
agreement reached between the parties on 2 December 2003.
F
[6] The appellant’s alleged causes of actions against the respondent can be
summarised as follows:
(a) the appellant’s cause of action for breach of contract arose from the
breach of agreement reached between the appellant and the respondent
G on 2 December 2003;
(b) the appellant’s cause of action for trespass arose from the respondent
allegedly trespassing into and wrongfully dumping rubbish on the
additional 3.479 acres of the appellant’s land. The appellant alleged that
H the actual portion of the appellant’s land used by respondent to dump
rubbish situated on Lot 77168 and part of Lot 77169 measured 39.478
acres, whereas the portion of the land leased by Golden Hope to the
respondent to be utilised as a dumpsite was only limited to 36 acres; and

I (c) the appellant’s cause of action in private nuisance arose from the
respondent’s act of trespass described in para (b) above coupled with its
refusal to rehabilitate the affected land, Lot 77168 and part of Lot
77169 had interfered with the condition of the land and consequently
caused injury to the appellant’s right of enjoyment of its land.
726 Malayan Law Journal [2021] 5 MLJ

[7] The appellant submitted that the causes of action against the A
respondent are not time-barred briefly because:
(a) the appellant’s cause of action for breach of contract only arose on
9 December 2016 when the respondent informed the appellant for the
first time that it had changed its mind and that it would no longer abide B
by the agreement reached between the parties on 2 December 2003; and
(b) the appellant’s causes of action in trespass and private nuisance are
continuing for as long as the rubbish dumped on the affected land
remains there and is not rehabilitated.
C
HIGH COURT’S DECISION/GROUNDS OF APPEAL

[8] The primary grounds of appeal raised by the appellant are:


(a) in respect of the appellant’s claim for breach of contract, the learned D
judge erred in finding that the appellant’s claim is time barred after
having found that the respondent had breached its contractual
obligation;
(b) in respect of the appellant’s claim for trespass, the learned judge erred in E
finding that the appellant failed to prove the allegation that the rubbish
dumped at the site without the appellant’s consent after it had become
the owner of the affected land; and
(c) in respect of the appellant’s claim for private nuisance against the
respondent, the learned judge erred in making no finding. F

OUR DECISION

Limitation
G
[9] It is not disputed that there is in existence a contract between the
appellant and the respondent whereby the latter had agreed to carry out the
rehabilitation works and pay 50% of the rehabilitation costs. This is evident
from the judgment of the learned judge where Her Ladyship held that the H
appellant had on the evidence proved its case as per the preceding para 9. The
reasoning of the learned judge is captured in paras 21–25, the latter of which
reads:
In my view, it is patently clear from the minutes of the meeting of 2 December 2003
and the letters dated 18 March 2004 and 15 April 2004 that the defendant had I
agreed to pay 50% of the rehabilitation costs and the source of the funds would
come from the State and the Federal Government. The defendant by its letter of
15 April 2004 acknowledged and confirmed the plaintiff ’s letter of 18 March 2004
which stated that the defendant had agreed to pay 50% of the rehabilitation costs.
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 727

A [10] Thus the only issue with regard to the appellant’s claim for breach of
contract is the question of when did the breach occur and consequently the
question of whether the appellant’s claim is time barred.

[11] On the law applicable, the learned judge had cited the locus classicus case
B of Nasri v Mesah [1971] 1 MLJ 32, a case common to both parties, and quoted
a passage appearing at p 34, right column, paras B to F where the Federal Court
held:
A ‘cause of action’ is the entire set of facts that give rise to an enforceable claim, the phrase
C comprises every fact which, it traversed, the plaintiff must prove in order to obtain
judgment (per Lord Esher MR in Read v Brown (1888) 22 QBD 128). In Reeves v
Butcher [1891] 2 QB 509; [1891-4] All ER Rep 943, CA, Lindley LJ said:
This expression, ‘cause of action’, has been repeatedly the subject of decision, and
it has been held, particularly in Hemp v Garland decided in 1843, that the cause
D of action arises at the time when the debt could first have been recovered by
action. The right to bring an action may arise on various events: but it has always
been held that the statute runs from the earliest time at which an action could be
brought.
In Board of Trade v Cayzer, Irvine & Co [1927] AC 610; [1927] All ER Rep Ext
E
778, Viscount Dunedin described ‘cause of action’ as that which makes action
possible. Now, what makes possible an action founded on a contract is its breach. In
other words, cause of action founded on a contract accrues on the date of its breach. In
the case of actions founded on contract, therefore, time runs from the breach
(per Field J in Gibbs v Guild (1881) 8 QBD 296). (Emphasis added.)
F
We note that the learned judge correctly stated that it is clear from the foregoing
passage that in calculating the period of limitation, time runs against a plaintiff
from the moment the breach of contract occurs.
G
[12] Statutorily, the learned judge took cognisance that the aforesaid
principle is recognised ‘Under s 6(1)(a) of the Limitation Act 1953 [where] an
action based on contract or tort must be commenced within six years of the
date which the cause of action arose. The period of six years commences from
H the date of the breach. Therefore in calculating the period of limitation, time
runs against a plaintiff from the moment the breach of contract occurs’.

[13] In respect of the issue of limitation, the learned judge held that that
I
there was a time frame for the respondent to commence and complete the
rehabilitation works and found that the appellant’s claim against the
respondent was time-barred as six years have elapsed since the cause of action
accrued in 2004–2005. Her Ladyship’s reasons for the existence of a time frame
set for the rehabilitation works are as stated in paras 34–35 as follows:
728 Malayan Law Journal [2021] 5 MLJ

The evidence on this issue is as follows. Not long after the meeting of A
2 December 2003, the plaintiff wrote to the defendant on 30 April 2004, expressing
its desire to advance the payment for the latter to call for tenders for the
rehabilitation works as there might be delay in the State Government releasing the
funds. The letter concluded, ‘advance payment hendaklah dikembalikan kepada
kami sebaik sahaja pihak Kerajaan Negeri meluluskan dan mengeluarkan B
belanjawan RM3 juta kepada MPK’. The plaintiff in offering to advance the monies
has clearly conducted itself as if it considered that the defendant had an obligation to
carry out the rehabilitation works in 2004.
It is therefore off that the plaintiff is now taking the position that there was no time
frame set for the works to be carried out. It is inconceivable that the plaintiff would C
have sent the letter of 30 April 2004 if there was no obligation on the defendant to start
the works in 2004/2005. It would follow that the defendant was in breach when it failed
to do so and time began to run. The plaintiff could have brought this action upon the
breach occurring. (Emphasis added.)
D
[14] We find that in its written submission, counsel for the respondent
supported the aforesaid findings of the learned judge referred in para 13 above
in holding that there was a time frame for the reasons proffered by the learned
judge. In addition, we find counsel for the respondent proffered a further
reason by drawing our attention to a letter from the appellant to the respondent E
dated 12 October 2010 seeking damages of RM5.4m. Counsel argued that by
claiming for damages for rehabilitation works from the respondent in itself is
proof that the breach of the agreement had occurred much earlier and not on
9 December 2016 as contended by the appellant when the respondent stated
that it would no longer abide by the agreement to rehabilitate the affected land. F

[15] With respect we are unable to agree with the respondent’s submission.
Instead we find there is merit when the lead counsel for the appellant,
Dato’ Sri Gopal Sri Ram submitted orally that the cause of action against the
respondent arose on 9 June 2016 where it was during a meeting held on the said G
date between the respondent represented by its new Yang Di Pertua,
YBhg Dato’ Hj Mohammad Yasid bin Bidin, Puan Zulina bt Yahya and Puan
Haziza bt Mad Salleh that the respondent informed the appellant for the first
time that the respondent had changed its mind to the effect that it would no
longer abide by the agreement to treat and rehabilitate the affected land. We H
find proof of the same in a letter dated 11 January 2017 from the appellant to
the respondent stating the following:
Berdasarkan kepada perbincangan pada hari tersebut, kami berasa amat kecewa
kerana selepas beberapa tahun surat-menyurat telah dikeluarkan serta mesyuarat I
dan perbincangan dengan pihak Majlis Perbandaran Klang (MPK) di mana pihak
MPK telah bersetuju untuk bersama-sama menanggung kos perbelanjaan bagi
rawatan bekas tapak pelupusan sampah di atas Lot 77168 dan sebahagian
Lot 77169 kepunyaan NBC Land Sdn Bhd (dahulunya dikenali sebagai
Banjaria Sdn Bhd) dengan nisbah 50:50, tetapi kini untuk pertama kalinya kami
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 729

A dimaklumkan oleh Y Bhg. Dato’ bahawa MPK telah mengubah pendirian dan tidak
akan bertanggungjawab atas isu tapak pelupusan sampah ini dan sebaliknya kami
diarahkan untuk merujuk kepada pihak Golden Hope Development Sdn Bhd (tuan
tanah terdahulu). (Emphasis added.)

B In this regard, we wish to correct ourselves when in our oral decision we did
inadvertently pronounced that the breach occurred on 11 January 2007, which
in fact is the date of the letter disclosing contemporaneously in all the
exchanges of correspondences between the appellant and the respondent that
there was an absolute refusal by the latter to perform its obligation to carry out
C the rehabilitation works in the manner agreed.

[16] We observed on the following evidence, prior to 9 December 2016, the


respondent had not at any time informed the appellant that it would renege on
the agreement reached on 2 December 2003:
D
(a) as is evident from the narrative stated in para 4 and the subparagraphs
thereunder and para 5 above, the appellant had between 2003 until the
end of 2016 continuously corresponded and engaged in further
discussion with the respondent to resolve the matter. During this period
E of time, the respondent delayed the fulfilment of its promises to treat
and rehabilitate the affected land;
(b) even as late as 23 September 2014, by their letter to the appellant, the
respondent informed the appellant that it was reviewing the matter and
that the appellant would be informed of the decision once made by
F them. It is vital that the said letter be reproduced (material parts) as
follows:
RAYUAN PENGELUARAN PERUNTUKAN BAGI MENJALANKAN
KERJA-KERJA RAWATAN PEMULIHAN TAPAK DI ATAS LOT 77168
DAN SEBAHAGIAN LOT 77169, MUKIM KLANG, DAERAH
G
KLANG, SELANGOR DARUL EHSAN, YANG DIMILIKI OLEH NBC
LAND SDN. BHD. (DAHULUNYA DIKENALI SEBAGAI BANJARIA
SDN BHD)
Dengan hormatnya, saya ingin merujuk kepada perkara di atas.
H 2. Dimaklumkan, Majlis mengambil maklum ke atas rayuan YBhg Dato’
berhubung perkara di atas. Majlis perlu menyemak semula dari aspek
perundangan dan sebarang keputusan akan dimaklumkan kepada pihak
YBhg Dato’ kemudian.

I [17] In so far as the letter from the appellant to the respondent dated
12 October 2010 seeking damages of RM 5.4m is concerned, in our considered
view nothing turned on the same because counsel for the respondent had
unequivocally stated that the respondent did not respond to the appellant’s
letter of 12 October 2010 which ended on the following note: ‘Justeru, kami
730 Malayan Law Journal [2021] 5 MLJ

amat berbesar hati sekiranya kami dapat mengaturkan A


perjumpaan/perbincangan bagi mencari jalan penyelasaian terhadap perkara
tersebut yang sekian lama menemui jalan buntu’.

[18] Having regard to the totality of the evidence available, we are of the
considered view that the learned judge erred in failing to judicially appreciate B
the evidence before her of which we are satisfied that the respondent by its
conduct was estopped from relying on the defence of limitation having regard
to the continuous correspondence between the parties in attempting to resolve
the matter. Further, we are also of the view that the learned judge had erred in
C
failing to take into account sufficiently the common assumption upon which
the parties had proceeded during the relevant period of their relationship as we
have alluded to above. An authority in point which is supportive of the
appellant’s cause of action for breach of contract is the oft-cited case of Boustead
Trading (1985) Sdn Bhd v Arab-Malaysian Merchant Bank Bhd [1995] 3 MLJ D
331 at p 345 B to H as follows:
We would add that it is wrong to apply the maxim ‘estoppel may be used as a shield
but not a sword’ as limiting the availability of the doctrine to defendants alone.
Plaintiffs too may have recourse to it. The true nature of the doctrine in this context
is that stated by Lord Russell of Killowen in Dawsons Bank v Nippon Menkwa E
Kabushiki Kaisha LR 62 IA 100 at p 108:
Estoppel is not a cause of action. It may (if established) assist a plaintiff in
enforcing a cause of action by preventing a defendant from denying the existence
of some fact essential to establish the cause of action, or (to put it in another way)
by preventing a defendant from asserting the existence of some fact the existence F
of which would destroy the cause of action.
It is also wrong to think that the doctrine is confined to cases where a representation
of fact has been made or were a party has been encouraged by another to believe in
the existence or in the non-existence of a fact. The decisions of the Privy Council in
Sarat Chunder Dey v Gopal Chunder Lala (1892) 56 JP 741 and the American Surety G
Co v Calgary Milling Co (1919) 48 DLR 295; [1919] 3 WWR 98 (among others) to
which we have referred earlier concerned cases involving representations not of fact
but of law.
The width of the doctrine has been summed up by Lord Denning in the
Amalgamated Investment case (Amalgamated Investment and Property Co Ltd (in H
liquidation) v Texas Commerce International Bank Ltd [1982] QB 84; [1981] 3 All
ER 577; [1981] 3 WLR 565) as follows:
The doctrine of estoppel is one of the most flexible and useful in the armoury of
the law. But it has become overloaded with cases. That is why I have not gone
I
through them all in this judgment. It has evolved during the last 150 years in a
sequence of separate developments: proprietary estoppel, estoppel by
representation of fact, estoppel by acquiescence, and promissory estoppel. At the
same time it has been sought to be limited by a series of maxims: estoppel is only
a rule of evidence, estoppel cannot give rise to a cause of action, estoppel cannot
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 731

A do away with the need for consideration, and so forth. All these can now be seen
to merge into one general principle shorn of limitations. When the parties to a
transaction proceed on the basis of an underlying assumption — either of fact or of
law — whether due to misrepresentation or mistake makes no difference — on which
they have conducted the dealings between them — neither of them will be allowed to
B go back on that assumption when it would be unfair or unjust to allow him to do so.
If one of the does seek to go back on it, the courts will give the other such remedy as the
equity of the case demands. (Emphasis added.)

[19] In light of the above, it is our judgment that the finding by the learned
C judge that there was a time frame set by the parties to the agreement of
2 December 2003 on when the rehabilitation works were to be carried out
cannot stand and is clearly erroneous. Undoubtedly, for the reasons explained,
the appellant’s cause of action in contract was not caught by limitation and was
well within the six years’ time bar stipulated under s 6 of the Limitation Act.
D
[20] At this juncture we pause to state that the appellant did raise the
argument that the causes of action in trespass and private nuisance are
continuing for as long as the rubbish dumped on the affected land remains
there and is not rehabilitated. The case of Slomowitz v Vereeniging Town
E
Council [1996] 3 CPD 317 (The South African Reports) at p 330 paras B to D
was cited as follows:
The statement in Halsbury, 2nd ed, vol 20, para 757: 3rd ed, vol 24, para 347,
which has often been cited in our Provincial Courts and received at least the
F inferential approval of this court in Mc Kenzie v Farmers’ Co-operative Meat
Industries Ltd, 1922 AD 16 at p 23, reads:
Apart from any statutory provision, a cause of action normally accrues when
there is in existence a person who can sue and another who can be sued, and
when all the facts have happened which are material to be proved to entitle the
G plaintiff to succeed.
Provided he could show damage, plaintiff would no doubt have been entitled to sue
immediately the road was closed. But I am unable to agree that, in the events that
have happened, such was plaintiff ’s only cause of action. For, as was said by
WATERMEYER, JA, at p 589 of the Oslo Land case, supra, and with mention of the
H earlier decision of this Court in Symmonds v Rhodesia Railways Ltd, 1917 AD 582,
it is necessary to distinguish between ‘a single wrongful act giving rise to one cause
of action and a continuing injury causing damage from day to day which may give
rise to a series of rights of action arising from moment to moment’.

I [21] Lead counsel for the appellant had submitted that the rehabilitation
issue is an issue common to the claim in contract and for trespass and private
nuisance and it would be sufficient if the appellant succeeded in its claim for
cause of action for breach of contract as the result would be the same in that
both causes of action were not time-barred. Given this submission and since we
732 Malayan Law Journal [2021] 5 MLJ

have decided that the appellant’s cause of action for breach of contract is not A
barred by limitation, we do not find it necessary to decide on the line of
argument canvassed by the appellant alluded in para 20 above.

Trespass and nuisance


B
[22] The learned judge decided that the appellant’s claim for damages for
trespass must fail stating at para 36 of the judgment the following:
The plaintiff case for trespass in respect of the additional 3.479 acres of land is
premised on the assertion that rubbish was dumped at this site without its consent C
after it had become the owner. There absolutely no evidence to substantiate the
allegation apart from the oral assertion of the plaintiff ’s witness.

[23] The appellant submitted that the learned judge erred in


misapprehending the appellant’s case for trespass in this manner: it is not the D
appellant’s case that the rubbish was dumped by the respondent on the
additional 3.479 acres of land after the appellant purchased the land from
Golden Hope and became its owner; rather it was premised on the fact that the
respondent had dumped rubbish on the affected land which was 39.478 acres
when the portion of the land leased by Golden Hope to the respondent was E
only limited to 36 acres. According to the appellant, this was the basis of its
claim pleaded in para 19 of the statement of claim for trespass by the
respondent for dumping rubbish on an additional 3.479 acres of the appellant’s
land.
F
[24] In the development of the aforesaid contention, the appellant relied on
the examination in chief evidence of Mr Vickneshwaran a/l M Ganapathy,
SP4, a qualified land surveyor that the actual portion of the appellant’s land
used by the respondent to dump rubbish situated on Lot 77168 and part of
Lot 77169 identified as 39.478 acres, comprised of 14.280 acres on Lot 77168 G
and 25.198 acres on Lot 77169. The appellant submitted that the sale and
purchase agreement dated 30 June 2020 entered into between the appellant as
purchaser and Golden Hope as vendor stated that the portion of the said land
that was leased to the respondent to be used as a dump site was only 36 acres
which was not contradicted by the appellant. H

[25] The appellant further submitted that upon the appellant’s request, the
respondent took steps in 2002 to relocate the rubbish to an area of 2.050 acres
in a survey prepared by SP4. Notwithstanding the relocation, the appellant also
submitted that the respondent remained a trespasser as no action was taken to I
rehabilitate the 3.479 acres of land.

[26] With respect, in our considered view, the appellant’s submission is


misconceived. Firstly, cl 6 of the sale and purchase agreement dated 30 June
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 733

A 2020 reads as follows:


6. The said property is freehold and free from all encumbrances. However
approximately an estimated area of 36 acres of the said Property is presently leased to
Majlis Perbandaran Klang as a dump site for refuse and rubbish and the said lease
expires on 22nd April 2002.
B

[27] SPI, Dato’ Ng Bee Chai in cross-examination confirmed that: (a) based
on cl 6 of the sale and purchase agreement dated 30 June 2020, the appellant
has knowledge regarding the usage of the land by the respondent as a dumpsite;
C (b) the land was used as a dumpsite before the appellant purchased the land;
and (c) he ‘supposed’ that permission to use the land for dumpsite was obtained
from Golden Hope but he did not have the evidence.

[28] We find, based on cl 6 of the sale and purchase agreement dated


D 30 June 2020 and supported by the evidence of SP1 referred in para 27 above,
it was proved that the usage as a dumpsite by the respondent of the land owned
by Golden Hope (prior to the sale) was with the knowledge of the appellant
and with the consent of Golden Hope.
E
[29] Secondly, the appellant’s submission that the portion of the said land
that was leased to the respondent to be used as a dumpsite was only 36 acres was
not contradicted by the appellant is flawed as there is evidence shown to the
contrary. Clause 6 of the sale and purchase agreement dated 30 June 2020 in
F crystal clear terms states ‘… However approximately an estimated area of
36 acres of the said Property is presently leased to Majlis Perbandaran Klang as
a dump site …’.

We agreed with the respondent’s submission that the usage of the words,
G ‘approximately an estimated area’ in cl 6, rendered that the acreage of 36 acres
of the land used by the respondent as a dumpsite is purely an estimate ‘di mana
terdapat kemungkinan bahawa keluasan yang digunakan oleh Responden
boleh menjadi lebih atau kurang daripada 36 ekar’.

H [30] We find there is evidence to show that the fact of the area of 36 acres
mentioned in cl 6 is an estimate was confirmed by SP1 in cross-examination.

[31] It is not disputed that the purchase of the said land by the appellant
from Golden Hope is on as is where is basis. However SP1 in cross-examination
I admitted that the appellant became aware of the extra usage of 3.479 acres after
the land survey was conducted; that the respondent had been using the extra
3.479 acres much earlier before the appellant became aware of the same; and
agreed when it was put to him that the extra usage of the land was before the
appellant entered the sale and purchase agreement dated 30 June 2020.
734 Malayan Law Journal [2021] 5 MLJ

[32] Further there is documentary evidence to show that the land survey A
conducted by the appellant was conducted in 2002, (two years after the sale)
another land survey in 2018 (after the action was filed).

[33] SP4 confirmed in cross-examination that the land surveys were


conducted in 2002 and in 2018 and the 2002 survey conducted by him was the B
first survey. To the following put question in cross-examination, SP4 replied:
MF: So Mr Vickneshwaran, since there was no land survey conducted before June year
2000, I put to you that there are possibilities of the total area of 39.478 acres in year
2002 are similar to the area of rubbish in June 2000 or before June in year 2000. C
VICK: I can’t be sure of that.
MF: Yes, but there are possibilities of being the same. VICK:
OK. There are possibilities correct. (Emphasis added.)
D
[34] Based on the evidence of SP4 and the survey reports of 2002 and 2018,
we find it was correctly submitted by the respondent that the appellant had
failed to prove that trespass (usage in excess of 3.479 acres) only occurred when
the appellant became the owner of the said land.
E
[35] The onus is on the appellant to prove its claim in trespass which in our
view the appellant failed to discharge (Selvaduray v Chinniah [1939] 1 MLJ
253; [1939] 1 LNS 107, SC). For the reasons explained above, we held the
view that the learned judge was correct in her finding that the appellant’s claim
for trespass must fail. F

[36] The appellant’s claim in nuisance hinges on proof of trespass being


established as referred in para 6(c) above. Since we have found that the
appellant’s claim for trespass has not been established, the appellant’s claim in
G
nuisance must necessarily fall. Therefore, in our considered view nothing turns
on the fact that the learned judge made no findings on the cause of action for
nuisance as submitted by the respondent.

CONCLUSION
H

[37] For the reasons adumbrated above, we are of the considered view that
there are merits in the appeal which warranted appellate intervention. In the
premises we unanimously made the following order:
(a) allowed the appeal in part in respect of the High Court decision in I
dismissing the appellant’s claim on limitation. Accordingly we set aside
the order of the High Court dated 8 August 2019 and remitted the case
to the High Court for assessment of general damages for breach of
contract;
NBC Land Sdn Bhd v Majlis Perbandaran Klang
[2021] 5 MLJ (Lau Bee Lan J) 735

A (b) dismissed the appeal in respect of the claim for trespass and nuisance;
and
(c) awarded costs of RM50,000 here and below to the appellant subject to
allocatur.
B
Order accordingly.

Reported by Mohd Kamarul Anwar

You might also like