2 Contractor Quality Control Plan For Civil Work
2 Contractor Quality Control Plan For Civil Work
1
Document Name:
Contractor Quality Control Plan for Civil Work
Inspection and Test Plan for Civil work
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
2
Document Name:
Contractor Quality Control Plan for Civil Work
Inspection and Test Plan for Civil work
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
3
Document Name:
Contractor Quality Control Plan for Civil Work
Inspection and Test Plan for Civil work
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
4
Document Name:
Contractor Quality Control Plan for Civil Work
Inspection and Test Plan for Civil work
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
- Joint sealer
- Subgrade paper
2) Concrete test
3) Finished elevation & thickness of
H
concrete
4) Undulation of surface courses
5) Surface drainage
1.6 Tank pads
1.6.1 Materials
1) Filling material
2) Concrete H
1) Re-bar
1.6.2 Sand filling compaction plate
Load test or field density test ASTM D1556 or H
(ASTM D2167)
1.6.3 Dimension
1) Location
2) Top surfaces of sand fill
3) Finished surface (Slope, elevation)
H
4) Foundation roundness
5) Foundation finished elevation
6) Settlement records
1.6.4 Particle size distribution H
1.6.5 Laboratory compaction H
1.6.6 Embankment test results H
1.7 Setting anchor bolts
1.7.1 Material Certificates H
1.7.2 Setting in concrete
1) Orientation
2) Position and location
H
3) Plumb
4) Projection
1.7.3 Visual check H
5
Document Name:
Contractor Quality Control Plan for Civil Work
Inspection and Test Plan for Civil work
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
H: Hold Point; Hold on the production till TPI Inspector performs inspection and supervise the
required test
If you want to use this draft for inspection and test plan, you need to fill the TPI and Owner
Column based your project requirement. You may use following abbreviation for filling the
columns:
W: Witness Point; Manufacture shall notify client and TPI Inspector but there is no hold on the
Construction;
R: Document Review; Review means Review document, which includes of material test
certificates, test reports, records and etc.
A: Approval
SW: Spot Witness; for items with spot witness contractor shall notify TPI inspector as fulfilling
the monitoring;