Flow Chart Under Fidic 1999
Flow Chart Under Fidic 1999
____________________________________________________________________________________
Page 1 of 30
Procedures and Notices required Under FIDIC 1999
< 28 days
Monthly Payment
< 56 days
Contractor
submit final Employer shall
Contractor submit
Statement and pay to the
draft of final
the written contractor the
Statement
discharge Final Statement
amount
____________________________________________________________________________________
Page 2 of 30
Procedures and Notices required Under FIDIC 1999
Either of the
parties shows
Either of the parties his
refers the dispute to dissatisfaction
D.A.B
____________________________________________________________________________________
Page 3 of 30
Procedures and Notices required Under FIDIC 1999
L.O.I
28 days
The contractor shall give notice to the Engineer whenever the works are
likely to be delayed or disrupted, the notice shall include details of the
necessary drawings or instruction, details of why and by when it should
be issued, and details of the nature and amount of the de lay or
disruption likely to be suffered if it is late.
a) Extension of time
____________________________________________________________________________________
Page 4 of 30
Procedures and Notices required Under FIDIC 1999
c) Extension of time
28 days
42 days
Employer shall issue such
evidence
____________________________________________________________________________________
Page 5 of 30
Procedures and Notices required Under FIDIC 1999
2 days
2 days
If no contradiction in writing
Engineer to make a letter to
within 2 days, it shall be
contradict
deemed to be an instruction of
the Engineer.
____________________________________________________________________________________
Page 6 of 30
Procedures and Notices required Under FIDIC 1999
42 days
____________________________________________________________________________________
Page 8 of 30
Procedures and Notices required Under FIDIC 1999
____________________________________________________________________________________
Page 9 of 30
Procedures and Notices required Under FIDIC 1999
Contractor shall give the engineer not less than 21 days’ notice of the
date on which any plant or a major item of other Goods will be
delivered to the site
Commencement date
Contractor to submit
monthly progress
reports
Page 10 of 30
Procedures and Notices required Under FIDIC 1999
If the contractor suffers delay and/or incurs cost from complying with
the instructions of the engineer related to fossils.
24 hours
____________________________________________________________________________________
Page 11 of 30
Procedures and Notices required Under FIDIC 1999
Letter of acceptance
Notice of Commencement
28 Days
____________________________________________________________________________________
Page 12 of 30
Procedures and Notices required Under FIDIC 1999
84 days
28 days
Suspension affect part of the scope, this part can be Suspension affects the full project; this will
considered by the contractor as omitted and shall entitle the contractor to termination of the
be treated under clause 13 contract and shall be treated under clause
16.2
____________________________________________________________________________________
Page 13 of 30
Procedures and Notices required Under FIDIC 1999
21 days
14 days
Delay on Tests
____________________________________________________________________________________
Page 14 of 30
Procedures and Notices required Under FIDIC 1999
14 days
Engineer shall issue the taking- Engineer shall reject the If the Engineer fails to
over certificate application, giving reasons and either issue the taking –
specifying the work required to over certificate or to reject
be done by the Contractor the Contractor’s
application within 28 days
and if the works are
substantially in accordance
with the Contract, the
taking –over certificate
shall be deemed to have
been issued on the last day
of that period.
____________________________________________________________________________________
Page 16 of 30
Procedures and Notices required Under FIDIC 1999
Cost is at Contractor’s risk if work is attributable to: If due to any other cause, the Contractor will
1. Any design for which to contractor is responsible be notified by the employer/ representative,
2. Plant, materials or workmanship not being in accordance and it shall be treated as a variation
with the contract
3. Failure by the Contractor to comply with any other
obligation
28 days
For unfulfilled obligations, even after the
Engineer shall issue a issuance of the performance certificate, each
Performance Certificate party is liable for the unperformed obligations
after the latest of the
expiry dates of notice
Contractor to remove all
equipment, materials, etc.
28 days
Clause 12.1 “Works to be Measured”
____________________________________________________________________________________
Works to be
Page 17 of 30 measured and valued
Procedures and Notices required Under FIDIC 1999
14 days
Contractor to give If no notice,
notice to the Engineer Contractor, it is
to which records are deemed as
inaccurate if he accepted and
disagrees to the accurate
measurement
Confirm Vary
____________________________________________________________________________________
Contractor to give notice to the
Page 18 of 30
Engineer with supporting
particulars
Procedures and Notices required Under FIDIC 1999
Page 19 of 30
Procedures and Notices required Under FIDIC 1999
If Contractor
cannot
Contractor, in compliance, Contractor shall Contractor Contractor readily obtain
submits: inform the shall execute to the goods
1. A description of the Engineer if he and be promptly required for
proposed work to be cannot comply bound by give notice the variation
performed and a programme and give reasons each to the
for its execution Engineer
therefor variation
2. The Contractor’s proposal for
stating the
any necessary modifications
to the programme reasons
3. Contractor’s proposal for with
evaluation of the variation supporting
particulars
Engineer to
act on the
proposal
Changes in
price
____________________________________________________________________________________
Increase/ decrease caused by Increase/ decrease of costs of
aPage
change
20 in
oflegislation/
30 laws labor, goods and other inputs to
of UAE the works
Procedures and Notices required Under FIDIC 1999
If Contractor
suffered or will Contractor to give There is “Table of Adjustment data” If there is no
suffer delay notice to the Engineer included in the Appendix to Tender “Table of
and/ or Adjustment
incurred or data” in the
will incur Appendix to
additional cost Contractor is entitled The adjustment will be based upon the
Tender, this
for an extension of formulae:
Pn= a + b Ln/Lo + C En/Eo + d Mn/Mo + Sub- clause
time and payment of
will not apply.
any cost
The adjustment of
prices shall be based
on whatever is more
favorable to the
Employer, either:
42 days 21 days
56 days
Whichever is later
Employer shall pay to the
contractor the final payment
____________________________________________________________________________________
Page 21 of 30
Procedures and Notices required Under FIDIC 1999
Contractor shall submit the final statement along with Engineer shall deliver to the employer
a written discharge which confirms that the total of with a copy to the contractor an interim
the Final statement represents full and final payment certificate for the agrees parts
settlement of all the moneys due to the contractor of the draft final statement, and a
under or in connection with the contract dispute should be referred to D.A.B
28 days
____________________________________________________________________________________
Page 22 of 30
Procedures and Notices required Under FIDIC 1999
Contractor to
submit Statement
of Completion
with supporting
documents in six
copies
28 days
If the Contractor failed to
submit an application
Contractor to submit
an application
Page 24 of 30
Procedures and Notices required Under FIDIC 1999
Immediate effect
Page 25 of 30
Procedures and Notices required Under FIDIC 1999
42 days after
Contractor shall be
the 56 days entitled to terminate
Contractor shall give a notice to the
Employer of his intension to suspend the the contract. After
work or reduce the rate of work giving a 14 days’
Contractor shall notice
be entitled to
terminate the 21 days
contract. After
giving a 14
Contractor shall be entitled to suspend the
days’ notice
work or reduce the rate of work
Notice of Suspension
Page 26 of 30
Procedures and Notices required Under FIDIC 1999
To the Employer
Notice of Termination
Grounds:
1. Non receipt of evidence w/in 14 days
Immediate effect
42 days after giving notice of prior notice
termination w/ respect to
Financial Arrangements Grounds are:
2. Engineer fails to issue payment To the Employer
1. Prolonged suspension
certificate after 56 days after 2. Bankruptcy/ insolvency of
receipt of statement and the Employer or has gone
supporting documents into liquidation
3. Non- payment of interim
payment certificate w/in 42
days after expiry of 56 days for
Employer to pay interim
payments
4. Non- performance of
obligation by the Employer
5. Failure to comply with the
Contract agreement by the
employer as regards signing of
contract agreement and
assignment of contract
Infringement (or
____________________________________________________________________________________
alleged infringement)
of Intellectual and/ or
Page 27 of 30
industrial property
rights
Procedures and Notices required Under FIDIC 1999
Occurrence of
Force Majeure
or should have
become aware
Within 14 days
Effective Termination
____________________________________________________________________________________
Page 28 of 30
Procedures and Notices required Under FIDIC 1999
The contractor became aware or should have become aware of the event or
circumstance
< 28 days
42 days
28 days
ARBITRATION
NOTICE OF
Notes:
▪ Under the rules of
arbitration of international
chamber of commerce
56 days after notice ▪ May be commenced prior to
of dissatisfaction or after the completion of
the Works
▪ Obligations of the parties,
On or after this period, to the Engineer and the DAB
commence even without shall not be altered by any
attempt to settle amicably. arbitration being conducted.
____________________________________________________________________________________
Page 30 of 30