Labour 2
Labour 2
Labour
14. Straight Piece Work: Payment is made on the basis of a fixed amount per unit of output
irrespective of time taken. It is the number of units produced by the worker multiplied by
rate per unit.
15. Differential Piece Rate: For different level of output below and above the standard,
different piece rates are applicable.
16. Wage Abstract: A summary giving details of wages to be charged to individual jobs,
work orders or processes for a specific period.
Basic Formulas
The formulas for different wage payment and incentive systems are given below:
1 Time Rate System
Earnings = Hours worked × Rate per hour
2 Straight Piece Rate System
Earnings = Number of units × Piece rate per unit
3 Differential piece Rate System
3.1 F.W. Taylor’s System
Efficiency Payment
Less than 100% 83% of the normal piece rate or 80% of piece rate when
below standard
Either 100% or 125% of the normal piece rate or 120% of piece rate
more than 100% when at or above standard
3.2 Merrick Differential Piece Rate System
Efficiency Payment
Up to 83 % Ordinary piece rate
83% to 100% 110% of ordinary piece rate (10% above the ordinary
piece rate)
Above 100% 120% or 130% of ordinary piece rate (20% to 30% of
ordinary piece rate)
4 Combination of Time and Piece Rate
4.1 Gantt Task and Bonus System
Output Payment
Output below standard Guaranteed time rate
Output at standard 120% of time rate
Question 1
Discuss the Gantt task and bonus system as a system of wage payment and incentives.
Answer
Gantt Task and Bonus System: This system is a combination of time and piecework system.
According to this system a high standard or task is set and payment is made at time rate to a
worker for production below the set standard.
Wages payable to workers under the plan are calculated as under:
Output Payment
(i) Output below standard Guaranteed time rate
(ii) Output at standard Time rate plus bonus of 20% (usually) of time rate
(iii) Output over standard High piece rate on worker’s output. (It is so fixed
so as to include a bonus of 20% of time rate)
Question 2
Discuss the accounting treatment of Idle time and overtime wages
Answer
Accounting treatment of idle time wages & overtime wages in cost accounts: Normal idle
time is treated as a part of the cost of production. Thus, in the case of direct workers, an
allowance for normal idle time is built into the labour cost rates. In the case of indirect
workers, normal idle time is spread over all the products or jobs through the process of
absorption of factory overheads.
Under Cost Accounting, the overtime premium is treated as follows:
¾ If overtime is resorted to at the desire of the customer, then the overtime premium may
be charged to the job directly.
¾ If overtime is required to cope with general production programme or for meeting urgent
orders, the overtime premium should be treated as overhead cost of particular
department or cost center which works overtime.
¾ Overtime worked on account of abnormal conditions should be charged to costing Profit
& Loss Account.
¾ If overtime is worked in a department due to the fault of another department the overtime
premium should be charged to the latter department.
Question 3
Discuss the effect of overtime payment on productivity.
Answer
Effect of overtime payment on productivity: Overtime work should be resorted to only when it
is extremely essential because it involves extra cost. The overtime payment increases the cost
of production in the following ways:
1. The overtime premium paid is an extra payment in addition to the normal rate.
2. The efficiency of operators during overtime work may fall and thus output may be less
than normal output.
3. In order to earn more the workers may not concentrate on work during normal time and
thus the output during normal hours may also fall.
4. Reduced output and increased premium of overtime will bring about an increase cost of
production.
Question 4
State the circumstances in which time rate system of wage payment can be preferred in a
factory.
Answer
Circumstances in which time rate system of wage payment can be preferred:
In the following circumstances the time rate system of wage payment is preferred in a factory.
1. Persons whose services cannot be directly or tangibly measured, e.g., general helpers,
supervisory and clerical staff etc.
2. Workers engaged on highly skilled jobs or rendering skilled services, e.g., tool making,
inspection and testing.
3. Where the pace of output is independent of the operator, e.g., automatic chemical plants.
Question 5
Discuss briefly, how you will deal with casual workers and workers employed on outdoor work
in Cost Accounts.
Answer
Causal and outdoor workers: Casual workers (badli workers) are employed temporarily, for
a short duration to cope with sporadic increase in volume of work. If the permanent labour
force is not sufficient to cope effectively with a rush of work, additional labour (casual workers)
are employed to work for a short duration. Out door workers are those workers who do not
carry out their work in the factory premises. Such workers either carry out the assigned work
in their homes (e.g., knitwear, lamp shades) or at a site outside the factory.
Casual workers are engaged on a dally basis. Wages are paid to them either at the end of the
day’s work or after a periodic interval. Wages paid are charged as direct or indirect labour cost
depending on their identifiability with specific jobs, work orders, or department.
Rigid control should be exercised over the out-workers specially with regard to following:
1. Reconciliation of materials drawn/issued from the store with the output.
2. Ensuring the completion of output during the stipulated time so as to meet comfortably
the orders and contracts.
Question 6
It should be management’s endeavor to increase inventory turnover but to reduce labour
turnover. Expand and illustrate the idea contained in this statement.
Answer
Inventory turnover: It is a ratio of the value of materials consumed during a period to the
average value of inventory held during the period. A high inventory turnover indicates fast
movement of stock.
Labour turnover: It is defined as an index denoting change in the labour force for an
organization during a specified period. Labour turnover in excess of normal rate is termed as
(iii) Instead of fixed percentage of time saved, bonus is in proportion of time saved to time
allowed.
(iv) Protects employer against loose rate setting.
(v) Employer shares the benefit of increased output.
The Rowan Scheme is better than Halsey Scheme because of the following reasons:
(i) In Halsey Scheme, bonus is set at 50% of time saved. It does not serve as a strong
incentive. If workers over speed, the quality of the products deteriorates.
(ii) In Rowan Scheme, there is an automatic check on the earnings and thus over
speeding is arrested. In Halsey Scheme if two third of the time is saved, the worker
can double his earning per hour and in Rowan Scheme, this is not possible.
(iii) The earning per hour in Rowan Scheme is higher upto 50% of time saved and falls
thereafter whereas in Halsey Scheme the earnings per hour increases at a slow
speed and can be doubled.
Consider the following example in which the time allowed for performing the job is 30 hours
and the wage rate is ` 1.00 per hour. We will depict with the help of imaginary figures in the
following example, how the earnings per hour under Halsey and Rowan plan will vary.
Example:
Time Time Wages Bonus Total Wages Earnings/hr
Allowed taken Halsey Rowan Halsey Rowan Halsey Rowan
(1) (2) (3=2×` 1) (4)` (5) ` (7 = 3+4) ` (8 = 3+5) ` (9 = 7/2)` (10 = 8/2)`
30 30 30 - - 30.00 30.00 1.00 1.00
30 20 20 5.00 6.67 25.00 26.67 1.25 1.33
30 15 15 7.50 7.50 22.50 22.50 1.50 1.50
30 10 10 10.00 6.67 20.00 16.67 2.00 1.67
30 5 5 12.50 4.17 17.50 9.17 3.50 1.83
Question 8
Explain the meaning of and the reasons for Idle time and discuss its treatment in cost
accounting.
Answer
Idle time refers to the labour time paid for but not utilized on production. It, in fact, represents
the time for which wages are paid, but during which no output is given out by the workers. This
is the period during which workers remain idle.
Reasons for idle time: According to reasons, idle time can be classified into normal idle time
and abnormal idle time. Normal idle time is the time which cannot be avoided or reduced in the
normal course of business.
The main reasons for the occurrence of normal idle time are as follows:
1. Time taken by workers to travel the distance between the main gate of factory and the
place of their work.
2. Time lost between the finish of one job and starting of next job.
3. Time spent to overcome fatigue.
4. Time spent to meet their personal needs like taking lunch, tea etc.
The main reasons for the occurrence of abnormal idle time are:
1. Due to machine break downs, power failure, non-availability of raw materials, tools or
waiting for jobs due to defective planning.
2. Due to conscious management policy decision to stop work for some time.
3. In the case of seasonal goods producing units, it may not be possible for them to produce
evenly throughout the year. Such a factor too results in the generation of abnormal idle
time.
Treatment in Cost Accounting: Idle time may be normal or abnormal.
Normal idle time: It is inherent in any job situation and thus it cannot be eliminated or reduced.
For example:- time gap between the finishing of one job and the starting of another; time lost
due to fatigue etc.
The cost of normal idle time should be charged to the cost of production. This may be done by
inflating the labour rate. It may be transferred to factory overheads for absorption, by adopting
a factory overhead absorption rate.
Abnormal idle time: It is defined as the idle time which arises on account of abnormal causes;
e.g. strikes; lockouts; floods; major breakdown of machinery; fire etc. Such an idle time is
uncontrollable.
The cost of abnormal idle time due to any reason should be charged to Costing Profit & Loss
Account.
Question 9
Discuss the objectives of time keeping & time booking.
Answer
Objectives of time keeping and time booking: Time keeping has the following two objectives:
(i) Preparation of Payroll: Wage bills are prepared by the payroll department on the basis of
information provided by the time keeping department.
(ii) Computation of Cost: Labour cost of different jobs, departments or cost centers are
computed by costing department on the basis of information provided by the time
keeping department.
(iii) The rate setting department being newly established are liable to commit mistakes.
You are required to devise a suitable incentive scheme and demonstrate by an illustrative
numerical example how your scheme answers to all the requirements of the management.
Answer
Rowan scheme of premium bonus (variable sharing plan) is a suitable incentive scheme for
the workers of the factory. If this scheme is adopted, the entire gains due to time saved by a
worker will not pass to him.
Another feature of this scheme is that a worker cannot increase his earnings or bonus by
merely increasing its work speed. The reason for this is that the bonus under Rowan Scheme
is maximum when the time taken by a worker on a job is half of the time allowed. As this fact
is known to the workers, therefore they work at such a speed which helps them to maintain the
quality of output too.
Lastly, Rowan System provides a safeguard in case of any loose fixation of the standards by
the rate setting department. It may be observed from the following illustration that in the
Rowan Scheme the bonus paid will be low due to any loose fixation of standards. Workers
cannot take undue advantage of such a situation. The above three features of Rowan Plan
can be discussed with the help of the following illustration:
Illustration
(i) Time allowed = 4 hours
Time taken = 3 hours
Time Saved = 1 hour
Rate = ` 5 per hour.
Time taken
Bonus = × Time saved × Rate
Time allowed
3 hours
= × 1 hour × ` 5 = ` 3.75
4 hours
In the above illustration time saved is 1 hour and therefore total gain is ` 5. Out of
` 5/- according to Rowan Plain only ` 3.75 is given to the worker in the form of bonus. In other
words a worker is entitled for 75 percent of the time saved in the form of bonus.
(ii) The figures of bonus in the above illustration when the time taken is 2 hours and 1 hours
respectively are as below:
Time taken
Bonus = × Time saved × Rate
Time allowed
2 hours
= × 2 hours × ` 5 = ` 5
4 hours
1 hours
Bonus = × 3 hours × ` 5 = ` 3.75
4 hours
The above figures of bonus clearly show that when time taken is half of the time allowed, the
bonus is maximum. When the time is reduced from 2 to 4 hours, the bonus figures fell by ` 1.25.
Hence, it is quite apparent to workers that it is of no use to increase speed of work. These
features of Rowan Plan thus protect the quality of output.
(iii) If the rate setting department erroneously sets the time allowed as 10 hours instead of 4 hours,
in the above illustration, then the bonus paid will be as follows:
3 hours
Bonus = × 7 hours × ` 5 = ` 10.5
10 hours
The bonus paid for saving 7 hours thus is ` 10.50 which is approximately equal to the wages of 2
hours. In other words the bonus paid to the workers is low. Hence workers cannot take undue
advantage of any mistake committed by the rate setting department of the concern.
Question 12
What do you mean by time and motions study? Why is it so important to management?
Answer
Time and motions study: It is the study of time taken and motions (movements) performed by
workers while performing their jobs at the place of their work. Time and motion study has
played a significant role in controlling and reducing labour cost.
Time Study is concerned with the determination of standard time required by a person of
average ability to perform a job. Motion study, on the other hand, is concerned with
determining the proper method of performing a job so that there are no wasteful movements,
hiring the worker unnecessarily. However, both the studies are conducted simultaneously.
Since materials, tools, equipment and general arrangement of work, all have vital bearing on
the method and time required for its completion. Therefore, their study would be incomplete
and would not yield its full benefit without a proper consideration of these factors.
Time and motion study is important to management because of the following features:
1. Improved methods, layout, and design of work ensures effective use of men, material
and resources.
2. Unnecessary and wasteful methods are pin-pointed with a view to either improving them
or eliminating them altogether. This leads to reduction in the work content of an
operation, economy in human efforts and reduction of fatigue.
3. Highest possible level of efficiency is achieved in all respect.
4. Provides information for setting labour standards - a step towards labour cost control and
cost reduction.
5. Useful for fixing wage rates and introducing effective incentive scheme.
Question 13
Discuss the treatment of overtime premium in Cost accounting.
Answer
Treatment of Overtime Premium in Cost Accounting
• If overtime is resorted to at the desire of the customer, then overtime premium may be
charged to the job directly.
• If overtime is required to cope with general production programme or for meeting urgent
orders, the overtime premium should be treated as overhead cost of the particular
department or cost center, which works overtime.
• If overtime is worked in a department, due to the fault of another department, the
overtime premium should be charged to the latter department.
• Overtime worked on account of abnormal conditions such as flood, earthquake etc.,
should not be charged to cost but to costing P/L A/c.
Question 14
ZED Limited is working by employing 50 skilled workers it is considered the introduction of
incentive scheme-either Halsey scheme (with 50% bonus) or Rowan scheme of wage payment
for increasing the labour productivity to cope up the increasing demand for the product by
40%. It is believed that proposed incentive scheme could bring about an average 20%
increase over the present earnings of the workers; it could act as sufficient incentive for them
to produce more.
Because of assurance, the increase in productivity has been observed as revealed by the
figures for the month of April, 2004.
Hourly rate of wages (guaranteed) ` 30
Average time for producing one unit by one worker at the previous 1.975 hours
Performance (This may be taken as time allowed)
Number of working days in the month 24
Number of working hours per day of each worker 8
Actual production during the month 6,120 units
Required:
(i) Calculate the effective rate of earnings under the Halsey scheme and the Rowan
scheme.
(ii) Calculate the savings to the ZED Limited in terms of direct labour cost per piece.
(iii) Advise ZED Limited about the selection of the scheme to fulfill their assurance.
Answer
Working notes:
1. Computation of time saved (in hours) per month:
= (Standard production time of 6,120 units – Actual time taken by the workers)
= (6,120 units × 1.975 hours – 24 days × 8 hrs per day × 50 skilled workers)
= (12,087 hours – 9,600 hours)
= 2,487 hours
2. Computation of bonus for time saved hours under Halsey and Rowan schemes:
Time saved hours = 2,487 hours
(Refer to working note 1)
Wage rate per hour = ` 30
Bonus under Halsey Scheme = ½ × 2,487 hours × ` 30
(With 50% bonus) = ` 37,305
Time saved
Bonus under Rowan Scheme = × Time taken × Rate per hour
Time allowed
2,487 hours
= × 9,600 hours × ` 30
12,087
= ` 59,258.38
(i) Computation of effective rate of earnings under the Halsey and Rowan
schemes:
Total earnings (under Halsey scheme) = Time wages + Bonus
(Refer to working note 2)
= 24 days × 8 hours + 50 skilled
workers × ` 30+ ` 37,305
= ` 2,88,000 + ` 37,305 = ` 3,25,305
Total earnings (under Rowan scheme) = Time wages + Bonus
(Refer to working note 2)
= ` 2,88,000 + ` 59,258.38
= ` 3,47,258.38
(ii) Computation of wages of each worker under piece work earnings basis
Since each worker has been guaranteed at 75% of basic pay, if his earnings are less
than 50% of basic pay, therefore, workers A and C will be paid the wages as computed
viz., ` 228 and ` 315 respectively. The computed wage of worker B is ` 75 which is less
than 50% of basic pay viz., ` 100 therefore he would be paid 75% × ` 200 or ` 150.
Working Notes:
1. Piece rate / per unit
Product Standard time per Piece rate each Piece rate per unit
unit in minutes minute (`) (`)
(a) (b) (c) (d) = (b) × c
P 12 0.10 1.20
Q 18 0.10 1.80
R 30 0.10 3.00
2. Time allowed to each worker
Worker A = 21 units × 12 minutes + 36 units × 18 minutes+46 units × 30 minutes
= 2,280 minutes = 38 hours
Worker B = 25 units × 30 minutes = 750 minutes = 12.5 hours
Worker C = 60 units × 12 minutes + 135 units × 18 minutes
= 720 minutes + 2.430 minutes = 3,150 minutes = 52.50 hours
(iii) Computation of wages of each worker under Premium bonus basis (where each
worker receives bonus based on Rowan Scheme)
Workers Time Time Time Wage Earnings Bonus Total of
allowed taken saved rate/hour earning &
hours hours hours bonus
(Refer to
W. Note 2) (`) (`) (`) (`)
A 38.00 38.00 - 6.00 228.00 - 228.00
B 12.50 40.00 - 5.00 200.00 - 200.00
C 52.50 34.00 18.50 7.20 244.80 86.26 331.06
Question 16
What do you understand by labour turnover? How is it measured?
Answer
Labour turnover in an organization is the rate of change in the composition of labour force
during a specified period measured against a suitable index. The standard of usual labour
turnover in the industry or labour turnover rate for a past period may be taken as the index or
norm against which actual turnover rate should be compared.
Question 18
From the following information, calculate Labour turnover rate and Labour flux rate:
No. of workers as on 01.01.2000 = 7,600
No. of workers as on 31.12.2000 = 8,400
During the year, 80 workers left while 320 workers were discharged 1,500 workers were
recruited during the year of these, 300 workers were recruited because of exits and the rest
were recruited in accordance with expansion plans.
Answer
Labour turnover rate:
It comprises of computation of labour turnover by using following methods:
(i) Separation Method:
No. of wor ker s left + No. of wor ker s disch arg ed
= × 100
Average number of wor ker s
(80 + 320) 400
= x100 = x100 =5%
(7,600 + 8,400) ÷ 2 8,000
Question 19
Discuss the two types of cost associated with labour turnover.
Answer
Types of cost associated with labour turnover
Two types of costs which are associated with labour turnover are:
(i) Preventive costs: This includes costs incurred to keep the labour turnover at a low level
i.e., cost of medical schemes. If a company incurs high preventive costs, the rate of
labour turnover is usually low.
(ii) Replacement costs: These are the costs which arise due to high labour turnover. If men
leave soon after they acquire the necessary training and experience of work, additional
costs will have to be incurred on new workers, i.e., cost of advertising, recruitment,
selection, training and induction, extra cost also incurred due to abnormal breakage of
tools and machines, defectives, low output, accidents etc., caused due to the inefficiency
and inexperienced new workers.
It is obvious that a company will incur very high replacement costs if the rate of labour
turnover is high. Similarly, only adequate preventive costs can keep labour turnover at a
low level. Each company must, therefore, workout the optimum level of labour turnover
keeping in view its personnel policies and the behaviour of replacement costs and
preventive costs at various levels of labour turnover rates.
Question 20
The management of a company are worried about their increasing labour turnover in factory
and before analyzing the causes and taking remedial steps, they want to have idea of the
profit foregone as –a result of labour turnover in the last year.
Last year sales amounted to ` 83,03,300 and the profit-volume ratio was 20 per cent. Total
number of actual hours worked by the Direct Labour Force was 4.45 lakhs. As a result of the
delays by the Personnel Department in filling vacancies due to labour turnover, 1,00,000
potentially productive hours were lost. The actual direct labour hours includes 30,000 hours
attributable to training new recruits, out of which half of the hours were unproductive.
The costs incurred consequent on labour turnover revealed on analysis the following:
(`)
Settlement costs due to leaving 43,820
Recruitment costs 26,740
Selection costs 12,750
Training costs 30,490
Assuming that the potential production lost as a consequence of labour turnover could have
been sold at prevailing prices, find the profit foregone last year on account of labour turnover.
Answer
Working notes:
1. Actual productive hours
Total number of actual hours worked 4,45,000
Less: Unproductive training hours 15,000
Actual productive hours 4,30,000
2. Sales per productive hours (` )
(Total sales / Actual productive hours.) ` 19.31
(` 83,03,300 / 4,30,000 hours)
3. Potential productive hours lost 1,00,000
4. Sales foregone (` ) 19,31,000
(1,00,000 hours × ` 19.31)
5. Contribution foregone (` ) 3,86,200
Sales foregone × P/V Ratio
(` 19,31,000 × 20%)
Statement of Profit foregone last year
on account of Labour Turnover
Contribution foregone 3,86,200
(Refer to working note 5)
Settlement costs due to leaving 43,820
Recruitment costs 26,740
Selection costs 12,750
Training costs 30,490
Total profit foregone 5,00,000
Question 21
The finishing shop of a company employs 60 direct workers. Each worker is paid ` 400 as
wages per week of 40 hours. When necessary, overtime is worked up to a maximum of 15
hours per week per worker at time rate plus one-half as premium. The current output on an
average is 6 units per man hour which may be regarded as standard output. If bonus scheme
is introduced, it is expected that the output will increase to 8 units per man hour. The workers
will, if necessary, continue to work Overtime up to the specified limit although no premium on
incentives will be paid.
The company is considering introduction of either Halsey Scheme or Rowan Scheme of Wage
Incentive system. The budgeted weekly output is 19,200 units. The selling price is ` 11 per
unit and the direct Material Cost is ` 8 per unit. The variable overheads amount to ` 0.50 per
direct labour hour and the fixed overhead is ` 9,000 per week.
Prepare a Statement to show the effect on the Company’s weekly Profit of the proposal to
introduce (a) Halsey Scheme, and (b) Rowan Scheme.
Answer
Working notes:
1. Total available hours per week 2,400
(60 workers × 40 hours)
2. Total standard hours required to produce 19,200 units 3,200
(19,200 units/6 units per hour)
3. Total labour hours required after the 2,400
introduction of bonus scheme to produce 19,200 units
(19,200 units / 8 units per man hour)
4. Time saved in hours 800
(3,200 hours – 2,400 hours)
5. Wage rate per hour (` ) 10
(` 400/40 hours)
6. Bonus:
1
(i) Halsey Scheme = × Time saved × Wage rate per hour
2
1
= x 800 hours x ` 10 = ` 4,000
2
Time saved
(ii) Rowan Scheme = × Time taken × Wage rate per hour
Time allowed
800 hours
= × 2,400 hours × ` 10 = ` 6,000
3,200 hours
Statement showing the effect on the Company’s Weekly
present profit by the introduction of Halsey & Rowan schemes
Present Halsey Rowan
(`) (`) (`)
Sales revenue: (A) 2,11,200 2,11,200 2,11,200
(19,200 units × ` 11)
Direct material cost 1,53,600 1,53,600 1,53,600
(19,200 units × ` 8)
Direct wages 32,000 24,000 24,000
(Refer to working notes 2 & 3) (3,200 hrs. 2,400 hrs. (2,400 hrs.
× ` 10) × ` 10) × ` 10)
Overtime premium 4,000 - -
(800 hrs.
× ` 5)
Bonus - 4,000 6,000
(Refer to working notes 6 (i) & (ii))
Variable overheads 1,600 1,200 1,200
(3,200 hrs. (2,400 hrs. (2,400 hrs.
× 0.50 P) × 0.50 P) × 0.50 P)
Fixed overheads 9,000 9,000 9,000
Total cost : (B) 2,00,200 1,91,800 1,93,800
Profit: {(A)- (B)} 11,000 19,400 17,400
Question 22
The standard hours of job X is 100 hours. The job has been completed by Amar in 60 hours,
Akbar in 70 hours and Anthony in 95 hours.
The bonus system applicable to the job is as follows:-
Percentage of time saved to time allowed Bonus
Saving upto 10% 10% of time saved
From 11% to 20% 15% of time saved
From 21% to 40% 20% of time saved
From 41% to 100% 25% of time saved
The rate of pay is ` 1 per hour, Calculate the total earnings of each worker and also the rate
of earnings per hour.
Answer
Statement of total earnings and rate of earning per hour
Workers: Amar Akbar Anthony
Standard hours of Job 100 hours 100 hours 100 hours
Time taken on the Jobs (i) 60 hours 70 hours 95 hours
Time saved 40 hours 40 hours 30 hours 5 hours
Percentage of time saved to time allowed 40% 30% 5%
Bonus hours (ii) (See Note 1) 6.5 hours 4.5 hours 0.5 hours
Total hours to be paid [(i) + (ii)] 66.5 hours 74.5 hours 95.5 hours
Total earning @ ` 1/- p.h. ` 66.5 ` 74.5 ` 95.5
Rate of earning per hour (See Note 2) ` 1.1083 ` 1.0642 ` 1.005
Note:
1. Bonus hours as percentage of time saved:
Amar : 10 hours × 10% + 10 hours × 15%
+ 20 hours × 20% = 6.5 hours
Akbar : 10 hours × 10% + 10 hours × 15%
+ 10 hours × 20% = 4.5 hours
Anthony : 5 hours × 10% = 0.5 hours
2. Rate of Earning per hour:
Total earning
=
Total time taken on the job
` 66.5
Amar : = ` 1.1038
60 hours
` 74.5
Akbar : = ` 1.0642
70 hours
` 95.50
Anthony : = ` 1.005
95 hours
Question 23
Distinguish between Direct and Indirect labour.
Answer
Direct labour cost is the labour costs that is specifically incurred for or can be readily charged
to or identified with a specific job, contract, work-order or any other unit of cost.
Indirect labour costs are labour costs which cannot be readily identified with products or
services but are generally incurred in carrying out production activity.
The importance of the distinction lies in the fact that whereas direct labour cost can be
identified with and charged to the job, indirect labour costs cannot be so charged and are,
therefore, to be treated as part of the factory overheads to be included in the cost of
production.
Question 24
What do you understand by overtime premium? What is the effect of overtime payment on
productivity and cost? Discuss the treatment of overtime premium in cost accounts and
suggest a procedure for control of overtime work.
Answer
Work done beyond normal working hours is known as overtime work. Overtime payment is the
amount of wages paid for working beyond normal working hours. The rate for overtime work is
higher than the normal time rate; usually it is at double the normal rates. The extra amount so
paid over the normal rate is called overtime premium. Overtime work should be resorted to
only when it is extremely essential because it involves extra cost. The overtime payment
affects to increase the cost of production in the following ways:
(1) The premium paid is an extra payment in addition to the normal rate.
(2) The efficiency of operators during overtime work may fall and thus the output may be
lesser than normal output.
(3) In order to earn more the workers may not concentrate on work during normal time and
thus the output during normal hours may also fall.
(4) Reduced output and increased premium will bring about an increase in costs of
production.
Under cost accounting the overtime premium is treated as follows:
(i) If overtime is resorted to, at the desire of the customer, then overtime premium may
be charged to the job directly.
(ii) If overtime is due to a general pressure of work to increase the output, the premium
may be charged to general overheads.
(iii) If overtime is due to the negligence or delay, it may be charged to the department
concerned.
(iv) If it is due to circumstances beyond control, e.g. fire, strike etc. it may be charged to
Costing Profit and Loss Account.
It is necessary that proper Control over the overtime work should be exercised in order to
keep it to the minimum. The procedure based on following steps may be adopted for
such control.
(1) Watch on the output during normal hours should be maintained to ensure that
overtime is not granted when normal output is not obtained during the normal hours,
without any special reasons.
(2) Statement concerning overtime work be prepared along with justifications, at
appropriate places for putting up before competent authority.
(3) Prior sanction about overtime should be obtained from competent authority.
(4) Actual rate of output produced during the overtime period should be compared with
normal rate of output.
(5) Periodical reports on overtime wages should be sent to top management for taking
corrective action
(6) If possible an upper limit may be fixed for each category of worker in respect of
overtime.
Question 25
During audit of accounts of G. Company, your assistant found errors in the calculation of the
wages of factory workers and he wants you to verify his work.
He has extracted the following information:
(i) The contract provides that the minimum wage for a worker is his base rate. It is also paid
for downtimes i.e. the machine is under repair or the worker is without work. The
standard work week is 40 hours. For overtime production, workers are paid 150 per cent
of base rates.
(ii) Straight Piece Work-The worker is paid at the rate of 20 paise per piece.
(iii) Percentage Bonus Plan- Standard quantities of production per hour are established by
the engineering department. The workers’ average hourly production, determined from
his total hours worked and his production, is divided by the standard quantity of
production to determine his efficiency ratio. The efficiency ratio is then applied to his
base rate to determine his hourly earnings for the period.
(iv) Emerson Efficiency Plan- A minimum wages is paid for production upto 66-2/3% of
standard output or efficiency. When the workers production exceeds 66-2/3% of the
standard output, he is paid bonus as per the following table:
Efficiency Level Bonus
2
Upto 66 % Nil
3
2
Above 66 % to 79% 10%
3
80% - 99% 20%
100% - 125% 45%
Your assistant has produced the following schedule pertaining to certain workers of a weekly
pay roll:
Workers Wage Incentive Plan Total Down Units Standard Base Gross
Hours Time Produced Units Rate Wages as
Hours (`) per Book
(`)
Rajesh Straight piece work 40 5 400 - 1.80 85
Mohan* Straight piece work 46 - 455 - 1.80 95
John Straight piece work 44 - 425 - 1.80 85
Harish Percentage bonus 40 4 250 200 2.20 120
plan
Mahesh Emerson 40 - 240 300 2.10 93
Anil Emerson 40 - 600 500 2.00 126
(40 hours production)
Working notes:
1. Minimum wages = Total normal hours × rate per hour
= 40 hours × ` 1.80 = ` 72
Gross wages (computed) = No. of units × rate per unit
as per incentive plan = 400 units × ` 0.20 = ` 80
2. Minimum wages = Total normal hours × rate per hour
+ Overtime hours × Overtime rate per hour
= 40 hours × ` 1.80 + 6 hours × ` 2.70
= ` 72 + ` 16.20 = ` 88.20
Gross wages (computed)
as per incentive plan = 455 units × ` 0.20 = ` 91.00
3. Minimum wages = 40 hours × ` 1.80 + 4 hours × ` 2.70
= ` 72 + ` 10.80 = ` 82.80
Gross wages (computed) = 425 units × ` 0.20 = ` 85
as per incentive plan
4. Minimum wages = 40 hours × ` 2.20 = ` 88
Actual production per hour
Efficiency of worker = × 100
Standard production per hour
(250 units/ 40 hours)
= × 100 = 125%
(200 units/40 hours)
Hourly rate = Rate per hour × Efficiency of worker
= ` 2.20 × 125% = ` 2.75
Gross wages (computed)
as per of bonus plan = 40 hours × ` 2.75 = ` 110/-
5. Minimum wages = 40 hours × ` 2.10 = ` 84
(240 units/ 40 hours)
Efficiency of worker = × 100 = 80%
(300 units/40 hours)
Bonus (as per Emerson’s plan) = Total minimum wages × Bonus percentage
= ` 84 × 20% = ` 16.80
Answer
Table showing Labour Cost per Article
Method of Payment Hours Weekly Number of articles labour cost
worked earnings produced per article
Existing time rate 49 ` 8,425.00 120 ` 70.21
Straight piece rate system 40 ` 8,640.00 135 ` 64.00
Rowan Premium System 40 ` 9,007.41 135 ` 66.72
Halsey Premium System 40 ` 8,600.00 135 ` 63.70
Working Notes:
Existing time rate
Weekly wages 40 hrs @ ` 160/hr = ` 6,400
9 hrs @ ` 225/hr = ` 2,025
` 8,425
Piece Rate System
Basic time: 5 hour for 15 articles.
Cost of 15 articles at hourly rate of ` 160/hr = ` 800
Add 20% = ` 160
` 960
∴ Rate per article = ` 960 / 15
= ` 64
Earnings for the week = 135 articles × ` 64
= ` 8,640.
Rowan Premium System
Basic Time : 5 hours for 15 articles
Add : 50% to time
7.5 hours for 15 articles
Or 30 minutes per article
∴ Time allowed for 135 articles = 67.5 hours
Actual time taken for 135 articles = 40 hours
⎡ TA − HW ⎤
∴ Earnings = (HW×RH) + ⎢ × HW × RH⎥
⎣ TA ⎦
⎛ 67.5 − 40 ⎞
= (40 hrs × ` 160) + ⎜ × 40 × ` 160 ⎟ = ` 9007.41
⎝ 67.5 ⎠
600
= × 100 = 6.82%.
8,800
Average Number of workers separated during the year
=Number of workers left the company during the year + Number of workers discharged
during the year
= 500 + 100 = 600.
8,000 + 9,600
Average number of workers on rolls during the year = = 8,800
2
2. Replacement Method:
Number of workers replaced during the year
Labour turnover rate = × 100
Average number of workers on rolls during the year
700
= × 100 = 7.95%.
8,800
3. Flux Method:
Number of workers separated + Number of workers replaced
Labour turnover rate = × 100
Average number of workers on rolls during the year
600 + 700
= × 100 = 14.77%.
8,800
Question 31
Using Taylor’s differential piece rate system, find the earning of A from the following
particulars:
Standard time per piece 12 minutes
Normal rate per hour (in a 8 hours day) ` 20
A produced 37 Units
Answer
⎛ 8 × 60 ⎞
Standard output per day ⎜ ⎟ = 40 units
⎝ 12 ⎠
Actual output = 37 units
37
Efficiency percentage × 100 = 92.5%
40
Under this method lower rate is 83% of the normal piece rate and is applicable if efficiency of
worker is below 100%.
20
Earning rate per unit = 83% of or 3.32 per unit
5*
Earning = 37 × 3.32 = ` 122.84
60 minutes
* In one hour, production will be = = 5 units
standard time per peice, i.e. 12 minutes
Question 32
Enumerate the various methods of Time booking
Answer
The various methods of time booking are:
(a) Job ticket.
(b) Combined time and job ticket.
(c) Daily time sheet.
(d) Piece work card.
(e) Clock card.
Question 33
Enumerate the remedial steps to be taken to minimize the labour turnover.
Answer
The following steps are useful for minimizing labour turnover:
(a) Exit interview: An interview be arranged with each outgoing employee to ascertain the
reasons of his leaving the organization.
(b) Job analysis and evaluation: to ascertain the requirement of each job.
(c) Organisation should make use of a scientific system of recruitment, placement and
promotion for employees.
(d) Organisation should create healthy atmosphere, providing education, medical and
housing facilities for workers.
(e) Committee for settling workers grievances.
Question 34
Standard output in 10 hours is 240 units; actual output in 10 hours is 264 units. Wages rate is
` 10 per hour. Calculate the amount of bonus and total wages under Emerson Plan.
Answer
264
Efficiency percentage = × 100 = 110%
240
As per Emerson plan, in case of above 100% efficiency bonus of 20% of basic wages plus 1%
for each 1% increase in efficiency is admissible.
So, new bonus percentage = 20 + (110 – 100) = 30
30
Total Bonus = (hours worked × rate per hour)
100
30
= × 10 × 10 = ` 30
100
Total wages = ` (10 × 10) + 30 = ` 130.
Question 35
Describe briefly, how wages may be calculated under the following systems:
(i) Gantt task and bonus system
(ii) Emerson’s efficiency system
(iii) Rowan system
(iv) Halsey system
(v) Barth system.
Answer
(i) Gantt task and bonus system: As per this system a higher standard is set and payment
is made at time rate to a worker for production below the standard. If the standards are
achieved or exceeded, the payment is made at a higher piece rate. The piece rate fixed
also includes an element of bonus to the extent of 20%. Bonus is calculated over the
time rate.
(ii) Emerson’s Efficiency System: Under this system wages may be calculated as below:
Performance Wages
Below 66⅔% efficiency − Time rate without any bonus
66⅔% - 100% efficiency − Bonus varies between 1% to 20%*
Above 100% efficiency − Bonus of 20% of basic wages plus
1% for every 1% increase in efficiency.
*At 100% efficiency the bonus percentage will be 20%.
(iii) Rowan System: As per this system standard time allowance is fixed for the performance
of a job and bonus is paid if time is saved.
time saved
Wages under Rowan System = (Time taken × rate per unit of time ) +
time allowed
× time taken × rate per unit of time
(iv) Halsey System: Under this system a standard time is fixed for each job. If there is no
saving on this standard time allowance, the worker is paid only his day rate.
Wages under Halsey System = Time taken × Time rate + (50% of time saved × time rate)
(v) Barth System:
Earnings under Barth System = Hourly rate × Standard hours × Hours worked
This is particularly suitable for trainees and beginners and also for unskilled workers
Question 36
Two workmen, A and B, produce the same product using the same material. A is paid bonus
according to Halsey plan, while B is paid bonus according to Rowan plan. The time allowed to
manufacture the product is 100 hours. A has taken 60 hours and B has taken 80 hours to
complete the product. The normal hourly rate of wages of workman A is ` 24 per hour. The
total earnings of both the workers are same. Calculate normal hourly rate of wages of
workman B.
Answer
A B
Time Allowed (Hrs.) 100 100
Time Taken (Hrs.) 60 80
Time Saved (Hrs.) 40 20
Let the rate of wages of the worker B is ` x per hour
Normal Wages 1440 80x
(Time taken × Hourly rate of wages) (60×24)
Bonus 480 16x
⎛ 20 ⎞
(1/2 × 40 × 24) ⎜ ⎟ × (80 × x)
⎝ 100 ⎠
1920 96x
According to the problem,
Total earnings of A = Total earnings of B
1920 = 96x
1920
x = = ` 20
96
∴ Hourly rate of wages of the worker is ` 20 per hour.
Alternative Solution:
In case of worker B, in place of x, it can be written as ‘80x hourly rate’.
Hence final equation will be
96 x hourly rate = 1920
1920
Hourly rate of B = = ` 20
96
Question 37
Discuss accounting treatment of idle capacity costs in cost accounting.
Answer
Treatment of Idle Capacity Cost
(a) If idle capacity is due to unavoidable reasons such as repairs & maintenance, change
over of job etc., a supplementary overhead rate may be used to recover the idle capacity
cost. In this case, the costs are charged to production capacity utilized.
(b) If idle capacity cost is due to avoidable reasons such as faulty planning, power failure
etc, the cost should be charged to P/L A/c.
(c) If idle capacity is due to seasonal factors, then the cost should be charged to cost of
production by inflating overhead rates.
Question 38
Standard Time for a job is 90 hours. The hourly rate of guaranteed wages is ` 50. Because of
the saving in time a worker A gets an effective hourly rate of wages of ` 60 under Rowan
premium bonus system. For the same saving in time, calculate the hourly rate of wages a
worker B will get under Halsey premium bonus system assuring 40% to worker.
Answer
Increase in Hourly Rate of Wages (Rowan Plan) is (` 60 – ` 50) = ` 10
This is Equal to
Time Saved
× Hourly rate
S tan dard Time
Time Saved
Or 10 = × 50
S tan dard Time
Time Saved
Or × 50 = 10
90
900
Time Saved = = 18 Hours
50
Time Taken = (90 – 18) = 72 Hours
Effective Hourly Rate under Halsey System
Time Saved = 18 Hours
Bonus @ 40% = 18 × 40% × 50 = ` 360
Total Wages = (50 × 72 + 360) = 3,960
Effective Hourly Rate = 3,960 ÷ 72 Hours = ` 55
Question 39
You are given the following information of a worker:
(i) Name of worker : ‘X’
(ii) Ticket No. : 002
(iii) Work started : 1-4-11 at 8 a.m.
(iv) Work finished : 5-4-11 at 12 noon
(v) Work allotted : Production of 2,160 units
(vi) Work done and approved : 2000 units
(vii) Time and units allowed : 40 units per hour
(viii) Wage rate : ` 25 per hour
(ix) Bonus : 40% of time saved
(x) Worker X worked 9 hours a day.
You are required to calculate the remuneration of the worker on the following basis:
(i) Halsey plan and
(ii) Rowan plan
Answer
No. of units produced and approved = 2,000
Standard time = 40 units per hour
Hourly Wage Rate = ` 25
Time allowed = 40 units per hour
2,000
Time allowed for 2,000 units = 50 hours
40
(i) Calculation of Remuneration under Halsey Plan:
Standard time allowed for 2,000 units : 50 hours
Actual time taken for 2,000 units : 40 hours
Time saved 10 hours
Basic wages for time taken 40 hours @ ` 25 = ` 1,000
40
Bonus: 40% of time saved ×10× 25 =` 100
100
Total ` 1,100
(ii) Calculation of Remuneration Under Rowan Plan:
Wages for time taken 40 hours @ ` 25 = ` 1,000
Time saved
Bonus = x (Time Taken x Hourly Rate)
Time allowed
40 × 10 × 25
= = ` 200
50
Total ` 1,200
Question 40
Enumerate the causes of labour turnover.
Answer
Causes of Labour Turnover: The main causes of labour turnover in an organisation/ industry
can be broadly classified under the following three heads:
(a) Personal Causes;
(b) Unavoidable Causes; and
(c) Avoidable Causes.
Personal causes are those which induce or compel workers to leave their jobs; such causes
include the following :
(i) Change of jobs for betterment.
(ii) Premature retirement due to ill health or old age.
(iii) Domestic problems and family responsibilities.
(iv) Discontent over the jobs and working environment.
Unavoidable causes are those under which it becomes obligatory on the part of management
to ask one or more of their employees to leave the organisation; such causes are summed up
as listed below:
(i) Seasonal nature of the business;
(ii) Shortage of raw material, power, slack market for the product etc.;
(iii) Change in the plant location;
(iv) Disability, making a worker unfit for work;
(v) Disciplinary measures;
(vi) Marriage (generally in the case of women).
Avoidable causes are those which require the attention of management on a continuous basis
so as to keep the labour turnover ratio as low as possible. The main causes under this case
are indicated below
(i) Dissatisfaction with job, remuneration, hours of work, working conditions, etc.,
(ii) Strained relationship with management, supervisors or fellow workers;
(iii) Lack of training facilities and promotional avenues;
(iv) Lack of recreational and medical facilities;
(v) Low wages and allowances.
Question 41
X executes a piece of work in 120 hours as against 150 hours allowed to him. His hourly rate
is ` 10 and he gets a dearness allowance @ ` 30 per day of 8 hours worked in addition to his
wages. You are required to calculate total wages received by X under the following incentive
schemes:
(i) Rowan Premium Plan, and
(ii) Emerson's Efficiency Plan
Answer
(i) Rowan Premium Plan `
Normal wages (10 x 120) 1,200
D.A. for 15 days (30 x 15 ) 450
Bonus :
120×30
Bonus hours = = 24 Hours
150
Bonus (24 x 10) 240
Differential piece rate: 80% of piece rate when output below normal and 120% of piece rate
when output above normal.
Under Halsey scheme, worker gets a bonus equal to 50% of Wages of time saved.
Calculate:
(i) Earning of workers under Halsey’s and Rowan’s premium scheme.
(ii) Earning of workers under Taylor’s differential piece rate system and Emerson’s efficiency
plan.
Answer
Calculation of earnings for workers under different incentive plans:
(i) Halsey’s Premium Plan: Worker – A Worker – B
Actual time taken 40 hours 40 hours
Standard time for actual 176 Pcs × 15 Min. 140 Pcs × 15 Min.
Production 60 Min.
60 Min.
= 35 hours
= 44 hours
Minimum Wages 40 hours x ` 40 40 hours x ` 40
= ` 1600 = ` 1600
Question 43
Accountant of your company had computed labour turnover rates for the quarter ended 30th
September, 2012 as 14%, 8% and 6% under Flux method, Replacement method and
Separation method respectively. If the number of workers replaced during 2nd quarter of the
financial year 2012-13 is 36, find the following:
(i) The number of workers recruited and joined; and
(ii) The number of workers left and discharged.
Answer
No. of wor ker s replaced
Labour Turnover Rate (Replacement method) =
Average No. of wor ker s
8 36
or, =
100 Average No. of wor ker s
or, Average No. of workers = 450
No. of workers separated
Labour Turnover Rate (Separation method) =
Average No. of workers
6 No. of workers separated
or, =
100 450
or, No. of workers separated = 27
No. of Separations + No. of accession (Joinings)
Labour Turnover Rate (Flux Method) =
Average No. of wor ker s
14 27 + No. of accessions (Joinings)
or, =
100 450
or, 100 (27 + No. of Accessions) = 6300
or, No. of Accessions = 36
(i) The No. of workers recruited and Joined = 36
(ii) The No. of workers left and discharged = 27
Question 44
Calculate the earnings of A and B from the following particulars for a month and allocate the
labour cost to each job X, Y and Z:
A B
(i) Basic Wages ` 100 160
Activity Ratio
i.e. Efficiency Ratio =
Capacity Ratio
Std.hours for actualproduction Budgeted hours
= x
Budgeted hours Actualhours worked
Std.hours for actualproduction
= x100
Actualhours worked
Activity Ratio = Capacity Ratio × Efficiency Ratio
Question 46
An article passes through five hand operations as follows:
Operation No. Time per article Grade of worker Wage rate per hour
(`)
1 15 minutes A 0.65
2 25 minutes B 0.50
3 10 minutes C 0.40
4 30 minutes D 0.35
5 20 minutes E 0.30
The factory works 40 hours a week and the production target is 600 dozens per week.
Prepare a statement showing for each operation and in total the number of operations
required, the labour cost per dozen and the total labour cost per week to produce the total
targeted output.
Answer
Statement of number of operators required and labour cost per dozen and per week.
Production target is 600 dozens per week.
Operation No.
Particulars Total
1 2 3 4 5
15 25 10 30 20
Time per article (minutes)
EXERCISE
1 Distinguish between Idle Time and Idle Facilities. How are they treated in Cost Accounts? Develop a system
of control for Idle Time in a factory.
Answer Refer to ‘Chapter No. 3 i.e. Labour’ of Study Material
2 What do you understand by Labour Turnover? How is it measured? What are its causes? What are the
remedial steps you would suggest to minimize its occurrence?
Labour Utilisation Statement
Department……………………….... Week
Ending…………………………….
Standard Time Causes
Sl. Category Number Output Time Standard Idle Break- Power Lack of Lack of Set Ineffi- Etc.
1 2 3 4 5 6 7 8 9 10 11 12 13 14
labour hours included 30,000 hours attributable to training new recruits, out of which half of the hours were
unproductive. The costs incurred consequent on labour turnover reveled on analysis the following:
`
Settlement cost due to leaving 27,420
Recruitment costs 18,725
Selection costs 12,750
Training costs 16,105
Assuming that the potential production lost due to labour turnover could have been sold at prevailing prices,
ascertain the profit foregone/lost last year on account of labour turnover.
Answer Total profit foregone (` ) 3,75,000
23 Calculate the earnings of workers A, B and C under Straight Piece Rate System and Merrick’s Multiple
Piece Rate System from the following particulars:
Normal Rate per Hour ` 5.40
Standard Time per Unit 1 Minute
Output per day is as follows:
Worker A – 390 Units
Worker B – 450 Units
Worker C– 600 Units
Working hours per day are 8.
Answer Earnings of Workers Under Straight Piece Rate System
Worker A = ` 35.10
Worker B = ` 40.50
Worker C = ` 54.00
Earnings of Workers Under Merrick’s Multiple Piece Rate System
A B C
Earnings (` ) 35.10 44.55 64.80
24 Calculate the earnings of a worker under (i) Halsey Plan and (ii) Rowan Plan from the following particulars:
(1) Hourly rate of wages guaranteed 0.50 paise per hour.
(2) Standard time for producing one dozen articles – 3 hours.
(3) Actual time taken by the worker to produce 20 dozen articles – 48 hours.
Answer (i) Earnings of a Worker under Halsey Plan ` 27
(ii) Earnings of a worker under Rowan Plan ` 28.80
25 Calculate the number of hours worked as overtime by the following workers in a week:
Ram Shyam
Monday 8 8
Tuesday 7 9
Wednesday 4.5 8
Thursday 8 7
Friday 10 9
Saturday 9 9
46.5 50
Answer Ram 1 hour; Shyam 2 hours
26 Three workers A, B and C are put on a common task for which the total remuneration is ` 150. A works for
40 hours, B works for 60 hours and C works for 44 hours on the job. The hourly rate is Re. 0.75 of A per
hour, B gets Re. 0.80 per hour while C’s remuneration is Re. 0.50 per hour. What should each man get ?
Answer A. ` 45; B. ` 75; C. ` 33.
27 A worker is paid @ 50 paise per hour plus a dearness allowance of ` 60 per month. The provident fund
contribution both by the employee and the worker is 6¼% each. The worker is entitled to 15 days leave with
full wages. His normal working per month is 25 days of 8 hours each. Calculate
(a) the wages per hour for costing purposes; and
(b) the amount to be paid to him for a week in which he puts in 52 hours of work.
Answer ` 0.895 per hour for costing purposes, ` 42.40
(amount to be paid, deducting ` 2.40 for PF).
28 The following particulars are available to you in respect of a worker:
Job No. Time Allowed Time Taken
1844 26 hours 20 hours
1826 30 hours 20 hours
Idle time (waiting) 8 hours 48 hours
The basic rate is ` 2 per day of 8 hours in addition there is a dearness allowance of ` 12 per week of 48
hours. Calculate the wage of the worker on (1) Time Basis (2) Piece Rate Basis (3) Halsey Plan Basis and
(4) Rowan Plan Basis.
Answer (1) ` 24; (2) ` 28; (3) ` 26; (4) ` 26-86.
29 A worker is paid 10% bonus on the hourly rate if he completes his work in the time allotted for it and a
further 1% on hourly rate for each 1% in excess of 100% efficiency. His hourly rate is ` 5 per hour and he
completed a job in 45 hours whereas the time allowed for it was 50 hours. Ascertain the wages earned by
this worker.
Answer ` 270
30 From the following data, calculate the labour turnover rate by applying :
(i) Separation method
(ii) Accession method
(iii) Flux method