BOQ Museum Tsunami 2021 Terbaru

This document is a bill of quantities (BOQ) for the revitalization of the Aceh Tsunami Museum located in Banda Aceh, Aceh. It includes items for video mapping of tsunami waves, multimedia displays to showcase potential tourism areas of Aceh and information about tsunamis. Equipment listed includes projectors, screens, computers and other hardware needed to create the interactive exhibits. The total cost of the project is not included in the summary.

Uploaded by

alfyn anestesya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views20 pages

BOQ Museum Tsunami 2021 Terbaru

This document is a bill of quantities (BOQ) for the revitalization of the Aceh Tsunami Museum located in Banda Aceh, Aceh. It includes items for video mapping of tsunami waves, multimedia displays to showcase potential tourism areas of Aceh and information about tsunamis. Equipment listed includes projectors, screens, computers and other hardware needed to create the interactive exhibits. The total cost of the project is not included in the summary.

Uploaded by

alfyn anestesya
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

REKAPITULASI

BILL OF QUANTITY (BOQ)

Nama Pekerjaan REVITALISASI MUSEUM TSUNAMI ACEH


:
Lokasi : Banda Aceh
Tahun Anggaran : 2021

NO ITEM PEKERJAAN JUMLAH HARGA


(Rp)
1 2 3

#REF! PEKERJAAN REHAB Rp -


A. PEKERJAAN PERSIAPAN Rp -
B. REHAB TOILET UMUM LANTAI 2 Rp -
C. REHAB TOILET UMUM LANTAI 3 Rp -
D. PEMBUATAN TOILET VIP LANTAI 2 Rp -
E. PEMBUATAN INTERIOR RUANG STUDI LANTAI 3 Rp -
F. PEMBUATAN TOILET KANTIN / MUSHALLA Rp -
H. PEKERJAAN REHAB LANTAI Rp -

B PEKERJAAN PENGECATAN Rp -
A. PENGECATAN INTERIOR Rp -
B. PENGECATAN EXTERIOR Rp -

C PEKERJAAN MULTIMEDIA Rp -
A. VIDEO MAPPING GELOMBANG TSUNAMI R. PAMER TETAP Rp -

TOTAL Rp -
PPN 10% Rp -
JUMLAH Rp -
DIBULATKAN Rp -

TERBILANG :

………………., ………………. 2021


PT/CV. …………………….

………………………..
DIREKTUR
Nama Pekerjaan : REVITALISASI MUSEUM TSUNAMI
Lokasi : Banda Aceh
Tahun Anggaran : 2018

No Uraian Item Spesifikasi Kuantitas Harga Satuan Jumlah Harga

1 2 3 4 5 6
HARDWARE
1 VIDEO MAPPING GELOMBANG TSUNAMI
1 Video Mapping file konten berdurasi 6 hingga 8 menit 1,00 pack 0
2 Projector 2,00 unit 0
15,000 Lumens
SXGA+ (1400 x 1050)
H/V Keystone
Quick Corner
Throw Ratio 1,62-2.65
(wide-tele),

Projection Technology
RGB liquid crystal
shutter projection
system (3LCD)
LCD Size: 1.06″ (D10)
Laser Lightsource :
20,000 / 30,000 hours
3 Projector Lens 2,00 unit 0
• Zoom Ratio: 1.0 -
1.2x
• Throw Ratio (4.3):
0.66 - .80
15 • Throw Ratio
(16:10): 0.65 - 0.78
• Throw Ratio
(16:10): 0.48 - 0.57,
for L1500 and L1505

4 Custom PC, Keyboard + mouse, Monitor 22" 1,00 unit 0


5 Operating System Windows 10 Original 1,00 unit 0
6 Mapping Software Resolume Arena 6 Original 1,00 unit 0
7 Datapath 1,00 unit 0
8 HDBaseT 1,00 unit 0
9 UPS 1,00 unit 0
10 Audio System 1,00 pack 0
11 Custom Bracket Projector 1,00 unit 0
12 Support Cable 1,00 pack 0
subtotal Rp -

2 VIDEO PARIWISATA POTENSI DAERAH ACEH


Video 1 pack Rp -
65-inch Ultra HD
monitor with a light
output of 350 cd/m².
The display has a
4K UHD resolution,
which results in razor-
Monitor LED Display 65" sharp images. Ideal 6 unit Rp -
display for
presentation or digital
signage purpose, 4K
Ultra HD resolution,
16/7 use

Media Player Raspberry Pi3 6 unit Rp -


USB Disk 16GB 6 unit Rp -
Custom Bracket Monitor Custom 6 unit Rp -
Support Cable 1 pack Rp -
subtotal Rp -

3 VIDEO INFORMASI TENTANG TSUNAMI


Video 1 pack Rp -
65-inch Ultra HD
monitor with a light
output of 350 cd/m².
The display has a
4K UHD resolution,
which results in razor-
Monitor LED Display 65" sharp images. Ideal 3 unit Rp -
display for
presentation or digital
signage purpose, 4K
Ultra HD resolution,
16/7 use

Media Player Raspberry Pi3 3 unit Rp -


USB Disk 16GB 3 unit Rp -
UPS 2000VA 1 unit Rp -
Custom Bracket Monitor 3 unit Rp -
Support Cable 1 pack Rp -
subtotal Rp -

4 VIDEO INFORMASI MASA REHAB REKON


Video 1 pack Rp -
Interactive 1 pack Rp -
55'' UHD
Content
Management/Group
Management,
SuperSign Control,
Monitor LED Display 55" SNMP, Wake-up On 12 unit Rp -
Lan, Crestron
Connected®
(Network Based
Control)

Layar: TFT 8.0 inches


Resolusi Layar: 1280 x
800 pixels
Chipset: Qualcomm
SDM429 Snapdragon
429 (12 nm)
CPU: Quad-core 2.0
GHz Cortex-A53
GPU: Adreno 504
PC Tablet 8" Memori Internal: 32 12 unit Rp -
GB, 2 GB RAM
Memori Eksternal:
microSDXC (dedicated
slot)
Kamera Belakang: 8
MP
Kamera Depan: 2 MP
Baterai: Li-Po 5100
mAh
Media Player Raspberry Pi3 12 unit Rp -
USB Disk 16GB 12 unit Rp -
UPS 2000VA 1 unit Rp -
Custom Bracket Monitor 12 unit Rp -
Custom Base Tablet 12 unit Rp -
Support Cable 1 pack Rp -
subtotal Rp -

5 PETA DUNIA DAN EFEK TSUNAMI PADA WILAYAH TERDAMPAK


Video 1 pack Rp -
Projector 15,000 Lumens 1 unit Rp -
SXGA+ (1400 x 1050)
H/V Keystone
Quick Corner
Throw Ratio 1,62-2.65
(wide-tele),

Projection Technology
RGB liquid crystal
shutter projection
system (3LCD)
LCD Size: 1.06″ (D10)
Laser Lightsource :
20,000 / 30,000 hours

• Zoom Ratio: 1.0 -


1.2x
• Throw Ratio (4.3):
0.66 - .80
Projector Lens • Throw Ratio 1 unit Rp -
(16:10): 0.65 - 0.78
• Throw Ratio
(16:10): 0.48 - 0.57,
for L1500 and L1505

PC
Monitor 22" 1
Custom PC unit Rp -
Keyboard + Mouse
wireless
Operating System Windows 10 pro 1 unit Rp -
Mapping Software Resolume Arena 6 1 unit Rp -
HDBaseT 1 unit Rp -
UPS 3000VA 1 unit Rp -
Audio System Active Speaker 1 pack Rp -
Custom Bracket Projector 1 unit Rp -
Construction Fasad 3x3m 1 pack Rp -
Support Cable 1 pack Rp -
subtotal Rp -
6 VIDEO INFORMASI PERUBAHAN PASCA TSUNAMI
Video 1 pack Rp -
Interactive 1 pack Rp -
55'' UHD
Content
Management/Group
Management,
SuperSign Control,
Monitor LED Display 55" SNMP, Wake-up On 5 unit Rp -
Lan, Crestron
Connected®
(Network Based
Control)

Layar: TFT 8.0 inches


Resolusi Layar: 1280 x
800 pixels
Chipset: Qualcomm
SDM429 Snapdragon
429 (12 nm)
CPU: Quad-core 2.0
GHz Cortex-A53
GPU: Adreno 504
PC Tablet 8" Memori Internal: 32 5 unit Rp -
GB, 2 GB RAM
Memori Eksternal:
microSDXC (dedicated
slot)
Kamera Belakang: 8
MP
Kamera Depan: 2 MP
Baterai: Li-Po 5100
mAh
Media Player Raspberry Pi3 5 unit Rp -
UPS 2000VA 1 unit Rp -
Custom Bracket Monitor 5 unit Rp -
Custom Base Tablet 5 unit Rp -
Support Cable 1 pack Rp -
subtotal Rp -

7 VIDEO INFORMASI PERUBAHAN PASCA TSUNAMI


Video 1 pack Rp -
WUXGA, 4400 lumens,
Speaker 16W,
Geomatric Correction,
1 Comp IN/OUT, 2
HDMI (1 Common
MHL), DVI-D, 2 Audio
IN/1 Audio OUT, 2
Projector 2 unit Rp -
USB Type-A/1 USB
Type-B, RS-232C, LAN,
Built-In Wifi, WiDi
(Miracast), 2
Interactive Pen,
Setting Plate, Control
Pad
PC 1070
Custom PC Monitor 22" Custom 2 unit Rp -
Keyboard + Mouse wireless
Operating System Windows 10 pro 2 unit Rp -
Mapping Software Resolume Arena 6 2 unit Rp -
UPS 3000VA 1 unit Rp -
Support Cable 1 pack Rp -
subtotal Rp -

8 VIDEO MAPPING PERUBAHAN PASCA TSUNAMI


Video 1 pack Rp -
WUXGA, 4400 lumens,
Speaker 16W,
Geomatric Correction,
1 Comp IN/OUT, 2
HDMI (1 Common
MHL), DVI-D, 2 Audio
IN/1 Audio OUT, 2
Projector 1 unit Rp -
USB Type-A/1 USB
Type-B, RS-232C, LAN,
Built-In Wifi, WiDi
(Miracast), 2
Interactive Pen,
Setting Plate, Control
Pad
PC
Custom PC Monitor 22" Custom 1 unit Rp -
Keyboard + Mouse wireless
Operating System Windows 10 pro 1 unit Rp -
Mapping Software Resolume Arena 6 1 unit Rp -
HDBaseT 1 unit Rp -
UPS 3000VA 1 unit Rp -
Audio System Active Speaker 1 pack Rp -
Custom Bracket Projector 1 unit Rp -
Support Cable 1 pack Rp -
subtotal Rp -
9 ALLIGNMENT MULTIMEDIA AND LIGHTING SETTING
VIDEO MAPPING GELOMBANG TSUNAMI 1 pack Rp -
VIDEO PARIWISATA POTENSI DAERAH ACEH 1 pack Rp -
VIDEO INFORMASI TENTANG TSUNAMI 1 pack Rp -
VIDEO INFORMASI MASA REHAB REKON 1 pack Rp -
PETA DUNIA DAN EFEK TSUNAMI PADA WILAYAH TERDAMPAK 1 pack Rp -
VIDEO INFORMASI PERUBAHAN PASCA TSUNAMI 1 pack Rp -
VIDEO MAPPING PERUBAHAN PASCA TSUNAMI 1 pack Rp -
subtotal Rp -
TOTAL Rp -
DAFTAR KUANTITAS DAN HARGA

Nama Pekerjaan : PEKERJAAN PENGECATAN


Lokasi : Banda Aceh
Tahun Anggaran : 2021

Harga Satuan Jumlah Harga


No. Uraian Kegiatan Volume Satuan Analisa
(Rp) (Rp)

1 2 3 4 5 6 7
A PENGECATAN INTERIOR
1 LANTAI 1
-Pengecatan Dinding Ruang Penitipan 189,91 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding Lobby 562,40 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding tangga Akses Karyawan 194,35 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding Peta Provinsi Aceh 296,85 m² Taksir - Rp -

-Pengecatan Plafon Ruang Penitipan 43,27 m² AHSP PU A.4.7.1.11 - Rp -


-Pengecatan Plafon Lobby 82,63 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon Lobby (Void Lantai 3) 151,37 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Ceiling Beton R. Tangga Akses Publik 34,78 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Ceiling Beton R. Tangga Akses Karyawan 46,75 m² AHSP PU A.4.7.1.11 - Rp -

2 LANTAI 2
-Pengecatan Dinding Area Lounge 249,59 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Audio Visual 112,21 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Tangga Akses Publik 123,10 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Tangga Akses Karyawan 114,65 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Manajemen 141,40 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Pamer Temporer 183,32 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding Selasar 526,12 m² AHSP PU A.4.7.1.11 - Rp -

-Pengecatan Plafon Area Lounge 165,50 m² AHSP PU A.4.7.1.11 - Rp -


-Pengecatan Plafon R. Audio Visual 63,74 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon R. Manajemen 54,26 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon R. Pamer Temporer 224,34 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon Selasar 322,22 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Ceiling Beton R. Tangga Akses Publik 34,78 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Ceiling Beton R. Tangga Akses Karyawan 28,30 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon Toilet Umum 73,36 m² AHSP PU A.4.7.1.11 - Rp -

-Pengecatan Handrail Besi 94,34 m² Taksir - Rp -


-Pengecatan Kisi-Kisi Bahan ACP area Selasar 1.324,80 m² Taksir - Rp -

3 LANTAI 3
-Pengecatan Dinding Area Mushalla 214,62 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Penyimpanan 182,67 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Perpustakaan 122,33 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Studi 113,33 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Pengelola 140,74 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Pamer 768,20 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Tangga Akses Publik 123,10 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Tangga Akses Karyawan 114,65 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding Selasar 530,46 m² AHSP PU A.4.7.1.11 - Rp -

-Pengecatan Plafon Area Mushalla 240,47 m² AHSP PU A.4.7.1.11 - Rp -


-Pengecatan Plafon R. Penyimpanan 75,03 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon R. Perpustakaan 110,95 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon R. Studi 107,17 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon R. Pengelola 63,74 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon R. Pamer 746,88 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon Selasar 323,31 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Ceiling Beton R. Tangga Akses Publik 34,78 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Ceiling Beton R. Tangga Akses Karyawan 28,30 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Plafon Toilet Umum 73,36 m² AHSP PU A.4.7.1.11 - Rp -

-Pengecatan Handrail Besi 97,04 m² Taksir - Rp -

Sub Jumlah Rp -
B PENGECATAN EXTERIOR
1 TIANG DEKORATIF
-Pengecatan Tiang Tipe A 200,00 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Tiang Tipe B 122,50 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Tiang Tipe C 157,50 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Tiang Tipe D 137,50 m² AHSP PU A.4.7.1.11 - Rp -
2 DINDING EXTERIOR LT.1
-Pengecatan Dinding R. Penitipan 510,48 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding Kantin ( GRC Kerawang) 106,20 m² Taksir - Rp -
-Pengecatan Dinding Mushalla 19,80 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Tangga Akses Karyawan 138,74 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Lobby Utama bag. Depan 240,66 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding R. Lobby Utama bag. Belakang 875,82 m² AHSP PU A.4.7.1.11 - Rp -
-Pengecatan Dinding Toko Souvenir ( GRC Kerawang) 512,22 m² Taksir - Rp -
-Pengecatan Dinding Tiang Kisi - Kisi Beton 412,80 m² AHSP PU A.4.7.1.11 - Rp -

3 DINDING EXTERIOR LT. 2/3/Rooftop


-Pengecatan Dinding Depan ( GRC Kerawang ) Setara Dulux Ext. 1.686,73 m² Taksir - Rp -
-Pengecatan Dinding Depan ( Panel ) 175,00 m² Taksir - Rp -
-Pengecatan Dinding Belakang ( GRC Kerawang ) 1.466,80 m² Taksir - Rp -
-Pengecatan Dinding Belakang ( Panel ) 175,00 m² Taksir - Rp -
-Pengecatan Dinding Belakang ( Beton ) 613,70 m² AHSP PU A.4.7.1.11 - Rp -

4 Pengecatan Ceiling beton Lantai Dasar 2.851,67 m² AHSP PU A.4.7.1.11 - Rp -

Sub Jumlah Rp -
Mata Pembayaran Perkiraan Biaya Penerapan Sistem Manajemen Keselamatan Konstruksi

SATUAN HARGA
NO URAIAN PEKERJAAN KUANTITAS TOTAL HARGA
UKURAN SATUAN
1 Penyiapan RKK
1.1 Pembuatan dokumen Rencana -
Ls 1 -
Keselamatan Konstruksi
1.2 Pembuatan prosedur dan instruksi kerja Ls 1 - -
1.3 Penyiapan formulir Ls 1 - -
2 0
2.1 Induksi Keselamatan Konstruksi Ls 1 - -
2.2 Pengarahan Keselamatan Konstruksi Ls 1 - -
2.3 Pertemuan mengenai keselamatan Ls 1 - -
3 Alat pelindung kerja dan alat pelindung diri
3.1 Tali Keselamatan Buah 5 - -
3.2 Body Harness Buah 5 - -
3.3 Helm Pelindung Buah 10 - -
3.4 Sarung Tangan Pasang 10 - -
3.5 Sepatu Keselamatan Pasang 10 - -
3.6 Rompi Keselamatan Buah 10 - -
3.7 Masker Kotak 2 - -
4 Asuransi dan perizinan
4.1 Asuransi dan kesehatan Ls 1 - -
5 Personil keselamatan konstruksi
5.1 Ahli K3 Konstruksi dan/atau Petugas bln 4 - -
Keselamatan Konstruksi
6 Fasilitas, sarana, prasarana dan alat kesehatan
6.1 Peralatan P3K (Kotak P3K, tandu, obat
luka, perban, dan lain-lain) LS 1 - -
7 Rambu-rambu yang diperlukan
7.1 Rambu Petunjuk Buah 2 - -
7.2 Rambu Peringatan Buah 2 - -
7.3 Pembatas Area Ls 1 - -
8 Konsultasi dengan ahli terkait keselamatan konstruksi
8.1 Ahli Teknik Bangunan Gedung Ls 1 - -
9 Kegiatan dan peralatan terkait dengan pengendalian resiko keselamatan konstruksi
9.1 Pemeriksaan dan pengujian peralatan Ls 1 - -
9.2 Alat Pemadam Api Ringan (APAR) Buah 7 - -
9.3 Lampu darurat Buah 5 - -
9.4 Pembuatan Kartu Identitas Pekerja (KIP) Buah 15 - -
9.5 Patroli keselamatan Ls 1 - -
-
DAFTAR KUANTITAS DAN HARGA

Nama Pekerjaan : PEKERJAAN REHAB


Lokasi : Banda Aceh
Tahun Anggaran : 2021

Harga Satuan Jumlah Harga


No. Uraian Kegiatan Volume Satuan Analisa
(Rp) (Rp)

1 2 3 4 5 6 7
A PEKERJAAN PERSIAPAN

1 Pembersihan Lapangan/Pemindahan Barang 1,00 ls Taksir - Rp -


2 Pembongkaran dinding dan Lantai keramik Toilet (2 unit Toilet) 1,00 Ls Taksir - Rp -
3 Buang Sisa bongkaran 1,00 Ls Taksir - Rp -
4 Sewa Scafholding 438,00 set Taksir - Rp -
5 Biaya Keselamatan Kerja K3 1,00 LS Taksir - Rp -
Sub Jumlah Rp -
B REHAB TOILET UMUM LANTAI 2

1 Pekerjaan Dinding
-Pemasangan Dinding Keramik 132,00 m² A.4.4.3.54c - Rp -
-Pemasangan Partisi / Sekat Bahan PVC Fin. HPL 22,39 m² Taksir - Rp -
-Pemasangan Partisi / Sekat Urinoir Bahan PVC Fin. HPL 2,88 m² Taksir - Rp -
-Pemasangan Pintu pada dinding partisi + Asesoris 7,00 Unit Taksir - Rp -

2 Pekerjaan Lantai
-Cor Beton Untuk Closet Jongkok 0,67 m3 A.4.1.1.1 - Rp -
-Pemasangan sekat lantai Bata 1/2 T= 20cm 3,27 m² A.4.4.1.7 - Rp -
-Pemasangan Lantai keramik 66,78 m² A.4.4.3.34b - Rp -
-Pemasangan Floor Drain 10,00 unit A.5.1.1.14 - Rp -

3 Pekerjaan Sanitair
-Pemasangan Closet Jongkok 7,00 unit A.5.1.1.2 - Rp -
-Pemasangan Kran Jet Shower kloset 7,00 unit taksir - Rp -
-Pemasangan Ulang Urinoir 4,00 unit taksir - Rp -

Sub Jumlah Rp -
B REHAB TOILET UMUM LANTAI 3

1 Pekerjaan Dinding
-Pemasangan Dinding Keramik 132,00 m² A.4.4.3.54c - Rp -
-Pemasangan Partisi / Sekat Bahan PVC Fin. HPL 19,31 m² Taksir - Rp -
-Pemasangan Partisi / Sekat Urinoir Bahan PVC Fin. HPL 2,88 m² Taksir - Rp -
-Pemasangan Pintu pada dinding partisi + Asesoris 10,08 m² Taksir - Rp -

2 Pekerjaan Lantai
-Cor Beton Untuk Closet Jongkok 0,67 m3 A.4.1.1.1 - Rp -
-Pemasangan sekat lantai Bata 1/2 T= 20cm 3,27 m² A.4.4.1.7 - Rp -
-Pemasangan Lantai keramik 66,78 m² A.4.4.3.34b - Rp -
-Pemasangan Floor Drain 10,00 unit A.5.1.1.14 - Rp -

3 Pekerjaan Sanitair
-Pemasangan Closet Jongkok 7,00 unit A.5.1.1.2 - Rp -
-Pemasangan Kran Jet Shower 7,00 unit taksir - Rp -
-Pemasangan Ulang Urinoir 4,00 unit taksir - Rp -

Sub Jumlah Rp -
C PEMBUATAN TOILET VIP LANTAI 2
1 Pekerjaan Dinding
-Pemasangan Dinding Keramik 19,40 m² A.4.4.3.54c - Rp -
-Cor Beton Meja wastafel 0,27 m3 A.4.1.1.1 - Rp -
-Cor Beton Sandaran Closet 0,48 m3 A.4.1.1.1 - Rp -
-Pemasangan Lemari Plywood Fin Cat 1,32 m² Taksir - Rp -
-Pemasangan Laci Plywood Fin Cat UK=P60cm*T30cm 1,00 unit Taksir - Rp -

2 Pekerjaan Lantai
-Pemasangan Lantai keramik 6,58 m² A.4.4.3.34b - Rp -

3 Pekerjaan Sanitair
-Pemasangan Closet Duduk 1,00 unit A.5.1.1.1 - Rp -
-Pemasangan Kran Jet Shower 1,00 unit Taksir - Rp -
-Pemasangan Wastafel + Kran 1,00 unit Taksir - Rp -
-Pekerjaan Plumbing 1,00 Ls Taksir - Rp -

4 Lain - Lain
-Pemasangan Cermin 1,00 unit Taksir - Rp -
-Pemasangan Gantungan Handuk 1,00 unit Taksir - Rp -

Sub Jumlah Rp -
D PEKERJAAN INTERIOR R. STUDI LANTAI 3
1 Tribun Panggung Rangka Hollow Penutup Plywood 18mm T=90cm 78,79 m² Taksir - Rp -
2 Pemasangan Lantai Vynil Setara Taco 109,82 m² Taksir - Rp -
3 Pemasangan Lampu Selang 44,20 m Taksir - Rp -
4 Pemasangan Saklar tunggal 1,00 unit Taksir - Rp -
5 Pemasangan Kabel NYA 1,00 unit Taksir - Rp -

Sub Jumlah Rp -
E PEMBUATAN TOILET MUSHALLA / KANTIN
1 Toilet Pria
-Pemasangan Sekat Partisi Bahan PVC Fin. HPL 1,44 m² Taksir - Rp -
-Pemasangan Pintu Sekat Partisi Bahan PVC Fin. HPL+ Asesoris 1,58 m² Taksir - Rp -
-Pemasangan Urinoir 1,00 unit Taksir - Rp -

2 Toilet Wanita
-Pemasangan Sekat Partisi Bahan PVC Fin. HPL 2,70 m² Taksir - Rp -
-Pemasangan Pintu Sekat Partisi Bahan PVC Fin. HPL + Asesoris 1,40 m² Taksir - Rp -
-Pemasangan Closet Jongkok 1,00 unit A.5.1.1.2 - Rp -
-Pemasangan Kran 1,00 unit Taksir - Rp -
-Cor Beton Untuk Closet Jongkok 0,10 m3 A.4.1.1.1 - Rp -

3 Pekerjaan Plumbing 1,00 Ls Taksir - Rp -

Sub Jumlah Rp -

G PEKERJAAN REHAB LANTAI


1 Pemasangan Lantai Vynil R. Pamer Temporer LT.2 Setara Taco 224,34 m2 Taksir - Rp -
2 Pemasangan Lantai Vynil R. Perpustakaan LT.3 Setara Taco 107,17 m2 Taksir - Rp -
3 Pemasangan Lantai Vynil R. Pengelola LT.3 Setara Taco 63,74 m2 Taksir - Rp -
4 Pemasangan Lantai Vynil R. Pamer LT.3 Setara Taco 764,88 m2 Taksir - Rp -

Sub Jumlah Rp -
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemasangan 1 m2 dinding keramik ukuran 20 cm x 25 cm


Satuan / Unit : M2
Analisa : A.4.4.3.54c

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0,9000 - -
2 Tukang OH 0,4500 - -
3 Kepala Tukang OH 0,0450 - -
4 Mandor OH 0,0450 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Keramik 40x40 m2 1,000 - -
2 Semen Portland Kg 9,300 - -
3 Pasir Pasang M3 0,018 - -
4 Semen Warna Kg 1,940 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemasangan 1 m2 lantai keramik ukuran 40 cm x 40 cm (anti Selip)


Satuan / Unit : M2
Analisa : A.4.4.3.34b

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0,7000 - -
2 Tukang OH 0,3500 - -
3 Kepala Tukang OH 0,0350 - -
4 Mandor OH 0,0350 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Keramik 40x40 m2 1,000 - -
2 Semen Portland Kg 8,190 - -
3 Pasir Pasang M3 0,045 - -
4 Semen Warna Kg 1,620 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemasangan 1 m2 dinding bata merah (5x10x20) cm tebal 1/2 batu campuran 1 SP : 2PP
Satuan / Unit : M2
Analisa : A.4.4.1.7

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0,3000 - -
2 Tukang OH 0,1000 - -
3 Kepala Tukang OH 0,0100 - -
4 Mandor OH 0,0150 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Batu Bata M3 80,000 - -
2 Semen Portland Kg 18,950 - -
3 Pasir Pasang M3 0,030 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Membuat 1 m3 beton mutu f'c = 7,4 Mpa (K 100), slump (12 ± 2) cm. w/c = 0,87
Satuan / Unit : M3
Analisa : A.4.1.1.1

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1,6500 - -
2 Tukang OH 0,2750 - -
3 Kepala Tukang OH 0,0280 - -
4 Mandor OH 0,0800 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Semen Portland Kg 247,0000 - -
2 Pasir Beton Kg 869,0000 - -
3 Kerikil Kg 999,0000 - -
4 Air Ltr 215,0000 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -

PEK. BETON
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemasangan 1 buah floor drain


Satuan / Unit : unit
Analisa : A.5.1.1.14

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0,0100 - -
2 Tukang OH 0,1000 - -
3 Kepala Tukang OH 0,0100 - -
4 Mandor OH 0,0050 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Floor Drain Bh 1,00 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -

Jenis Pekerjaan : Pemasangan 1 buah closet jongkok porcelain


Satuan / Unit : unit
Analisa : A.5.1.1.2

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 1,0000 - -
2 Tukang OH 1,5000 - -
3 Kepala Tukang OH 0,1500 - -
4 Mandor OH 0,1600 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Closet Jongkok Setara Toto Bh 1,000 - -
2 Semen Portland Kg 6,000 - -
3 Pasir Pasang Ls 0,010 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X E -
F Harga Satuan Pekerjaan ( E + F ) -
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemasangan 1 buah closet duduk/monoblock

Satuan / Unit : Unit


Analisa : A.5.1.1.1

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 3,3000 - -
2 Tukang OH 1,1000 - -
3 Kepala Tukang OH 0,0100 - -
4 Mandor OH 0,1600 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Closet Duduk Bh 1,0000 - -

Jumlah Bahan -
C. PERALATAN % 6 -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -

ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pengecatan Tembok Lama (1 x cat dasar, 2 x cat penutup)


Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.11

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0,0280 - -
2 Tukang OH 0,0420 - -
3 Kepala Tukang OH 0,0042 - -
4 Mandor OH 0,0025 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Cat dasar tembok Kg 0,1200 - -
2 Cat tembok Kg 0,1800 - -

Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -
ANALISA HARGA SATUAN PEKERJAAN

Jenis Pekerjaan : Pemasangan 1 m2 wallpaper lebar 50 cm


Satuan / Unit : M2
Analisa : AHSP PU A.4.4.3.60

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A. TENAGA
1 Pekerja OH 0,3500 - -
2 Tukang OH 0,1750 - -
3 Kepala Tukang OH 0,0170 - -
4 Mandor OH 0,0020 - -
Jumlah Tenaga Kerja -
B. BAHAN
1 Wallpaper Kg 1,1000 - -
2 Lem Walpaper Kg 0,2500 - -
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) -
E Overhead & Profit 10% X D -
F Harga Satuan Pekerjaan ( D + E ) -
DAFTAR HARGA UPAH, BAHAN DAN PERALATAN

Harga Satuan Dasar


No Uraian Satuan
(Rp)
I UPAH
1 Pekerja Galian Tanah OH Rp -
2 Pekerja OH Rp -
3 Tukang OH Rp -
4 Tukang Kayu OH Rp -
5 Kepala Tukang OH Rp -
6 Mandor OH Rp -
7 Penjaga Malam OH Rp -
8 Penyelam OH Rp -
9 Supir OH Rp -
10 Operator OH Rp -
11 Pembantu Operator OH Rp -
12 Pembantu Juru Ukur OH Rp -
13 Juru Ukur OH Rp -

Harga Satuan Dasar


No Uraian Satuan
(Rp)
II Material / Bahan
1 Air Liter Rp -
2 Agregat Kasar M3 Rp -
3 Agregat Halus M3 Rp -
4 Alkasit Kg Rp -
5 Ampelas lembar Rp -
6 Batu Bata Bh Rp -
7 Batu Gunung/ Batu Kali M3 Rp -
8 Besi Beton Polos Kg Rp -
9 Besi Beton Ulir Kg Rp -
10 Besi Strip Tebal 5 mm Kg Rp -
11 Beton Rooster/ Kerawang Bh Rp -
12 Bubungan Seng M' Rp -
13 Cat Kayu Dasar Kg Rp -
14 Cat Kayu Mengkilat/Penutup Kg Rp -
15 Cat Kayu Penutup Kg Rp -
16 Cat Menie Besi Kg Rp -
17 Cat Menie Kg Rp -
18 Cat dasar tembok Kg Rp -
19 Cat Tembok Kg Rp -
20 Cat Penutup/ epoxy kg Rp -
21 Dempul Kayu Kg Rp -
22 Engsel Jendela Pasang Rp -
23 Engsel Pintu Pasang Rp -
24 Floor Drain Bh Rp -
25 Gypsum board 9 mm Lbr Rp -
26 Grendel Jendela / Pintu Bh Rp -
27 Hak Angin Bh Rp -
28 Kaca Bening Uk. 5 mm M2 Rp -
29 Kawat Beton Kg Rp -
30 Kawat Duri Kg Rp -
31 Kawat Las Listrik Kg Rp -
32 Kayu dolken dia. 8-10 cm, L = 4 M Btg Rp -
33 Kayu Kelas I M3 Rp -
34 Kayu Balok Kelas I M3 Rp -
35 Kayu Papan Kelas I M3 Rp -
36 Kayu Kelas II M3 Rp -
37 Kayu Balok Kelas II M3 Rp -
38 Kayu Kelas III M3 Rp -
39 Kayu Kelas IV M3 Rp -
40 Kayu 5 x 7 cm (Klas IV) M3 Rp -
41 Kayu Kaso 5 x 7 cm M3 Rp -
42 Kayu Papan 2/30 (Klas IV) M3 Rp -
43 Kasa Gypsum Roll Rp -
44 Kerikil M3 Rp -
45 Kerikil (KR) Kg Rp -
46 Keramik Artistik M2 Rp -
47 Keramik uk. 30 x 30 cm M2 Rp -
48 Keramik uk. 40 x 40 cm M2 Rp -
49 Keramik (granito) 60 x 60 cm (Polished) Bh Rp -
50 Kertas Amplas Lbr Rp -
51 Kloset Jongkok Keramik Bh Rp -
52 Kloset Jongkok Porselen Bh Rp -
53 Kuas Uk 2" - 3" Bh Rp -
54 Kuas Bh Rp -
55 Kunci Pintu Bh Rp -
56 Lem Kayu Kg Rp -
57 Lem Walpaper Kg Rp -
58 Lempengan Rumput M2 Rp -
59 Minyak Cat Liter Rp -
60 Minyak Pelumas Liter Rp -
61 Minyak Bekisting Liter Rp -
62 Multiplek 4 mm Lbr Rp -
63 Multipleks t= 6 mm Lbr Rp -
64 Mutipleks tebal 9 mm Lbr Rp -
65 Nok / Rabung Seng 0,35 Cat Pabrik Lbr Rp -
66 Nok / Rabung Seng 0,35 tidak di cat Lbr Rp -
67 Oli Liter Rp -
68 Paku Kayu Kg Rp -
69 Paku 2" -3" Kg Rp -
70 Paku 5 cm - 10 cm Kg Rp -
71 Paku 3/4 "- 1" Kg Rp -
72 Paku Seng Kg Rp -
73 Paku Sekrup Kg Rp -
74 Pasir Batu (Sirtu) material jalan M3 Rp -
75 Pasir Beton M3 Rp -
76 Pasir Beton (PB) Kg Rp -
77 Pasir Pasang M3 Rp -
78 Pasir Pasang Kg Rp -
79 Pasir Urug M3 Rp -
80 Plamir Tembok Kg Rp -
81 Plamir Kayu Kg Rp -
82 Penjaga jarak bekisting/ Spacer Bh Rp -
83 Pengencer Liter Rp -
84 Residu Ltr Rp -
85 Reservoir Fiber Glass 1 M3 Unit Rp -
86 Reservoir Stainless Steel 1 M3 Unit Rp -
87 Rangka Hollow m' Rp -
88 Semen Portland 40 kg Zak Rp -
89 Semen Portland Kg Rp -
90 Semen Putih 50 Kg Zak Rp -
91 Semen Warna Kg Rp -
92 Seng BJLS 0,30 Lbr Rp -
93 Solar Liter Rp -
94 Tanah Timbun M3 Rp -
95 Tepung Gypsum Kg Rp -
96 Terawang (Roster ) Bh Rp -
97 Kerosene (Minyak Tanah) Industri liter Rp -
98 Urugan Pilihan M3 Rp -
99 Wallpaper M2 Rp -
99 Alat Bantu Jam Rp -