2013 Ground Improvemen (Klaus Kirsch, Alan Bell (Eds.) )
2013 Ground Improvemen (Klaus Kirsch, Alan Bell (Eds.) )
Improvement
Third Edition
This book contains information obtained from authentic and highly regarded sources. Reasonable
efforts have been made to publish reliable data and information, but the author and publisher cannot
assume responsibility for the validity of all materials or the consequences of their use. The authors and
publishers have attempted to trace the copyright holders of all material reproduced in this publication
and apologize to copyright holders if permission to publish in this form has not been obtained. If any
copyright material has not been acknowledged please write and let us know so we may rectify in any
future reprint.
Except as permitted under U.S. Copyright Law, no part of this book may be reprinted, reproduced,
transmitted, or utilized in any form by any electronic, mechanical, or other means, now known or
hereafter invented, including photocopying, microfilming, and recording, or in any information stor-
age or retrieval system, without written permission from the publishers.
For permission to photocopy or use material electronically from this work, please access www.copy-
right.com (http://www.copyright.com/) or contact the Copyright Clearance Center, Inc. (CCC), 222
Rosewood Drive, Danvers, MA 01923, 978-750-8400. CCC is a not-for-profit organization that pro-
vides licenses and registration for a variety of users. For organizations that have been granted a pho-
tocopy license by the CCC, a separate system of payment has been arranged.
Trademark Notice: Product or corporate names may be trademarks or registered trademarks, and are
used only for identification and explanation without intent to infringe.
Visit the Taylor & Francis Web site at
http://www.taylorandfrancis.com
and the CRC Press Web site at
http://www.crcpress.com
Preface
v
Contents
Preface v
Editors vii
Contributors ix
3 Dynamic compaction 57
BARRY SLOCOMBE
iii
iv Contents
CONTENTS
When faced with dificult ground conditions at a project site, an engineer has a
number of possible strategies to employ in order to achieve the project objectives.
The most obvious is to ind another site, but this is only very rarely practicable.
Pressure on land, the need to use poor sites, and the location of many cities
in estuaries or river situations make this option increasingly dificult. Another
option is to redesign the building or structure to accommodate the prevailing
dificulties arising from the ground, and where possible this is a good solution.
Yet another possibility is to remove the troublesome ground and to replace it
with more suitable material, and this can often be cost effective providing the
depth to be addressed and the quantities concerned are relatively small.
If none of these avoiding strategies are technically or economically real-
istic, then the prevailing ground conditions must be addressed. A common
potential solution is to adopt a system such as piling, in order to bypass
the dificult ground and found in suitable material. However, this can be
expensive and time consuming and may actually be dificult to achieve in
1
2 Ground improvement
This third edition of Ground Improvement will provide the reader with a
sound basis for understanding and further study of the most widely used
processes for ground improvement.
Introduction and background 3
TRD and the panel-mixing CSM approaches. Several new case histories are
also included. Chapter 10 covers dry soil mixing using the Scandinavian
approach, as this process has continued to see worldwide application.
In the remainder of the present chapter several topics which would not
justify a separate chapter are included, such as the history of the two main
means of creating improvement (see Section 1.3). Brief notes on health and
safety for ground improvement sites are included in view of its common
relevance (Section 1.4). The effects of ground improvement on greenhouse
gas emissions have increasingly been addressed since the second edition and
now warrant inclusion (Section 1.5). Overviews of two ground improve-
ment techniques which, by their nature, have somewhat limited ranges of
application have also been included. Blasting can be an effective means of
improving granular soils by densiication and is described in Section 1.6.
The only reversible ground improvement process of ground freezing can be
powerful where applicable, and is outlined in Section 1.7.
Since earliest times humankind has found ways of dealing with poor
ground in order to form pathways and later roads using such simple strate-
gies as placing beds of reeds or saplings to support the weight of people
and animals over soft ground. It is only relatively recently that the means
of engineering dificult ground by compaction, consolidation, or by adding
materials by permeation or mixing has seen signiicant advances. These
processes developed during and after the Industrial Revolution, but mainly
in the early twentieth century. In these years, better understanding of soil
mechanical behaviour emerged through the work of Terzaghi and others;
practical ground investigation became possible; and equipment and materi-
als development reached the stage that signiicant volumes of soil could be
treated. Two main approaches are in worldwide use today, namely deep
vibratory treatment and injection or mixing of grouts. A brief historical
review of these two topics follows in view of their importance.
Kirsch and Kirsch (2010) describe how depth vibrators were developed
in Germany in the 1930s. Initially aimed at concrete densiication, they
soon were applied more effectively for sand compaction. Consequently,
deep vibratory stabilisation for both natural and illed cohesionless soils
was used widely for a range of applications in Germany and further aield,
particularly after 1945. A further major area of application was added in
1956 when depth vibrators were employed to form stone columns in silty
materials, leading to the application to cohesive soils more generally.
Further development and improvement of the special plant and equip-
ment necessary for the execution of this ground improvement method
together with the experience gained in practice considerably increased the
Introduction and background 5
grout ports with rubber sleeve valves, are placed in boreholes to attain the
depths required, and are grouted in place using a relatively weak sleeve
grout. One set of ports can be isolated at a time, and grout can be injected
into the surrounding ground after it expands the surrounding seal and
breaks the sleeve grout. This enables control of grout volume or pressure
during injection at speciic points in the subsoil. Littlejohn (1993) provides
a useful summary of the history of injection processes.
Subsequent grouting development has concentrated more on the develop-
ment of entirely new ground improvement processes using simple cement
grouts, partly due to concerns over toxicity of some chemical grouts and
partly to the desire for improved performance. By the early 1990s jet grout-
ing; compaction grouting; soilfracture grouting; and soil mixing methods
were all widely and successfully applied in addition to permeation grouting
(e.g., Bell 1994). Since then there has been increased use of all of these, and
soil mixing in particular is now more widely used. Further technical devel-
opment of all grouting methods has continued, particularly in relation to
electronic monitoring and control on site. Some history on these methods is
included in Chapters 6 through 9.
the key greenhouse gases released by the process (for example, Hammond
and Jones 2011).
Calculations can also be used to compare different ground improve-
ment and other geotechnical processes such as piling methods, and this
can be important in minimising the total carbon dioxide equivalent for a
given project. Wintzingerode et al. (2011) list seven key potential sources of
greenhouse gas emissions for ground improvement systems, namely:
r Raw materials
r Transport for materials
r Transport for personnel
r Transport for equipment
r Product manufacture
r Waste or spoil emissions
r Transport for waste or spoil
executed at relatively low costs generally for very large volumes of granular
deposits. However, it does not yield such high densities as those achieved
by vibro compaction with its scope of application being a moderate but
rather homogeneous densiication (Smoltczyk 1983). It should be noted that
directly at the location of the charge, some heterogeneity or loosening can
arise, particularly if the ines content in the soil is high.
The method can be used from irregular surface conditions and from
ground unsuitable for heavy plant, but it is restricted to loose granular soils
with low silt contents. Only occasionally the method has also been used to
compact ine grained soils, such as loess. The depth range of the method is
generally beyond the reach of vibro compaction, as has been reported by
Solymar et al. (1984). The effective range of the explosion impact deter-
mines the placement of the charges in the ground. It is between 10 m for
low charges of 10–15 kg of TNT equivalent per bore hole and up to 20
m for charges of 30 kg. Placement of the charges is generally in boreholes
often supported by bentonite slurry.
Similar to vibro compaction and the effect of an earthquake, the explo-
sive impact results in shear waves leading to partial or even total liquefac-
tion of the granular deposit and ultimately to a densiication of the soil
when the pore water overpressure has dissipated. The density that can be
achieved by the blasting method depends of course on the explosive energy,
the distance of the bore holes containing the charges in the ground, and on
the same soil characteristics determining the suitability of granular soils
for vibro compaction. The improvement expressed by the increase in rela-
tive density Dr is generally ΔDr = 15%–30%, in exceptional cases more,
particularly when the original density is very low. The extension of the
compaction reaches 20%–50% deeper than the installation depth of the
explosive charge. The success of deep compaction by blasting also depends
on the layout of the blast holes and the sequence of the ignitions in multiple
blasting. Quality control measures are similar to those applicable for vibro
compaction. In the absence of a reliable theory and simple design rules the
method application relies on experience and on trial compactions ahead of
any contract work. Gohl et al. (2000) have produced a promising theory
based on cavity expansion theory and compare with experience on nine
projects.
Densiication arising from compaction blasting of loose water-saturated
granular soils is strongest, whereas the effect on denser deposits tends to
be less. This behaviour leads to an equalisation of density and homogenises
the granular deposit. Although the method is regarded as an economical
means of compaction, its application remains scarce, probably because the
use of explosives for subsurface blasting requires special permissions that
are not easy to obtain. In addition, the environmental impact is substantial:
the emission of noise and far-reaching shock waves needs to be investigated
and controlled throughout the project, as does the emission of gases and
12 Ground improvement
fumes from the explosion, which are injected into the ground and may con-
taminate the ground water.
The need to rehabilitate large deposits in the open brown coal mining
areas in eastern Germany has resulted in an extensive use of the compac-
tion blasting method in parallel to vibro compaction. It has triggered inter-
esting ield trials of blasting and intensive research work on this method
of ground improvement (Kolymbas 1992, Raju 1994, Tamaskovics 2000).
However, its application has been diminishing at this site due to safety con-
siderations. General descriptions of the deep blasting ground improvement
method can be found in Damitio (1970), Mitchell (1981), Kolymbas (1992),
Gohl et al. (2000) and Gambin (2004).
The artiicial freezing of soil has been known for well over 100 years.
The method was patented in 1883 by Poetsch in Germany but previously,
in 1862, practiced in the UK (Harris 1995, Jessberger and Jagow-Klaff
2003). By this method water-bearing soils are chilled to such an extent
that the pore water freezes, providing the frozen soil with considerably
higher strength than in its original state and rendering it at the same time
impermeable to water. These changed soil conditions are transient and
reversible as the soil returns to its original characteristics when thawing,
provided that no changes in water content occur, which may happen in
cohesive soils due to the development of ice lenses. Soil freezing is therefore
the only reversible method of ground improvement, and it requires a con-
tinuous supply of energy during its application to maintain the necessary
soil temperature and desired state (for example, its stiffness, strength, or
impermeability).
The method was originally developed to sink large mining shafts through
water-bearing soils. Only relatively recently soil freezing has also been used
in tunnel construction and to resolve dificult problems in ground engineer-
ing, often as the method of last resort (closure of leakages in water barriers;
retrieving of artefacts or valuable machinery from dificult ground condi-
tions). It is also used in soil investigation measures to obtain undisturbed
samples of saturated noncohesive soils to measure their density. Very
recently the method has also been proposed in environmental engineering
to freeze (encapsulate and immobilise) and subsequently safely remove haz-
ardous soil. Its application is generally restricted in time.
Soil freezing is achieved by taking heat away from the ground, generally
using either of the two methods:
Both methods require special piping to be installed in the soil for the
introduction of the coolant. Liquid nitrogen is generally used for short
time, small volume applications (shock freezing) as the frost body builds
up quickly at temperatures of −196°C of the coolant resulting in frozen soil
temperatures between −20°C and −30°C, or even deeper. Brine freezing
uses coolant temperatures of between −30°C and −40°C, allowing frost
body temperatures of −10°C to −20°C to develop. Brine freezing is used in
general for large-volume, long-duration projects since the installation costs
of the refrigerating system are considerable and the time required to achieve
the necessary frost body temperature is longer.
Soil freezing is generally used in water-bearing soils. Ground water low
strongly inluences the development of the frozen soil body and needs to be
considered in the analysis when it reaches values above 1 m/day, as a rule
of thumb. The necessary energy to build up and maintain over time for
the required frozen soil body dimensions can be calculated using the heat
exchange formulae based upon the thermal characteristics of the soil (ther-
mal capacity and conductivity). The design of these dimensions is based
upon structural and heat transfer–related parameters of the frozen and
unfrozen soil. Strength and deformation characteristics of frozen soil are
time dependent and responsible for the creep developing and resulting from
the visco-plastic behaviour of the frozen pore water. The dependency of the
frozen soil strength from temperature and soil characteristics (mainly water
content, density, grain size distribution, and salinity of the ground water)
has been the subject of intensive research in recent years. Recommendations
and special publications (such as from the International Symposium on
Ground Freezing, ISGF) provide details of the method, including the nec-
essary site and laboratory investigations prior to the design and execution
of a soil-freezing project. The thermal and rheological computations to
describe the time and temperature dependent stress strain behaviour of the
frozen soil body are best carried out using the FE method (Kirsch and
Borchert 2008).
Ground water conditions such as seepage low velocity, temperature,
and salinity are important factors of inluence for maintaining the integ-
rity of the frost body dimensions and are often decisive in determining the
distances between the freeze tubes. Their proper knowledge is essential
in optimising the energy cost of any soil freezing project. Quality-control
measures are as with other methods of special foundations; they include
temperature measurements indispensible to guarantee the integrity of the
dimensions of the frost body throughout its maintenance.
It is a well-known phenomenon that freezing of the pore water is accom-
panied by a volume increase of 9%, which results in frost-susceptible soils,
generally of ine contents in excess of 15% in unwanted soil heave. In addi-
tion, the development of ice lenses leads to continuous increase of heave
and/or stresses. This heave is small with suficient surcharge and generally
14 Ground improvement
REFERENCES
CONTENTS
For over 70 years, depth vibrators have been used to improve the bearing
capacity and settlement characteristics of weak soils. Vibro compaction
is probably the oldest dynamic deep compaction method in existence. It
was introduced and developed to maturity by the Johann Keller Company
in 1936, which enabled the compaction of noncohesive soils to be per-
formed with excellent results. A detailed description of the method from
17
18 Ground improvement
suspension near the bottom of the vibrator (Jebe and Bartels 1983). The voids
of the stone column skeleton are thereby illed with this suspension. Finally,
vibro concrete columns were developed using a conventional concrete pump
to deliver the concrete to the bottom of the vibrator via the tremie system.
In very soft nearly liquid soils, vibro replacement is not applicable due
to the lack of lateral support of the soil. A geotextile coating may be used
around the column to ensure ilter stability and to activate tensile forces to
avoid lateral spreading of the column. This method was developed in 1992
and irst applied in early 1993 for a dam project in Austria (Keller 1993).
A compilation of various projects with geotextile-coated columns may be
found in Sidak et al. (2004).
These techniques have been chosen for many major structures in the
United States and Europe, endorsing their value in promoting safe and eco-
nomic foundations to a wide range of buildings and soil conditions. Probably
the oldest recommendation on the use of vibro was issued by the German
transport research society in 1979 (FGFS 1979). Later, the US Department
of Transportation published the manual Design and Construction of Stone
Columns (USDT 1983), followed by the British ICE Speciication for Ground
Treatment (ICE 1987) and the BRE publication Specifying Stone Columns
(BRE 2000). The latest effort has been made by the European community
to standardise the execution of vibro works in Ground Treatment by Deep
Vibration (European Standard EN14731, 2005).
Figure 2.1 Vibro compaction method operating phases. (Courtesy of Keller Group.)
Grain diameters of the stones and gravel which comprise the ill material
for the wet method range from 30 to 80 mm. Stone column installation to
depths as great as 43 m has been reported (Wehr 2008). The wet method
guarantees stone column continuity for a wide range of soft soils.
Grain diameters of the stones or gravel that comprise the ill material
when using a bottom feed vibrator typically range from 10–40 mm. The ill
is delivered to the vibrator tip by means of a pipe. After the vibrator arrives
at the speciied depth, compressed air is used to help deliver the ill as the
vibrator is subsequently lifted in stages as it compacts the ill (Figure 2.2).
Carrier equipment typically consists of specially designed machines,
known as vibrocats, which have vertical leaders. The vibrocats control the
complex bottom feed vibrators, equipped with material lock and storage
units, which deliver ill material to the vibrator by means of specialised
mechanical or pneumatic feeding devices (Figure 2.3).
Vibro cats possess a particular feature which is an additional downward
force (Figure 2.4). This so-called ‘activation force’ of approximately 150 kN
causes a better vertical compaction of the column material and a repeated
vertical loading. Furthermore, it is possible to increase the column diameter
easily because the vertical action of the vibrator tip leads to a horizontal
displacement with eficient compaction.
The installation of vibro mortar columns is similar to the dry vibro
replacement method apart from the cement suspension illing the voids of
the stone skeleton inside the column. This results in a much stiffer column
compared to a conventional vibro stone column.
For the installation of vibro concrete columns, the tremie system is con-
nected to a mobile concrete pump. Before penetrating, the system is charged
with concrete. The vibrator then penetrates the soil until the required depth
has been achieved. The founding layer, if granular, is further compacted by
the vibrator. Concrete is pumped out from the base of the tremie at positive
pressure. After raising the vibrator in steps, it re-enters the concrete shaft,
displacing it into a bulb until a set resistance has been achieved. Once the
bulb end is formed, the vibrator is withdrawn at a controlled rate from
the soil while concrete continues to be pumped out at positive pressure.
Once completed, the column can be trimmed and reinforcement placed as
required.
Vibro geotextile columns consist of a sand or stone core with a geotextile
coating. The advantage of a vibro geotextile column to other geotextile
columns (Schüßler 2002) is the well-densiied granular inill resulting only
in small settlements of the soil-column system (Trunk et al. 2004).
The installation is usually performed in several steps in order not
to damage the geotextile. First a hole is created with the vibrator to the
required depth and the vibrator is extracted. In the next step the geotextile
is mounted over the vibrator above the ground surface, and subsequently
the penetration is repeated with the geotextile to the same depth as before.
Deep vibro techniques 23
Material gate
Vibrator and
pipe extension
(storage container)
Elastic coupling
Pipe for
material
Electric motor
Eccentric
weight
Material outlet
Figure 2.3 Vibro cat with bottom feed vibrator. (Courtesy of Keller Group.)
Deep vibro techniques 25
Activation force
Displacement
and
compaction
Figure 2.4 Vibro cat with activation force. (Courtesy of Keller Group.)
26 Ground improvement
On the way up, it is preferable that stones are illed and densiied inside the
geotextile like in the usual dry bottom feed process.
If there is only one certain very soft layer it is possible to irst build a
vibro stone column below this layer, insert a vibro geotextile column or
a vibro mortar column only in the very soft layer for economical reasons,
and inish the upper part of the column as an ordinary vibro stone column.
The equipment developed for the vibro compaction and vibro replacement
processes comprises four basic elements:
Extension
Elastic coupling
Water
or
air supply
Electric motor
Eccentric
weight
Tip
Figure 2.5 Depth vibrator and principle of vibro compaction. (Courtesy of Keller
Group.)
given on vibrators apply to those which are freely suspended, lacking lateral
coninement.
It is up to the designer to create a vibrator optimal for the speciic appli-
cation. One major challenge of design lies with keeping maintenance costs
within standards that are economically tolerable. Based on ield experience,
the most effective compaction of sands and gravels is done by vibrating fre-
quencies which approach the natural soil-vibrator system frequency, or ‘res-
onance’ for elastic systems, which ranges between 20–30 Hz (Wehr 2005).
Fellin (2000), who considered vibro compaction a ‘plasto-dynamic prob-
lem,’ has conirmed theoretically knowledge gained from practical vibro
operation conditions. Fellin’s goal, by constant analysis of information
obtained on the vibrator movement during compaction performance, was
to create ‘on-line compaction control.’ His work’s theoretical results con-
irm the observation that when using a constant impact force, the vibra-
tion’s effect range increases as the vibrator frequency decreases, whereas
compaction increases when the impact force increases.
The thickness of soil depths to be treated determines the overall length
of vibrator, extension tubes, and lifting equipment, which in turn deter-
mines the size of crane to be used. Purpose-built tracked base machines
28 Ground improvement
Transition
Clay Silt Sand zone Gravel
100 100
80 80
60 Vibro-replacement 60
Passing by weight [%]
Vibro-compaction
40 40
20 20
0 0
0,002 0,006 0,02 0,06 0,2 0,6 2,0 6,0 20 60
Particle size [mm]
Figure 2.6 Range of soil types treatable by vibro compaction and vibro replacement
(stone columns).
Deep vibro techniques 29
a/sin 60º
a
(1 + b a
(1 + 2b a
3 × a/3
b = 0.2 – 0.4
Compaction probe
Pre - penetration test
Post - penetration test
Figure 2.7 Trial arrangement for vibro compaction. (From Moseley, M.P. and Priebe, H.J.
(1993). In: Moseley, M.P. (ed.) Ground Improvement, London, England: Blackie
Academic & Professional.)
20
15 Sand
10
Initial value
5
0.06 2.0
Grid area A
0
0 1 2 3 4 5 6 7 8 9 10 m2
Figure 2.8 Results of vibro compaction trial. (From Moseley, M.P. and Priebe, H.J. (1993).
In: Moseley, M.P. (ed.) Ground Improvement, London, England: Blackie Academic
& Professional.)
values of soil compatibility for compaction methods. Given that the local
skin friction-to-point resistance (friction ratio) falls between 0 and 1 and
the point resistance is a minimum of 3 MPa, the soil can be considered to
be compatible (Massarsch 1994).
The eficiency of compaction is also greatly inluenced by the perme-
ability of the soil. When permeability is too low (<10 –5 m/s), compaction
effectiveness decreases as permeability decreases, whereas when permeabil-
ity is too high (>10 –2 m/s), penetration of the soil by the vibrator becomes
increasingly more dificult as the permeability increases (Greenwood and
Kirsch 1983).
The carbonate or shell content is important for the densiication of
highly compressible soils with low cone resistance and high friction ratio.
Cemented soils are not considered here.
Correlations between the CPT cone resistance and the relative density
are well established for silica sand. Unfortunately there are not many refer-
ences concerning this correlation for calcareous sands. Vesic (1965) added
10% of shells to quartz sand, which resulted in a decrease of the CPT cone
resistance by a factor of 2.3. Bellotti and Jamiolkowski (1991) compared
CPT cone resistances qc (silica)/qc (shells) = 1 + 0.015(Dr-20) yielding ratios
between 1.3 and 2.2 increasing with relative density Dr. Almeida et al.
(1992) compared normalised CPT cone resistances of calcareous Quiou
sand and silica Ticino sand, which yielded ratios from 1.8–2.2 proportion-
ate to increasing relative density. Foray et al. (1999) compared pressure-
meter limit pressure of silica sand and carbonate sands, which resulted in
ratios ranging from 2–3 proportionate to increasing initial vertical stress.
Finally Cudmani (2001) looked at normalised cone resistances of seven
sands yielding ratios between 1.4–3.5 depending on initial soil pressure
and relative density. Meier (2009) executed systematic calibration chamber
tests to investigate the inluence of different silica/carbonate sand ratios
including the inluence of coarse material. This concept has been applied to
the Palm Island projects in Dubai by Wehr (2005a).
Shear strength of
Shear strength stone material
τ of soil
σ0
Z
σh
Cu
σ
γZ σh Kp σh = σ0
ϕ
Figure 2.9 Inluence of lateral support on column stress. (From Brauns, J. (1978).
Bautechnik 55(8):263–271.)
Deep vibro techniques 33
Figure 2.10 Failure mechanism of vibro replacement stone columns in the case of group
effect. (From Hu, W. (1995). Physical Modelling of Group Behaviour of Stone
Column Foundations, PhD Thesis, University of Glasgow.)
being punched into the underlying soil, such as with ‘loating’ foundations
(Figure 2.11). However, such high rates of deformation precede the failure
in every case that the column’s serviceability is generally no longer pro-
vided. Therefore, we can conclude that the equations used to calculate the
deformation, or ‘serviceability state’ of the discussed foundation, are much
more relevant than the outcome of limit load assessment of stone columns.
Soyez (1987) and Bergado et al. (1994) have conducted a thorough over-
view of the various design methods. The authors show the distinction
between calculating single columns and calculating column grid patterns.
In Europe, Priebe’s (1995) design method for vibro replacement stone col-
umns has gained acceptance as a valid method (Figure 2.12).
Thus, in Figure 2.12, the improvement factor, depending on angles of
internal friction of the stone column, is related to the ratio of the stone
column area and the area being treated by the column. The improvement
factor indicates how many times the compression modulus increases for a
grid of stone columns and to what extent the settlement of a raft founda-
tion will be reduced. Angles of internal friction are usually higher than 45°
(Herle et al. 2008).
34 Ground improvement
P P
Figure 2.11 Failure mechanism of vibro replacement stone columns under vertical load.
(From Brauns, J. (1978). Bautechnik 55(8):263–271.)
The basic design curves assume the stone column material to be incom-
pressible, and Figure 2.13 allows an adjustment to be made for this by
plotting a ictitious area ratio, which has to be added to the actual area
ratio, against the compression modulus ratio for soil and stone column
material.
5
ϕc = 45.0°
Improvement factor n
ϕc = 42.5° µs = 1/3
4
ϕc = 40.0°
ϕc = 37.5°
3
ϕc = 35.0°
1
1 2 3 4 5 6 7 8 9 10
Area ratio A/Ac
Figure 2.12 Design diagram for improving the ground by vibro replacement stone col-
umns. (From Priebe, H.J. (1995). Ground Engineering, December, pp. 31–37.)
Deep vibro techniques 35
2.0
ϕc = 45.0°
Addition to the area ratio ∆ (A/Ac)
1.6
ϕc = 42.5° µs = 1/3
ϕc = 40.0°
1.2
ϕc = 37.5°
ϕc = 35.0°
0.8
0.4
0.0
1 2 3 4 6 8 10 20 30 40 60 80 100
Constrained modulus ratio Dc /Ds
Figure 2.13 Area ratio addition. (From Priebe, H.J. (1995). Ground Engineering, December,
pp. 31–37.)
0.8
Settlement ratio s/s∞
1600
900
0.6
Figure 2.14 Settlement evaluation for isolated footings. (From Priebe, H.J. (1995). Ground
Engineering, December, pp. 31–37.)
Ac 1
n0 = 1 + ⋅ − 1
A K ac ⋅ (1 − A c A)
and
where
A = attributable area within the compaction grid
A c = cross-section of stone columns
ϕc = friction angle of column material.
A D
Liquefaction
30°
B C
Impermeable non-liquefiable layer
Figure 2.15 Stabilised area (ABCD) adjacent to foundation. (From Japanese Geotechnical
Society. (1998). Remedial Measures against Soil Liquefaction, from Investigation
and Design to Implementation. Rotterdam, Netherlands: A. A. Balkema.)
40 Ground improvement
2
Oil tank L= 3
1
5 m ≤ L ≤ 10 m
I
L
Figure 2.16 Soil improvement area for oil tanks. (From Japanese Geotechnical Society.
(1998). Remedial Measures against Soil Liquefaction, from Investigation and
Design to Implementation. Rotterdam, Netherlands: A. A. Balkema.)
without compaction, leaving the sand or stone in a state ranging from loose
to medium dense (European Standard EN 15237, 2007).
Vibro stone columns are not suitable in liquid soils with a very low und-
rained cohesion because the lateral support is too small. However, vibro
stone columns have been installed successfully in soil with 5 kPa < cu < 15
kPa, see Section 2.7. In case of very hard and/or cemented layers (i.e., cap-
rock) or very well-compacted surface layers, pre-boring may be necessary
to assist the penetration of the vibrator. Concerning the distance to build-
ings the same applies as for vibro compaction (Achmus et al. 2010). Depths
down to 43 m have been improved so far by vibro replacement.
Part of the state of the art methods is to monitor and record in great detail
the operating parameters of any deep vibro work. Details are given in
the European Standard ‘Ground treatment by deep vibration’ (European
Standard EN 14731, 2005).
Vibro compaction is monitored online with devices that record, as a
function of time, penetration depth, energy consumption of the motor and,
if necessary, pressure and quantity of the lushing media used. If the vibra-
tor frequency can be adjusted during the compaction process, this param-
eter is also recorded.
For the vibro replacement method, all of the essential parameters of
the production process (depth, up/down speed, activation force, vibrator
energy, and stone/concrete consumption) are recorded continuously as a
function of time, providing the user with visible and controllable data for
producing a continuous stone column. A typical printout for stone column
construction is given in Figure 2.17. Monitoring of the activation force is
important to check that there is suficient vertical compaction and hori-
zontal displacement of the column material. Additionally, the monitoring
of the ill level in the material supply tube indicates exactly how much
material is inserted per linear metre column length. Monitoring the acti-
vation force and the ill level together guarantees a high-quality column.
Such instrumentation is available for leader-mounted, bottom feed vibra-
tor systems and has been used in Europe since the 1980s (Slocombe and
Moseley 1991).
Vibro compaction and vibro replacement are increasingly evaluated by
means of 2D and 3D plots whereby areas of inhomogeneous soil can be
detected. To monitor the installation quality covering a large area, the
programme ‘VibroScan’ visualises automatically recorded vibro data, like
depth, compaction energy, and activation force. Borelogs from core drill-
ings, cone penetration tests, and standard penetration tests (SPT) represent
only punctual explanations, which can never show the entire ground. After
Deep vibro techniques 43
Process:
Inventar: 9130744 Site: 331297
Lot: 96 Point: 156 Ref. No.: 13
Date: 08.04.03 Time: 13:23:08 Interval: 2 sec
3
Weight: 16.0 kN/m Dep.: Consulting and development
Legende:
200
400
600
800
1000
1200
Total time: 19.85 min Col. Length: 7.3 m Depth 7.3 m
Figure 2.17 Typical printout for stone column construction. (Courtesy of Keller Group.)
collecting the data of all compaction points with VibroScan, a planar over-
view of the entire area of the ground improvement is displayed. Such areas
are highlighted whose soil conditions deviate from the remaining area, and
therefore a deviating quality of the ground after ground improvement mea-
sures is shown. The execution grid can be adapted to the respective soil
44 Ground improvement
Beginning with the ratiication of the Kyoto Protocol in 1997, the awareness
of the global warming effect has risen all over the world. Approximately
1/5 of global greenhouse gas emissions are associated with the manufac-
turing and construction industries. In recent years, the awareness of the
carbon footprint has reached the construction industry, leading to sev-
eral certiicates for buildings and engineering structures. The foundation
of a building can have a signiicant impact on the total carbon footprint,
Deep vibro techniques 45
900
750-800
800
660-690
700
kg CO2 - eq./m
600
500
400
300 243-247
200 134-141139-143
70-73 79-82 92-96
100
7-10 10-12 42-45 55-58
0
VSC VSC VMC VCC VMC CF VCC CFA DSM DSM BP BP
with with with with with ∅ with ∅ with with ∅ ∅
gravel ballast BC BC PC 45 cm PC 64 cm BC PC 60 cm 90 cm
Figure 2.18 CO2 equivalents for ground improvement and/or deep foundation meth-
ods. VSC = vibro stone columns, VMC = vibro mortar columns, VCC =
vibro concrete columns, CFA = continuous light auger piles, DSM = deep
soil mixing, BP = bored piles, PC = Portland cement, BC = blast furnace
cement. (From Zöhrer, A., Wehr, W., and Stelte, M. (2010). Is ground engi-
neering environmentally friendly? Proceedings of the 11th International EFFC-
DFI Conference, Session 3: Sustainability in the Foundation Industry, May 26–28,
2010, London, England.)
46 Ground improvement
addition to these ield trials and load tests, numerical calculations have been
executed to examine additional soil improvement effects by means of stiffness
improvement of the soil surrounding the columns and stiffness improvement
by means of displacement effects between columns. The static load tests and
the numerical calculations resulted in a required stiffness modulus of 21 MN/
m2 and a stone column pattern of 2.75 m × 2.75 m. To be on a safe side, an
execution point distance pattern of 2.5 m × 2.5 m was chosen. For some
single footings, a reduction of the point distance to a smaller pattern was nec-
essary to meet the settlement criteria. All compaction points were identiied
by means of GPS technology. The friction angle of the stone columns, used in
the numerical calculations was obtained by means of laboratory shear tests
prior to the design works, resulted in a friction angle φ = 57°. After inishing
of the soil improvement works, the settlements have been observed during the
ongoing construction of roads and bridges. The measured settlements stayed
clearly below the forecasted values (Kirsch et al. 2009).
Soil investigation was carried out in and around the facility by means of
boreholes. Soil proiles for approach roads and hard standing pavements
showed marine clay down to 10 m, with SPT N = values of 2 to 4, underlain
by weathered rock/bedrock with SPT N > 50.
Both the approach roads and hard standing pavements have to be
designed for the heavy trafic loads during the transportation of the 400-
ton shipbuilding hull blocks to the ship assembly area. The long term settle-
ments were to be less than 200 mm and 150 mm for the hard standing
pavements and approach road section, respectively.
Vibro stone columns were chosen as a foundation solution to meet these
settlement limits. The design of the stone columns was carried out in accor-
dance with Priebe’s (1995) method. In order to meet the performance cri-
teria, 900-mm-diameter columns were executed. The average installation
depth was 12 m, with a triangular grid spacing of 2.5 m centre-to-centre. A
section of stone columns along the approach road and hard standing pave-
ment is shown in Figure 2.20.
Several vibro rigs with crane-hung vibrators were used to complete the
installation works. About 144,000 linear metres of vibro replacement col-
umns were installed in 2008 and 2009 to treat a total area of 57,500 m2. To
ensure quality and that the columns were consistently formed, the installa-
tion works were monitored and logged in real time by computers (Raj and
Dikshith 2009).
14 m
road
400 tons
hull block
3m Transport 3 m
median vehicle median
1 m thick pavement
0.00
Moorum filling
–2.5
900 mm ∅
Marine clay stone column
–12.5
Hard strata
Figure 2.20 Typical section of approach road with vibro replacement columns. (From
Vibro replacement columns for shipyard infrastructure at Pipavav, Gujarat,
India. In: Leung C.F., Chu J., Shen R.F. (eds.) Ground Improvement Technologies
and Case Histories, Singapore: Research Publishing Services, pp. 763–769.)
Deep vibro techniques 49
Pump TNB
Legend: sub-station
station
Vibro concrete columns
N
Figure 2.21 Different ground improvement methods for the sewage treatment plant
(From Keller (2009). Brochure 10-65E: Foundation Works for a Sewage
Treatment Plant Using Ground Improvement Methods in Malaysia.)
50 Ground improvement
2.9 CONCLUSIONS
Vibro systems have proven over 70 years to offer safe and economic meth-
ods of improving weak soils for a wide range of applications. Vibro com-
paction has been used to densify granular soils to signiicant depths (65 m),
and the ability of this technique to reduce the risk of liquefaction during
an earthquake is well documented. Vibro replacement is a widely accepted
technique for improving cohesive and ine-grained soil to support a wide
range of structures. Vibro concrete columns are a good alternative to piles.
REFERENCES
Achmus, M., Wehr, W., and Spannhoff, T. (2010). Building vibrations due to deep
vibro processes. Proceedings of the 7th International Conference on Ground
Improvement Techniques, June 23–25, 2010, Seoul, Korea, pp. 33–42.
Almeida, M.S.S, Jamiolkowski, M., and Peterson, R.W. (1991). Preliminary result
of CPT tests in calcareous Quiou sand. Proceedings of the International
Symposium on Calibration Chamber Testing, June 28–29, 1991, Potsdam,
New York, United States, pp. 41–53.
Arbeitsgruppe Untergrund-Unterbau der Forschungsgesellschaft für das
Straßenwesen (AUFS) (1979). Köln, Merkblatt für die Bodenverdichtung im
Straßenbau.
Baez, J.I. (1995). A Design Model for the Reduction of Soil Liquefaction by Vibro
Stone columns, PhD Thesis, University of Southern California, United States.
Baez, J.I. and Martin, G.R. (1992). Liquefaction observations during installation
of stone columns using the vibro replacement technique, Geotechnical News,
10(3): 41–44.
Balaam, N.P. and Booker J.R. (1981). Analysis of rafts and granular piles,
International Journal for Numerical and Analytical Methods in Geomechanics,
5: 379–403.
Deep vibro techniques 51
Bell, A.L. (1915). The lateral pressure and resistance of clay and the supporting
power of clay foundations. In: A Century of Soil Mechanics, London, England:
Institution Civil Engineers, pp. 93–134.
Bellotti, R. and Jamiolkowski, M. (1991). Evaluation of CPT and DMT in Crushable
and Silty Sands: Third Interim Report ENEL/CRIS, Milano, Italy.
Bergado, D.T., Chai, J.C., Alfaro, M.C., and Balasubramaniam, A.S. (1994).
Improvement Techniques of Soft Ground in Subsiding and Lowland
Environment. Rotterdam, Netherlands: Balkema.
Brauns, J. (1978). Die Anfangstraglast von Schottersäulen in bindigem Untergrund.
Bautechnik 55(8):263–271.
Brauns, J. (1980). Untergrundverbesserungen mittels Sandpfählen oder
Schottersäulen. Tiefbäu, Ingenieurbau, Straßenbau 8:678–683.
Brennan, A.J. and Madabhushi, S.P.G. (2002). Liquefaction remediation by verti-
cal drain groups, Proceedings of the International Conference on Physical
Modelling in Geotechnics, St. John’s, Newfoundland, July, pp. 533–538.
British Research Establishment. (2000). Speciiying Vibro Stone Columns.
Chambosse, G. and Kirsch, K. (1995). Beitrag zum Entwicklungsstand der
Baugrundverbesserung, Schriftenreihe des Lehrstuhls und Prüfamtes für
Grundbau, Bodenmechanik und Felsmechanik der Technischen Universität
München, Munich, Germany, pp. 411–426.
Covil, C.S., Luk, M.C.W., and Pickles, A.R. (1997). Case history: ground treatment
of the sand ill at the new airport at Chek Lap Kok, Hong Kong. Proceedings
of the 3rd International.Conference on Ground Improvement Geosystems,
London, England, pp. 149–156.
Cudmani, R.O. (2001). Statische, alternierende und dynamische Penetration in nich-
tbindigen Böden, Dissertation, Karlsruhe University.
Cudmani, R.O., Osinov, V.A., Bühler, M.M., and Gudehus, G. (2003). A model
for the evaluation of liquefaction susceptibility in layered soils due to earth-
quakes, 12th Pan-American Conference on Soil Mechanics and Geotechnical
Engineering, Cambridge, Massachusetts, United States, Vol. II, pp. 969–976.
Engelhardt, K.and Golding, H.C. (1975). Field testing to evaluate stone column per-
formance in a seismic area. Géotechnique 25(1):61–69.
European Standard EN 14731. (2005). Ground Treatment by Deep Vibration.
European Standard EN 15237. (2007). Ground Treatment by Vertical Drainage.
Fellin, W. (2000). Advances in Geotechnical Engineering and Tunnelling:
Rütteldruckverdichtung als plastodynamisches Problem, Vol. 3, Rotterdam,
Netherlands: A.A. Balkema.
Foray, P.Y., Nauroy, J.-F., and Colliat, J.L. (1999). Mechanisms governing the
behaviour of carbonate sands and inluence on the design of deep founda-
tions, Proceedings of the 2nd International Conference on Engineering for
Calcareous Sediments Vol. 1, February 21–24, 1999, Bahrain, pp. 55–68.
Forschungsgesellschaft für das Straßenwesen (FGFS). (1979). Merkblatt für die
Untergrundverbesserung durch Tiefenrüttler.
German Patent: Nr. 22 GO 473.
Goughnour, R.R. and Bayuk, A.A. (1979). Analysis of stone column–soil matrix
interaction under vertical load. Paris Colloque International Renforcement
des Sols: Terre Armée et Autres Méthodes, Vol. 1, March 20–22, 1979, Paris,
France, pp. 271–277.
52 Ground improvement
Van Impe, W.F. and Madhav, M.R. (1992). Analysis and settlement of dilating stone
column reinforced soil. ÖIAZ: Österreichische Ingenieur- und Architekten-
Zeitschrift 137(3):114–121.
Vesic, A.S. (1965). Ultimate loads and settlements of deep foundations in sand.
Proceedings of the Symposium on Bearing Capacity and Settlement of
Foundations in Sand, Duke University, Durham, North Carolina, United
States, pp. 53–68.
Wehr, J. and Raju, V.R. (2002). On- and offshore vibro compaction for a crude
oil pipeline on Jurong Island, Singapore; International Conference on Ground
Improvement Techniques, Malaysia, pp. 731–736.
Wehr, W. (1999). Schottersäulen – das Verhalten von einzelnen Säulen und
Säulengruppen, Geotechnik 22(1):40–47.
Wehr, W. (2004). Stone columns—single columns and group behaviour, Proceedings
of the 5th International Conference on Ground Improvement Techniques,
March 22–23, 2004, Kuala Lumpur, Malaysia, pp. 329–340.
Wehr, W. (2005). Variation der Frequenz von Tiefenrüttlern zur Optimierung der
Rütteldruckverdichtung, Proceedings of the 1st Hans-Lorenz-Symposium,
October 13, 2005, Berlin, Germany, pp. 67–78.
Wehr, W. (2005a). Inluence of the carbonate content of sand on vibro compaction,
Proceedings of the 6th International Conference on Ground Improvement
Techniques, July 18–19, 2005, Coimbra, Portugal, pp. 625–632.
Wehr, W. (2006). The undrained cohesion of the soil as criterion for the column instal-
lation effect with a depth vibrator, Transvib 2006: International Symposium
on Vibratory Pile Driving & Deep Soil Vibratory Compaction, November 12,
2005, Paris, France, pp. 157–162.
Wehr, W. (2006a). Stone columns – group behaviour and inluence of footing lexibil-
ity. Proceedings of the Sixth European Conference on Numerical Methods in
Geotechnical Engineering, September 6–8, 2005, Graz, Austria, pp. 767–772.
Wehr, W. (2008). Offshore Schottersäulen in Singapur und Malaysia, Darmstädter
Geotechnik Kolloquium, Technischen Universität Darmstädt, March 13, 2008,
Darmstädt, Germany, pp. 85–93.
Yee, Y.W., Chua, C.G., and Yandamuri, H.K. (2009). Foundation works for a sewage
treatment plant using ground improvement methods in Malaysia. In: Leung
C.F., Chu J., Shen R.F. (eds.) Ground Improvement Technologies and Case
Histories, Singapore: Research Publishing Services, pp. 677–684.
Zöhrer, A., Wehr, W., and Stelte M. (2010). Is ground engineering environmentally
friendly? Proceedings of the 11th International EFFC-DFI Conference, Session
3: Sustainability in the Foundation Industry, May 26–28, 2010, London,
England, on DVD.
Chapter 3
Dynamic compaction
Barry Slocombe
CONTENTS
3.1 INTRODUCTION
57
58 Ground improvement
3.2 HISTORY
safely. As a result the Health and Safety Executive in Britain requires that a
crane should operate at not more than 80% of its safe working load. Some
cranes are better suited than others to the rigours of this type of work, even
though on paper they appear to be of similar capacity.
Recent crane developments allow automation of the whole work cycle.
This is controlled by a data processing unit that plots for each compaction
point its location, number, weight size, drop height, number of blows, and
measurement of imprint achieved. A particular feature of one European
crane is the free-fall winch, which adjusts the rope length automatically
after each blow. Some cranes include the ability for synchronous operation
of two winches to lift larger weights than the conventional crane rating.
The majority of British and American contracts have utilised weights
within the range of 6 to 20 tonnes dropped from heights of up to 20 m.
The majority of UK work is now performed using 8-tonne weights dropped
from heights of up to 12 m. Standard crawler cranes have also been used in
America for weights of up to 33 tonnes and 30 m height. Specialist lifting
frames with quick release mechanisms have been utilised to drop weights
of up to 50 tonnes, and Menard built equipment to drop 170 tonnes from
22 m height in France. In America, and increasingly in Britain, the system
is known as dynamic deep compaction.
Weights are typically constructed using toughened steel plate, box-steel
and concrete, or suitably reinforced mass concrete where durability is the
prime requirement. The effect of different sizes and shapes of the weight
has also been extensively researched with narrower weights generally
being used to speciically drive material down to depth to form dynamic
60 Ground improvement
3.4 TERMINOLOGY
The original concept for dynamic compaction was to collapse voids, particu-
larly for the treatment of natural sands plus granular, mixed, and cohesive
ills. This was then extended to iner natural soils where the high impact
energy effectively provided localised surcharge to squeeze water out of silts
and clays, this being termed dynamic consolidation. Dynamic replacement
was then developed to drive large-diameter columns of coarse imported mate-
rials through soft near-surface soils, particularly for peat and Sabkha strata.
The worldwide use of dynamic compaction has resulted in a large number
of important terms, some of which can have different meanings to differ-
ent nationalities or could be confused with other geotechnical descriptions.
The following terms have been adopted in Britain:
(6) ‘Recovery period’ is the time allowed between tamping passes to per-
mit the excess pore pressures to dissipate to a low enough level for
the next pass.
(7) ‘Induced settlement’ is the average reduction in general site levels as
a result of the treatment.
(8) ‘Threshold energy’ is the energy input beyond which no further
improvement can practically be achieved or where adverse response
starts to develop.
(9) ‘Overtamping’ is a condition in which the threshold energy has been
exceeded, sometimes deliberately, causing remoulding and dilation
of the soil.
(10) ‘Shape test’ is the detailed measurement of a single or group of
imprint volumes and surrounding heave or draw-down effect, which
permits comparison of overall volumetric change with increasing
energy input.
(11) ‘Imprint’ is the crater formed by the weight at a tamping location.
reduced drop height. The surface layers then receive a continual tamp of
a small number of drops from low height on a continuous pattern. It is
sometimes feasible to combine, and sometimes necessary to subdivide, the
basic tamping passes for the reasons outlined in the subsequent discussion.
The performance of increasing correctly controlled total energy input
will normally lead to better engineering performance of the treated ground.
However, analysis of several hundred contracts where in-situ and large load-
ing tests were performed has shown that this is not a linear relationship and
that the post-treatment parameters are heavily dependent upon the charac-
teristics of the soil. As a general rule, similar total energies, whether per m 2
of area or m3 of treatment depth, provide better performance to granular
than mixed soils. Mixed soils are then better treatable than cohesive, with
refuse-contaminated soils generally offering the least performance.
For treatment using RIC the operator monitors and can record the num-
ber of impacts, the total energy input applied, the foot penetration per blow,
and the cumulative penetration. When a speciied parameter is reached, for
example, foot penetration or set per blow, the RIC equipment is moved
and positioned at the next treatment point. This primary treatment pass is
normally performed on a closely spaced grid pattern, typically 1.5 to 2.5 m.
Additional offset and/or lower energy passes, or conventional proof roller
compaction, are occasionally performed to achieve better coverage.
Original level
Level after tamping
Hard
plug
Water table
Volume
(positive)
Resultant
(loose soils)
Imprint volume
(loose soils)
Resultant
(dense soils)
Draw down
(loose soils)
3
5
83 B
10
However, below the water table the higher proportion of ines developing
with increasing energy input results in a rapid change from a granular to a
pseudo-cohesive soil response.
The existence of very dense layers within the ground can cause anom-
alous results. Where, for example, cemented layers occur within natural
sands, these tend to absorb the energy impulse and arch over the underlying
stratum. A similar phenomenon can occur with vibro treatment where the
cemented zones do not collapse around the vibrator to permit densiica-
tion to occur. In these situations, where they occur at shallow depth, the
dynamic compaction will break up the cemented layer. However, at greater
depth, the energy levels required to break the stratum may be beyond the
capabilities of the equipment on site. The presence of such layers is often
not adequately revealed by normal site investigation.
In summary, excellent engineering performance can easily be achieved in
dry granular soils using both DC and RIC equipment. However, care must
be exercised for the treatment of soils with signiicant silt content, particu-
larly below the water table.
Water table
Volume
(positive)
Resultant
(dry soils)
Where the clays occur below the water table, a much larger reduction in
moisture content is generally required in the presence of a smaller available
pore-pressure gradient and a longer drainage path. These conditions can, if
not properly controlled, result in the threshold energy being achieved much
more rapidly and resulting in localised failure of the clay matrix. Control is
then achieved by using greater numbers of tamping passes of lower energy
input, requiring greatly extended contract periods in comparison to normal
productivity.
To date, only nominal degrees of improvement have been achieved in thick
layers of relatively weak saturated alluvial clays and silts, even with addi-
tional measures such as drainage trenches illed with sand or wick drains.
Where such layers are relatively thin and require treatment, a better speed
of response is recorded due to the shorter drainage path. In some instances
coarse granular material is driven into these materials to provide better grad-
ing that is more suited to treatment, or to displace from speciic locations
beneath part of a building area. It is, however, more common in the UK to
adopt vibro stone columns in such soils to more critical locations, such as
more heavily loaded foundations, and then perform dynamic compaction to
Dynamic compaction 67
preload the ground (see Slocombe 1989) with the beneit of the stiffer col-
umns also acting as drains to control excess pore-water pressures.
For predominantly clay-type ill materials above the water table, the
clay lumps can be considered as large weak particles of almost granular
response. However, the major improvement is achieved by collapsing voids
to provide a more intact structure. Clearly the strength of the lumps and
sensitivity of the clay is of paramount importance in such soils. Differing
degrees of weathering can also give rise to markedly variant responses on
a site and experienced observation is required to deine such locations.
Mudstone and shale fragments can break down to a material of clayey
response, particularly when heavy rainfall occurs.
For clay-type ills below the water table, the voided structure allows
higher mobility of water causing lower excess pore pressures and shorter
recovery periods in comparison to natural clays. The constituents would
be of higher moisture content but again improvement would be achieved
mainly by collapse of voids. Monitoring of excess pore-water pressures by
means of piezometers is clearly useful but problematic above the water table.
It cannot be emphasised too strongly that the treatment of clay ills and
clay soils requires experienced control on site. During treatment, after a
small number of drops, heave starts to develop around the edges of each
imprint. If tamping continues, the heave can build up to such an extent that
it can exceed the volume of the imprint. Clearly this is the precise opposite
of what is desired. Also, additive heave can occur by the performance of the
adjacent tamping position at too narrow a grid dimension.
Particular care has to be exercised in the timing of successive tamping
passes to permit adequate recovery of pore pressures to avoid excessive
remoulding of the soils. Such approach can however be relatively slow and,
in view of the emphasis placed these days on productivity, the vibro stone
column in advance of dynamic compaction method described above is
sometimes adopted.
If excessive heave around an individual imprint does start to occur, it
is essential that the tamping at that position be stopped. This may only
extend over a relatively conined area with better ground elsewhere. In soft
areas it is better that twice the number of lighter energy input tamping
passes be performed in a ‘softly softly’ approach.
Similar considerations apply when attempting to provide treatment to a
signiicant depth where the surface layers are clayey. The strength of the
surface soils can reduce in the short term and time has to be spent improv-
ing a disturbed matrix to reconstitute its original, let alone desired, proper-
ties. This is particularly dificult where thick crusts to, say, 2–3 m depth
of stiff to very stiff clays overlay a granular deposit requiring treatment. In
this situation even higher than normal energies are required to attain the
deeper layers giving rise to even greater potential for virtually destroying
the surface soils.
68 Ground improvement
2m
4m
6m
8m
Before treatment
The treatment of clayey soils will nearly always require a larger number
of tamping passes when compared to a similar proile of predominantly
granular constituents. Eficient treatment is achieved by attempting to pro-
vide as much improvement as quickly as possible while recognising that
the response of the soils will dictate the speed of the treatment operations.
Clay soils will continue to improve for a signiicant period after treat-
ment as reported by West (1976). Figure 3.5 illustrates further measure-
ments on this site taken ive years after treatment.
In summary, dry cohesive ills respond well to dynamic compaction.
Care must be exercised in the treatment of weak natural clayey soils or clay
ills below the water table. The prior performance of vibro stone columns
to both stiffen the ground and enhance drainage has been successfully com-
bined with dynamic compaction to weak clayey soils.
3.5.3 Landfills
The capability of dynamic compaction to treat every square metre of road
and parking areas is increasingly used in the development of former landill
sites where, depending on their age, the original degradable constituents
Dynamic compaction 69
have decayed to create extensive voids. It has also been performed to reduce
ground levels to avoid costly removal to specialist tip to permit develop-
ment at the desired site level.
As a general rule, the older the landill, the less the residual presence
of matter susceptible to long-term decay and some older ills, particularly
those of high ash content, have been compacted to also support structures
that would normally be piled. However, the more recent ills generally con-
tain signiicant proportions of organic matter and structures would nor-
mally be piled.
There is as yet little documented proof that dynamically compacted
landill can affect the rate of decay of residual degradable constituents,
although a paper by Sharma and Anirban (2007) clearly records far bet-
ter post-treatment performance at creep rate of 2% per log cycle than for
static surcharge over a monitoring period of about 15 years. As there will
be ongoing decay, when this technique is combined with piled structures,
increasing differential settlements will become apparent with time and a
degree of maintenance may be required at some future time.
The principle of treatment to landills is comparable to the treatment of
mixed clayey ills but with generally higher energy input than for inert ills.
This is to collapse near-surface voids and to ‘‘overcompact’’ the remaining
inert constituents. If a void then starts to develop due to localised long-
term decay, the inert materials will tend to ravel into the void, bulk up, and
spread the void effect rather than have a localised sharp deformity in the
inished surface. Geogrids have also been used for a number of sites where
the movements of heavy goods vehicles were critical to the development
operations.
Many landill sites have clay capping with basal clay liners to avoid down-
ward migration of leachate into an aquifer. The DC drop energy should be
limited to avoid shearing of the basal clay liner and care exercised in the
design of the treatment operations to avoid the surface clays developing into
a quagmire when attempting to apply the higher than for inert ill energy
input to signiicant depth.
As with vibro designs, the extent of the site investigation should be appro-
priate to the type of development. For deep ill sites, desk studies to estab-
lish the locations of buried high walls plus age and degree of control of
placement are essential data. Water contents for comparison with liquid
and plastic limits should be performed for clayey constituents. Densities
as revealed by SPT and CPTs plus the basal soils, whether clay, sand, and
gravel or rock are also required. The presence of any overhead wires, bur-
ied services, or nearby structures should also be established.
Menard originally proposed that the effective depth of treatment was related
to the metric energy input expression of (WH)0.5 where W is the weight in
tonnes and H the drop height in metres. This was modiied by a factor of
0.5 by Leonards et al. (1980) for relatively coarse, predominantly granu-
lar soils, and factors of 0.375 to 0.7 by Mitchell and Katti (1981) for two
soil types. The most exhaustive analysis yet published has been provided
by Mayne et al. (1984). The author suggests that the range of treatment
depths varies with initial strength, soil type and energy input as illustrated
in Figure 3.6, as well as the depth to the groundwater table. Figure 3.6 sug-
gests that factors as high as 0.9 could apply for shallow depths of loose soils
and as low as 0.25 for deeper treatment.
There are many factors affecting this dimension, not least of which are
the type and competence of the surface layers, position of the water table,
and numbers of drops at each location. Assessment of in-situ results to
determine such depths also tends to be subjective and will be affected by
the recovery period after treatment. As noted in the previous section, a
solid ‘plug’ of very dense material can form beneath the impact locations to
inhibit the improvement to depth. Weak surface soils and a high water table
Dynamic compaction 71
Depth of
influence (m) D = √WH D = 0.5 √WH
15
Loose or
10 weak soils
Stiffer or
dense soils
5
5 10 15 20 25 30
√WH
As noted earlier, high-impact energies can weaken the surface layers, and
the aim is therefore to combine effects to achieve improvement through-
out the whole of the desired treatment zone. For example, on a project
in Saudi Arabia, drop height, numbers of drops, and the treatment grid
were adjusted to provide treatment to three distinct sand layers requir-
ing improvement in a single tamping pass (Dobson and Slocombe 1982).
Clearly, if all structures are founded at depth there is no need for the inal
tamping pass for treatment to the surface layers, provided the grid of the
earlier tamping passes produces overlapping effects at the founding level.
40
30
20
10
10 20 30 40 50 60 70
Distance (m)
Large weight
Dynamic
Normal compaction
Vibro
There are a number of practical factors that must be taken into account
when performing dynamic compaction contracts. The large crawler crane
must be safely supported by a free-draining working surface, the thickness
of which will depend upon the type of ground being treated. If the surface
1.0 m layer is basically granular, no imported working carpet is generally
required. However, when working from a sandy surface, particularly dur-
ing wet weather, ly-debris has been seen ejected through the air up to 60
m from the point of impact. If work is carried out near roads, railways, or
property, a moveable screen is often used to intercept such ly-debris, albeit
these affect productivity. Alternatively, the programme should contain suf-
icient lexibility to permit treatment to be performed within, say, 50 m of
such features only when the surface conditions permit its safe operation.
Dynamic compaction 75
As the RIC foot remains in contact with the ground, there tends not to be
ly-debris issues with this equipment.
Where cohesive surface conditions exist, a free-draining granular work-
ing carpet is normally required. The thickness can be as little as 150 mm
for light energy treatment in reasonably competent soils up to 1.5 m when
treating heavily voided refuse ills. When aiming for substantial depth of
treatment, thick working carpets of 1.0 m or more have been found to
inhibit the stress impulse. A more eficient operation, which also provides
greater control of backill quantities, is to start with only 0.5 m thick-
ness and to backill imprints directly, thus preserving the working carpet
for successive tamping passes. In such cases it is useful to compare the
imported quantities to the assessed volume of the directly inilled imprints.
The most commonly adopted approach is to blade these preferably coarse
(up to 200 mm or single brick size) granular materials into the localised
deep imprints using a large dozer. In such cases it is useful to perform a
grid of levels before and after treatment to assess the induced settlements.
Winter working will place more onerous requirements on the adequacy
of the working surface. The general rule is to increase the depth of the gran-
ular working carpet by 25% in comparison to summer thickness. When
working in arid climates, there is often no need for any working surface,
even for clayey soils.
As the performance of dynamic compaction tends to induce increases
in water pressures, a pre-existing groundwater table within about 1.0 to
1.5 m of the working level can inhibit the productivity of the technique. In
such cases bottom-feed vibro stone columns may be the preferred approach.
Safe working is a prime consideration. If more than one rig unit is to
be used, they should be separated by at least 30 m. Similarly, subsequent
operations by the main contractor may have to be delayed until the treat-
ment operations are suficiently remote. Whilst dynamic compaction can
be performed over areas of vibro stone columns it has to be performed
before any adjacent piling operations to avoid possibly damaging the con-
structed piles.
The general densiication and collapse of voids will induce general reduc-
tion in site levels, the induced settlement being dependent on the total
energy input and the manner in which it is applied. Initial shape tests are
performed when the soils are loosest. As such, simple extrapolation of these
results will overestimate the amount of induced settlement. Mayne et al.
(1984), as part of his survey of 124 different sites, reported that the magni-
tude of induced settlement depended on the applied total energy input, also
stating that the thickness of the layer was probably an important factor for
76 Ground improvement
six soil types. This analysis does not, however, take into account either the
initial softness/density of the soils or the proportion of total energy applied
by the high velocity initial passes or low velocity inal tamping pass that
numerically is very signiicant in determining total energy input. Also, the
application of too high an energy in clayey soils will result in less than opti-
mum induced settlement occurring in practice.
A convenient simple approach is to adopt approximate percentages of
the target treatment depth for 8-tonne (50 to 100 tonne-metres/m 2) and
12-tonne equipment (100 to 200 tonne-metres/m 2), the total energies with
the 12-tonne energy applying to greater depth of treatment.
Higher percentages can be induced. However, the increase in energy
input will not be linear (e.g., to increase from 10%–15% induced volume in
refuse would require 200%–250% of the normal energy because during the
treatment the material becomes progressively stronger and there is less and
less potential void reduction available). Care has to be exercised to avoid
overtreatment and possible loss in strength in these situations, especially
since refuse tips tend to be capped by clay soils.
Loose materials will obviously settle more than denser soils. As noted
earlier, ash and certain types of slag also tend to break down during treat-
ment to produce induced movements towards the higher value for granular
ills given above (see Table 3.1).
3.12 TESTING
20 40 60 80 100 120
Load (tonnes)
10
20
30 Granular
Cohesive
40
Settlement
(mm)
3.12.2 Pressuremeter
The dynamic compaction technique has been historically associated with
this test. While this method is often used in mainland Europe, it is now
rarely used in Britain.
3.12.5 Dilatometer
This method would appear to have potential. However, no information has yet
been published for its evaluation of the treatment of the soils and ills of Britain.
using three tamping passes with 8-tonne weight and drop heights of up to
12 m to achieve an undrained Young’s modulus of 50 MPa, as proven by
1.5 × 1.5 m large plate test loaded to 150 kPa.
The construction of a football stadium in Poland required treatment to
depths of 15 m and 10 m beneath the stadium and pitch areas, respectively.
A minimum CPT qc of 15 MPa was speciied below 1.0 m depth to permit
the adoption of foundation design pressures of up to 300 kPa.
The upper 3–4 m depth comprised peat and organic silt. These were to be
excavated and replaced by sandy soils. The soils to about 10 m depth then
comprised ine silty sands of about 10% silt content with pre-treatment qc
of about 5 MPa. The sands then became slightly coarser with up to 5%
silt content and qc varying between about 6 and 15 MPa. The sands also
contained thin silty layers and occasional traces of organics. Groundwater
was at about 1.5 m depth. As there were existing structures on several site
boundaries, the ground improvement design was based on vibro compac-
tion to the deeper sands followed by dynamic compaction to the upper
layers. Extensive vibro trials were irst performed, followed by dynamic
compaction trials. These revealed that wide vibro compaction grids alone
could achieve the speciied qc > 15 MPa at depth, but not to the shallower
layers. Closer and/or secondary vibro compaction grids to suitable depth
could then be performed or the dynamic compaction be designed to treat
to greater depth. Comparative costings revealed the optimum approach to
be relatively wide vibro compaction grids followed by dynamic compac-
tion using a 16-tonne weight dropped in free-fall from almost 20 m height
to improve the upper 8 m depth of the sands. The high groundwater table
would, however, have inhibited the eficient performance of such DC treat-
ment, with water entering the deep imprints before the full drop numbers
could be performed, thereby requiring phased treatment passes with suit-
able recovery periods between. Site levels were therefore raised by about 1.0
m to permit just two DC treatment passes for faster programme.
Post-treatment testing by CPT conirmed all speciied criteria had been
achieved (see Figure 3.9) with recorded settlements induced by dynamic
compaction, performed after the vibro compaction, of about 200 to 300 mm.
6
Depth below ground level (m)
10
12
14
16
Before treatment 14 days after Vibro compaction (3.0m grid)
7 days after DC Acceptance criterion qc = 15MPa
ACKNOWLEDGMENT
The author extends his appreciation to the various companies within the
Keller Group for permission to publish this information.
REFERENCES
BRE Digest 403 (1995). Damage to structures from ground-borne vibration. Building
Research Establishment, Watford.
BRE Report BR 458 (2003). Speciication for Dynamic Compaction. Building
Research Establishment, Watford.
BS 5228-1 and 2 (2009). Code of practice for noise and vibration control on con-
struction and open sites. British Standards Institution.
BS 7385 (1990). Part 1. Evaluation and measurement for vibration in buildings.
British Standards Institution.
Institution of Civil Engineers (1987). Speciication for Ground Treatment. Thomas
Telford, London.
D’Appolonia, E. (1953). Loose sands—their compaction by vibrolotation.
Symposium on Dynamic Testing of Soils, American Society of Testing
Materials, STP, p.156.
Dobson, T. and Slocombe, B.C. (1982). Deep densiication of granular ills. 2nd
Geotechnical Conference, Las Vegas, Nevada. April 1982.
Greenwood, D.A. and Kirsch, K. (1983). Specialist ground treatment by vibratory
and dynamic methods—state of the art report. Proceedings, Piling and Ground
Treatment for Foundations, London, pp. 17–45.
Jamiolkowski, M. et al. (1985). New developments in ield and laboratory testing
of soils. Theme lecture, 11th Int. Conf. on Soil Mechanics and Foundation
Engineering, San Francisco.
Kerisel, J. (1985). The history of geotechnical engineering up until 1700. Proceedings,
11th International Conference on Soil Mechanics and Foundation Engineering,
San Francisco (August 1985), pp. 3–93.
Leonards, G.A., Cutter, W.A. and Holtz, R.D. (1980). Dynamic compaction of gran-
ular soils. J. Geotech. Eng., ASCE 106 (GT1), pp. 35–44.
Lucas, R.G. (1995). Geotechnical Engineering Circular No. 1: Dynamic Compaction,
US Department of Transportation, Publication No. FHWA-SA-95-037.
Lundwall, N.B. (1968). The Saint George Temple. Temples of the Most High,
Bookcraft, Salt Lake City, Utah, Chapter 3, p. 78.
Mayne, P.W., Jones, J.S. and Dumas, J.C. (1984). Ground response to dynamic com-
paction. J. Geotech. Eng., ASCE 110 (6), pp. 757–774.
Menard, L. and Broise, Y. (1976). Theoretical and practical aspects of dynamic con-
solidation. Proceedings, Ground Treatment by Deep Compaction, Institution
of Civil Engineers, London, pp. 3–18.
Mitchell, J.K. and Katti, R.K. (1981). Soil improvement – state of the art report.
Proceedings, 10th International Conference on Soil Mechanics and Foundation
Engineering, Stockholm (June 1981), pp. 509–565.
Dynamic compaction 85
Mitchell, J.K. and Solymar, Z.V. (1984). Time-dependent strength gain in freshly
deposited or densiied sand. J. Geotech. Eng., ASCE 110 (11), pp. 1559–1576.
Rollins, K.M. and Kim, J. (2010). Dynamic compaction of collapsible soils based on
US case histories. J. Geotech. Geoenviron. Eng., ASCE 133 (9), pp. 1178–1186.
Seed, H.B. and Idriss, I.M. (1971). Simpliied procedure for evaluating soil liquefac-
tion potential. J. Geotech. Eng., ASCE 97 (SM9), pp. 458–482.
Serridge, C.J. and Slocombe, B. (2012). Ground improvement. ICE manual of geo-
technical engineering. Eds. Burland, Chapman, Skinner and Brown. Chapter
84, pp. 1247–1269.
Serridge, C.J. and Synac, O. (2006). Application of the Rapid Impact Compaction
(RIC) technique for risk mitigation in problematic soils. Engineering Geology
for Tomorrow’s Cities. Eds. Culshaw, Reeves, Jefferson and Spink. Engineering
Geology Special Publication 22, Paper 294 (CD-ROM), Geological Society of
London.
Sharma, H.D. and Anirban, D. (2007). Municipal solid waste landill settlement:
Postclosure perspectives. Journal of Geotechnical and Geoenvironmental
Engineering, ASCE 133 (6), pp. 619–629.
Slocombe, B.C. (1989). Thornton Road, Listerhills, Bradford. Proceedings,
International Conference on Piling and Deep Foundations, London (May
1989), pp. 131–142.
West, J.M. (1976). The role of ground improvement in foundation engineering.
Proceedings, Ground Treatment by Deep Compaction, Institution of Civil
Engineers, London, pp. 71–78.
Chapter 4
CONTENTS
87
88 Ground improvement
4.1 INTRODUCTION
The size of the PVDs has been standardised to a width of around 100 mm
and a thickness of 3 to 6 mm. Although PVDs are used for almost all the
projects, sand drains are still in use for some special projects. One example
is the Kansai International Airport where 400 mm diameter sand drains
were installed from an offshore barge into the soft seabed soils (Kitazume,
2007). PVDs made of natural products such as jute or coconut coir (Lee
et al., 2003) are also available.
A great deal of experience and development in both research and con-
struction have been accumulated in the past as a result of the extensive
use of PVDs. Two books devoted exclusively to the use of PVDs for soil
improvement have been published (Holtz et al., 1991; Bo et al., 2003).
A number of other books and reports with good coverage of PVDs have
also been published. These include Mitchell and Katti (1981), ICE (1982),
Jamiolkowski (1983), Akagi (1994), Bergado (1996), Moseley and Kirsch
(2004), Raison (2004), Hansbo (2005), Indraratna and Chu (2005), Chu
et al (2009a), and Chu et al. (2012).
This chapter intends to provide a practical guide to researchers and
practicing engineers who have to deal with design and construction issues
related to PVDs. It also tries to introduce briely the latest development and
technologies in the use of PVDs. Two case studies are also given to illus-
trate the real operation of soil improvement using PVDs.
∂ue ∂ 2 ue kv
= cv and cv = (4.1)
∂t ∂z 2 mvγ w
90
Method Description/Mechanisms Typical applications Advantages Limitations
Ground improvement
Preloading A. Preloading Preloading is a process to apply The method is Rate of consolidation can be The method may not be
methods using ill with surcharge load on to ground applicable to soils greatly accelerated. The applicable when the
vertical drains prior to the placement of having low construction time can be construction schedule is very
structure or external loads to permeability or when controlled by adjusting the tight or when the ground is
consolidate the soil until most the compressible soil spacing of the drain. so soft that vertical drains
of primary settlement has layer is thick. cannot be installed.
occurred.Vertical drains are
used to provide radial
drainage and accelerate the
rate of consolidation by
reducing the drainage paths.
B. Vacuum The method is the same as A, The method is 1). The method does not 1). This method causes
preloading except the surcharge is applicable to ground require ill material; inward lateral movement
with vertical applied using vacuum and consists of mainly 2). The construction and cracks on the ground
drains pressure. The vacuum saturated, low period can be shorter, surface, which may affect
pressure is usually distributed permeability soils. The as no stage loading is surrounding buildings or
through vertical drains. It also method can be used required; structures;
provides immediate stability when there is a 3). It may be more 2). The vacuum pressure is
to the system. The treated stability problem with economical than using limited to 50–90 kPa,
soil is enclosed by an air- and ill surcharge. This ill surcharge; depending on the system
watertight barrier in all method can also be 4) The vacuum brings adopted.
directions. used to extract immediate stability to
polluted ground pore the system.
water, if required.
C. Combined ill The method is a combination The same as for A 1). Construction time can 1). It is technically more
and vacuum of A and B when a surcharge and B. be much reduced as demanding than A and B;
preloading more than the limit of vacuum compared to staged 2). Data interpretation is
with vertical pressure is required. loading using ill also more complicated.
drains surcharge alone;
2). The lateral movement
of soil can be
controlled by balancing
the amount of vacuum
and ill surcharge used;
3). The vacuum brings
immediate stability to
the system.
Dynamic D. Drainage This method improves the soil This method can be 1). This method makes the 1). The method may only
consolidation enhanced properties by combining the used to improve the application of DC work for cohesive soil
methods dynamic DC method with vertical bearing capacity of possible to ine-grained with relatively low
consolidation drains which facilitates the soft soil with low soil; plasticity index;
(DC) dissipation of pore water permeability. 2). The duration of soil 2). The compaction energy
pressure generated during improvement can be applied has to be within a
DC. reduced. certain limit, so that the
depth of improvement is
limited;
3). The technique has not
been fully developed.
Thus, the success of the
method cannot always be
guaranteed.
91
92 Ground improvement
mainly in the horizontal direction. In this case, the following radial con-
solidation theory is required (Barron, 1948):
∂2 u 1 ∂ue ∂ue kh
ch 2e + = and ch = (4.2)
∂r r ∂r ∂t mvγ w
∂ 2 ue ∂ 2 ue 1 ∂ue ∂ue .
cv + c h + = (4.3)
∂z 2
∂r
2
r ∂r ∂t
For ground improvement, the progress of consolidation of soil is evaluated
using the average degree of consolidation, U, of the compressible clay layer:
Sc (t)
U " 100% (4.4)
(Sc )ult
where Sc(t) is the consolidation settlement at a given time and (Sc)ult is the
ultimate consolidation settlement.
Using Terzaghi’s consolidation equation, Equation 4.1, and by assuming
the form of initial pore water pressure distribution, a relationship between
the average degree of consolidation and the time factor Tv = cvt/Hd2 can be
established as shown in Figure 4.1 or expressed approximately in equations
by curve itting. One of the closed-form equations is given by Sivaram and
Swamee (1977):
− 8Th
Uh = 1 − exp (4.6a)
F ( n )
n2 (3n 2 − 1)
F(n) = 2 ln(n) − ≈ ln(n) − 0.75 (4.6b)
(
n −1 ) 4 n2
Prefabricated vertical drains 93
0
0.1 m=∞
2 e –M2TV
UV = 1 – ∑
Average consolidation ratio UV
0.2 M2
m=0
0.3 (4TV /π)0.5
= 0.179
0.4 1 + (4TV /π)2.8
0.5
0.6 UV =
0.7
0.8
0.9
1
0.01 0.1 1 10
TV
Figure 4.1 Relationship between average degree of consolidation Uv and time factor Tv
derived based on solutions to Equation 4.1. (Redrawn from Bo, M.W., Chu, J.,
Low, B.K. and Choa, V. (2003). Soil Improvement: Prefabricated Vertical Drain
Technique, Thomson Learning, Singapore.)
ch t
Th = (4.7)
de2
de
n" (4.8)
dw
whereTh is the time factor, n is the ratio between the diameter of soil dis-
charging water into a vertical drain, de, and the diameter of the drainage
well or equivalent diameter of a vertical drain, dw, as shown in Figure 4 2.
In this igure, a and b are the thickness and width of band drain.
The solutions given in Equations 4.6 through 4.8 were developed for a
unit cell (i.e., a cylindrical column of soil surrounding a circular well, as
shown in Figure 4.2). A graphical illustration of the relationships between
Uh and Th for different n values is shown in Figure 4.3. The curve shown
in Figure 4.1 for vertical low is also plotted in Figure 4.3 for comparison.
However, it should be noted that a PVD band drain is not circular. It has
a typical width of 100 mm and thickness ranging from 3–6 mm. To use
Equations 4.6 through 4.8, a conversion to compute the equivalent drain
diameter, dw, is thus necessary. One conversion method based on an equal
perimeter has been proposed by Hansbo (1979) as:
2(a + b)
dw = (4.9)
π
94 Ground improvement
de
a
Band drain
0.1 n = 100
40
0.2
20
0.3
15
0.4
Uv and Uh
n = 10
0.5
7
0.6
5
0.7
n = de / dw
0.8 Vertical flow
0.9 Horizontal flow
1
0.01 0.1 1
Figure 4.3 Relationships between Uh and Th for different n according to Equation 4.6
and Uv and Tv according to Equation 4.5. (Redrawn from Bo, M.W., Chu, J.,
Low, B.K. and Choa, V. (2003). Soil Improvement: Prefabricated Vertical Drain
Technique, Thomson Learning, Singapore.)
Prefabricated vertical drains 95
The diameter of soil discharging water into a vertical drain, de, is depen-
dent on the drain spacing and the drain installation pattern. The de is calcu-
lated based on equivalent cross-section area. For PVDs installed in a square
grid pattern with a spacing s as shown in Figure 4.4a, de can be calculated as:
U de 2
s2 = , i.e., de = 1.128s (4.10)
4
For PVDs installed in a triangle grid as shown in Figure 4.4b, de can be
calculated as:
(1 − U ) = (1 − U ) × (1 − U )
vh v h
(4.12)
kh
F(n) ≈ ln(n) − 0.75 + π z(2l − z) (4.13)
qw
de
s s
de
It can be seen from Equation 4.13 that when qw is suficiently large, the
last term in Equation 4.13 will become very small so that the effect of well
resistance can be ignored. Some modern high-quality PVD products can
provide suficiently large qw. Therefore, well resistance may be ignored in
the design when PVDs with suficient large qw are used. Practically this
requires the qw value of PVDs to be speciically checked as part of the
quality-control process during the construction. It is thus important to
ensure that the PVDs are selected properly and the quality of the PVD
products is checked whenever PVDs are used for soil improvement (Chu
et al., 2004).
From Working Example 4.1, it can be seen that the consolidation due to
vertical drainage is normally small when the PVD is relatively long (say,
more than 10 m). Therefore, depending on the design situation, it is possi-
ble to design based on radial drain alone as a more conservative estimation.
Another commonly encountered design problem is to calculate the time
taken to achieve a certain degree of consolidation, Uvh, for a given PVD
installation scheme. When time t is not known, it is dificult to calculate
Tv and Th and thus Uv, Uh, and Uvh. There are three methods to solve this
problem.
Prefabricated vertical drains 97
(1) Take Uh = Uvh and calculate t using Equation 4.6 by ignoring the
contribution of vertical consolidation.
(2) By a trial and error method. The t calculated in method 1 can be
used as the irst estimate to calculate Uvh. If Uvh is greater than the
assumed, then a smaller t can be used to calculate Uvh again until the
Uvh value matches the assumed.
(3) Use a special function ‘‘GoalSeek’’ in the Microsoft Excel to carry
out iterations automatically to obtain the time required to achieve
the required degree of consolidation. The detail of the third method
and Excel code that can be used for this purpose are provided in Bo
et al. (2003).
It should be pointed out that these solutions are provided for perfect
drain conditions (i.e., the installation of PVDs does not affect the soil prop-
erties). However, during the PVD installation process, the soil around the
PVDs is disturbed or smeared. The ‘smear’ effect comes from the compress-
ibility of soil and the disturbance to the soil structure during the inser-
tion and removal of the mandrel (see Section 4.3 for details). The zone in
which the soil is disturbed or smeared is called the smear zone, as shown in
Figure 4.5. The diameter of the smear zone, ds, varies from soil to soil and
is also affected by the size of the mandrel. Based on past studies (e.g., Holtz
and Holm, 1972; Hansbo, 1981, 1983; Indraratna and Redana, 1998;
Onoue et al., 1991; Hird and Moseley, 2000; Xiao, 2002), Bo et al. (2003)
have proposed that ds to be estimated as:
dw
Vertical drain
Smear zone
Perfect drain
de/2
Undisturbed
clay
ds
ds = (4 to 7) dw or ds = (3 to 4) dm (4.14)
kh = (2 to 3) ks (4.15)
However, the study of Bo et al. (2003) and Chu et al. (2004) indicates that
the reduction in permeability can be as large as 2 to 10 times depending on
the sensitivity of the soil.
By taking the smear effect into consideration, Barron (1948) and Hansbo
(1979, 1981) have derived another set of consolidation equations by assum-
ing an annulus of the smeared clay around the drain with a diameter of ds
and a permeability of ks:
− 8Th
Uh = 1 − exp
)
Fs ( n
k
Fs (n) ≈ ln(n) − 0.75 + ln(s) h − 1 (4.16b)
ks
It should be pointed out that all the above analytical methods were
established based on Darcian low. For non-Darcian low, solutions have
also been provided by Hansbo (1997; 2001; 2004). However, the non-
Darcian low consolidation theory has not been widely used in practice.
Furthermore, the effect of non-Darcian low on one-dimensional consoli-
dation is negligible in the beginning of the consolidation process (Hansbo,
2004). As the non-Darcian low consolidation equations have been pre-
sented elsewhere (Hansbo, 1997; 2001; 2004; 2005), it will not be elabo-
rated in this chapter.
Note that the use of the analytical solutions presented above is restricted
to the assumptions of one-dimensional, linear-elastic, small strain behav-
iour of soil. The spatial variation of soil properties is also not taken into
consideration. For the modelling of two- or three-dimensional bound-
ary value problems with spatial variation of soil properties, such as con-
solidation under an embankment, the inite element analysis should be
used. Several numerical procedures have been developed for this purpose.
However, the coverage of these topics is beyond the scope of this chapter.
Interested readers are referred to Hird et al. (1992); Bergado et al. (1993b);
Chai et al. (1995; 2001); Indraratna and Redana (1997; 2000); Indraratna
et al. (2005); Rujikiatkanjorn et al. (2008); and Chu et al. (2012).
4.3 DESIGN
For the design of a soil improvement project using preloading and PVDs,
the following design and construction procedure can be adopted:
( oil profile
Soil
( Geotechnical properties
investigation
( Design parameters
PVD depth
and pattern
(square or
triangular)
To check
( AOS of the filter
PVD type Quality
( Permeability of the filter
selection control test
( "! #'
( ensile strength
Drain spacing
Settlement
check and
surcharge
plan
Install PVD
Spacing and
and quality
depth check
control
Check
degree of
consolidation
Check
specification
for design
adjustment
(1) The preconsolidation stress, σp′, and the overconsolidation ratio (OCR).
(2) The coeficient of consolidation in both horizontal and vertical direc-
tions, c h and cv.
(3) The coeficient of permeability in both horizontal and vertical direc-
tions, kh and kv.
(4) The diameter of the smeared zone, ds, and the permeability of the
smeared soil, ks.
(5) The coeficient of compressibility, C c, the coeficient of recompress-
ibility, C r, and sometimes the secondary compression index, C α , are
required for settlement estimation.
(6) The undrained shear strength, cu, and the undrained Young’s modu-
lus, E u, may also be required for analysing the stability of a dike or
the stability of a drain installation rig on soft clay.
*
TH d2 mvγ w ,…
t = = TH d2
cv kv
– dkv ,
dt = TH mv γ w2
d
kv2
dt TH mvγ w – dkv 1 – dkv – dkv
2
d
= = cv =
t t kv kv cv kv kv
Prefabricated vertical drains 103
settlement prediction for projects using vertical drains is the same as those
without the use of vertical drains. Those methods are covered in many
textbooks (e.g., Holtz and Kovacs, 1981). As far as land reclamation or the
other similar types of geotechnical problems (where the extent of load is
much greater than the thickness of the compressible layer) are concerned,
the settlement predicted using the one-dimensional analysis and param-
eters determined by laboratory tests is reasonable although not always reli-
able. Ground settlement should always be monitored as part of the soil
improvement works.
Different types of laboratory and in-situ tests that are suitable for the
determination of consolidation properties are discussed in detail in Chu
et al. (2002) and Bo et al. (2003). One example for the determination of the
c h values for the intact Singapore marine clay at Changi by different methods
is presented in Figure 4.7. Among the tests shown in Figure 4.7, the in-situ
tests and the Rowe cell test measure the c h values, whereas the conventional
oedometer test measures cv. The c h back-calculated based on the settlements
measured at different elevations are also presented in Figure 4.6. In the
back-calculation, the ultimate settlement was estimated based on Asaoka’s
method (Asaoka, 1978). As shown in Figure 4.6, the back-calculated c h
values were lower than the c h values determined by either laboratory or
in-situ tests. Similar observations have been made at other sites in the
Singapore marine clay (Chu et al., 2002) and by Balasubramaniam et al.
(1995) for the Bangkok clay. Prefabricated vertical drains were installed
at those sites at a close spacing. It implies that when vertical drains are
used in soft marine clay, the overall c h value of the soil will be lower than
the c h value of the intact soil. This could be due to the smear effect to soil
induced by the installation of vertical drains. The effect of disturbance can
be relatively large particularly when the drains are installed at a close spac-
ing (Chu et al., 2002).
It has been generally observed from the comparisons made in Figure 4.7
and the other cases that:
(a) The c h of soft clay determined by the Rowe cell test is generally 2–4
times larger than the cv by the conventional oedometer test, relecting
the anisotropic nature of the soil.
(b) The CPTU dissipation test tends to agree reasonably well with that
from the Rowe cell tests. Therefore, CPTU can be a good tool for c h
determination if it is calibrated properly.
0
SBPM
DMT
10
CPTU
Ch(Lab)
Depth (m)
20 Cv(Lab)
Field
30
40
0 5 10 15 20
Cv or Ch (m2/yr)
PVD where the core is adhered to the ilter, as shown in Figure 4.9. This
type of PVD offers a number of advantages over the ordinary type of PVDs.
For examples, it offers a higher discharge capacity and tensile strength as
discussed in detail by Liu and Chu (2009). The third type is circular PVDs.
A picture of it is shown in Figure 4.10. The circular PVD has better resis-
tance to buckling and has been used exclusively for vacuum preloading
projects (Chu et al., 2009).
It should be mentioned that there are different types of drains, such
as electric vertical drain with a metal foil embedded in the drains as
anodes and cathodes for electro-osmosis (Shang, 1998; Bergado et al.,
2000; Karunaratne, 2011). There are also PVDs for geoenvironmental
use. For example, PVDs have been used for a vapour extraction sys-
tem (Schaefer et al., 1997; Collazos et al., 2002). There have also been
100 ± 2 mm
5 ± 1 mm
Figure 4.9 Integrated type of PVDs. (Redrawn from Liu, H.L. and Chu, J. (2009).
Geotextiles and Geomembranes, Vol. 27, No. 2, pp. 152–155.)
108 Ground improvement
Figure 4.10 Circular type of drain used for some vacuum preloading projects.
The quality and suitability of the drains play a key role in the whole
soil improvement scheme involving PVDs. Different design situations
require different types of PVDs. For example, it is not necessary to use a
vertical drain with a high discharge capacity value if the drain is short.
The drain ilter should also match the soil type. The unit price of verti-
cal drain is another important consideration besides meeting the design
requirements. A considerable saving can be achieved without sacriicing
the performance of the drain, if the control factors for a vertical drain can
be identiied and the design requirements are speciied accordingly. The
factors that control the selection of vertical drain, apart from the cost,
are as follows.
qw
D" (4.17)
khl m2
Equation 4.17 relects the fact that the larger the k h or the longer
the drain, the larger the discharge capacity is required. The effect of
well resistance can be evaluated using this discharge factor. Based on a
numerical study, Xie (1987) established that in order to meet the assump-
tion that the well resistance can be ignored, the following condition must
be met:
π kh 2
l < 0.1 (4.18)
4 qw m
qw (4.19)
D= ≥ 7.85
khl m2
1000
k = 10–9 m/s
100
Required discharge capacity
10–10 m/s
(× 10–6 m3/s)
10
10–11 m/s
1
0.1
0.01
0 20 40 60 80
Maximum drain length (m)
Figure 4.11 Required discharge capacity as a function of PVD length and permeability of soil.
Prefabricated vertical drains 111
and
where O95 is the AOS of ilter, O50 is the size which is larger than 50%
of the fabric pores, and D85 and D50 refer to the sizes for 85% and 50%
of passing of soil particle by weight. O95 ≤ 0.075 mm, or 75 μm, is often
speciied for PVDs.
The D85 of the Singapore marine clay was in the range of 0.01–0.02
mm (Bo et al., 2003). The O95 of the PVD ilter speciied for the Changi
land reclamation project was less than 0.075 mm. An AOS of 0.075 mm
exceeded the AOS speciied by Inequality (4.21a). This was permitted for
the following two reasons. First, PVDs with such O95 had been used suc-
cessfully in the previous land reclamation projects in Changi (Choa et al.,
1979). Second, there were not many types of PVDs which offer an O95
much smaller than 0.075 mm available in the southeast Asian market. To
verify whether the ilter was adequate, some drains had been pulled out
from the site at the end of the project. The inner side of the drain was quite
112 Ground improvement
clean. The same was observed from the drains used for some long-term
consolidation tests in the Singapore marine clay (Chu and Choa, 1995).
Therefore, the ilter criterion set by Inequality (4.21a) appears to be too
conservative for the Singapore marine clay based on this study. A more
relaxed criterion: O95 ≤ (4 ~ 7.5) D85, may be applicable to the Changi East
land reclamation project. For the Bangkok clay, a more relaxed criterion for
O95 has also been proposed (e.g., Bergado et al., 1993a).
The permeability of the ilter is normally required to be at least one
order of magnitude higher than that of the soil. Considering the clog-
ging effect, a much higher permeability should be required for the ilter.
Nevertheless, even more stringent requirements on the permeability of il-
ter can be met easily as most of the PVDs have a ilter permeability higher
than 10 –4 m/s, which is far greater than what is required. For example,
the permeability of the Singapore marine clay was in the order of 10 –10
m/s. The permeability of the ilter of the PVDs used for the Changi land
reclamation project was higher than 10 –4 m/s. This is 105 times greater.
The thickness of the ilter is another consideration. Normally the thicker
the ilter, the better it becomes, given other conditions the same. Based on
Wang and Chen (1996), the mass to area ratio should be generally larger
than 90 g/m 2 .
First, the settlement prediction using oedometer testing data can only be
as reliable as the data. For this reason, it is important to obtain good one-
dimensional consolidation test results. This requires good quality samples
to be used. It is well known that the sample quality affects the determina-
tion of preconsolidation stress and compression index (Holtz and Kovacs,
1981). A small error or uncertainty in the determination of preconsolida-
tion stress can cause a large variation in the settlement. Furthermore, it
should be noted that the preconsolidation stress changes with the method
of testing and rate of loading when the constant-rate-of-strain method is
adopted. Second, the preconsolidation stress and vertical stresses in soil
also vary with depth. It is therefore necessary to determine the precon-
solidation stresses at different depths and calculate the consolidation
settlement using the subdivision method unless the compressible layer is
relatively thin. Third, the surcharge applied by ill can change with the
settlement of the ground as part of the ill may submerge into water and the
effective surcharge load can thus be reduced. One such example is given by
Bo et al. (1999). Finally, it should be pointed out that this one-dimensional
approach is only reasonable when the extent of the load applied is much
larger than the thickness of the compressible soil layer such as in a land
reclamation project. Even in this case, settlement prediction has never been
an easy task, as elaborated by Duncan (1993). For this reason, settlement
prediction using ield monitoring data is essential for preloading projects
using PVDs.
Sometimes, the settlement due to secondary compression needs to be
estimated too. The conventional method of estimating the secondary com-
pression is to use
Δe = C α (Δlog t) (4.22)
4.4 CONSTRUCTION
4.4.1 Installation
The PVD installation procedure is illustrated in Figure 4.12. A PVD instal-
lation rig is normally used to penetrate a metal mandrel with PVD inside.
The PVD installation rigs used on land can be classiied into three types:
(1) static push-in type for normal ground (see Figure 4.13 for an example);
(2) vibratory drive-in type for irm to stiff ground or soft soil with a hard
crust; (3) light rigs on trucks for PVD installation on very soft ground, as
shown in Figure 4.14. For offshore or above-water PVD installation, a raft
or a PVD installation barge has been used. A raft such as the one in Figure
4.15 is only workable in quiet, shallow water. The barge is required in the
relatively deep water of an offshore environment. The PVD installation
barge shown in Figure 4.16 can install 12 PVDs at the same time. It has
been used for a port project in China (Yan et al., 2009).
The mandrel used for PVD installation is normally much larger than a
PVD in terms of cross-section areas as it has to be strong enough to pre-
vent it from bending or buckling. There are four different types of man-
drels according to the shape of the cross-sections: rhombic, rectangular,
Figure 4.15 A loating raft for PVD installation in shallow water (From Chu, J., Bo,
M.W. and Arulrajah, A. (2009). Soil improvement works for an offshore
land reclamation. Proceedings of the Institution of Civil Engineers—Geotechnical
Engineering, Vol. 162, No. 1, pp. 21–32.)
square, and circular. The irst two are more commonly used. A picture of
their cross-sections is shown in Figure 4.17. The typical dimensions are
120–145 mm long, 60–mm wide, and 10–mm thick for rectangular cross-
section mandrel and 120–145 mm long, 50–85 mm wide, and 5–15 mm
thick for rhombic ones. It should be noted that the smear effect is greatly
affected by the cross-section area of the mandrel. Therefore, the cross-
section of the mandrel should be as small as possible in order to reduce the
Figure 4.16 A PVD installation barge. (From Yan, S.W., Chu, J., Fan, Q.J., and Yan, Y.
(2009). Building a breakwater with prefabricated caissons on soft clay.
Proceedings of ICE, Geotechnical Engineering, Vol. 162, No. 1, pp. 3–12.)
118 Ground improvement
Figure 4.17 Cross-section of mandrels. (From Bo, M.W., Chu, J., Low, B.K. and Choa,
V. (2003). Soil Improvement: Prefabricated Vertical Drain Technique, Thomson
Learning, Singapore.)
Anchor bar
150 mm
12 mm
200 mm
Staple
Anchor plate
150 mm
80 mm
190 mm
Figure 4.19 Typical designs of anchors. (Redrawn from Bo, M.W., Chu, J., Low, B.K.
and Choa, V. (2003). Soil Improvement: Prefabricated Vertical Drain Technique,
Thomson Learning, Singapore.)
Figure 4.20 Use of an anchor plate for PVD installation. (Courtesy of J. Han.)
120 Ground improvement
300mm 300mm
New roll Old roll New roll Old roll
Inner core
Filter
Insert the opened core into the new drain and ensure smooth overlap: Overlapped length should be 300mm
Secured by staples Secured joint by tape Secured joint by tape Secured by staples
Figure 4.21 Details of splicing: (a) Colbond type of drain. (b) Mebra type of drain. (From Bo, M.W., Chu, J., Low, B.K. and Choa, V. (2003). Soil
Improvement: Prefabricated Vertical Drain Technique, Thomson Learning, Singapore.)
121
Table 4.4 Speciications used for different projects in different countries
122
Netherlands
Ground improvement
Description Unit Standard Case I Case II Singapore Thailand Hong Kong Malaysia Taiwan Australia Finland Greece
Tensile strength kN/10cm ASTM >0.5 >0.5 >1 (at >0.5 >2 >1 >1
(dry) D4595 10%)
Tensile strength >0.5 >0.5 >1 (at >2 >1 >1
(wet) 10%)
Elongation % 2–10 (at 0.5 kN) <30 <20 15-30
(at 1 kN) (yield)
Discharge capacity 10–6 m2/s ASTM >10 at >50 at >25 at 350 >16 at 200 >5 at 200 >6.3 at >10 at >100 at >10 >10
(straight) D4716 and 350 350 kPa 28 kPa, kPa 400 kPa, 300 300 kPa at
others kPa 30 kPa 30 days 7 days, i=1 kPa, 100
days days i = 1. i=1 kPa
Discharge capacity 10–6 m2/s >7.5 at >32.5 at >10 >6.3 at
(folded) 350 350 400 kPa
kPa kPa
Crushing strength kN/m3 500
Equivalent mm 50 65
diameter
Free surface ilter mm2/m 150,000
Tear strength N ASTM D4533 100 >300 >250 >380
Graph strength N ASTM D4632 >350
Puncture strength kN ASTM D4833 >200
Bursting strength kPa ASTM D3785 >900
Pore size O95 μm ASTM D4751 <160 <80 <75 <90 <120 <75 <90
Permeability of 10–5 m/s ASTM D4491 >5 >10 >1 >10 >17 >50
ilter
Case I: Stable layer less than 10 m thick; Case II: Unstable layer more than 10 m thick
Source: Modiied from Bo et al., 2003.
Prefabricated vertical drains 123
Water supply
Load
Head loss 3
Manometer 8
Rubber membrane 9
Flow meter 10
Flow direction 1
Sample length
extension plate is used to anchor the drain and to allow another layer of
marine clay to be put on top of the drain. The top cap is then placed and
the screws are tightened. Square shaped O-rings are used to seal the tester.
The vertical pressure is applied via an oedometer loading frame. This test
is simple and can be easily conducted in a site laboratory. The results are
Soil
Filter
Core
Allen screw
Top cap
Hollow
‘O’ Rings
extension plate
Marine clay
Drain 100mm × 100mm
Marine clay
Valve Valve
Base
easily reproducible and therefore can be counter checked easily. This test
also provides a mean to compare and benchmark the discharge capacity
values of different drains. The discharge capacity measured using this new
drain tester is lower than that measured by the ASTM4716 method. It is
safer to use the smaller value measured to compare with the speciication.
A buckled drain tester, as shown in Figure 4.27, is also used to measure
the discharge capacity of the deformed drain (Chu and Choa, 1995). A
buckled sample is shown in Figure 4.28. In conducting this test, it is not
necessary to wait until the soil in the drain tester has achieved a high degree
of consolidation as the dissipation of excess pore pressure should not affect
the discharge capacity measurement. However, it is troublesome to carry
out a discharge capacity test using a tester shown in Figure 4.25. An alter-
native is a method suggested in BS EN 15237 (2007) using an apparatus
shown in Figure 4.29 in which a drain specimen inside a rubber membrane
is bent in a way shown in Figure 4.29. Another method is to use a device
shown in Figure 4.30 where a drain specimen is bent to a 30-degree angle
(Figure 4.30b) using two pieces of water impervious foam (Bo et al., 2003).
It should be mentioned that as a standard, the discharge capacity should
be reported as the value measured at 20°C. If the discharge capacity test
is not conducted at this temperature, a conversion in the same way as for
permeability test should be made.
It should be pointed out that the discharge capacity also reduces with
time. This might be due to the creep of the drain materials under pressure.
Prefabricated vertical drains 127
Water discharge
To piezometer
board
Marine clay
Vertical drain
Geotextile
Figure 4.28 Deformed drain after it is tested in the buckled drain tester.
128 Ground improvement
Rod
50
Drain specimen
Guide rod 30
Figure 4.29 Device for measuring the discharge capacity of a bent drain recommended
by BS EN 15237 (2007).
The reduction in the discharge capacity over four weeks can be as high as
60% (Chu and Choa, 1995). For this reason, a creep factor is introduced to
account for the creep effect. Although it is too time consuming to measure
the long-term discharge capacity, some long-time discharge capacity tests
should be conducted to assess the rate of reduction in discharge capacity
with time or verify the creep factor adopted.
It is generally observed that the discharge capacity reduces with hydraulic
gradient (Kamon et al., 1984; Broms et al., 1994; Park and Miura, 1998).
As such, when the value of discharge capacity is reported, the hydraulic
gradient, i, at which the discharge capacity is measured should be stated.
For practical purposes, the discharge capacity should be measured at a
hydraulic gradient comparable to the ield conditions. However, the in-situ
hydraulic gradient is dificult to estimate. Reports on the ield hydraulic
gradient are also rare, except one case reported by Nakanado et al. (1992)
in which the in-situ hydraulic gradient was estimated to be in the range of
0.03–0.8. From the testing point of view, Akagi (1994) pointed out that
when the hydraulic gradient is higher than 0.5, the low inside the vertical
drain may not be laminar anymore. He suggested the discharge capacity
(a) (b)
Rod
Drain specimen
Guide rod
Figure 4.30 Device for measuring the discharge capacity of deformed drain.
Prefabricated vertical drains 129
160
Straight
140 Buckled
Discharge capacity (10–6 m3/s)
100
80
60
40
20
0 50 100 150 200 250 300 350 400
Pressure applied (kPa)
Figure 4.31 Typical PVD discharge capacity test results using the straight and buckled
drain testers.
rate is normally too expensive for a site laboratory to equip. On the other
hand, a compression machine used for triaxial tests is commonly available
in a geotechnical laboratory. Therefore, a method that uses a modiied
compression machine to conduct tensile strength tests for vertical drains
has been developed (Chu and Choa, 1995). The only shortcoming of using
a compression machine is that it does not provide a pulling rate as high
as 300 mm/min. However, this will not be a problem for the following
reasons—irst, the drain installation speed is as high as 25,000 mm/min.
As even 300 mm/min is far too low, whether a pulling rate is 300 mm/min
or lower does not make much difference. Second, the slower the rate, the
smaller the tensile strength measured, and the use of a slower pulling rate
will result in a more conservative measurement. This is good for quality-
control purposes.
When a compression machine is used to conduct tensile strength tests,
a pair of clamps designed according to ASTM D4632 need to be used to
clamp the drain specimen to the machine. A drain specimen of 200 mm in
gauged length is used. The test setup is shown in Figure 4.32. The load was
applied under constant-rate-of-extension (CRE). For wet conditions, the
specimen, either the entire drain or the ilter, was immersed in water for 48
hours before testing. Some typical tensile strength tests for two different
types of PVDs are shown in Figure 4.33.
2.4
Dry
Drain 1
2
Wet
1.6
Tensile stress (kN)
Dry
Drain 2
1.2 Wet
0.8
0.4
0
0 10 20 30 40
Tensile strain (%)
Figure 4.33 Tensile stress versus tensile strain curves measured for 2 typical drains.
in the PVD installation records. There were cases where PVDs were not
installed deliberately to the required depths. Therefore, a method that can
directly measure the installation depth of PVD is also required. In the fol-
lowing, three new methods that can measure the penetration depth of PVDs
directly after the PVD has been installed are introduced. These three new
methods are digitised PVD, PVD with two wires, and PVD with one wire.
Figure 4.34 PVD with scale printed on it for PVD penetration depth measurement.
(From Liu, H.L., Chu, J. and Ren, Z.Y. (2009). Geotextiles and Geomembranes,
Vol. 27, No. 6, pp. 493–496.)
Prefabricated vertical drains 133
Figure 4.35 PVD with two copper wires embedded for PVD penetration depth. (From
Liu, H.L., Chu, J. and Ren, Z.Y. (2009). Geotextiles and Geomembranes, Vol. 27,
No. 6, pp. 493–496.)
134 Ground improvement
Figure 4.36 Readout unit for the measurement of PVD penetration depth. (From Liu,
H.L., Chu, J. and Ren, Z.Y. (2009). Geotextiles and Geomembranes, Vol. 27,
No. 6, pp. 493–496.)
Figure 4.37 PVD with one copper wire embedded for PVD penetration depth mea-
surement. (From Liu, H.L., Chu, J. and Ren, Z.Y. (2009). Geotextiles and
Geomembranes, Vol. 27, No. 6, pp. 493–496.)
Sandfill
Old alluvium
Figure 4.38 Typical details of onshore and adjacent offshore ield instrumentation clusters. SP = Settlement plate, DS = Deep settlement gauge,
PP = Pneumatic piezometer, WS = Water stand-pipe. (From Arulrajah, A., Bo, M.W. and Chu, J. (2009). Instrumentation at the
Changi land reclamation project, Singapore. Geotechnical Engineering, Proceedings of the Institution of Civil Engineers, Vol. 162, No. 1,
pp. 33–40.)
Prefabricated vertical drains 137
Figure 4.39 Putting piezometer inside a PVD for pore water pressure measurement.
the time interval used (Matyas and Rothenburg, 1996; Bo et al., 1999). In the
hyperbolic method, settlement data are plotted as time/settlement versus time
curve (Sridharan and Rao, 1981). The Sult is estimated as the inverse of the
linear slope of the plot. However, Sult obtained from this method is affected
by the degree of consolidation achieved. The higher the degree of consoli-
dation that the soil has attained, the smaller the Sult obtained as observed
by Matyas and Rothenburg (1996), Bo et al. (1999), and Goi (2004). The
uncertainties involved in the ultimate settlement calculation will affect the
estimation of the degree of consolidation. As a result, different degrees of
consolidation are obtained using different methods. As an alternative, pore
water pressure data can be used to assess the degree of consolidation.
Once the pore water pressures at different depths are measured dur-
ing preloading, the initial and inal pore water pressure distributions with
depth can be plotted (Chu et al., 2000). For generality, a combined ill
surcharge and vacuum load case is considered. The typical pore water pres-
sure distribution proiles for a combined vacuum and ill surcharge loading
case are shown schematically in Figure 4.42. Using this proile, the average
degree of consolidation, Uavg, can be calculated as:
Uavg = 1 −
∫ [u (z) − u (z)] dz
t s
(4.24)
∫ [u (z) − u (z)] dz
0 s
and
us(z) = γwz − σ, kPa.
138
Elapsed time (day)
Ground improvement
9 109 209 309 409 509 609 709 809 909 1009
Soil profile Soil 10
Ref. Borehole DC-013 instrument
Surcharge (mCD)
E.L. Dept Soil 8
(mCD) (m) type E.L. (mCD)
0 Sand SP-082(3.51)
4 6
4
DS-095(–8.4)
–8.4 12.4 Clay 2
PP-110(–10)
DS-096(–14) 0
0 DS-104
PP-112(–18) DS-101 DS-100
DS-097(–20) 0.5 DS-99
Settlement (cm)
DS-098(–24) DS-98
PP-114(–25.8) 1 DS-97
DS-099(–27.8)
1.5 DS-96
–28.02 32.02 Sand
–29.88 33.88 Clay 2 DS - Deep Settlement Gauge
PP-116(–35) DS-95
DS-101(–36) 2.5 SP - Surface Settlement Plate
SP-82
–38.93 42.93 Silt 3
PP-119(–47)
20
PP - Pneumatic Piezometer
PP El. (mCD)
Figure 4.40 Typical settlement and pore water pressure data obtained from the third pilot test. (From Chu, J., Bo, M.W. and Choa, V. (2006).
Geotextiles and Geomembranes, Vol. 24, No. 6, pp. 339–348.)
Prefabricated vertical drains 139
Sult
Settlement at time t, Sn Sn
S3
S2
45°
S1 S2 ....... Sn-1
Settlement at time t-1, Sn-1
Hydrostatic pore
water pressure
line, uw (z)
ut (z)
Depth, z (m)
u0 (z)
S ∆σv
Pore water pressure (kPa)
Figure 4.42 Schematic illustration of pore water pressure distributions versus depth
under combined surcharge and vacuum load.
140 Ground improvement
With the use of PVD, the pore pressure transducers are installed within
half of the drains’ spacing distance to a PVD. This distance may vary
depending on the verticality of the PVD during installation and the
subsequent deformation of the PVD. One concern is that the random
uncertainties of the distance between the pore pressure transducers and
the PVDs will affect the pore pressure distribution proile, as shown in
Figure 4.40. This is true only when the depth of PVD is relatively short,
say, less than 10 m. This is because when a random variable varies over a
long distance, the overall effect of the random variation over the entire dis-
tance reduced greatly due to a statistical property called spatial variance
reduction. This explains why the method illustrated in Equation 4.21
has worked well for a number of projects (Chu et al., 2000; Chu and
Yan, 2005; Yan and Chu, 2003; 2007; Chu et al., 2009). More details
and comparisons are also made in the case histories published in these
references.
Degree of consolidation may also be estimated using the undrained shear
strength distribution proile. One example will be shown in the Case Study
in Section 4.7.
Prefabricated vertical drains 141
Standards for the execution of PVDs, AS8700 (2011). The use of these
codes and standards is important in maintaining the quality standards of
soil improvement works.
The Chinese Quality Inspection Standard for PVDs (JTJ/T257-96)
requires every batch of PVDs and every 200,000 m within the same batch
to be sampled and tested for quality-control purposes. What is interest-
ing is that JTJ/T257-96 speciies the thickness of PVDs to vary according
to the depth of installation as well as the discharge capacity and tensile
strength (see Table 4.5). Although no reasons were given for the speciic
values used, the use of a thicker and thus larger discharge capacity PVD
is in line with the requirement expressed in Inequality (4.20). The other
recommended speciications for PVDs are also given in Table 4.5.
The European Standard BS EN 15237 includes the application of PVDs
and sand drains and deals with requirements to be placed on design,
drain material, and installation methods. For the material properties of
PVD, the main properties required and their testing methods are listed in
Table 4.6. All the PVD properties used in Table 4.6 have been explained in
this chapter except for the velocity index of ilter vh50 and durability. The
‘velocity index of ilter’ sounds new, but is merely another way to measure
ilter permeability in Europe. It deines the iltration velocity corresponding
Table 4.5 Minimum thickness and other speciications for PVD as speciied by the
Chinese Code JTJ/T257-96
(a) Minimum thickness
Type L < 15 m L < 25 m L < 35 m Stud type
Thickness (mm) > 3.5 > 4.0 > 4.5 >6
(b) Other speciications
Description Unit L < 15m L < 25m L < 35m Testing conditions
Discharge cm /s
3 15 25 40 Under pressure of
capacity (m3/yr) (670) (1,115) (1,784) 300 kPa
Permeability of cm/s 5 × 10–4 After the sample is
ilter immersed in water for
24 h
Pore opening of μm < 75 O95
ilter
Tensile strength kN/10 > 1.0 > 1.3 > 1.5 At 10% elongation
of PVD cm
Tensile strength kN/cm > 15 > 25 > 30 At 10% elongation
of ilter (dry)
Tensile strength kN/cm > 10 > 20 > 25 At 10% elongation. Sample
of ilter (wet) immersed in water for
24 h.
Prefabricated vertical drains 143
10
0.5
Permeability of soil, m/year
0.1
0.05 2000
Discharge capacity, m3/year
1000
0.01 500
0.005 200
100
0.001 50
5 10 20 30 40 50
Depth of installation, m
Filter:
Thickness 25,000 m2 EN 9863-1
Mass per unit area 25,000 m2 EN 9864
Pore size 200,000 m2 EN 12956
Velocity index 200,000 m2 EN 11058
Tensile strength in the longitudinal direction 200,000 m2 EN 10319
Tensile strength in the cross direction 200,000 m2 EN 10319
Drain composite:
Width and thickness 25,000 m EN 9863-1
Mass per unit length 25,000 m –
Tensile strength in the longitudinal direction 100,000 m EN 10319
Elongation at maximum tensile force 100,000 m EN 10319
Discharge capacity straight 500,000 m BS EN 15237
Discharge capacity buckled 500,000 m BS EN 15237
Tensile strength of ilter seam 100,000 m EN 10321
Durability 500,000 m EN 13252
Source: BS EN 15237. (2007). European Standard on Execution of Special Geotechnical
Works—Vertical Drainage. European Standard.
Prefabricated vertical drains 145
When PVDs are used together with vacuum preloading for soil improve-
ment, some special arrangements may be required. The PVDs in this case
will not only discharge water, but also transmit vacuum pressure as shown
in Figure 4.44. Therefore, the PVDs used for a vacuum preloading project
should possess better quality than normal. Sometimes, prefabricated circu-
lar drains (see Figure 4.10) are also used. More detailed description of the
vacuum preloading system shown in Figure 4.44 can be found in Chu and
Yan (2005b).
The vacuum preloading system shown in Figure 4.44 works well when
the low permeability compressible soil extends all the way to the ground
surface so that membranes can be used to seal the top surface for vacuum
pressure application. However, when there is a relatively thick layer of per-
meable soil on top, a cut-off wall extending all the way to the bottom of
A A
1 2 3 4 5 6 7 8
8 7 4 10 11
A–A
Plastic pipe
Sand layer
PVD
Clay
layer
(a) (b)
Figure 4.45 BeauDrain vacuum preloading system. (a) Concept. (Courtesy of Cofra, Holland.)
(b) Direct connection of PVD with plastic pipe for vacuum application.
the permeable soil layer will have to be installed around the whole soil
improvement site. This can be too expensive. An alternative is to connect
each individual PVD to a plastic pipe as shown in Figure 4.45. The plastic
pipe can be installed together with PVD into the ground and going through
the entire permeable soil layer as shown in Figure 4.45a. In this way, the
need to use cut-off wall and membrane for creating an airtight seal is no
longer required. This so-called BeauDrain technique has been developed by
Cofra Holland (Kolff et al., 2004) and used for a number of soil improve-
ment projects (Seah, 2006; Saowapakbiboon et al., 2008). However, this
method has its own limitations. First, it requires the soil proile at the PVD
installation points to be known precisely. This can be dificult sometimes.
Second, the length of each PVD and the plastic pipe connected has to be
determined and preconnected beforehand. Third, for installation, each
PVD with the plastic pipe has to be pulled through a mandrel with the
plastic pipe on top and then installed into the ground using a PVD instal-
lation machine, see Figure 4.46. The plastic pipes are then connected to a
main vacuum line which is linked to a vacuum pump, see Figure 4.47.
Prefabricated vertical drains 147
Clay
layer
dredging seabed to an elevation of −22 mCD (Chart Datum) for the stor-
age of silt and clay washings from other sand-quarrying activities. The
thickness of the ultra-soft slurry varied from 1–20 m with an average
value of 15 m. The grain size distribution curves indicate a ines content
in the range of 70%–93%. The upper bound of the mean grain size D50
was 0.024 mm, but mostly in the range smaller than 0.001 mm and D85
was in the range of 0.004–0.02 mm. The water content of the slurry was
mainly in the range of 140%–180%. The bulk unit weight of the slurry
ranged mainly from 11–13 kN/m 3. As the slurry was deposited recently
with little consolidation, it was ultra-soft and highly compressible.
Based on the properties of the slurry and the depth of installation, the
properties of the PVDs were chosen as shown in Table 4.8. The analysis
for the selection of PVD is detailed in Chu et al. (2006).
The procedure adopted for the reclamation of the slurry pond was plac-
ing a sand-capping layer on top of the slurry before PVDs could be installed
and used for the consolidation of the slurry. As the slurry had essentially
no strength, the land reclamation work was carried out by spreading thin
layers of sand using a specially designed sand spreader (Chu et al., 2009).
To ensure the stability of the ill, small lifts of 20 cm were used in the irst
phase of the spreading. This phase of sand spreading took about 13 months
including the waiting time between the lifts. There was a slurry burst when
the ill reached an elevation between –1 and +2 mCD (Chu et al., 2009).
Otherwise, the reclamation using sand spreading was workable. After the
ill was exposed above the water level, PVDs were installed with 2 × 2 m
square spacing. The surcharge was then placed to +6 mCD. The settlement
of the ill was monitored. After about 1.5 m of settlement had occurred,
a second round of PVDs with the same 2 × 2 m spacing was installed.
During the installation of PVDs, slurry was observed to come out through
the annulus of the mandrel, as shown in Figure 4.48. This is indicative
that the pore water pressure in the ground was still high and the installa-
tion process itself helped in the dissipation of pore water pressure and thus
the consolidation process. This is another advantage of the two-stage PVD
installation method.
Settlement gauges and pore pressure transducers were installed in the
ultra-soft clay layer to monitor the consolidation process of the ultra-soft
soil. The typical arrangement of instrument layout and proile are shown in
Figure 4.49. The surcharge history and settlement and excess pore pressure
Figure 4.48 Extrusion of viscous pore water and mud during PVD installation. (From
Chu, J., Bo, M.W. and Choa, V. (2006). Geotextiles and Geomembranes, Vol. 24,
No. 6, pp. 339–348.)
+4.0 mCD
+3.50
PP 467
DS 504 PZ 049
DS 505 PP 468
SP 506 PZ D48
DS 503 PP 466 Sand
DS 507 PP 047
DS 511 WS 110
PBS 5
–5.30 DS 503
Very soft slurry soil
–8.00 DS 504 PP 446 PZ 047
–14.30 DS 507
Sand
Figure 4.49 Arrangement of instrumentation. (a) Plan view. (b) Elevation view. (From
Chu, J., Bo, M.W. and Choa, V. (2006). Geotextiles and Geomembranes, Vol. 24,
No. 6, pp. 339–348.)
150 Ground improvement
versus time curves are shown in Figure 4.50. As indicated in Figure 4.50a,
the second round of PVD installation was carried out about 80 days after
the irst round of PVD installation, where the top of the slurry had settled
nearly 1.5 m. It should be noted that the surcharge load was reducing with
time as the ill used for surcharge was gradually submerged into water due
to the settlement of the ground. As shown in Figure 4.50b, the slurry had
settled for about 2.7 m in 500 days.
The excess pore pressures versus time curves measured by piezometers
PZ047, PZ048 and PZ049 (see Figure 4.49) are shown in Figure 4.50c.
The piezometers were installed after the irst PVD installation. A quick
increase in pore pressure was observed after 90 days at all three locations.
This was caused by the installation of the 2nd round of PVDs. The excess
pore pressure dissipations as measured by PZ047 at −8 mCD and PZ048 at
−10 mCD were slow despite of the occurrence of large settlement. The lack
of pore pressure dissipation may signify a sedimentation and self-weight
consolidation stage prior to consolidation under additional ill. During this
stage, slurry was transforming from a liquid to a solid state in which water
was dissipating, but the soil particles did not have suficient contacts to
allow the soil skeleton to take up external load. The Mandel–Cryer effect
and non-uniform consolidation of soil around the PVD were thought to be
the other reasons accounting for the lack of pore water dissipation (Chu
et al., 2006). The pore pressure dissipation measured by PZ-49 at −12
mCD was relatively quick. This was because the soil at this elevation was
near the silty sand layer below it.
Based on the pore water pressure measurements shown in Figure 4.48c,
the pore water pressure versus depth proile can be plotted in Figure 4.51.
The initial excess pore water pressure, which had the same magnitude as
the surcharge and the hydrostatic pore water pressure line, is also plotted
in Figure 4.51. Using the method introduced in Equation 4.24, the average
degree of consolidation is estimated to be 42% (Chu et al., 2009). If we
use settlement data and apply Asaoka’s method to Figure 4.48b, the average
degree of consolidation is calculated as 91% (Chu et al., 2009), which was
overestimated.
Field vane shear and CPT tests were conducted 14 months after the appli-
cation of the surcharge. A comparison of the undrained shear strength pro-
iles obtained from ield vane shear tests conducted before and 14 months
after surcharge as well as from CPT (with pore pressure measurement)
tests conducted 14 months after surcharge is shown in Figure 4.52. Note
that the ground had settled for more than 2 m within 14 months, as shown
in Figure 4.50a. This explains why the starting points of the in-situ tests
conducted before and after the surcharge are different. In Figure 4.52, the
undrained shear strength proile estimated by assuming a uniform degree
of consolidation of 90% is also plotted for comparison. As mentioned, a
silty sand was present at an elevation of −12.5 mCD and a sand blanket
Prefabricated vertical drains 151
7
2nd PVD
3
1st PVD
installation Surcharge elevation
Water level
1
0 90 180 270 360 450 540
(a) Time (days)
0.5
Settlement (m)
1.5
150
Excess pore pressure (kPa)
125
100
75
PZ-47
50 PZ-48
PZ-49
25
0
0 90 180 270 360 450 540
(c) Time (days)
Figure 4.50 Monitoring data during the reclamation of slurry pond. (a) Surcharge varia-
tion versus time. (b) Settlement versus time. (c) Excess pore pressure ver-
sus time. Initial positions of the instruments: SP-506 at +3.5 mCD; DS-503
at −5.3 mCD; PZ-47, DS-504 and PP-466 at −8 mCD; PZ-48, DS-505 and
PP-467 at −10 mCD; PZ-49, DS-511 and PP-468 at −12 mCD. (From Chu, J.,
Bo, M.W. and Choa, V. (2006). Geotextiles and Geomembranes, Vol. 24, No. 6,
pp. 339–348.)
152 Ground improvement
–6
–7
–8
Elevation (m)
–9
–10
–11
Hydrostatic
–12 Surcharge
At 16 mths
–13
0 10 20 30 40 50 60 70 80 90 100
–7
–8 FVT (prior to
reclamation)
–9 FVT
Elevation (mCD)
CPT
–10
90% DOC
–11
–12
–13
Shear strength (kPa)
Figure 4.52 Comparison of undrained shear strength proiles measured before and after
consolidation for 14 months. (Redrawn from Chu, J., Bo, M.W. and Choa, V.
(2006). Geotextiles and Geomembranes, Vol. 24, No. 6, pp. 339–348.)
Prefabricated vertical drains 153
was placed on the top surface. Therefore, there was combined vertical and
horizontal drainage near the top and bottom boundaries. This explains
why the shear strength increment was the largest at both the top and the
bottom. The consolidation in the middle of the clay layer ranging from
−9.5 to −12.0 m was contributed mainly by horizontal drainage to the
PDVs. Applying a method similar to Equation 4.24, the degree of consoli-
dation can be estimated as 45%, which is similar to that based on pore
water pressure.
W E
I II III
30.0 m
50.0 m
80.0 m 119.0 m 27.881 m
Figure 4.53 Project site layout and plan view of instrumentation. (Redrawn from Yan,
S.W. and Chu, J. (2005). Canadian Geotechnical Journal, Vol. 42, No. 4,
pp. 1094–1104.)
by the vacuum and surcharge loads for Section II are shown in Figure 4.54.
The vacuum load was applied for 4–8 weeks before ill surcharge loads
were applied in stages. The total ill height applied was 3.5 m for Section
II. The maximum surface settlement induced by the vacuum and surcharge
loads in this section was 1.614 m.
120
Preload (kPa)
80
Vacuum pressure under membrane
40
Duration (day)
0
30 60 90 120 150 180
Settlement (cm)
–40
Zone II
–80 Surcharge h = 3.50 m
–120
–160
Figure 4.54 Loading sequence and ground settlement measured at Section II. (Redrawn
from Yan, S.W. and Chu, J. (2005). Canadian Geotechnical Journal, Vol. 42,
No. 4, pp. 1094–1104.)
Prefabricated vertical drains 155
0.1
3.0
4.5
10.0
6.0
7.0
9.0
10.5
12.0
12.5
14.5 15.0
16.5 16.5
Figure 4.55 Elevation view of instrumentation. (Redrawn from Yan, S.W. and Chu, J.
(2005). Canadian Geotechnical Journal, Vol. 42, No. 4, pp. 1094–1104.)
156 Ground improvement
Duration (days)
0 20 40 60 80 100 120 140 160 180 200
0.0
–0.2
Settlement (m)
–0.4
–0.6
3.8
7.0
–0.8 10.5
12.5
14.5
–1.0
Figure 4.56 Settlement measured at different depths against duration at Section II. (The
arrows represent where staged loads were applied)
Duration (days)
0 20 40 60 80 100 120 140 160 180 200
0.0
+1.0
–2.0
–20.0 –5.0
–8.0
Pore water pressure
–11.0
reduction (kPa)
–40.0 –12.5
–60.0
–80.0
–100.0
Figure 4.57 Pore water pressure reductions measured at different depths against dura-
tion at Section II (the arrows represent where staged loads were applied).
(Redrawn from Yan, S.W. and Chu, J. (2005). Canadian Geotechnical Journal,
Vol. 42, No. 4, pp. 1094–1104.)
Prefabricated vertical drains 157
the entire 16-m soft clay. The reductions in the pore water pressures mea-
sured by the piezometers installed at different depths are plotted versus
loading duration in Figure 4.57 for Section II. Under the vacuum load, the
pore water pressures reduced quickly with time. However, when the ill sur-
charge was applied, a localised pore pressure increase occurred. The times
at which staged surcharge loads were applied are indicated by arrows in
Figure 4.57. It can be seen that the localised increase in pore water pressure
coincides with the application of surcharge loads.
Based on the pore water pressure monitoring data shown in Figure
4.57, the pore water pressure distributions with depth at the initial stage,
30 and 60 days, and the inal stage are plotted in Figure 4.58. Before
the application of vacuum and surcharge loads, the initial pore water
2 Static
Suction
4 Final
30 days
6 60 days
u0 + ∆σ
8
Depth (m)
u0 (z) + ∆σ
10
u0 (z)
12
us
14
16
uf (z)
18
Figure 4.58 Pore water pressure distributions with depth at Section II. (Redrawn from
Yan, S.W. and Chu, J. (2005). Canadian Geotechnical Journal, Vol. 42, No. 4,
pp. 1094–1104.)
158 Ground improvement
pressures, u 0(z), were greater than the hydrostatic pore water pressure.
The total ill surcharge was about 60 kPa for Section II. Using the verti-
cal stress calculated, the initial pore water pressure distribution after the
application of the ill surcharge is shown as u 0(z) + Δσ in Figure 4.58.
The suction line for a suction of −80 kPa is also plotted in Figure 4.58 as
the line u s. The pore water pressure distributions at 30 and 60 days and
the end of preloading (uf (z)) are also shown in Figure 4.58. These curves
show the changes of the pore water pressure proiles with time. The area
bound by the inal pore water pressure curve, uf (z), and the suction line,
u s , represents the remaining excess pore water pressures that have not
dissipated.
The degree of consolidation can be estimated using either settlement or
pore water pressure data. For the former, Asaoka’s method was applied
to predict the ultimate settlements, S ∞, using the ground settlement data
shown in Figure 4.54. The results are given in Table 4.9. Using the pore
water pressure distribution proile shown in Figure 4.58 and Equation
4.24, the average degree of consolidation at the end of preloading, Uf, can
be estimated as 82%. The reasons why the degree of consolidation esti-
mated based on settlement is higher than that based on pore water pressure
were explained in Yan and Chu (2005).
Field vane shear tests were conducted before and after preloading in
Section II and the results are presented in Figure 4.59. It can be seen that
considerable improvement in the vane shear strength was achieved through-
out the entire depth of 16 m where ield vane shear tests were conducted.
On average, the vane shear strength increased twofold.
4.8 SUMMARY
Section II
8
Depth (m)
12
16
Before
After
20
Figure 4.59 Field vane strength proile before and after soil improvement at Section II.
(Redrawn from Yan, S.W. and Chu, J. (2005). Canadian Geotechnical Journal,
Vol. 42, No. 4, pp. 1094–1104.)
speciications are also discussed. Some speciic methods for using PVDs for
vacuum preloading are also introduced. Finally, two case studies, one for
the use of PVDs for soil improvement of slurry type of soil and another for
the use of PVDs for a combined ill and vacuum surcharge for the improve-
ment of the soft soil below a storage yard, are presented to illustrate the
practical applications of PVDs for different soil improvement projects. In
conclusion, suficient research development has been made and practical
experience been gained over the years on the use of PVDs for soil improve-
ment. However, it is still more of an art than science as far as for the predic-
tion of the outcome of a soil improvement scheme is concerned. A holistic
approach is thus advocated for the implementation of PVD techniques for
soil improvement. The design methods proposed should be used together
160 Ground improvement
ACKNOWLEDGMENTS
Some of the work presented in this chapter formed part of a research pro-
gramme at the Nanyang Technological University, Singapore. The contri-
butions of Prof. Victor Choa, Dr. Myint Win Bo, Prof. Bak Kong Low,
Prof. A. Arulrajah, Dr. Daping Xiao and Haojie Liu to the programme are
gratefully acknowledged. The irst author has beneited greatly from col-
laborations with Prof. Shuwang Yan, Prof. Hanlong Liu, Prof. Buddhima
Indraratna, Prof. Dennes Bergado, Prof. Pedro Pinto, Prof. Robert Lo,
Prof. Cholachat Rujikiatkamjorn, Kok Pang Lam, Serge Varaksin and
Kenny Yee. Their support and cooperation is also much appreciated.
Finally the writers would like to thank Dr. Zhiwei He for proofreading
the manuscripts.
REFERENCES
ASTM D4716. (2008). Standard Test Method for Determining the (In-plane) Flow
Rate per unit Width and Hydraulic Transmissivity of a Geosynthetic Using a
Constant Head, ASTM Standards.
ASTM D4751. (2004). Standard Test Method for Determining Apparent Opening
Size of a Geotextile, ASTM Standards.
AS8700 (2011) Execution of Prefabricated Vertical Drains, Standards Australia.
Balasubramaniam, A.S., Bergado, D.I., Long, P.V. and Thayalan. (1995). Experiences
with sand drains and prefabricated vertical drains in ground improvement of
soft clays, Seminar on Engineering for Coastal Development, Singapore.
Barron, R.A. (1948). Consolidation of ine-grained soils by drain wells, Trans ASCE,
Vol. 113, Paper 2346, pp. 718–54.
Bergado, D.T., Singh, N., Sim, S.H., Panichayatum, B., Sampaco, C.L. and
Balasubramaniam, A.S. (1990). Improvement of soft Bangkok clay using ver-
tical geotextile band drains compared with granular piles, Geotextiles and
Geomembranes, Vol. 9, No. 3, pp. 203–231.
Bergado, D.T., Sampaco, C.L., Shivashankar, R., Alfaro, M.C., Anderson, L.R. and
Balasubramaniam, A.S. (1991). Performance of a welded wire wall with poor
quality backills on soft clay, Proc. ASCE Geotechnical Congress, Boulder,
Colorado, pp. 909–922.
Bergado, D.T., Alfaro, M.C., and Balasubramaniam, A.S. (1993a). Improvement of
soft Bangkok clay using vertical drains, Geotextiles and Geomembranes, Vol.
12, No. 7, pp. 615–663.
Bergado, D.T., Mukherjee, K., Alfaro, M.C. and Balasubramaniam, A.S. (1993b).
Prediction of vertical-band-drain performance by the inite-element method,
Geotextiles and Geomembranes, Vol. 12, No. 6, pp. 567–586.
Bergado, D.T., Long, P.V., Lee, C.H., Loke, K.H. and Werner, G. (1994). Performance
of reinforcement embankment on soft Bangkok clay with high strength geo-
textile reinforcement, Geotextiles and Geomembranes, Vol. 13, pp. 403–420.
Bergado, D.T., Manivannan, R., Balasubramaniam, A.S. (1996a). Proposed cri-
teria for discharge capacity of prefabricated vertical drains, Geotextiles and
Geomembranes, Vol. 14, pp. 481–505.
Bergado, D.T., Anderson, L.R., Miura, N. and Balasubramaniam, A.S. (1996b). Soft
Ground Improvement in Lowland and Other Environments, ASCE Press,
ASCE, New York.
Bergado, D.T., Balasubramaniam, A.S., Fannin, R.J. and Holtz, R.D. (2002).
Prefabricated vertical drains (PVDs) in soft Bangkok clay: a case study of the
New Bangkok International Airport project, Canadian Geotechnical Journal,
Vol. 39, pp. 304–315.
Bo M.W., Chu, J. and Choa, V. (1999). Factors affecting the assessment of degree
of consolidation, Proc. International Conference on Field Measurements in
Geomechanics, Balkema, Rotterdam, pp. 481–486.
Bo, M.W., Chu, J., Low, B.K. and Choa, V. (2003). Soil Improvement: Prefabricated
Vertical Drain Technique, Thomson Learning, Singapore.
Bo, M.W. (2004). Discharge capacity of prefabricated vertical drain and their ield
measurements, Geotextiles and Geomembranes, Vol. 22, No. 1–2, pp. 37–48.
Bo, M.W., Chu, J., Choa, V. (2005). Changi East Reclamation and Soil Improvement
Project. In: Chapter 9, Ground Improvement—Case Histories. Indraratna, B.,
Chu, J. (Eds.), Elsevier, Amsterdam, pp. 247–276.
162 Ground improvement
Broms, B.B., Chu, J., and Choa, V. (1994). Measuring the discharge capacity of band
drains by a new drain tester, Proc. 5th Int. Conf. on Geotextiles, Geomembranes
and Related Products, Vol. 3, Singapore, pp. 803–806.
BS EN 15237. (2007). European Standard on Execution of Special Geotechnical
Works—Vertical Drainage. European Standard.
Carillo, N. (1942). Simple two- and three-dimensional cases in the theory of consoli-
dation of soils. Journal of Mathematics and Physics, Vol. 21, No. 1, 1e5.
Carroll, R.G., (1983). Geotextile ilter criteria. Transportation Research Record, No.
916, pp. 46–53.
Chai, J.C., Miura, N., Sakajo, S. and Bergado, D.T. (1995). Behaviour of vertical
drain improved subsoil under embankment loading, Soils and Foundations,
Vol. 35, No. 4, pp. 49–61.
Chai, J.C., Shen, S.L., Miura, N. and Bergado, D.T. (2001). Simple method of model-
ling PVD improved subsoil, Journal of Geotechnical and Geoenvironmental
Engineering, ASCE, Vol. 127, No.11, pp. 965–972.
Choa, V., Bo, M.W., and Chu, J., (2001). Soil improvement works for Changi East
reclamation project. Ground Improvement, Vol. 5, No. 4, pp. 141–153.
Choa, V., Vijiaratnam, A. Karunaratne, G.P., Ramaswamy, S.D. and Lee, S.L. (1979).
Pilot test for soil stabilisation at Changi Airport, Proceedings 7th European
Regional Conference on Soil Mechanics and Foundation Engineering, Brighton,
Vol. 3, pp. 29–36.
Chu, J. and Choa, V. (1995). Quality control tests of vertical drains for a land
reclamation project, Compression and Consolidation of Clayey Soils,
In: Yoshikuni, H., Kusakabe, O. (Eds.), Proceedings of an International
Symposium, Hiroshima, Japan, 10–12 May, A.A. Balkema, Rotterdam, pp.
43–48.
Chu, J., Yan, S.W. and Yang, H. (2000). Soil improvement by the vacuum pre-
loading method for an oil storage station. Géotechnique, Vol. 50, No. 6, pp.
625–632.
Chu, J., Bo, M.W., Chang, M.F., and Choa, V. (2002). Consolidation and per-
meability properties of Singapore marine clay, Journal Geotechnical and
Geoenvironmental Engineering, ASCE, Vol. 128, No. 9, pp. 724–732.
Chu, J., Bo, M.W. and Choa, V. (2004). Practical consideration for using vertical
drains in soil improvement projects, Geotextiles and Geomembranes, Vol. 22,
pp. 101–117.
Chu, J. and Yan, S.W. (2005a). Estimation of degree of consolidation for vacuum
preloading projects, International Journal of Geomechanics, ASCE, Vol. 5, No.
2, pp. 158–165.
Chu, J. and Yan, S.W. (2005b) Application of the vacuum preloading method in
land reclamation and soil improvement projects. Chapter 3, In Ground
Improvement—Case Histories, B. Indraratna and J. Chu, (Eds.), Elsevier, pp.
91–118.
Chu, J., Goi, M.H. and Lim, T.T. (2005). Consolidation of cement treated sewage
sludge using vertical drains. Canadian Geotechnical Journal, Vol. 42, No. 2,
pp. 528–540.
Chu, J., Bo, M.W. and Choa, V. (2006). Improvement of ultra-soft soil using pre-
fabricated vertical drains, Geotextiles and Geomembranes, Vol. 24, No. 6,
pp. 339–348.
Prefabricated vertical drains 163
Chu, J., Varaksin, S., Klotz, U. and Mengé, P. (2009a). Construction processes.
State-of-the-Art-Report, Proc. 17th International Conf on Soil Mechanics and
Geotechnical Engineering, Alexandria, Egypt, 5–9 Oct., Vol. 4, pp. 3006–3135.
Chu, J., Bo, M.W., and Arulrajah, A. (2009b). Reclamation of a slurry pond in
Singapore, Geotechnical Engineering, Proceedings of the Institution of Civil
Engineers, Vol. 162, No. GE1, pp. 13–20.
Chu, J., Bo, M.W. and Arulrajah, A. (2009c). Soil improvement works for an off-
shore land reclamation. Proceedings of the Institution of Civil Engineers—
Geotechnical Engineering, Vol. 162, No. 1, pp. 21–32.
Chu, J., Indraratana, B., Yan, S. and Rukikiatkamjorn, C. (2012). Soft soil improve-
ment through consolidation: an overview. State-of-the-art Report, Proc.
International Conference on Ground Improvement and Ground Control,
Vol. 1 (in print).
Collazos, O.M., Bowders, J.J. and Bouazza, A. (2002). Prefabricated vertical drains
for use in soil vapor extraction applications. Transportation Research Record,
No. 1786, pp. 104–111.
Duncan, J.M. (1993). Limitations of conventional analysis of consolidation settle-
ment, 27th Karl Terzaghi Lecture, Journal Geotechnical and Geoenvironmental
Engineering, ASCE, Vol. 119, No. 9, pp. 1333–1359.
Fang, Z. and Yin, J.H. (2006). Physical modelling of consolidation of Hong Kong
marine clay with prefabricated vertical drains. Canadian Geotechnical Journal,
Vol. 43, pp. 638–652.
Goi, M.H. (2004). Use of stabilised sewage sludge for land reclamation, MEng the-
sis, Nanyang Technological University, Singapore.
Guido, V. A. and Ludewig, N. M. (1986). ‘A compative laborotry evaluation of band-
shaped prefabricated drains’. Consolidation of Soils: Testing and Evaluation.
ASTM STP 892, Yong, R. N. and Townsend, F. C. Eds. 642–662.
Hansbo, S. (1960). Consolidation of clay, with special reference to inluence of verti-
cal sand drains, Proc. Swedish Geotechnical Institute 18, Linkoping.
Hansbo, S. (1979). Consolidation of clay by band-shaped prefabricated drains,
Ground Engineering, Vol. 12, No. 5, pp. 16–25.
Hansbo, S. (1981). Consolidation of ine-grained soils by prefabricated drains, Proc.
10th International Conference Soil Mechanics and Foundation Engineering,
Stockholm, Vol. 3, pp. 677–682.
Hansbo, S. (1983). How to evaluate the properties of prefabricated drains, Proc. 8th
European Conf. on Soil Mechanics and Foundation Engineering, Helsinki, Vol.
2, pp. 621–626.
Hansbo, S. (1997). Aspects of vertical drain design: Darcian or non-Darcian low,
Géotechnique, Vol. 47, pp. 983–992.
Hansbo, S. (2001). Consolidation equation valid for both Darcian or non-Darcian
low, Géotechnique, No. 1, pp. 51–54.
Hansbo, S. (2004). Band drains. In Ground Improvement (2nd edition), Spon Press,
pp. 4–56.
Hansbo, S. (2005). Experience of consolidation process from test areas with and
without vertical drains. In B. Indraratna and J. Chu (Eds.), Chapter 1, Ground
Improvement—Case Histories, Elsevier, Oxford, pp. 3–50.
Hight, D.W., Bond, A.J. and Legge, J.D. (1992). Characterisation of Bothkannar clay:
an overview, Géotechnique, Vol. 42, No. 2, pp. 303–347.
164 Ground improvement
Hird, C.C., Pyrah, I.C., and Russell, D. (1992). Finite element modelling of vertical
drains beneath embankments on soft ground, Géotechnique, Vol. 42, No. 3,
pp. 499–511.
Hird, C.C. and Moseley, V.J. (2000). Model study of seepage in smear zones around
vertical drains in layered soil, Géotechnique, Vol. 50, No. 1, pp. 89–97.
Holtz, R.D. and Holm, B.G. (1972). Excavation and sampling around some sand
drains at Ska-Edeby, Sweden, Proc. 6th Scandinavian Geotechnical Meeting,
Trondheim, Norwegian Geotechnical Institute, pp. 75–89.
Holtz, R.D. and Kovacs, W.D. (1981). An Introduction to Geotechnical Engineering,
Prentice-Hall, Englewood Cliffs, New Jersey.
Holtz, R.D. (1987). Preloading with prefabricated vertical strip drains, Geotextiles
and Geomembranes, Vol. 6, No. 1–3, pp. 109–131.
Holtz, R.D., Jamiolkowski, M., Lancellotta, R. and Pedroni, R. (1991). Prefabricated
Vertical Drains: Design & Performance, CIRIA Ground Engineering Report,
Butterworth-Heinemann Ltd., London.
Holtz, R.D., Shang, J.Q. and Bergado, D.T. (2001). Soil improvement, in Geotechnical
and Geoenvironmental Engineering Handbook, R. K. Rowe (Ed.), pp. 429–462.
ICE. (1982). Vertical Drains, Thomas Telford Ltd., London.
Indraratna, B., Balasubramaniam, A.S. and Ratnayake, P. (1994). Performance of
embankment stabilized with vertical drains on soft clay, Journal of Geotechnical
Engineering, ASCE, Vol. 120, No. 2, pp. 257–273.
Indraratna, B. and Redana, I.W. (1997). Plane strain modelling of smear effects asso-
ciated with vertical drains, Journal of Geotechnical and Geoenvironmental
Engineering, ASCE, Vol. 123, No. 5, pp. 474–478.
Indraratna, B. and Redana, I.W. (1998). Laboratory determination of smear zone
due to vertical drain installation, Journal Geotechnical Engineering, ASCE,
Vol. 124, No. 2, pp. 180–184.
Indraratna, B. and Redana, I.W. (2000). Numerical modelling of vertical drains with
smear and well resistance installed in soft clay, Canadian Geotechnical Journal,
Vol. 37, pp. 132–145.
Indraratna, B., Chu, J. (Eds.) (2005). Ground Improvement Case Histories, Elsevier,
Oxford, 1115 pp.
Indraratna, B., Rujikiatkamjorn, C., Balasubramaniam, A.S., and Wijeyakulasuriya,
V. (2005). Predictions and observations of soft clay foundations stabilised with
geosynthetic drains and vacuum surcharge. In: Indraratna, B. and Chu, J. (Eds.),
Ground Improvement—Case Histories. Elsevier, Amsterdam, pp. 199–229
(Chapter 7).
Jamiolkowski, M., Lancellotta, R. and Wolski, W. (1983). Precompression and
speeding up consolidation, General Report—Specialty Session 6, Proc. 8th
European Soil Mechanics and Foundation Engineering, Helsinki, Vol. 3, pp.
1201–1226.
JTJ/T256-96. (1996). Code of Practice for Installation of Prefabricated Drains.
Ministry of Communications, China.
JTJ/T257-96. (1996). Quality Inspection Standard for Prefabricated Drains. Ministry
of Communications, China.
Kamon, M., Pradhan, B.S., and Suwa, S. (1984). Laboratory evaluation of the pre-
fabricated band-shaped drains, soil improvement, Current Japanese Materials
Research, Vol. 9, Cambridge University Press, Cambridge, UK.
Prefabricated vertical drains 165
Karunaratne, G.P. (2011). Prefabricated and electrical vertical drains for con-
solidation of soft clay, Geotextiles and Geomembranes, Vol. 29, No. 4, pp.
391–401.
Kitazume, M. (2007). Design, execution and quality control of ground improve-
ment in land reclamation, Proc. of the 13th Asian Regional Conference on Soil
Mechanics and Foundation Engineering, keynote lecture.
Kjellman, W. (1948). Accelerating consolidation of ine grained soils by means of
cardboard wicks. Proc. 2nd International Conference on Soil Mechanics and
Foundation Engineering. Vol. 2, Rotterdam, pp. 302–305.
Kolff, A.H.N., Spierenburg, S.E.J. and Mathijssen, F.A.J.M. (2004). BeauDrain: a
new consolidation system based on the old concept of vacuum consolidation,
Proc. 5th International Conference on Ground Improvement Techniques,
Kuala Lumpur, Malaysia.
Kremer, R.R.H.J., Oostven, J.P., Van Weele, A.F., Dejager, W.F.J., and Meyvogel, I.J.
(1983). The quality of vertical drainage, Proc. 8th European Conf. on Soil
Mechanics and Foundation Engineering, Vol. 2, Helsinki, pp. 721–726.
Lee, S.L., Karunaratne, G.P. and Aziz, M.A. (2003). Design and performance of
Fibredrain in soil improvement projects. Ground Engineering, Vol. 10, No. 4,
pp. 149–156.
Lee, C.H. and Kang, S.T. (1996). Discharge capacity of prefabricated vertical band
drains, Final Year Report, Nanyang Tech. Univ., Singapore.
Leroueil, S. (1996). Compressibility of clays: fundamental and practical aspects.
Journal Geotech. Engrg. Div., ASCE, Vol. 122, No. 7, pp. 534–543.
Li, A.L. and Rowe, R.K. (2001). Combined effects of reinforcement and prefab-
ricated vertical drains on embankment performance, Canadian Geotechnical
Journal, Vol. 38, No. 6, pp. 1266–1282.
Liu, H.L. and Chu, J. (2009). A new type of prefabricated vertical drain with improved
properties, Geotextiles and Geomembranes, Vol. 27, No. 2, pp. 152–155.
Liu, H.L., Chu, J. and Ren, Z.Y. (2009). New methods for measuring the installation
depth of prefabricated vertical, Geotextiles and Geomembranes, Vol. 27, No.
6, pp. 493–496.
Matyas, E.L. and Rothenburg, L. (1996). Estimation of total settlement of embank-
ments by ield measurements, Canadian Geotechnical Journal, Vol. 33, pp.
834–841.
Mesri, G and Castro, A. (1987). The Cα/Cc concept and K0 during secondary com-
pression. Geotech. Engrg. Div., ASCE, Vol. 112, No. 3, pp. 230–247.
Mesri, G. and Lo, D.O.K. (1991). Field performance of prefabricated vertical drains,
Proc. Int. Conf. on Geotechnical Engineering for Coastal Development,
Yokohama, Vol. 1, pp. 231–236.
Mesri, G., Kjlouni, M.A., Feng, T.W. and Lo, D.O.K. (2001). Surcharging of soft
ground to reduce secondary settlement. Soft Soil Engineering, Lee, C.F. et al.
(Eds.), pp. 55–65.
Mitchell, J.K. and Katti R.K. (1981). Soil improvement—state of the art report,
Proceedings 10th International Conference Soil Mechanics and Foundation
Engineering, Stockholm, Vol. 4, pp. 509–565.
Moseley, M.P. and Kirsch, K. (2004). Ground Improvement (2nd ed.), Spon Press.
Nakanado, H., Hanai, H. and Imai, W. (1992). Permeability of plastic board drains.
Technical Report, Vol. 17, Hukken, Co. Ltd., pp. 139–151.
166 Ground improvement
Onoue, A., Ting, N.H., Germaine, J.T. and Whitman, R.V. (1991). Permeability of
disturbed zone around vertical drains, Proc. of ASCE Geotechnical Engineering
Congress, Colorado, pp. 879–890.
Park, Y.M. and Miura, N. (1998). Soft ground improvement using prefabricated
vertical drains (PVD). In: Miura, N., Bergado, D. (Eds.), Improvement of Soft
Ground, Design, Analysis, and Current Researches, pp. 35–48.
Park, J.H., Yuu, J. and Jeon, H.Y. (2010). Green geosynthetics applications to sus-
tainable environmental ields from the viewpoint of degradability, Proceedings
International Symposium and Exhibition on Geotechnical and Geosynthetics
Engineering: Challenges and Opportunities on Climate Change, 7–8 Dec
Bangkok, pp. 43–50.
Raison, C. (2004). Ground and Soil Improvement: Thomas Telford, London.
Ren, Z.Y. (2004). A prefabricated vertical drain with capability for penetration depth
measurement, China patent No. 0119469.0.
Rujikiatkamjorn, C., Indraratna, B. and Chu, J. (2008). 2D and 3D Numerical
Modeling of Combined Surcharge and Vacuum Preloading with Vertical
Drains, International Journal of Geomechanics, Vol. 8, No. 2, 144–156.
Saowapakbiboon, J., Bergado, D.T., Chai, J.C., Kovittayanon, N., and de Zwart,
T.P. (2008). Vacuum-PVD combination with embankment loading consolida-
tion in soft Bangkok clay: A case study of Suvarnabhumi Airport project,
Proc. 4th Asian Regional Geosynthetics Conference, Shanghai, China, pp.
440–449.
Schaefer, V.R., Abramson, L.W., Drumheller, J.C., Hussion, J.D., & Sharp, K.D.
(1997). Ground improvement, Ground Reinforcement and Ground Treatment:
Developments 1987–1997, ASCE GSP 69.
Seah, T.H. (2006). Design and construction of ground improvement works at
Suvarnabhumi Airport. Geotechnical Engineering Journal of Southeast Asian
Geotechnical Society, Vol. 37, pp. 171–188.
Shang, J.Q. (1998). Electroosmosis-enhanced preloading consolidation via vertical
drains. Canadian Geotechnical Journal, Vol. 35, pp. 491–499.
Sivaram, B. and Swamee, P. (1977). A computational method for consolidation coef-
icient. Soils and Foundations, Vol. 17, No. 2, pp. 48–52.
Sridharan, A. and Sreepada Rao, A. (1981). Rectangular hyperbola itting method
for one-dimensional consolidation, Geotechnical Testing Journal, Vol. 4, No.
4, pp. 161–168.
Suits, L.D., Gemme, R.L. and Masi, J.J. (1986). Effectiveness of prefabricated drains
on laboratory consolidation of remolded soils. In: Yong, R.N., Townsend, F.C.
(Eds.), Consolidation of Soils: Testing and Evaluation, ASTM STP 892, pp.
663–683.
Towhata, I. (2008). Geotechnical Earthquake Engineering, Springer.
Varaksin, S. & Yee, K. (2007). Challenges in ground improvement techniques for
extreme conditions: Concept and Performance, Proc. 16th Southeast Asian
Geotechnical Conference, 8–11 May: Kuala Lumpur, pp. 101–115.
Wang, T-R. and Chen, W-H. (1996). Development in application of prefabricated
drains in treatment of soft soils, General Report, Proc. 3rd Symp. On Weak
ground Improvement using PVDs, Oct., Lianyuangang, China, pp. 13–40.
Xiao, D.P. (2002). Consolidation of soft clay using vertical drains, PhD thesis,
Nanyang Tech. Univ., Singapore.
Prefabricated vertical drains 167
Xie, K.H. (1987). Consolidation theories and optimisation design for vertical drains,
PhD Thesis, Zhejiang University, China.
Yan, S.W. and Chu, J. (2003). Soil improvement for a road using the vacuum pre-
loading method, Ground Improvement, Vol. 7, No. 4, pp. 165–172.
Yan, S.W. and Chu, J. (2005). Soil improvement for a storage year using the com-
bined vacuum and ill preloading method. Canadian Geotechnical Journal, Vol.
42, No. 4, pp. 1094–1104.
Yan, S.W., Chu, J., Fan, Q.J., and Yan, Y. (2009). Building a breakwater with prefab-
ricated caissons on soft clay. Proceedings of ICE, Geotechnical Engineering,
Vol. 162, No. 1, pp. 3–12.
Yin, J.-H. and Graham, J. (1999). Elastic visco-plastic modeling of the time-depen-
dent stress-strain behavior of soils. Canadian Geotechnical Journal, Vol. 36,
No. 4, pp. 736–745.
Chapter 5
Permeation grouting
Gert Stadler and Harald Krenn
CONTENTS
5.1 INTRODUCTION
169
170 Ground improvement
* Structural repair of cracked concrete in a double curvature arch dam (the Koelnbrein Dam,
Figure 5.1) was accomplished by a specialized application of grouting with epoxy resins of high
viscosity and strength (applied under a considerable head of water!). Lombardi provided the
design for this repair work and took the occasion to apply his concept of a Grouting Intensity
Number (GIN) at this major repair project. Another typical example of grouting applications
is grouting of horizontal barriers (blankets) in sand below city excavations. To reduce seepage
during excavation of construction pits at gradients of as much as 10, it is possible to reduce per-
meabilities to around 1 × 10 -7 m/s, which corresponds to seepage values of 1.5 l/s per 1000 m2.
Permeation grouting 171
KW-MALTA KOELNBREINSPERRE
MASSIGER GNEIS GEOLOGIE AN DER SPERRENSTELLE
ANSICHT VON DER LUFTSEITE
PLATTENGNEIS
SCHIEFERGNEIS
30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 09 08 07 06 05 04 03 02 01
1900
1800
1700
LAGE
y = –1000
18 17 16 15 14
13
19 12
1 20 11
222 10
23 9
x = –5000
24
N 26 R. 25 8
7
O CK 27 6
28 5
BL 29 4
30 0 50 100m 3
2
QUERSCHNITT 1
KGS
0 10 20m
Figure 5.1 Kölnbrein Dam, Austrian Drau Hydro Power Company, typical sections.
172
Item
Ground improvement
Item No Group Main Sub Unit Quantity Price price
1.01 Mobilization, site General site installation Ofices, store, personnel LS
installation, demobilization W/Shop, vehicles, etc
1.02 Rigs & equipment Mixing/batching plant No
1.03 Drill rig (Type) No
1.04 Grout pump (single, No
containerised)
1.05 Testing unit No
1.06 Additional units Type as above or other No
speciied
1.091 Relocating rigs & equipment Within project area Per item 1.02-1.06 No
(Type)
1.092 From site to site Per item 1.02-1.06 No
2.01 Rental of equipment General site installation Cal. week
2.02 Rigs & equipment Per item (as above) Cal. week
3.0 Idle/downtime (as speciied) Personnel (Category) on site Man hour
4.00 Setup & rigging drill over
hole
4.01 incl displacing rig > 2.5m No
4.02 Without displacement of rig No
5.00 Drilling for coring or grouting, in all types of ground, all directions and inclinations, collaring < 2.0m above working area
5.01 Coring 75-115mm
5.011 0-15m m
5.012 15-30m m
5.013 30-60m m
5.014 Extra over for casing m
5.02 Roto-Percussion drilling 56 bis 76 mm
5.021 0-6m m
5.022 6-12m m
5.023 12-20m m
5.03 Over burden drilling 115 to 133mm (in loose ground)
5.031 0-15m m
5.032 15-30m m
6.01 Supply, install and sheath MS 2'' dia, port distance 66cm m
grout sleeve pipes (tubes a
manschettes),
6.02 ditto in HDPE m
6.0 Supply, maintain, position Packers: all dia, all depths
and remove.
6.01 Single packer No
6.02 Double Packer No
6.03 MPSP-inlatable packer No
6.04 Circulation-packer incl return line No
6.05 Inlatable double-packer for tubes a manschettes No
Permeation grouting
7.0 Operating grout pump, incl Documentation of pressure,
weighing, batching, storing, rate and quantity as per EN
ducting of grout mixes of 12715 requirement
all kind, operating grout
pump under pressure,
electronic data aquisition
7.01 Hour operation of one only H
(irst) pump
173
Continued
Table 5.1 Proposed standard schedule of rates/ bill of quantities for grouting works (Continued)
174
Item
Ground improvement
Item No Group Main Sub Unit Quantity Price price
7.02 Hour operation of a second H
pump at same site location,
simultaneously with operating
the irst pump
7.03 Hour operation of a third H
pump at same site location,
simultaneously with operating
the irst and second pump
8.0 Material for grout mix
8.01 OPC (Blaine > 3.900 cm2/g) to
8.02 UFC (D80 < 12μm) to
8.03 Sodium-Bentonit to
8.04 Calcium-Bentonit to
8.05 Sodiumsilicat (liquid, 38ºBé) kg
8.06 PU (single shot) kg
8.07 PU (two-component mix) kg
8.09 Acrylat-(as per tenderers kg
proposal)
9.0 Borehole test Water pressure test in rock No
(Lugeon), permeability test in
loose ground (Lefranc), incl all
pumps, ducts, packers and
data recording/
documentation, all depth
Total, net Currency
Permeation grouting 175
It is important that the designer is aware of both the possibilities and the
limitations of grouting. The principles of luid mechanics might on irst
glance seem to govern grouting in the same way as they do the propaga-
tion of luids in other media like pipes and ducts. The lack of knowledge
of the intricate rheology of the grout and of the complex geometry of
low paths in the ground, however, poses serious problems to arriving at
mathematically ‘exact solutions’. Data on the rheology of the luid do lack
information on interstitial adhesion, surface tension relative to wetted
surface, and whether capillary forces would tend to support or prevent
penetration of the grout. It is particularly the small sections of intercon-
nected porosities for which it is dificult to develop a good low model.
This is because the very narrow parts of low channels will – particularly
when its diameter is getting close to the grain size of the suspension –
govern the penetration of grout more by actions of surface tension and
afinity of the luid relative to the wetted surface of the ground than by
iltration, viscosity and yield.
Cementitious grouts are the most common type of particulate grouts;
that is to say they contain particles (i.e., the grains of cement in a water
suspension). Cement as a material requires a water-cement ratio by weight
of about 0.38 to achieve complete hydration. However, in this form it would
be an extremely stiff paste, so for injection purposes additional water is be
added to the mix for the purpose of transporting the cement grains within
the issure (or pores of a sediment). The addition of water has the combined
effects of reducing the strength of the grout, increasing its shrinkage, and
increasing its setting time. The higher the water-cement ratio employed, the
weaker the grout, the greater the shrinkage, and the longer the setting time
that will result.
The question of setting time is important. Cements are manufactured
so that they have a setting time of about 4–5 hours. This period is stan-
dardised to provide a suitable period of workability for normal structural
applications. If we greatly dilute cements the setting time is delayed; 10–16
hours may result for water-cement ratios of 2:1 and 3:1, respectively. The
addition of clays or bentonite into the mix will further delay the setting
of the cement. Accelerator admixtures may be employed to reduce setting
times, but these work best on low water-cement ratio mixes and have the
disadvantage that they tend to increase the viscosity of the mix.
The penetrability of a cement-based grout into issures depends on two
main factors: the grain size of the cement used and the rheological (and
dispersive, particle-separating) properties of the suspension. As is well
known, the success of the grout is characterised by the size of the solid
particles of the grout in relation to those of the issures to be grouted.
However, to study the penetrability of a mix by merely studying the size
176 Ground improvement
dv
1 τ = η dx
τ
dv
2 τ = C + ηB dx η′ dv
dx
2
η = Dynamic viscosity
ηB = Plastic viscosity
ηB 1
1 (dyn. visc. of plastic body)
η′B η′ = Apparent viscosity
C 1 η
1 dv C = Cohesion or yield value
dx
τ dv
dx
Figure 5.2 Rheogram of luids. (From Kasumeter, International Society for Rock
Mechanics, Widmann, R. (1996), Int. J. Rock Mech. Min. Sci. & Geomech.,
33(8):803–847.
Permeation grouting 177
that the cohesion determines the maximum distance the grout can reach,
and the viscosity determines the low rate, and therefore the time necessary
to complete the injection at given pressures.
Simple theoretical considerations and elementary experimental evidence
show that, as soon as internal friction appears in a particulate mix, grouting
is no longer possible. If the cement grains are not transported by the luid
and come into contact, they will develop friction between the particles and
effectively stop grouting. This phenomenon is particularly important since
during the grouting process the initial water-cement ratio may decrease
due to loss of water under the applied pressure (i.e., pressure iltration) or
simply due to gravity (bleeding).
As we have seen from the previous discussion on grout theory, a low
viscosity grout mix is required to achieve suitable low rates in ine aper-
ture issures. The viscosity of the grout is normally measured by means
of the cone eflux test whereby the time required for a measured quantity
of grout to drain from a conical funnel of ixed dimensions is measured.
Various funnel geometries are used for different types of grout. For testing
common grouts used for injection purposes, the Marsh cone is normally
employed.
The ability of particulate grouts to penetrate into ine aperture issures is
controlled by the ability of the particles themselves to enter the issure and
by the degree of elastic widening of the issure that occurs during the grout-
ing process. Various authors have attempted to correlate these parameters.
The following comments indicate the range of results obtained.
The D95 particle size of a cement means that 95% of the particles within
the cement are smaller than this size. A Type I Ordinary Portland Cement
typically has a D95 particle size of about 60 microns, and a Type III rapid
hardening OPC (of the type commonly used for grouting) may typically
have a D95 particle size of about 40 microns. Microine cements are avail-
able with D95 particle sizes as small as 12 microns. The D95 particle size of
Bentonite clay is typically also about 60 microns.*
Following common iltration criteria, Karol (1990) like other authors
proposed for rock grouting that for cement-based grouts to penetrate a is-
sure within a rock mass, the aperture of the issure must be at least three
times the particle size of the cement grains. We consider that in practice
the joint width must be wider than this rule and that in addition to this
initial aperture, further elastic widening of the joint during injection is
necessary.
The ACEL research programme,† like other research (e.g., by Baban
1992) revealed (in carefully instrumented strain measurement tests using
microine cements and epoxy resin components) elastic opening and clos-
ing of the fracture zone by as much as 100 microns during the grouting
operation. This dimension being some eight times the D95 particle size of
the microine cement decidedly proves the importance of the elastic defor-
mation of the rock mass for a successful treatment.
In attempted grouting of water bearing rock at a depth of 830 metres
using microine cement grouts, Naudts (1990) reported that it was not
possible to inject a stable microine cement grout into a strata observed
to have a permeability of over 100 Lugeons. This value would be con-
sistent with very heavily fractured rock (of >>10 fracs/meter and cor-
responding frac widths of 50 to 100 microns), which would normally
be expected to be readily treatable with such materials. In this case it
could be suspected that insuficient pressure might have contributed to
the phenomenon.This is because grouts, when entering a issure, have
to initially overcome resisting forces of friction, being frequently in the
range of speciied maximum grouting-pressure limits! (Feder, see FN,
ISRM 1996).
Suppliers’ catalogue information for microine cements indicates that for
the repair of concrete structures, microine cements with a D95 particle size
of 12 microns will penetrate cracks as ine as 0.25–0.3 mm. In this applica-
tion overpressurisation and elastic opening of the crack is not appropriate,
and this rule of thumb represents a ratio between crack aperture and par-
ticle size of some 20 times.
In order for cement grouts to be successfully injected it is necessary
for the cement particles to remain in suspension during injection. When
injected under pressure the mix may lose water into the issure. This loss
of water will cause a thickening of the mix and the generation of internal
friction, increased viscosity, and rigidity of the grout with (in the end) the
formation of a dense dry cake. These phenomena may eventually block any
further low of the grout into the issure.
If high grouting pressures are to be employed, the grout mix must have
a pressure iltration characteristic that is stable at the required pressure.
Pressure iltration testing requires either laboratory equipment like an API
ilter press or (for lesser requirements) may commonly be replaced by a
simple bleeding test, which measures the tendency for the cement particles
to settle out of suspension. In this test a fresh sample of grout is placed in a
glass measuring cylinder and covered to prevent evaporation. The amount
of free water left on top of the cylinder after two hours is generally termed
the bleeding characteristic of the grout. A grout is considered to be ‘stable’
if there is less than 5% of free water of the total volume of the grout sample
after two hours.
In order to produce stable grout (albeit with a relatively high viscosity)
without further additives or admixtures a water-cement ratio of about
0.6 to 0.8 is required for OPC cements and about 0.9 to 1 for microine
cements. The difference between the two would mostly arise from the
Permeation grouting 179
iner particle size of the latter. However the rheological properties of these
grouts are unsuitable for normal injection applications, being too viscous
and cohesive.
Two courses of action are possible. It is possible to add additional water
to the grout mix to give suitably low values of viscosity and cohesion and
to stabilise the mix by the use of a colloidal additive. The most common
of these colloidal additives is bentonite clay, which is normally added to
the mix water in the ratio of 1%–6% by weight. When added to water
and hydrated, bentonite gives the mix water thixotropic gel properties, and
this acts to inhibit the settlement of the cement grains. However, the addi-
tion of bentonite strongly increases the cohesion, and to a lesser extent the
viscosity, of the mix. The bentonite particles are of a similar size to OPC
particles and do not affect the penetrability of these materials. However,
the bentonite particles are considerably larger than microine cement par-
ticles and stabilising microine cement grouts in this manner would limit
their performance. Other, more powerful, colloidal admixtures in the
form of long chain polymers such as methyl cellulose are available, but at
high concentrations these materials will signiicantly increase the cohesion
(reducing the reach of grouts) and viscosity of the mix. Catalogue informa-
tion indicates that a 2% solution of methyl cellulose in water at 20°C has
a viscosity of 4,000 centipoises. Note that the viscosity of water at 20°C is
approximately 1 centipoise.
The stability of grouts may also be improved to some degree by the
addition of very ine-grained pozzolanic materials such as silica fume.
This material is the by-product of the ferro-silica industry and generally
has to be imported in bulk from Norway. It therefore attracts substantial
transport costs for those outside Europe. The material is extremely ine,
having a grain size with a mean diameter of 0.1–0.15 microns, about 100
times iner than Ordinary Portland Cement. The material reacts with the
lime of the cement liberated during the hydration to form an amorphous
gel. Vipulanandan et al. (1992) reported tests on grout mixtures compris-
ing an Ordinary Portland Cement that had been stabilised by either the
addition of 5% bentonite, or 5% silica fume material. Both mixes had a
water/binder (cement + silica fume where used) of 1:1. He observed that the
measured bleeding of both mixes were similar, about 8% after two hours.
Penetrability, however (of the silica fume mix), would in comparison be
expected to be much better.
The alternative method is to use a stable grout mix with a lower water-
cement ratio and to achieve the required rheological properties by add-
ing of a super-plasticiser such as a Na-metacrylate. These admixtures are
surface active agents that negatively charge the cement grains and act to
reduce the grain agglomeration, apparent cohesion, and viscosity of the
grout. Grout mixes formulated with this type of admixture have the added
advantages that they are stronger, set faster, and suffer less shrinkage than
180 Ground improvement
conventional cement bentonite grouts. Set and workability are also easier to
control when using accelerator admixtures.
Stadler and Hornich (2008), for the purpose of design and prepara-
tory works, classify grouting into ive different categories. It should be
mentioned that all techniques associated with intended deformation while
grouting will not be considered in this section of the chapter. However, it
still is important to realise that every grouting application under pressure
is hydraulically introducing energy into the ground. Making hydraulic
forces act onto surfaces of grains in sediments, or onto the surface of is-
sures in rock, causes displacements even of a minor order be it intended
for deformation or not. So let us assume and accept that even permeation
grouting is a process where such (largely elastic, and only to a minor
extent plastic) deformations do occur, and in fact do support the pen-
etration of grout, the saturation of voids, and thus the success of the
treatment.
Design speciications for permeation grouting should carefully view this
aspect, particularly when limitations on grouting pressures are stipulated.
The difference between a useful and unavoidable (intrinsic) deformation by
the pressure in a propulsed grout low, and the avoidance of a frac pressure
which overpowers the structural resistance in the ground (causing undesir-
able deformation and heave) is not necessarily reconcilable with the weight
of the overburden! Today, this still remains the governing concept for the
stipulation of such a pressure limit. Viscous Bingham-luid grouts disperse
considerable energy in the irst decimetres after entering the ground, and
exhibit a strongly digressive pressure distribution in the porosities pene-
trated. Thus, the corresponding uplift forces remain limited. The ultimate
proof, however, still is a ield test to verify the genuine ground reaction
(instrumented with proper deformation gauges) under different pumping
velocities and grout types.
An overview on grouting techniques (principles and methods) is given
in Figure 5.3 and in EN 12715, Execution of Special Geotechnical Work,
Grouting (2001), under Pt 7.3.1.1. For the case of rocks, the Report on
Grouting (ISRM, 2000) is the literature of common reference. Ground
Improvement (Second Edition, 2005) contains a reference where a prac-
tical crossover between virgin permeabilities in soils and rock is com-
bined with types of grout mixes to choose, placement techniques, and
grouting protocols (for operative parameters like pressure, quantity,
energy, etc.).
Adequate knowledge of the relevant properties of the subsoil is of prime
importance for designing grouting works. It cannot be overemphasised
that with grouting being a predominantly hydraulic process, site investi-
gation does primarily require reconnaissance of hydraulic properties of
the ground. In particular, the stratiication of sediments and the type, fre-
quency, and orientation of discontinuities in rock are important features.
Soil Rock
Type Fine Coarse Type Diffuse issurisation, Discrete joints (fracs)
Kakinites
Grout ways, Drillrods & Collapsble/ Stable rock Unstable
ports lances Unstable
Perforated pipes Ports Multiple packerSleevePipe
Sleeved manchette pipes single/double packer
Open-ended System Stage grouting Bottom Stage
pipes up
grouting
System Displacement (frac. compaction) Penetration (pore grouting, permeation) Frac(Fissure) Permeation grouting
grouting
Grout mixes Silicate/ Grout mixes Acrylate/
Acrylate Epoxy
Microine binder Microine binder
Bentonite/Cement Ordinary Portland Cement
Mortar Mortar
Virgin Kf 10.E-6 10.E-5 10.E-4 10.E-3 10.E-2 >>10.E-1 Virgin Lug. 1 5 10 25 50 >>100
Permeation grouting
Grouting Energy and Grout limited Limitation of Grouting Energy and saturation Pressurelimitation/Energy
parameters displacement quantities below quantity and parameters criteria criteria
criteria frac pressure until pressure split-spacing/from inside outwards//from outside inwards
resurgance or
interconnections
do occur
Figure 5.3 Overview of grouting techniques. (From Stadler, G. (2004). ‘Cement grouting,’ in Moseley, M.P. and Kirsch, K., Ground Improvement,
2nd ed Spon Press: Abington.)
181
182 Ground improvement
Since its early application at the Aswan project (built in the years 1960 to
1971, Figure 5.4), grouting of alluvial ground is accomplished by using the
sleeve pipe method (tube à manchette). Pipes inserted into boreholes usu-
ally are of 1½ to 2 inches in diameter (single-port 1/2-inch pipes are now
also used in uniform sands). The annular space between sleeve pipe and
borehole is sealed by a ‘plastic’ sheathing grout of cement—bentonites.
This sheath grout is intended to prevent grout escaping to the surface
instead of penetrating into the ground. However, this technique is not
suitable in rock.
Grouting through drill rods or driven pipes (lances) are techniques
for grouting applications of lesser requirement in coarse-grained ground
of high porosity and at low pressures. Grout mix in these cases will be
placed through perforated pipes which are driven or inserted in predrilled
boreholes; via borehole casings during withdrawal from the borehole; and
through the drill bit itself when drilling the grout hole.
The range of penetration and the degree of illing of voids using drill rods
or lances is limited. Fine-grained and cohesive soils are less apt to treatment
with particulate grouts or chemicals for reasons of iltration. Schulze (1993)
did some research on pore size distribution and penetrability of sediments
by relating grain size distribution of OPC and microine binders to the sieve
analysis of soil samples. Comparable efforts to deine the application of
Figure 5.4 Recent view of a cross-section of Aswan High Dam (on-site tourist poster).
184 Ground improvement
m
50/
10/
k[m/s]
Smooth joints
10–5
1/m
10–6
/m
b
5/m 10 2 50/m100
a c
/m 0/m
Rough joints
10–7 d
1/m
10–8
1
on
ns
ns
01
uge
geo
geo
1L
Lu
Lu
100
10
10
100
Figure 5.5 Grouter’s diagram (From ISRM, modiied by Stadler, G., Howes and Chow
(1998). ‘100 years of engineering geology,’ symposium, TU-Wien).
150
Resistance
to flow
(Shear strength
dynes/cm2)
Compressive strength (N/mm2)
50 100
40
30 28
Day 50
compressive 0.2
20 strength
Bleed
capacity
10 0.1
Bleed
0
0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Water/cement ratio (by weight)
1 kg.f = 981 × 103 dynes
Figure 5.6 Viscosity, shear strength, and bleeding of OPC suspensions. (From Littlejohn,
G. and Stadler, G. (1976). Joint lectures on anchoring and grouting at SAICE,
South Africa; and EUROCK 2004 & 53rd Geomechanics Colloquium,
Salzburg, Austria.)
even for remote control and interpretation. Storage and handover to the
engineer on discs for documentation purpose is standard. Interference in
the daily routines of a grouting operation from remote interpretation of
data is not recommended.
Quality assurance of the grout mix and its consistency are of prime
importance:
Figure 5.7 Drakensberg Pumped Storage Scheme, RSA, Tailrace Tunnel, Precompression
grouting, ESCOM, Rodio SA, 1970s.
Permeability tests before and after grouting may be helpful to assess the
degree of saturation achieved by grouting. The higher the virgin perme-
abilities of the ground, the greater the chance of a considerable improve-
ment. Wherever possible, upstream/downstream piezometers or seepage
rates should form the acceptance criteria for a successful impermeabilisa-
tion scheme and reduction of take of subsequent passes would indicate the
progress of illing.
Drilling energy measured when drilling (roller or ish-tail bit, borehole
supported by drilling mud) test holes before and after grouting indicate
the gain of strength. Core sampling for laboratory testing is more suit-
able in rocks than in soils. The system is inevitably failing in soils, even
using diamond core drills with uniaxial strengths of the cored material
dropping below 5 MPa, since obtaining intact samples, which would sat-
isfy laboratory requirements, is almost impossible. However, recovered
sample can still be used for visual inspection of the grouting success.
Open pit inspection sometimes is suficient to ascertain an improved
cohesion of grains or the visible presence of grout in the ground but
limited in depth.
mixing heats the grout and triggers the hardening process of hydration at
too early a stage. The mix should be kept (if at all) in agitating tanks where
low energy paddles keep the grout in motion and prevent particles from
sedimenting.
Many experts are of two minds about the requirements on the ‘evenness’
(continuity) of the grout low, though a slightly pulsating regime inds many
supporters. But what is even more essential is the possibility to regulate
low and pressure of the pump in a way that makes either a constant energy
concept possible or a constant rate or constant pressure scheme.
Pressure limiters with ON/OFF function are not suitable and hence not
recommended; pumps with an uncontrollable direct drive need a bypass
system which is prone to early wear; abrasive grouts should be handled
by low wear plunger pumps; ease of cleaning and maintenance is of great
importance (downtime!) especially when using chemicals.
The correct choice of grouting material for the grouting works is of major
importance. In recent years, new chemical products have been introduced
on the market by several suppliers. Experience shows that the new materi-
als are often only tested under off-site ambient conditions and rarely under
conditions corresponding to the ones prevailing on site. Studying datasheets
may not be considered suficient. Depending on the grouting application,
laboratory tests need to be set up in accordance between designer and con-
tractor in an endeavour to appropriately test envisaged grouting materials.
The user needs to be aware that laboratory standards and experience may
be different in each country and even more different from continent to
continent.
Portland cement as a grouting material is well known and suitable for
most standard grouting applications. Very often in a two-stage grouting
process it can be found that in a primary grouting phase OPC is injected
with a Blaine value of around 3900 cm2/g or higher, and for the second
stage (to ill voids of a smaller cross-section) an ultra-ine cement (UPC)
may be applied. In Europe, the use of UPC is well established but on other
continents scarcely available. Also, a combined application of OPC fol-
lowed by a chemical grout such as a gel is common. Experience using foams
show that foams are not always suitable for permanent applications. Foams
should be used for tasks such as stoppage of water inlow into a tunnel
or into an excavation pit, and applying a second run using cement-based
grouts for ‘illing up’ or as a more rigid supplement.
In ‘modern grouting methods’ the requirement for controlled (low) vis-
cosity and yield (cohesion) may be achieved by adding of a ‘super-plasti-
ciser’ as an admixture, making a much lower water/cement ratio possible.
196 Ground improvement
The latter is recommended for making the grout more stable, less prone
to washout, producing less excess water under grouting gradients, and
avoiding pocketing of iltration water in the ground. The yield value (or
‘cohesion’ of the luid at zero low, measured by ball harp or Kasumeter)
should be carefully monitored to avoid producing ‘sticky’ grout, which
prevents free travel of the luid beyond a certain range.* Typically, when
using an OPC grout, the water/cement ratio would range from 0.8 to 1.5.
For microine cements (due to the greater ineness of these materials) the
water-cement ratio would be in the range of 1.1 to 2.0. A lower water-
cement ratio of any particulate grout makes it stable by its own constitu-
ents, and there is no requirement to add bentonites or other clay material.
The combination of low water/cement ratios and the absence of clay in the
mix has the advantage of
* Remember that the formula (for the ‘range’ of grout travelling from a borehole) follows
principally: R=Pgrout*Awidth of void/τf yield of luid (grout) (where the dimensions would be for R
[m], P[bar], A [m], τ [bar]).
† Stephen and Gert (1999)
Permeation grouting 197
Chemical reactive
components
Organomineral resins
Silicate resins
be achieved. Soft gels are mainly used for sealing applications (for example,
in excavations) and do attain strength of 0.1 to 0.5 N/mm2. Gels consist
of approximately 50%–70% of water, 30%–45% of sodium silicate plus
hardener or locking agent. The major advantage of a hard gel compared
to cement mixes is the respective setting/hardening time. Hard gels may
develop their inal strength within hours. For a more detailed summary
on chemical grouts and special chemical grouts, the reader is referred to
Hornich and Stadler (2009) and subsequent paragraphs on silicate and
acrylate grouts.
‘[Chemical grouts] is a generic term that can be applied to all forms of grout
that contain chemicals in solution either in water or with each other. The
family includes silicates, phenolic resins, lignosulphates, acrylamide, acry-
lates, acrylic, soluble lignates, sodium carbomethylcellulosis, amino resins,
polyurethane, polyester, epoxies, etc. Commonly these chemicals are dis-
solved in water to form aqueous solutions and rely on a chemical reaction
to cause a change of state from a luid to either a foam gel or a solid. In this
type of grout there are no suspended particles, hence by deinition chemical
grouts are stable and the application of a bleeding test to this class of grout
employed for injection into completely weathered rocks and soils after hav-
ing been pretreated with particular suspensions.
Liquid sodium silicates are highly alkaline, with a pH in the order of 10.5
to 11.5. They will react with an acid or acid salt to form a gel. Amongst
the gelling agents commonly used were sodium bicarbonate, sodium alu-
minate, and various other inorganic or organic acids. In the late 1950s a
new generation of gelling agents was developed consisting of methyl and/
or ethyl diesters formed from the action of aliphatic diacide mixtures on
methanol and/or ethanol. These gelling agents when dispersed in a sodium
silicate solution in the correct proportions go through a slow saponiica-
tion, which after a predetermined time provokes the liquid to gel in the
form of a white mass: SILICA GEL. These reagents are proprietary chemi-
cal systems, such as Hardener 600, and are marketed by specialist com-
panies such as Rhone Poulenc of France. The silicate grouts in common
usage today are a combination of a sodium silicate resin with a proprietary
chemical agent (hardener).
In application for grouting, the gelling agent or hardener is mixed with
the diluted sodium silicate shortly before injection into the soil. This grout
penetrates into the interstitial voids between the soil particles, conferring
on the formation the required cohesion and impermeability when solidify-
ing during setting.
Silica gels suffer from the phenomena of syneresis, which refers to the
progressive extrusion by the gel of a signiicant quantity of water. The
phenomenon is particularly problematic in dilute low viscosity gels, which
have been formulated for a long setting time. When injected into ine sands
syneresis is not normally a problem when the interstitial pore dimensions
within the soil are small. However, the phenomenon may become problem-
atic if injection takes place into coarse sands or open issures in rock where
the pore aperture dimensions are larger. In these materials the strength
of the gel itself becomes of importance and syneresis can lead to the inal
failure of the gel.
Silica gel can also be subject to washing out. When grouted sand samples
are immersed in lowing water it is observed that the gel will progressively
break down, leading eventually to a complete disintegration of the sample
for certain gel types. The water solubility of the silica gel is due to the
presence of non-neutralised soda, which attacks the silica. Laboratory tests
have shown that the higher the non-neutralised soda concentration, the
greater this solubility becomes. Shirlaw (1987) described the piping failure
in coarse beach and alluvial sands treated with silicate grout and attributed
the failure to these mechanisms. The same formulations had previously
been successfully when injected into ine-grained sands and weathered
rocks that had a smaller pore structure.
It should be noted that the suppliers of gelling agents for sodium silicate
grouts do not recommend these materials for grouting of issures in rock,
200 Ground improvement
* Stadler (2001).
Permeation grouting 201
UK—EEC
Very toxic LD50 = 0–25 mg/kg
Toxic LD50 = 25–200 mg/kg
Harmful LD50 = 200–2000mg/kg
USA
Very toxic LD50 = 5–50 mg/kg
Moderately toxic LD50 = 50–500 mg/kg
Very slightly toxic LD50 = 500–5000mg/kg
Canadian Environmental Protection Compendium, in an inverse order
to the above:
Practically non toxic LD50 = > –15,000 mg/kg
Slightly toxic LD50 = 5000–15,000 mg/kg
Moderately toxic LD50 = 500–5000 mg/kg
Very toxic LD50 = 50–500 mg/kg
Extremely toxic LD50 = 5–50 mg/kg
Super toxic LD50 = <5mg/kg
Karol describes the LD50 for acrylamides (used in acrylamide grout prod-
ucts such as AM9, Nitto SS, AV100, etc.) to be 200 mg/kg and the LD50 for
the methylene-bis-acrylamide commonly used as the cross-linking agent as
390 mg/kg. Karol quotes the methanol acrylamide used in ROCAGIL BT
as having a toxicity of 50% of Nitto SS.
Obviously and in consequence, when working with chemicals which to
any principal extent might be toxic, it is necessary to establish safe expo-
sure levels signiicantly below the fatal dose and to ascertain any degree of
cumulative toxicity.
Permeation grouting 203
Many and most of the ‘adverse effects’ (from skin irritation to neurotox-
icity) are not fatal, however, but obviously do already occur at consider-
ably lower levels of exposure than the LD50 dosage. In summary, the safe
application of chemical grouts has to be meticulously established by proper
planning before any use on site. Grouts which require extensive quality
assurance programmes (as a consequence of differentiated dosing and mix-
ing programmes on site) should be used last. Grouts which are particularly
reaction-sensitive to even marginal dosing errors and temperatures should
be avoided. The fact that ever-demanding speciications are aiming at per-
meability coeficients below 10 -7 m/s in sandy gravels or below 0.1 Lugeon
in rock will increasingly make the use of chemicals beyond the range of
application of microine binders inevitable in future.
The more questions of material interrelate with aspects of engineering
application, the more it becomes the duty of engineers to perceive both
disciplines when realising demanding grouting works. They also have to
be prepared and educated enough to accept responsibility not only for the
engineering aspects, but for questions of safety and the proper environmen-
tally responsible use of such materials.’
For special grouting applications where high strength is a criterion,
cement-based grouts need to be modiied with additives to fulil design cri-
teria such as volume stability, degree of expansion, and degree of sedimen-
tation. Quite a number of additives are available on the market. The user
needs to be aware that the majority of the additives have been developed
for the concrete industry and just been modiied to be used in grouts. It is
important to undertake proper laboratory testing to verify the suitability
and successful functioning of the additive. The average volume of additives
used in cement-based grouts is in the range of 1%–2%. The laboratory tests
shall also consider the way grout will be mixed on site, considering the rota-
tion per minute, the time of mixing, and the order of adding the materials
into the mixer. The latter is particularly important when mixing chemical
grouts. Chemical grouts such as resin or gels do often consist of two to four
components. For small grouting jobs this is suitable; however, for larger jobs
with large quantities the appropriate equipment for preparing a grout out of
four components may often not be available. As mentioned before, cement is
the most common material for producing grout, especially Portland cement.
Blended hydraulic cements, blast furnace cements, and other special cements
such as microine cement are less used for grouting. When designing a grout-
ing application, it is important to be aware that cement standards and dei-
nitions differ between countries. For example, in Europe cement is deined
by its strength followed by its mineralogical composition and original prime
material. In North America, cement is basically deined by its application,
originating materials, and its characteristics of strength development. In
recent years, cement manufacturers have specialised and developed ready-
mixes of cement-based material (so-called binders) for standard grouting
204 Ground improvement
applications and also for illing the annular space between the manchette
tubes and the ground (sheath grout). One of the popular standard additives
to grouting mixes is clay containing high proportions of montmorillonite.
In the construction industry these clays are better known as bentonites.
Bentonite is usually added to reduce the sedimentation of aggregates (pro-
viding for ‘stability’ of the mix), and does change the low characteristic
(rheology) and viscosity of the mixed grout. This can be achieved by adding
just 1 to 2% of bentonite (by weight of cement).
Literature over the last few decades has seen quite a number of reports
on successful grouting applications, with detailed reports about their
design, execution, and performance, including many hydro and irrigation
dams (ICOLD). Several useful conclusions may be drawn from these expe-
riences, but it is not always wise to compare project situations without
detailed knowledge on ground conditions and drilling-grouting technolo-
gies applied, or targets set and (measurably) achieved. In order for cement
grouts to be successfully injected, it is necessary for the cement particles
to remain in suspension during injection. Equally important are effective
grouting pressures, suficiently high to overcome substantial pressure losses
when entering ine voids and to enlarge issures elastically in order to facili-
tate the entry of the grout particles.
Simple theoretical considerations and elementary experimental evidence
show that, as soon as internal friction in a particulate mix occurs, grout-
ing is no longer possible. The penetrability of a cement-based grout into
issures depends on two main factors: the grain size of the cement used and
the rheological properties of the suspension.
However, merely studying the size of a single dry grain is misleading: sin-
gle dry grains have a tendency to grow in size during hydration and agglom-
erate, producing ‘locs’ larger than the single dry particle. To improve the
penetrability of a particulate grout (suspensions are most popular because
of being cheap), it is necessary to both keep the grain size low, stay within
or delay the start of hydration, and reduce/prevent the tendency for single
grains to locculate in the mix.
The question of setting time (irrespective of the type of grout) is impor-
tant for the management of the grouting process against time, and the
choice of a correct treatment system altogether. Cements are manufactured
so that they have a setting time for industrial applications of about 4–5 h. If we
greatly dilute cements the setting time is irst delayed (10–16 h may result
for water-cement ratios of 2:1 and 3:1, respectively), and then accelerated
again during iltration. The addition of clays, bentonites, or accelerator
admixtures reduces setting times (simultaneously increasing the viscosity
Permeation grouting 205
of the mix). It is quite clear that the rheological behaviour of the suspension
follows delicate relationships which have to be monitored and engineered
on a continuous basis.
In conclusion, the essential ingredients for a successful grouting proj-
ect are
REFERENCES
Jet grouting
George Burke and Hiroshi Yoshida
CONTENTS
207
208 Ground improvement
6.1 INTRODUCTION
6.2 HISTORY
The scouring power of water has probably been employed as a soil excava-
tion method since early times, especially in the mining industry, where use
of it is documented in the Middle Ages.
The earliest patent regarding jet grouting was applied for in England
in the 1950s; however, the real practical development of jet grouting took
place for the irst time in Japan. This technology was initially aimed at
improving the effectiveness of water tightness in chemical grouting by erod-
ing the untreated or partially treated soil, which was then ejected to the
surface for disposal, being replaced with cement-based slurry for impervi-
ousness. Subsequently, jet grouting was irst applied to create thin cut-off
walls, as shown in Figure 6.2.
For preventing water ingress, a derivative of panel jet grouting was
evolved which sealed the gap between declutched sheet piles, for example.
Air
Grout Grout Air
Water Air
Air Grout
Air
Air
Grout
limited investigation into the soil and a lack of understanding of the real
elementary process that occurs when the jet meets the soil.
In the late 1980s, a new concept provided an innovative progress for jet
grouting systems, namely, dual jets colliding with each other to limit their
eroding capability, thus achieving an exact intended diameter regardless of
soil type. The arrangement of these jets is shown in Figure 6.8a while an
exposed column is shown in Figure 6.8b.
The conceptual comparison of conventional and colliding methods is
shown on Figure 6.9, noncolliding jets producing columns of variable
diameter in variable ground. Colliding jet grouting has raised the required
design quality since its appearance under the name of ‘crossjet grout-
ing’. In the early 1990s, colliding jetting was further evolved to include
the deep mixing method to substantially increase the range of applica-
tion. Conventional in-situ soil mixing suffers from a serious drawback of
imperfect continuity when executed adjacent to walls; however, attaching
an assembly of colliding jetting equipment at the tip of a drilling bit or
blade as in Figure 6.10 has enabled the construction of optimal interlock-
ing, as shown in Figure 6.11.
Furthermore, the enhancement in this in-situ mixing system results in
more than four times the treated volume using the same equipment. This
is shown in Figure 6.12, the conceptual schematic of the jet and churning
system management (JACSMAN) system.
1m 2m
(a)
Water jet
at 40 MPa
and 180 l/min
(b)
Figure 6.8 (a) Dual colliding jets. (b) Columns produced by dual colliding jets.
Many factors inluence the eficiency and effectiveness of the jet grouting
process and require consideration when designing and constructing jet
grout columns.
(a)
(b) (c)
Profile
N-value
Soil
20 40
10 30 50
Sand
and
gravel
Sand
and
clay
Fine
sand
Figure 6.9 Principles of cross jetting. (a) Strike marks of dual colliding jets on pressure-
sensitive ilm. (b) Soil cutting by a dual colliding jet. (c) Soil cutting by a single jet.
Jet grouting 215
1000 1300
2300
2300
Figure 6.12 Treated area enhanced by colliding jets in JACSMAN (all dimensions are in mm).
216 Ground improvement
Limit break
pressure (plimit)
Breaking speed ( vcut)
Minimum break
pressure (pmin)
Sand Clay
Unconfined compressive Unconfined compressive
strength qu = 80 kN/m2 strength qu = 150 kN/m2
Eroding distance (mm)
30 30
25 25
20 20
15 15
10 10
5 5
0 0
0 100 200 300 400 0 100 200 300 400
Jet pressure (kPa) Jet pressure (kPa)
Figure 6.14 Eroding distances vs. jet pressure for sandy and clayey soil (results of small-
scale laboratory tests).
p0 p
v0 = m 2 g = m 2 0 (6.1)
γ ρ
where p0: initial pressure at the nozzle, v0: initial velocity at the nozzle, g:
acceleration of gravity, m: nozzle eficiency, γ: luid unit weight, and W: luid
mass density.
Jet grouting 217
0.1
Figure 6.15 Dynamic pressure ratio (p/po) along jet centre axis with various air velocities.
jet centre axis with various air velocities). Jet grouting requires compressed
air for successful operation in several respects. It is irst indispensable for
obtaining maximum eroding energy and then of vital importance for con-
veying spoil up to the ground surface.
0.5
3 1
Dynamic pressure ratio
0.1
0.05
2
0.01
Figure 6.16 Dynamic pressure ratio (p/po) along jet centre axis.
Jet grouting 219
Clean sands
Table 6.1 The standard soilcrete diameters (m) for sandy and clayey soil using triple
luid jet grouting
N valuea
Gravelb
Sandy soil N ≤ 30 30 < N 50 < N 100 < 150 < 175 <
≤ 50 ≤ 100 N ≤ 150 N ≤ 175 N ≤ 200
Clayey soil – N≤3 3< N ≤ 5 5< N ≤ 7 – 7<N≤9
Organic soilc
Effective diameter vs. depthd
0 < Z ≤ 30m 2.0 2.0 1.8 1.6 1.4 1.2
30 < Z ≤ 40m 1.8 1.8 1.6 1.4 1.2 1.0
Lifting rate (min/m) 16 20 20 25 25 25
Pumping rate (m /min)
3 0.18 0.18 0.18 0.14 0.14 0.14
Note: For cohesion c around 50 kN/m2, the standard diameter may be dificult to obtain. For sandy
soil with N > 150, and clayey soil with N > 7, the grouting speciications must be determined with
considerable examination such as a ield veriication trial.
a The largest SPT-N value of the soil to be treated should be used.
b For gravelly soils, the soilcrete diameter expected is tabulated diameter less 10%. A ield trial to
verify the diameter is recommended prior to production.
c For organic soil, considerable examination is recommended to determine the grouting speciications.
d For the depth Z > 40, considerable examination is recommended to determine the grouting
speciication.
density, soil matrix, and other conditions. When soil contains more than
30% gravel, or the size of gravels exceeds 10 cm in diameter (cobbles),
resulting soilcrete diameter may be smaller than expected. Reducing
tool rotation or increasing slurry pump rate may solve this type of prob-
lem. Boulders will block the jet stream and a ‘shadow’ of untreated soil
will exist beyond. Buried obstructions can also include trees, utilities, or
cemented soil.
Table 6.2 The standard soilcrete diameters (m) for sandy and clayey soil using superjet
grouting
N value
Sandy soil N ≤ 50 50 < N ≤ 100 100 < N ≤ 150 150 < N
Clayey soil N≤3 3<N≤5 5<N≤7 7<N≤9
Organic soil
Effective diameter vs. depth
0 < Z ≤ 30m 5.0 4.5 4.0 3.5
30 < Z 4.5 4.0 3.5 3.0
Notes:
1. A ield trial prior to production works is recommended to verify the diameter.The tabulated diam-
eter is sometimes dificult to obtain in soil with certain characteristics.
2. For gravelly soil, a ield trial to verify the diameter must be performed prior to production works.
Soilcrete diameter with the tabulated diameter less 10% may be used for preliminary designing.
3. For soft soil (sandy soil N < 10, clayey soil N < 1), the diameter sometimes exceeds the tabulated
diameter, which leads to shortage of solidifying material and results in lower compressive strength
than expected. A ield trial to verify the diameter is recommended prior to production.
4. Sandy soil with N < 150 in the table applies only to nonsolidiied sandy soil. For clayey soil with
N > 9, you may consult the SuperJet Association for some speciications to achieve the construc-
tion objective. A ield trial to verify the diameter is recommended prior to production.
5. For cohesion c around 50 kN/m2, the standard diameter may be dificult to obtain.
If the jet is sound, the pressure-sensitive ilm reveals an annulus, with the
centre destroyed, which is the so-called core of the jet still maintaining suf-
icient eroding energy to penetrate the ilm, as sketched in Figure 6.18, left (a
focused low). For a defective jet, the ilm relects a totally coloured spot, with
no central penetration as sketched in Figure 6.18, right (a turbulent low).
Apart from dynamic pressure and low rate, there are other parameters
that have an inluence on the eroding power of a liquid jet. An experimental
equation explains this:
( )
−1 / 1.4
R = 4.95Kp0−1.4 Qw−1.6 N t−0. 2 vn−0.3 (6.3)
where:
R = Eroding distance (m)
K = Improvement factor (experience based) (m/sec)
p 0 = Pumping pressure (tonnes/m 2)
Qw = Flow rate (m3/sec)
Nt = Repetition frequency (number of times a jet nozzle passes the same
point)
vn = Rotational velocity of nozzle (m/sec) = Dm × π × Rs/60 (Dm: Diameter
of the monitor, R s: rpm of the monitor).
4.0
Rs (Rotating speed: rpm)
3.5
Column radius (m)
3.0
2.5
2.0
Rs = 1.25
Rs = 2.5
1.5 Rs = 5
2.5
1.0
0 5 10 15 20
Repetition frequency
Figure 6.19 Experimental results for optimal repeating frequency of eroding jet.
(a) (b)
t t
Figure 6.20 Lifting methods. (a) Intermittent lift. (b) Steady lift.
both columns must be installed correctly and the achieved properties must
be in accordance with those values required by the design.
1.3σ 1.3σ
50 50
x = 27.8 x = 127
40 40
Frequency
σ = 13.3 σ = 54.3
30 30
20 20
10 10
0 0
1 2 3 4 5 6 (MPa.) 20 60 120 140 180 220 260 (MPa.)
Unconfined compressive strength Unconfined compressive strength
Figure 6.21 Histograms of unconined compressive strength using triple luid jet grout-
ing in clayey soil (left) and sandy soil (right).
224 Ground improvement
and cohesive (clayey) soils. The Japan Jet Grouting Association has adopted
these distribution charts, deining the unconined compressive strength to
be taken for design to be the minimum safe values which range between
1% and 3% from the least values in the whole group. Table 6.3 shows the
standard properties for soilcrete using triple luid jet grouting.
This deinition gives the standard unconined compressive strengths as
follows (where the water/cement ratio of the grout is 1):
According to the German E DIN 4093 (draft) for the design of all kinds
of stabilised soil, the maximum allowable unconined compressive strength
(qu,k) to be used for jet grouting is:
qu,k < 10 MN/m2, which is calculated as the minimum of either the smallest
value measured in a series of four samples or (0.6 to 0.75) times the mean
value of the series of samples. The design value (qu,d) is: qu,d = qu,k × 0.85/γm
where qu,d is the design value, 0.85 is a factor to consider long-term load-
ing, and γm is the partial safety factor for this material. The partial factors
for the loads (load case 1) vary between 1.35 (for dead weight) and 1.5 (live
loads). The resulting global safety factor between mean value and design
Table 6.3 The standard properties for soilcrete using triple luid jet grouting
Unconined Modulus
compressive Bonding Tensile (E50) of
Grout strength Cohesion strength strength deformation
material Soil type (MN/m2) (MN/m2) (MN/m2) (MN/m2) (MN/m2)
JG-1(H) Sandy soil 3 0.5 1/3C 2/3C 300
Clayey soil 1 0.3 100
JG-1(L) Sandy soil 2 0.4 200
Clayey soil 0.7 0.2 70
JG-2 Sandy soil 3 0.5 300
JG-3 Sandy soil 1 0.3 100
JG-4 Organic soil 3 0.3 30
JG-5 Clayey soil 1 0.1
Notes:
1. All data are 28-day cured strength and were determined from core samples.
2. Strength-controlled soilcrete material is usually used for sandy soil. In case it is used for the soil
stratiied with sandy and clayey layers, the strength of clayey layers are reduced with the following
rates:
JG-2: 70% of JG-1
JG-3: 50% of JG-1
3. The densities of soilcrete are regarded to be similar to those of the in-situ soil.
4. For gravelly soil, sandy soil data are to be used.
5. Seven-day strength of soilcrete is regarded to be 30%–40% of the four-week strength.
Jet grouting 225
strength from this is between 4.4 and 3.2. For this purpose, samples are
tested after a curing time of 28 days.
The directory from Japan Road Association states that permeability is in a
range of 1 × 10−6 to 1 × 10−7 cm/s. The uses of the grout material are as follows:
PSI (MN/m2)
1500
(10.34)
Cement
content
1250 150-250
(8.61) kg/m3
Unconfined compressive strength
0
0 10 20 30 40 50 60
Age (days)
Figure 6.22 Strength–material type chart. (Redrawn from Burke, G.K. (2004). Jet
grouting system: advantages and disadvantages, Proceedings of Sessions of the
GeoSupport Conference: Innovation and Cooperation in the Geo-Industry, Jan.
29–31, 2004, Orlando, Florida, United States; sponsored by International
Association of Foundation Drilling (ADSC) and the Geo-Institute of the
American Society of Civil Engineers.)
226 Ground improvement
4.00
3.50
3.00
2.50
2.00
1.50
1.00
0.50
y (m)
0.00
–0.50
–1.00
–1.50
–2.00
–2.50
–3.00
–3.50
x (m) –4.00
Figure 6.23 Effects and risks related to drilling deviations, and effect of poor drilling
tolerance on column construction.
Jet grouting 227
r A borehole restriction
r Too small a drill hole (annulus)
r Too small a hole through a footing
r Soft, squeezing clays
r Gravels that are collapsing
r Loss of air return
r Open, porous, gravely zones
r Fibrous peats
r Very soft clays
r Cohesive soil erosion
r Erodes in pieces that block the annulus
r Very thick (viscous) spoil
r Depth
r Withdrawal rate and
r Step height and step timing (considering rotation speed)
r Uniform lift rate (considering rotation speed)
r Air pressure and low rate
r Grout or water pressure and low rate
r Rotation speed
r Grout density
In addition, some specialists have developed inclinometers built into the jet
grout monitor that measure deviation of the drill string. It is also equally impor-
tant to carry out quality control testing on the grouts used. This normally
includes speciic gravity, viscosity, and strength by 28-day cube strengths.
The knowledge of all these parameters allows the site engineer to review
the column installation and come to a decision as to whether any column
is misplaced or incorrectly installed. This is of paramount importance for
base slabs or tunnel break-in or break-out where the omission or misplace-
ment of a column can have the most serious effect on performance or safety.
A further dificulty is the repair of these jet grout bodies as usually failures
are dificult to locate.
Franz (1972), Fritsch and Kirsch (2002), and Kirsch and Sondermann
(2002) list standards and publications relating to the control and execution of
Jet grouting 229
r Groundwater control
r Movement control
r Support
r Environmental
230 Ground improvement
These lists show that jet grouting has a multitude of uses, all of which
must be understood, designed, and executed accordingly. Some important
main applications are now described in more detail.
6.4.2 Underpinning
Underpinning of structures using jet grout normally involves the construc-
tion of a body of improved ground beneath the structure such that the
Jet grouting 233
+26.10 mWN
±0.00 m
−3.00 m
First cut −3.50 m
−4.00 m
L = 14.7
0m
Alpha =
10°
Second cut −7.00 m 208.16 kN/m
−7.50 m L = 17.60 m
Alpha = 5°
416.59 kN/m
−9.78 m
Soilcrete
−11.78 m
260
The Academia of Japan dictates that normally the thickness of this slab
must exceed half of the span between shaft walls. This is not the case out-
side of Japan, where sealing slabs have incorporated tie-down anchors, or
were placed well below the excavation depth, to counter the buoyant forces.
Thinner slabs are possible by employing circular arc beams on which only
compressive stress acts, as illustrated in Figure 6.26. This method of design
results in an arch prop 3 m in thickness even at a position of 40 m below
ground level.
A tentative calculation gives a maximum value of 1.1 MN/m 2 and a mini-
mal value of 0.95 MN/m 2 as compressive stress on both sides of the arch. As
the average unconined compressive strength of treated soils by jet grouting
commonly exceeds 3 MN/m 2 , this gives a high assurance of success.
GL
WL GL
WL
40.0
–40.0
VA VA 1.5 1.5 3.0
NA NB
All dimensions in m
12.0
(a) (b)
Figure 6.26 Base sealing of a shaft. (a) Conceptual cross-section. (b) Layout of jet-
grouted arch.
∂σ r σ − σr
= θ (6.4)
∂r r
where Xr = radial stress, Xϕ = tangential stress, and r = variable radius.
236 Ground improvement
Displacement (mm)
Soil SPT
OUT IN
0 0 50 –20 0 70
Short strut
GL–3.0m
Actual
Calculation (with grouted props)
(with grouted
props) NS
Depth (m)
GL–9.1m
10
Grouted props (1 m thick)
RN
Calculation (with no grout prop)
SN
SS
NS
Soils description
20
NS –Clayey silt
SN –Silt Clay
RN –Clayey silt with gravel
SS –Fine sand
Next, since a failure takes place when the failure envelope becomes hori-
zontal and the internal friction angle becomes zero, Equation 6.5 is derived as:
σ θ − σ r = 2c (6.5)
where c = cohesion.
σθ σr
H
R
a Π
+φ/2
ϕ
φ
R γ
(
ln = t H − R
a 2c
) (6.6)
6.4.4.1 Encapsulation
Achieving encapsulation of contaminants at depths where conventional
excavation would be dificult, as for the example shown in Figure 6.29.
Additionally, the grouted body is usually more impermeable than with con-
ventionally grouted ground, leading to more security in contaminant control.
Trench
backfill
Brick
culvert
Historic
grout sealing
Location of
phenolic
contamination
Jet grout
columns
221 m MW–42
213 m
MW–341
205 m
Building
MW–321
River
MW–47
MW–52
Jet grout
MW–48 Barrier location
Figure 6.31 Dual axis jet grouting operation for the jet-grouted soilcrete barrier wall.
The double luid system of jet grouting was used, utilising a dual axis rig
(Figure 6.31). This enabled two columns to be constructed concurrently
from the horsepower of a single grout pump. Pairs of columns were con-
structed ‘fresh-in-fresh’, meaning that set was intentionally not required so
to ensure jetting energy connected with adjacent work to preclude leaving
windows in the wall. This raised the certainty of closure of the barrier and
left only drilling verticality as a potential problem for the continuous wall.
Slowed drilling penetration and high speed rotation ensured vertical drill-
ing after setup.
Treme pipe
Abandoned Current
sheet pile –20
Piles mud
line
–30
–40
New
Soilcrete dredge
line
–50
Figure 6.33 Typical port cross-section and solution for berth deepening.
242 Ground improvement
Downstream berm
Existing dam placed after jet grouting
Existing ground
0 m (ft)
Gravel with sand 3.9 m
(13 ft) 8.2 (27)
Sand 12.1 (40)
Volcanic ash
15.2 (50)
Diatomaceous silt
Dense silt and sand 18.2 (60)
19.8 (65)
Diatomaceous silt Soilcrete
26.2 (86)
Dense silt and sand
1500
(10.34)
AVG
AVG
1000
(6.89)
AVG AVG
500
(3.44)
Figure 6.36 Unconined compressive strength test results from Wickiup Dam. The
owner required a minimum speciic gravity, which kept the strength higher
than what the speciication called for.
244 Ground improvement
Overburden soil
(Loessial alluvial deposits)
T1D
Original planned tunnel location
LIMESTONE
BEDROCK
As-built tunnel location
Figure 6.37 Section view of tunnel alignment with soilcrete access shaft locations.
N
Legend
Ground water
level 5.5 m (18 ft) Minimum 5 cm
(2 in) shotcrete
Soilcrete and welded wire Embedded
Soilcrete
full column
Loessial & alluvial
deposits
Bottom of soilcrete
34.4 m (113 ft)
9.1 m (30 ft)
#8 × 6'-10''
rock bolts at
1.5 m (5 ft)
Limestone 9.7 m (32 ft) ID
c-c vertical
bedrock
spacing
Bottom of shaft
required geometry. The test columns were installed using early setting cement
so that veriication coring could be performed three days after installation.
During production, neat cement grout and in-situ soilcrete samples were
taken once daily and cast for UCS testing. Average compression test results
for both shafts were 6.13 MN/m2 for wet soilcrete samples at 28 days. Once
the columns achieved adequate strength, four continuous 85-mm-diameter
soilcrete core samples were taken from columns equidistant around the shaft
circumference. The irst core hole was taken at the interstice area of the test
columns. The three remaining core holes were taken from production col-
umns at their interstice areas. A total of 32 core samples from each shaft were
tested. Eight samples were tested at 28 days for each core-hole location. The
average UCS test result of the cores from each shaft was 5.86 MN/m2 at 28
days, offering good correlation with the wet samples. All core-hole locations
were illed with neat cement grout after this testing was performed.
Vertical ground movements of the surrounding area were monitored
before and after each production shift. No ground heave was detected.
Twelve vibrating wire strain gauges were installed into each full column at
both shafts immediately after grouting. The strain gauges were installed at
three elevations for a comprehensive reading (Figure 6.41).
150/1 0
130/.89 Measured hoop stress (psi/mpa, 55 ft/16m level)
10/3.0
110/.75 Excavation depth
20/6.0
positive hoop stress indicates compression;
90/.62
70/.48 30/9.1
Measured hoop stress psi/mpa
–50/.34 80/24.3
–70/.48 90/27.4
–90/.62
100/30.4
–110/.75
–130/.89 110/33.5
–150/1 120/36.5
7/19
7/29
8/5
8/13
8/21
8/29
9/11
9/19
9/27
10/7
10/15
10/23
10/31
11/8
11/19
11/27
12/4
12/12
12/19/2002
12/26/2002
1/5/2003
1/13/2003
1/21/2003
1/29/2003
6-Feb-03
14-Feb-03
24-Feb-03
2-Mar-03
Jet grouting
Date
Figure 6.41 Measured hoop stress provided from strain gauges.
247
248 Ground improvement
5.2 m
Soilcrete
Unconfined compressive
strength = 3.44 MN/m2
Granite
Figure 6.43 Cross-section of jet-grouted soilcrete cofferdam around and below the
existing conduit.
Figure 6.44 Soilcrete seal around and below the conduit with the bulkhead visible within
the conduit.
250 Ground improvement
Figure 6.45 Excavated Avery Hall façade underpinned with jet-grouted soilcrete
columns.
(a) (b)
28”
Jet grouted soilcrete 13”
underpinning column Working (exist) grade
(typ)
Tieback
Soilcrete
Bottom of excavation
Figure 6.46 (a) Partial plan view of jet-grouted soilcrete underpinning columns beneath
Avery Hall façade. (b) Section view.
Jet grouting 251
by bearing below the excavation of the new mat foundation, and provided
the necessary temporary excavation support along the façade.
The grouting extended to a minimum of 0.6 m above the bottom of the
foundation in order to bind the rubble foundation together. Work was
sequenced such that any movements would be minimised. Before produc-
tion work, a test programme consisting of the installation of two soilcrete
columns was performed to enable the grouting contractor to conirm or
adjust the jet grouting parameters to ensure column geometry.
2-7m future
embankment fill
Building Building
Gravel
7000
7854
Clay
Sand
13136
0.3m 0.3m
0.4m 0.4m
0.8m 0.8m
PZ-27 sheet pile
0.5m (repair wall) 0.5m
Canal side
Figure 6.50 Plan view of jet-grouted soilcrete locations for sheetpile seal.
Existing grade
north meadow
Wall (varies)
Sand fill
El. –0.7 m
MHW Concrete platform
Reinforced concrete pile cap Concrete beam Minimum limit of
El. –0.6 m continuous grout wall
MLW Varies
45.7 cm Timber sheeting
rip-rap
(typ)
–2.1 m Sand
Fill (typ)
Jet grouting
Figure 6.51 Proile of jet-grouted soilcrete wall at Battery Park City Authority.
255
256 Ground improvement
REFERENCES
Abramovich, G.N. (1963). The Theory of Turbulent Jets, Cambridge, MA: MIT
Press.
Boehm, D.W. (2004). The utilization of jet grouting and soil mixing methods to
repair and support bulkhead structures, Proceedings of the American Society
of Civil Engineers Ports 2004 Conference, May 23–26, 2004, Houston, Texas,
United States.
Building and Civil Engineering Standards Committee, Technical Committee.
European Standard DIN EN 12716 (2001). CEN/TC 288, Execution of special
geotechnical works – Jet grouting, 05.18.07.
Burke, G.K, Cacoilo, D.M., and Chadwick, K.R. (2003). SuperJet grouting new
technology for in situ soil improvement, TRB Transportation Research Record
1721, Paper No. 00-0665.
Jet grouting 257
Burke, G.K. (2004). Jet grouting system: advantages and disadvantages, Proceedings
of Sessions of the GeoSupport Conference: Innovation and Cooperation in the
Geo-Industry, Jan. 29–31, 2004, Orlando, Florida, United States; sponsored
by International Association of Foundation Drilling (ADSC) and the Geo-
Institute of the American Society of Civil Engineers.
Burke, G.K. (2007). Vertical and horizontal groundwater barriers using jet grout panels
and columns (GSP 168), Proceedings of Geo-Institute’s Geo-Denver 2007: New
Peaks in Geotechnics, February 18–21, 2007, Denver, Colorado, United States.
Burke, G.K. (2007). New methods for underpinning and earth retention, grouting
for ground improvement: Innovative concepts and applications (GSP 168),
Proceedings of Geo-Institute’s Geo-Denver 2007: New Peaks in Geotechnics,
February 18–21, 2007, Denver, Colorado, United States.
Burke, G.K. (2009). Quality control considerations for jet grouting, Geotechnical
News, December 2009, BiTech Publishers Ltd.
Burke, G.K. (2012). The state of the practice of jet grouting, Proceedings 4th
International Conference on Grouting and Deep Mixing, February 15–18,
2012, New Orleans, Louisiana, United States; sponsored by the Geo-Institute
of the American Society of Civil Engineers.
Carey, M.A., Fretwell, B.A., Mosley N.G., and Smith, J.W.N. (2002). Guidance on
the use of permeable reactive barriers for remediating contaminated groundwa-
ter, National Groundwater and Contaminated Land Centre Report NC/01/51,
Bristol, England: Environment Agency.
Camper, K.E. (2002). Safe passage: jet grouted columns on Rand & Bates tunnel,
Tunnel Business Magazine, December 2002.
Endo, W.K. (2009). The use of jet grouting techniques in permeable reactive barriers,
presented to Chemical Grouting Co., Ltd., Japan, July 29, 2009.
European Standard Amendment Draft 4093 to DIN EN 12716.
Franz, N.C. (1972). Fluid additives for improving high velocity jet cutting, Proceedings of
the 1st International Symposium on Jet Cutting Technology, British Hydromechanics
Research Association, April 5–7, 1972, Coventry, England, A7–93.
Fritsch, M. and Kirsch, F. (2002). Deterministic and probabilistic analysis of the soil
stability above jet grouting columns, 5th European Conference on Numerical
Methods in Geotechnical Engineering, NUMGE, Paris, Presses de LENPC.
Furth, A.J., Burke, G.K., and Deutsch, W.L. (1997). Use of jet grouting to cre-
ate a low permeability horizontal barrier below an incinerator ash landill,
Proceedings of the 1997 International Containment Technology Conference
and Exhibition, February 9–12, 1997, St. Petersburg, Florida, United States.
Hermans, J.J. (1953). Flow Properties of Disperse Systems, Amsterdam, The
Netherlands: North Holland Publishing Company.
Kirsch, F. and Sondermann, W. (2002). Zur GewÖlbestabilität über Soilcrete-
Korpern. 9. Darmstädter Geotechnik Kolloquium, Technische Universität
Darmstädt, March 14, 2002, Darmstadt, Germany.
Kirsch, K. (1997). Contractor’s view on the risks involved with deep excavations in water
bearing soils. Proceedings of the 14th International Conference on Soil Mechanics
and Foundation Engineering, September 6–12, 1997, Hamburg, Germany.
Lichtarowicz, A. (1995). Future of water jet technology basic research, Proceedings
of the 4th Paciic Rim International Conference on Water Jet Technology, April
20–22, 1995, Shimizu, Japan, pp. 13–26.
258 Ground improvement
Soilfracture grouting
Eduard Falk and Clemens Kummerer
CONTENTS
259
260 Ground improvement
7.1 INTRODUCTION
Figure 7.1 Supporting framework consisting of solid veins and lamellae for transferring
concentrated stresses.
262 Ground improvement
~18 m
+/– 0.0
Reinforced slab
Figure 7.3 Shrinkage processes caused by cyclic drying of the soil lead to differential
settlement occurring in stages.
Intensity of
treatment 1
45 m
Intensity of
treatment 2
10 m
26.4 m
Intensity of treatment 1 Intensity of treatment 2
Figure 7.4 The intensity of the stabilisation process by hydraulic fracturing to be adapted
to the existing loads.
technical conferences, but the basic project assumptions still are a subject
of discussion by experts. This is why the attached references contain publi-
cations that deal with the further development of mathematical models, in
particular involving numerical methods, current improvements in measur-
ing technology, and well-founded views on the interaction resulting from
forced deformation between the soil and the structure.
~30 m
+/– 0.0
–6.0
g’
epin
‘Cre
8m
Clayey silt
Soilfrac treatment
Weathered rock
Figure 7.5 Stopping creep movements after deformation in the retaining structures had
led to cracks in existing structures.
[m]
55
Historical buildings
50
45
40 Working
shaft Historical buildings
35
30
25 Soilfrac
20
15
10
5
0
–5
–10
0 10 20 30 40 50 60 70 80 [m]
Figure 7.6 Compensating for settlements above two station buildings for an underground
railway which was built in stages over a period of approximately two years.
266 Ground improvement
Rua Garrett
Rua capelo
Shaft 2
Station tunnel east Shaft 3
Rua lvens
Figure 7.7 Arrangement of shafts and drilling for the installation of grouting pipes for
settlement correction in densely built-up area of approximately 15,000 m2.
[mm]
20
–20
Settlement
–80
–100
–120
Date
Phase 1
Phase 2, 3
Phase 4, 5
Phase 6, 7, 8, 9
Figure 7.8 Illustration of the average compensation success, indicating the compensation
procedure in small stages during the individual excavation phases.
Soilfracture grouting 267
Surface
Fill 10 m
11.5
Sand
18 m
1.5
Sleeve pipes
5.0
Gravel
Tunnel 9.4 m
in diameter
Figure 7.9 Compensation grouting for the protection of a railway bridge with 9.4-m twin
tunnel excavation and differential settlement limits of 1/3,000.
900 30
TBM 1 TBM 2
158 m3 67 m3
Total grouted volume [m3]
700 10
600 0
20/06 04/07 18/07 01/08 15/08
2005 2005 2005 2005 2005
Figure 7.10 Grouted quantities for irst and second TBM drive. The mean advancement
rate was 18 m/day.
The criterion for effectively applying the method consists of being able
to control the movements in the soil as well as the interaction between
such movements and the structure concerned. The more or less com-
plex requirements demand close interdisciplinary cooperation between
geotechnology, structural analysis, structural process technology, and
268 Ground improvement
After it was recognised that the phenomenon from traditional grouting and
the equipment in the oil ields can be combined successfully to solve geo-
technical problems, the lifting method using cement grout was irst used in
Essen for the purpose of raising a coke furnace, as described by Bernatzik
(1951). Essential steps for improving the method and for widening its range
of application consisted of adapting the valve pipe technology (in approxi-
mately 1970) and in integrating electronic data processing, which allowed
for actively compensating settlement troughs.
In the meantime, the method has spread to many geographic locations.
It is known to have been used in Germany, Italy, Austria, The Netherlands,
Portugal, Spain, Belgium, United Kingdom, United States, Canada,
Australia, and Puerto Rico.
3m
3m
O
3m
L
Sleeves at
0.5 m spacing
Figure 7.11 Sleeve pipes can be arranged on several levels and can serve different
purposes. This igure shows a detail of a lifting mat used in compensation
grouting with two horizons: ‘O’ and ‘L’ for the purpose of stress distribution,
plus a central lifting layer ‘M’.
Silos
Cement Filler Bentonite
Pump container
High shear Agitator
mixing tanks Pumps Control unit
Water
Measured data
Grouting programme
Data aquistion +
Monitoring
site management
Zone of treatment
Measured data
Figure 7.12 Data on deformation measurements and parameter recording are used by
the site manager for determining actual grouting programmes.
7.3 EQUIPMENT
Grouting
Surface
Detail Detail
Figure 7.13 Sleeve pipes (TAMs) are installed in a stable (cased) borehole and sealed by
an annular grout. Individual valves can be pressurised by double packers.
3. From surface
1. Shaft 2. Basement
4. Excavation pit
Soilfrac treatment
Tunnel
5. Service tunnel
Figure 7.14 As far as the drilling geometry is concerned, a large number of options are
available for reaching distinct areas in the soil to be treated.
[%]
100%
= 1m3 w w w w w
80
Components:
c w - Water
c
60 c
% of weight
c c - Cement
c f - Filler
40 s - Sand
f f b - Bentonite
f
20
f
s
b b b b b
M1 M2 M3 M4 M5
Figure 7.16 Examples of suspension compositions that can be used in different soils and
operations.
[L/min] [bar]
Grout pressure
60
15
40
Pumping rate
10
Pressure
Pumping rate
(const.)
20
5
Pumped volume Σ 20-80 I
Figure 7.17 Typical injection graph showing a drop in pressure after the occurrence of
‘fracs’.
or variable pump rate. The pumps have to be suitable for a pressure range
of 0–100 bar and a pump rate of 1–20 litres per minute; any parameter set
within these ranges is expected to be kept constant even for suspensions
with a high solid content. In modern grout modules, it is a common practice
to combine 2–8 pumps of similar design. The essential pump parameters
are either graphically recorded immediately or stored electronically and, via
software programmes processed in databanks and printed out. In any case,
the type of data saved has to ensure that in each individual grouting opera-
tion the pressure and quantity ratios must be clearly associated with the
respective location of the grouting operation. This is the reason why modern
grouting data recording and visualisation programmes are coupled; they
permit an early interpretation of data (Figures 7.17, 7.18, and 7.19).
Vr
lFrac
Q = x l/min
b Fr
V=t.Q
ac
daverage
Mm
Figure 7.18 A frac usually has a lat, oblong shape and starts from an initial crack in the
sleeve grout. However, frequently there occur secondary fracs whose geo-
metric description can be given in statistical form only.
a wire mesh and have a rubber surface, and are inlated either with com-
pressed air or water.
The pressure applied has to be clearly higher than the maximum
grouting pressure expected. After completion of the grouting opera-
tion, the grouting pipes are cleaned by high-pressure hoses integrated
into the packer system or by separate cleaning systems. The quality of
the individual components and their careful use are the key to an effi-
cient process application and their successful use over longer periods
of time.
Figure 7.19 Coloured frac sample deriving from grouting in cohesive soils.
276 Ground improvement
Injecting solid material into the soil leads to deformation on all sides. The
directions in which individual injections spread largely depend on the
homogeneity conditions in the soil. From a statistical point of view, it has
to be assumed that the greatest part of the volume introduced into the soil
Soilfracture grouting 277
Fracture grouting
Figure 7.21 The model of the ‘conining’ ring comprises the sum of all forces that allow
for a central lifting injection.
278 Ground improvement
Pre-treatment 100% 0%
V Heave
σoverburden + external load σoverburden + external load
Displacement
σ1 σ1 σ1 σ1
σ2,3 ≤ σ1 σ2,3 ≤ σ1 σ2,3 ≥ σ1 σ2,3 ≥ σ1
Resistance
Figure 7.22 Heterogeneities in the soil and the stress distribution inluence the defor-
mation direction, which is the result of an imposed addition of material and
all-round resistance.
A
Reference level
σA B
σB
bA
αlimit bB
αA αB tinj
dA dB
hinj
rinj
Figure 7.23 Recommendations for geometrical relations and load intensities to permit
controlled levelling: αlimit = 10–25°; dA /dB ≤ 1.5 with αA + αB ≤ 20°; bA /dA ≥ 1
resp. bB/dB ≤ 2; σA /σB ≤ 3 with αA + αB ≥ 20°. Situations exceeding these
indications need additional veriication or practical trial.
280 Ground improvement
Foundation
Grouting zone
Pipes A-B-C-D
Tunnel
Figure 7.24 Plane strain Finite Element model for the back analysis of the construction
stages for the tunnelling at Antwerp Central station.
282 Ground improvement
4
Vertical displacement [mm]
1 Measurement P470
Calculation P470
0
g
B*
*
D
C*
C
t
v
in
ca
pe
ro
pe
pe
p
nn
pe
p
ex
p
m
m
tg
Pi
Pi
m
Pi
m
gi
Pi
Co
Co
el
Co
ac
Co
Be
nn
nt
Tu
Co
Figure 7.25 Comparison between ield measurements and FEM back analysis for the
compensation grouting work of the Antwerp Central station.
7.4.4 Monitoring
The concept for comprehensive deformation measurements always
includes the two completely different sets of problems of the structure
on the one hand and of the soil underneath on the other hand. As far as
structures are concerned, monitoring the level of supporting components
is of primary importance. In addition, loors and existing cracks can
be provided with instruments whose values are read automatically or
visually. Measuring instruments such as inclinometers, extensometers,
incremental extensometers, settlement piezometers, and similar devices
can be arranged in the ground with the objective of determining spatial
deformations and their directions in the direct vicinity of the area treated
(Figures 7.26 and 7.27).
Moreover, the pretreatment phase, where the voids are illed in order to
condition the soil, and preheaving have to be taken into account.
Soilfracture grouting 283
20 m
15
10
5
-1.1
1.0
1.4
1.7
0.1
1.4
0.0
0
1.5
0.00
1.5
1.00
0
1.00
-2.00
00
-3.2
-1.0
230
0.3
0.8
1.1
1.
-0.6
2.00
1.00
0
0
2.0
1.0
0.4
0.00
0
1.1
-1.0
0
0
3.0
-2.0
0
2.0 4.00
1.2
0.0
1.00
0.00
0
-0.7
2.8
4.8
2.0
0
0
1.2
5.0
-3.0
4.4
3
5.1
1.6
0
2.7
1.7
4.0
0
4.4
1.0
4.00
-1.00
2.00
-2.00
3.00
5.00
-3.00 -3.4
-2.4
-0.5
1.00
0
2.0
0
5.0
1.9
0.1
0
0.9
3.0
4.00
0.00
4.0
0
1.0
-0.4
3.00
2.0
1.5
0
1.6 2.0
-1.00
-2.00
4.3 4.4
3.4 3.7
1.7
4.3
0.1
0.0
0
3.003.7
-0.1
1.0
2.00
1.0
0.0-0.7
0
2.00
0
3.0
1.1
2.5
-3.0
-0.4
2.5
2.4
2.1
3.4
2.0
-0.9
1.5
1.1
3.6 3.1
2.9
1.00
0
-2.0
2.00
3.00
0
2.3
0.5
2.6
2.2
1.0
1.7
-
9.9
1.9
-.9
465
Figure 7.26 Example illustrating the deformation of a historic railway station which was
continuously monitored by means of a complex measuring system.
Grouting area
Surface
s
∆s
Volume to be compensated
Settlement curve
Figure 7.27 Actual settlements and the allowable deformation state basically determine
the volume to be considered during the compensation phase.
Hydraulic fracturing can be used for different objectives and types of settle-
ment reduction operations. The spectrum ranges from pure prevention or
repair works after settlement damages have already taken place to simulta-
neous compensation of excavation induced settlements for inner-city areas.
A number of examples illustrate the opportunities for this method and
should provide creative ideas for the planning engineer.
Small
Surface strip foundations
Soft silt
Stiff silt
Zone of improvement
Figure 7.28 Increasing the load-bearing capacity in the areas where additional loads have
to be carried due to addition of two storeys.
Historical building
10 m
Wall displacement
Settlement prediction
15 m
Excavation
level
Zone of improvement
Sand
Sealing slab
Figure 7.29 Passive settlement reduction by carrying out speciic soil improvement in
the area subject to deformation.
was considered to improve the block of soil behind the diaphragm wall
by means of soil fracturing which, if needed, would also allow for volume
losses to be compensated during the excavation phase (Figure 7.29).
Surface
10 m
1:85 Fill/gravel
Peat
Lfting zone
Moraine
Zone of stabilization
Park garage
0 Shaft
Silt
Grouting pipes
Marl
Tunnel
10 m
Figure 7.31 Settlement compensation for a car park with very small cover.
Surface
Shaft
3.8mm
13.7mm
Figure 7.32 Cross section of the City Tunnel Leipzig project with settlement curve
showing the difference between nontreated and grouted zone.
was speciied. More than 30,000 m of drilling and 1,100 liquid levelling
points were installed. The settlement reduction can clearly been seen in
Figure 7.32. In the areas outside the soilfrac treatment, a settlement of 13.7
mm occurred wheareas in the treated areas only 3.8 mm were registered.
A recent case of compensation grouting for a TBM excavation was made
for a Metro Line in Rome. Fracture grouting substituted the initially con-
sidered jet grouting operation, as less impact in terms of occupied public
space and discharge of spoil was given and in addition an active control
of the building protection was possible. Two EPB-tunnel-boring machines
passed underneath masonry and concrete buildings with a mimimum cover
of less than 3 m. More than 6,000 m of directional drillings were made,
settlements introduced due to drilling were about 1.5 mm although the
distance to the foundation was only 1 m in certain cases. The measured
settlements were less than 5 mm, signiicantly below the limit of 10 mm,
see Figures 7.33 and 7.34.
Monitoring
Artificial magnetic field
ca. 5.5 m
8.0 m
1.5 m
TAM array
Tunnel
Figure 7.33 Cross section of the Metro Rome settlement protection by means of
soilfracturing.
Monitoring
Fill
Tunnel Gravel
25m
Figure 7.34 Transversal cross section of the Metro B1 in Rome with Soilfrac area.
292 Ground improvement
dimension of the treated soil body must permit the delection of the stress
occurring can be the simple guide principle.
If there is doubt, large-scale tests have always been useful. These can be
integrated into subsequent main works and thus do not incur substantial
additional costs.
A
Plan view
HI
HI
Figure 7.35 Layout of a large-scale ield test which was planned as part of the subsequent
settlement compensation measure.
O 0.5 mm
970 kN 350 kN
350 kN
4 mm
4 mm
HI + 10.5 bar Shaft 1
3.2 mm + 0.2 bar 3.5 mm
+ 0.2 bar
HI
max. + 0.1 bar
+ 0.1 bar Vertical inclinometer
4 mm
Extensometer
Tunnel Electronic water level
Horizontal inclinometer
Earth pressure cell
Figure 7.36 Test results which show the suitablility of the measure for specifically
lifting individual foundations and the negligible influence on the tunnel
shell, respectively.
ca. 50 kPa
20 mm 30 mm 23 mm
Fill
Piles
600 mm diameter
–23.0 m
Gravel
Sleeve pipes
Figure 7.37 Cross section of the ield trial performed to prove that piled foundations
can be lifted with soil fracturing in a controlled manner.
Soilfracture grouting 295
Diaphragm wall
Piles
600 mm diameter
A A
Figure 7.38 Plan view of the ield trial performed with the monitoring system.
of the soil and of the respective condition of the structure on which atten-
tion is focused. When agreements are drafted in connection with complex
structural methods, it is important to clarify at an early stage ownership
conditions and the interests of those who may be affected. The chemical
environmental compatibility of the individual injection components has to
be proved. In cases of doubt, additional tests of the actually used combina-
tion of materials and products have to be carried out.
Agreements regarding the realisation of projects involving hydraulic frac-
turing are concluded on the basis of mutually agreed projects. As some of
the effects of the measures applied can often not be speciied at that par-
ticular point in time, the agreement must permit the consistent use of the
observation method. The type of reaction to possible scenarios in the indi-
vidual construction phases has to be planned and contractually permitted,
of course with the intention of safeguarding the rights of third persons and
the economic execution of the project in the interest of solving an existing
problem. While taking into account the measures associated with strategies
against undesirable effects, it should be noted that a performance schedule
can list additional measures for limiting or warding-off injection effects.
Equally, the acceptance of crack formations and arching taking place in
the foot path region while a building is being lifted can be included in the
working agreement as part of the overriding project objective.
REFERENCES
Compaction grouting
James Hussin
CONTENTS
299
300 Ground improvement
8.1 INTRODUCTION
‘low mobility grout’ (LMG) was proposed in the late 1990s (Byle, 1997) to
describe the grout and the broad process of using LMG. Compaction grout-
ing would be a subcategory of LMG.
In 2010, the Grouting Committee of the Geo-Institute of the American
Society of Civil Engineers (G-I ASCE) published the ‘Compaction Grouting
Consensus Guide’ (ASCE/G-I 53-10). In this guide, compaction grouting is
deined as follows:
Figure 8.1 Compaction grouting to densify soil beneath existing foundation. (Courtesy
of Hayward Baker Inc.)
302 Ground improvement
used to compact soils and for other applications. The term ‘low mobility
grout (LMG)’ shall be used for the grout.
8.2 HISTORY
Protected
building
Settlement foundations
without
grouting
Compaction
grout bulb
Compaction grout bulb
Tunnel
Tunnel
Mid-1980s Prior to this time, slurry grout (Portland cement and water)
was used to stabilise sinkhole conditions in karst regions.
However, since the grout was very luid and the limestone
contained many cracks and crevasses, the required grout
quantity was very dificult to predict, resulting in frequent
large cost overruns. A specialty contractor in Florida
(Henry, 1986) realised that LMG offered the beneit of
illing the larger voids and compacting loosened soil while
at the same time, its stiff nature would limit grout takes in
the thin cracks of the limestone formation (Figure 8.4). The
process was very successful and essentially replaced slurry
grouting to stabilise sinkholes, compact resulting loos-
ened sands, and relevel overlying settled structures. Soon
after, the technique saw its irst use to treat sites in sink-
hole prone areas prior to construction to reduce the poten-
tial for future sinkholes. This application has since been
adopted in karst geology regions throughout the United
States. By the late 1980s the technique began to be applied
in Europe, notably the UK, mainly for ground improve-
ment and foundation remedial works (see Crockford and
Bell, 1996).
Circa 1990 Compaction grouting was exported to Japan where it
began to gain acceptance to raise structures and was later
used to relevel structures that settled as a result of the
Kobe earthquake (1995).
Figure 8.3 Compaction grouting combined with vibro-replacement and dynamic com-
paction beneath planned structures at Georgia submarine base. (Courtesy of
Hayward Baker Inc.)
304 Ground improvement
Figure 8.4 LMG to stabilise large sinkhole at a central Florida mining facility. (Courtesy
of Hayward Baker Inc.)
The news of the applications and successes spread and LMG is now used in
many parts of the world. The term ‘compaction grouting’ is still used outside
the United States to mean the whole process used in the full range of applica-
tions including ground densiication, relevelling, or compensation using LMG.
8.3 APPLICATIONS
Compaction grouting
Figure 8.5 Low mobility grout applications. (Courtesy of Hayward Baker Inc.)
305
306 Ground improvement
LMG has been applied in almost all soil types. The process can be con-
trolled to construct a column of mortar grout which acts as a reinforcing
element in the soil. The ability of the process to compact the surrounding
soils (compaction grouting) is inluenced by the soil’s properties.
The process of compacting soil constricts the void spaces, requiring any
water within the void to exit. Therefore, compaction grouting is most effec-
tive in soils which have a high permeability and/or low degree of satura-
tion. Loose, highly permeable granular soils are best suited for compaction
grouting. As the ines content increases (particularly clay content), the soil
permeability decreases along with the effectiveness of compaction grout-
ing. Sands with less than 10% silt and no clay compact well above and
below the water table. Some limited compaction has been accomplished in
nonsaturated, nonplastic, ine-grained soils with a very slow grout injec-
tion rate and a carefully designed grout mix (detailed later in this chapter).
Collapsible soils have also been successfully treated with compaction grout-
ing. Soils best suited for compaction grouting are presented in Figure 8.6.
LMG is particularly effective as a load transfer element in noncom-
pactable soil layers where the layer thickness is only several feet thick. In
this situation, a compaction grout column with a minimum diameter equal
to half of the layer thickness can effectively support the load that would
otherwise induce stress in the layer. As previously stated, LMG has been
effectively used to ill subsurface voids and to build columns in abandoned
mines to provide roof support (Figure 8.7).
Reinforcable
Unsaturated with drainage
Percent passing
50
30
Saturated
10
0
10 5 2 1.0 0.5 0.2 0.1 0.05 0.02 0.01 0.005
Particle size - mm
Figure 8.6 Range of soil gradation curves best suited for compaction grouting. (Courtesy
of Hayward Baker Inc.)
Figure 8.7 LMG used to ill a mine tunnel. (Courtesy of Hayward Baker Inc.)
provide the ines necessary to make the grout pumpable and is required when
the design requires the grout to carry load or span a void as in the case of cap
grouting in karst applications. Other materials used as ines in LMG mixes
include lyash and silt (when natural silty ine sand is used in the mix).
8.6.2 Constraints
The above- and below-ground constraints must be understood prior to
designing the grouting programme. Some areas of the site may not be acces-
sible or may require limited access equipment or hand-held equipment.
Both above- and below-ground utility locations must be carefully identi-
ied. Subsurface structures or adjacent retaining walls must be identiied to
avoid damage during the high-pressure injection of the grout.
Compaction grouting 309
8.6.3 Requirements
The requirements of the programme are important to understand before
the LMG programme can be designed. The requirements could involve
densiication of the soils, reinforcement with grout columns, relevelling of
foundations or compensation for loss ground due to tunnelling.
If densiication is the target, the minimum required post-treatment
density must be determined. Relevelling of an existing structure could be
necessary. In the scenario of compaction grouting above soft ground tun-
nelling to avoid excessive settlement of overlying structures, the maximum
allowable settlement must be deined.
8.6.4 Criteria
The criteria that deine success or failure must be deined and understood
by all involved parties. Common acceptance criteria include injected grout
volume, injected grout pressure, inal elevation of lifted structures and test
results (SPT, CPT, etc.) of soil between injection locations. Often, the same
test is performed both before and after grouting to allow an accurate deter-
mination of the improvement (see Figure 8.8).
308
304
Post-grout N values
Elevation (ft) [1 ft = 0.3 m]
302
300
298
296
294
292
290
0 10 20 30 40 50 60
N value
(blows/ft = blows/0.3 m)
Figure 8.8 Sample SPT results before and after compaction grouting. (Courtesy of
Hayward Baker Inc.)
310 Ground improvement
8.6.5 Layout
The design of the grout injection pipe layout is based on the subsurface condi-
tions, site constraints, programme requirements, and the criteria to be achieved.
8.6.5.1 Spacing
The spacing of the pipes in plan depends primarily on the soil type and
the criteria to be achieved. Spacing generally varies between 3–15 feet
(0.9–4.6 m) on centre. These are extreme examples. The spacing is on the
lower end of the range for shallow treatment (low overburden or overly-
ing structural load) and in ine-grained soils. Spacing is on the higher end
of the range for deeper treatment (greater overburden or heavier overly-
ing structural load), in granular soils, or when limited improvement is
required. Most compaction grouting is performed at a spacing of 5–7 feet
(1.5–2.1 m) (see Figure 8.9).
S S S S S
P P P P P P
S S S S S
P P P P P P
Figure 8.9 Sample compaction grouting layout plan. (Courtesy of Hayward Baker Inc.)
Compaction grouting 311
by the skipped locations (secondary locations), see Figure 8.9. The primary
injections provide coninement of the soils during the secondary grouting.
The vertical sequence at a speciic injection location can also be varied.
LMG may begin at the bottom of the treatment zone and proceed upward
(upstage) or at the top of the treatment zone and proceed downward (down-
stage). The upstage process involves installation of the grout pipe to the
bottom of the treatment zone and then slowly extracting the pipe as the
LMG is injected. The upstage process is generally easier, quicker, and less
costly. The downstage process involves installation of the grout pipe to the
top of the treatment zone, injecting the LMG at that depth, waiting for the
grout to set, drilling through the grout, and then pumping grout beneath
the previously injected grout. The process is repeated until grout has been
injected into the full treatment depth. This process is more effective when
lifting structures from a shallow depth and shallow weak soils.
8.6.6 Procedures
8.6.6.1 Injection pressure
Injection of LMG requires relatively high pressures, possibly in excess of
1,000 psi (6.99 MPa). It may require 100–200 psi (0.7–1.4 MPa) just to
pump the stiff LMG through the grout hose and injection pipe before the
pipe is inserted into the ground. Once the pipe is inserted into the ground,
the additional pressure required to displace and compact the surrounding
soils increases with depth and with soil density. The pump injection pres-
sure will typically increase as the injection continues at a particular loca-
tion due to the increase in density of the surrounding soils.
8.6.6.4 Heave
Heave typically occurs when the resistance to grout displacement is less
above the grout than it is laterally. It can also be an indication that fractur-
ing has occurred. Heave is a limiting factor in that when it occurs, little
additional compaction is occurring in the surrounding soils. Heave can
also damage overlying structures. However, if the objective is to restore
the levels of an overlying structure which has previously experienced settle-
ment, some heave may be desirable to relevel the structure.
Heave can occur when grouting at shallow depths. It is dificult to den-
sify soils at depths shallower than 10 feet (3 m) because the limited over-
burden pressure is less than the lateral pressure of the soils. Heave can also
occur during deeper grouting when the surrounding soils have been com-
pacted such that they resist further displacement. Once heave is detected,
grouting is generally discontinued at that depth. Compaction of overlying
loose zones can still be achieved.
The heave criteria should be established before the grouting programme
begins. It is important to realise that heave is often cumulative. Therefore,
the maximum heave criteria at any particular depth should be less than the
maximum allowable for the overlying structure to allow continued grout-
ing in soils above the depth where the heave criterion is irst observed. For
example, if 0.5 inch (12.7 mm) is the maximum total allowable heave, a rea-
sonable refusal criterion for any particular depth might be 0.1 inch (2.5 mm).
During grout injection the grout pressure and volume should be moni-
tored and recorded versus depth. The pressures in the hose should be moni-
tored and recorded both near the pump and near the top of the injection
pipe (requiring pressure gauges at these locations). The pressure at the
top of the pipe is a close indication of the injection pressure into the soil.
A comparison of the two gauges reveals if high pressures or grout refusal is
a result of grout plugs within the line.
The three parameters that often are speciied as controlling when a grout-
ing stage is complete are grout injection pressure, grout volume, and ground
heave. The reasoning behind specifying a maximum pressure is that when
achieved, the soils surrounding that injection stage have been suficiently com-
pacted. A maximum volume is speciied when the design requires a grout
column of a deined diameter to carry a load or possibly at primary locations
to provide coninement of the soils during the subsequent secondary location
grouting. A maximum heave is speciied to avoid excessive grouting without
additional compaction and to avoid damage to overlying structures. Grouting
is often continued at a stage until one or the other of these is irst observed.
8.8 EQUIPMENT
Figure 8.10 Concrete truck delivers LMG to grout site. (Courtesy of Hayward Baker
Inc.)
Figure 8.11 Examples of on-site LMG batch plants. (Courtesy of Hayward Baker Inc.)
a belt which travels beneath the material storage bins. The materials are then
mixed with water in a continuous screw auger which then feeds the grout into
the pump. These batch plants can produce as much as 50 cubic yards of grout
(38 cubic metres) per hour. Sample batch plants are depicted in Figure 8.11.
8.8.2 Pumps
LMG is typically pumped with modiied concrete pumps. These are piston
pumps which pump a deined volume per stroke (the volume of the piston).
The typical concrete pump generally requires modiication of the piston
diameter and control mechanisms to be capable of pumping at the high pres-
sures (1,000 psi or 6.9 MPa or greater) and slow rates of less than 2 cubic
feet (57 litres) per minute required to perform compaction grouting.
Figure 8.12 Hand equipment to install LMG injection pipe. (Courtesy of Hayward Baker
Inc.)
8.8.4 Miscellaneous
Several miscellaneous items are also important to consider.
Compaction grouting 317
Figure 8.13 Small-wheeled and large-tracked drills to install LMG injection pipe.
(Courtesy of Hayward Baker Inc.)
8.8.4.2 Hoses
High-pressure hoses or steel pipes with lush joints and a minimum diam-
eter of 2 inches (51 mm) are required to avoid excessive resistance to pump-
ing the grout through the lines. The ittings (couplings) between sections
of hose or pipe should be tight to avoid water leaks which could lead to
blockages in the lines.
8.9 QC & QA
A properly speciied quality control (QC) and quality assurance (QA) pro-
gramme is essential to the successful performance of a LMG programme.
318 Ground improvement
Figure 8.14 Hydraulic ram to extract LMG injection pipe. (Courtesy of Hayward Baker
Inc.)
Figure 8.15 Pressure gauge and gauge saver near top of grout injection pipe. (Courtesy
of Hayward Baker Inc.)
Compaction grouting 319
Figure 8.16 Casting test cylinders and measuring LMG slump. (Courtesy of Hayward
Baker Inc.)
320 Ground improvement
8.9.8 Heave
During grout injection, the grout will displace the ground in the direction of
least resistance. In loose soils and when injecting at depth, the overburden
weight provides more resistance than the lateral passive resistance, result-
ing in the grout displacing the soil horizontally. As the soils become denser
and when injecting at depths shallower than about 10 feet (3 m), the path
of least resistance may be towards the ground surface. This may result in
heave of the ground surface and overlying structures. Little additional soil
compaction is occurring during heave. Many different instruments are used
to monitor when heave occurs and the magnitude of the heave. Examples
include crack monitors, tilt meters, plumb bobs, and spirit levels.
Figure 8.17 Compaction grout DAQ system with grout line under table where grout
pressure and volume is measured. (Courtesy of Hayward Baker Inc.)
Figure 8.18 Large track-mounted drill rigs with telescopic masts installed the injection
pipes in a single stroke to the maximum required treatment depth of 50 feet
(15.2 meters). (Courtesy of Hayward Baker Inc.)
10 10 10
20 20 20
30 30 30
40 40 40
50 50 50
60 60 60
70 70 70
Max. grout pressure Grout volume(ft3) Grout rate (ft3/min.)
(psi) (1 ft3 = 0.03 m3)
(1 psi = 6.89 kPa)
Figure 8.19 Real-time plots of grouting data and three-dimensional visualization graphic. (Courtesy of Hayward Baker Inc.)
qt [tsf] Rf [%] CSR and CRR Factor of safety Settlement [in]
0 200 0 2 0 2 0 2 0 2
0 0 0 0 0
10 10 10 10 10
20 20 20 20 20
Depth [ft]
Depth [ft]
Depth [ft]
Depth [ft]
Depth [ft]
30 30 30 30 30
40 40 40 40 40
Compaction grouting
50 50 50 50 50
CPT-4 CPT-4
CRR
CSR
60 60 60 60 60
Bottom of footing elevation = 7.5'' Work area 3-CPT 493N 1 tsf = 95.76 kPa Post-treatment seis. settlement = 0.0''
Approx. footing depth = 10' Harlem hospital, NY 1 ft = 0.3 m Pre-treatment seis. settlement = 3.2''
(16.5' × 16.5' footing) 10/13/08 1 in = 2.54 cm
325
Figure 8.20 Sample of pre- and post-treatment CPT and analysis results. (Courtesy of Hayward Baker Inc.)
326 Ground improvement
Figure 8.21 Small-tracked drill installing the injection pipes (left) and truck mounted
batch plant producing LMG (right). (Courtesy of Hayward Baker Inc.)
between holes. Five rows of holes were drilled along the pile lines. Figure
8.22 shows the grout layout and testing pattern for one of the bridge
abutments.
Once the casings were installed, compaction grout was injected in up-
stage fashion to densify the soil. Compaction grouting was conducted until
one of four criteria were met: (1) a given overpressure was achieved; (2) a
given quantity of grout was injected into the zone; (3) grout exited the
ground surface; and (4) ground or structural heave was observed. Once
refusal occurred, the casing was pulled up 2 feet (0.6 metres) and compac-
tion grouting continued. This process continued until the entire hole was
grouted.
SPT and CPT testing were conducted to verify that the soil had been suf-
iciently densiied following compaction grouting (Figure 8.23). The loca-
tion of the SPT or CPT test was determined by the owner, and was usually
midway between injection points. The acceptance criteria for the project
were to achieve minimum SPT blow count N160 of 36 or a CPT tip resis-
tance > 19 MPa.
A total of 766 holes were drilled, for a total length of 35,200 feet (10,732
metres). Grout consumption for the project was 53,208 cubic feet (1,507
cubic metres), or an average of 1.5 cubic feet (42 litres) per foot (0.3 metres)
of hole.
‘A’ line
Compaction grouting
Critical phase 1 Critical Critical phase 1
phase 2
0.50 m
A’
Notes:
1. Primary grout hole location, inclined primary grout hole.
2. Secondary grout hole location, inclined secondary grout hole.
3. Pre-CPT location
4. Post-CPT location
Figure 8.22 Grout injection and testing layout pattern. (Courtesy of Hayward Baker Inc.)
327
328 Ground improvement
Figure 8.23 Compaction grouting densiies soils loosened during tunneling operations.
(Courtesy of Hayward Baker Inc.)
REFERENCES
CONTENTS
329
330 Ground improvement
9.1 INTRODUCTION
The use of soil mixing (SM) to improve the engineering and environ-
mental properties of soft or contaminated ground has increased widely
since its genesis. Growing interest for SM mainly results from the high
lexibility of this method, which can be purposely adapted to speciic
project requirements and site conditions, as well as from cost-to-per-
formance eficiency of respective geotechnical solutions. In this method
of ground improvement, soils are mixed in situ with different stabilis-
ing binders, which chemically react with the soil and/or the groundwa-
ter. The stabilised soil material that is produced generally has a higher
strength, lower permeability, and lower compressibility than the native
soil. The improvement becomes possible by cation exchange at the sur-
face of clay minerals, bonding of soil particles, and/or illing of voids
by chemical reaction products. The most important binders are cements
and limes. However, blast-furnace slag, gypsum, and ashes as well as
other secondary products and compound materials are also used. For
environmental treatment, binders are replaced with chemical oxidation
agents or other reactive materials to render pollutants harmless.
In-situ soil mixing 331
Soil mixing can be subdivided into two general methods: the deep mix-
ing method (DMM) and the shallow mixing method (SMM). Both DMM
and SMM include a variety of proprietary systems.
The more frequently used DMM is applied for in-situ stabilisation of the
soil to a minimum depth of 3 m (a limit depth introduced by EN 14679:2005).
The binders are injected into the soil in dry or slurry form through hollow
mixing shafts tipped with various cutting tools and equipped with auger
lights, mixing blades, or paddles to increase the eficiency of the mixing
process. The shafts, mounted in single or multiple arrangements, rotate
about the vertical axis and produce individual or overlapping soil-mix
columns. In the case of special cutting/mixing arms equipped with cut-
ter wheels mounted on horizontal axes to create panels or with a revolv-
ing cutting chain to create continuous walls, the slurry is pumped through
injection pipes and outlets mounted along the arm. In some methods, the
mechanical mixing is enhanced by simultaneously injecting luid grout at
high velocity through nozzles in the mixing or cutting tools.
The complementary SMM has been specially developed to reduce the
costs of improving loose or soft supericial soils overlying substantial areas,
including land disposed dredged sediments and wet organic soils a few
metres thick. It is also a suitable method for in-situ remediation of contami-
nated soils and sludges. In such applications, the soils have to be thoroughly
mixed in-situ with an appropriate amount of wet or dry binders to ensure
stabilisation of the entire volume of treated soil. Therefore, this type of soil
mixing is often referred to as ‘mass stabilisation’. Mass stabilisation can
be achieved by installing vertical overlapping columns with up and down
movements of rotating mixing tools, as in the case of standard DMM, and
is most cost-effective when using large-diameter mixing augers or multiple
shaft arrangements. For shallow depth applications, however, generally
limited to about 5 m, another very eficient method of mass stabilisation is
usually implemented, and the mixing process is carried out repeatedly in
vertical and horizontal directions through the soil mass using various cut-
ting and mixing tools that are different from the tools developed for DMM
(e.g., mixing drums). Consequently, in the classiication scheme used in this
chapter the SMM includes both systems of mass stabilisation.
In-situ soil mixing is a versatile ground improvement method. It can be
used to stabilise a wide range of soils, including soft clays, silts and ine-
grained sands. Stabilisation of organic soils such as gyttja (sedimentary
organic soil), peat, and sludges is also possible, but is more dificult and
requires carefully tailored binders and execution procedures. However, the
engineering properties of the stabilised soil will not only depend on the
characteristics of the binder. They will also depend, to a large extent, on
the inherent characteristics of each soil and the way it has been depos-
ited, as well as on mixing and curing conditions at a particular worksite.
Therefore, a thorough understanding of chemical reactions with these
332 Ground improvement
The roots of deep soil mixing go back to the mid-1950s, when the
mixed-in-place (MIP) piling technique was developed by Intrusion-Prepakt
Inc. (FHWA, 2000). In this method a mechanical mixer was used to mix
cementitious grout into the soil for the purpose of creating foundation ele-
ments and retaining walls. The grout was injected from the tip of a mixing
tool consisting of a drilling head and separated horizontal blades. Modern
deep mixing techniques relect, however, mainly Japanese and Scandinavian
efforts over the last ive decades as well as recent European achievements in
cutter wheel and trench-type mixing systems.
The level of research and development activity in Japan in relation to
DMM remains the highest in the world. The irst commercial application
of the deep lime mixing (DLM) method, utilising a mechanical binder
feeding system, was conducted in 1974 by Fudo Construction Co. Ltd.
using the Mark IV machine to improve reclaimed soft alluvial clay in
Chiba Prefecture in Japan. The irst marine use of DLM was in 1975 at
Tokyo Port (Terashi, 2002a). In an effort to improve the uniformity of
the stabilised soil, a new concept using cement mortar and cement-water
slurry as binders was implemented in the mid-1970s, with CMC and DCM
(deep cement mixing) methods developed by Kawasaki Steel & Fudo and
Takenaka Group, respectively, with close supervision from Port Harbour
Research Institute. The irst on-land and marine applications of CMC and
DCM were conducted in 1976. Also that year, the Seiko Kogyo Co. devel-
oped and introduced the soil-mixed wall (SMW) method using discontinu-
ous augers and paddles positioned at discrete intervals, usually along three
shafts arranged in a row. This method was applied primarily for excavation
support and groundwater cut-off walls, with the possibility for installation
of reinforcing steel sections within fresh columns to increase bending stiff-
ness of the supporting DM elements.
Major marine ground improvement works at Daikoku Pier, beginning in
1977 and continuing for about 10 years, contributed to important develop-
ments of the wet method of deep mixing (e.g., DCM, DECOM, POCOM,
and others). These developments included the elaboration of design stan-
dards and construction control procedures, slowly hardening binders and
new positioning systems for offshore applications (Terashi, 2002a).
A general method using a variety of stabilising binders in slurry form
(wet method) has been named cement deep mixing (CDM) method. In
1977, the CDM Association was established in Japan to promote and
improve the CDM method via a collaboration of general contractors,
marine works, and foundation works contractors, as well as industrial
and research institutes. As a result, new eficient machines were developed,
such as CDM-Mega, CDM-LODIC, CDM-Land4, and CDM-Column
21. For marine applications the CDM method has mainly been used to
improve the foundations of revetments, as well as quay wall and breakwa-
ter foundations. The diameter of the mixing blades ranges from 1.0–1.6 m
334 Ground improvement
∅1000
830 mm
Figure 9.1 (a) CDM barges for marine deep mixing works using the wet method, Japan.
(Courtesy of CDM Association, Japan.) (b) Possible arrangement of eight
mixing shafts.
In-situ soil mixing 335
Figure 9.2 CDM machine for on-land deep mixing works using the wet method, Japan
(note auger screws along the shafts enabling partial extrusion of disaggre-
gated soil).
(a) (b)
Figure 9.3 (a) Execution of a cut-off wall with the TRD method (Herbert Hoover Dike
rehabilitation project in Florida), (b) close-up of the cutting/mixing chain.
(Courtesy of Hayward Baker, Inc.)
336 Ground improvement
(a) (b)
Figure 9.4 (a) DJM machine for on-land deep mixing works using the dry method, Japan.
(b) Two mixing tools, diameter 1.0 m.
In-situ soil mixing 337
(a) (b)
Figure 9.5 Dry method deep mixing near Elbla˛g (Poland) using the Nordic method.
(a) Keller/LCM equipment. (b) Dry mixing in winter.
of wet DMM in Poland is probably the highest in Europe (except for envi-
ronmental applications), including the irst worldwide applications of DM
for the foundations of highway bridges (irst in 2002) and modern wind
turbines (irst in 2007).
In Belgium Smet-Boring NV has developed a modiied DM system, called
TSM (Tubular Soil Mixing). TSM uses a mixing auger inside an outer cas-
ing, diameter 43–63 cm, equipped with a set of nozzles for high-pressure
jetting. The casing contains holes at its bottom section in order to avoid
blockage in the ground if pressure in the soil-slurry mixture builds up.
The casing also reduces the lateral displacement of soil/slurry and improves
homogeneity of soil-mix. The major applications are for excavation sup-
port, with a rather small column overcut (about 5 cm) because of a high
accuracy of vertical alignment.
Another important European achievement is the cutter soil mixing (CSM)
system, derived from the cutter diaphragm walling technique, jointly devel-
oped by Bauer Maschinen GmbH and Bachy Soletanche since 2003. The
soil is broken down and mixed in situ with slurry by two sets of cutting/
mixing wheels rotating about horizontal axes (cf. Fiorotto et al., 2005).
The CSM system offers signiicant advantages over other walling tech-
niques, and has been successfully transferred to countries outside Europe,
including Japan and the US.
Deep SM is also very popular in China and Southeast Asia. In China
DMM and DJM were introduced in 1977 and 1983, respectively (Zheng
and Liu, 2009). Both methods are now widely used for a variety of applica-
tions and proved to be competitive in terms of costs and time of execution.
To improve the performance of DM columns various types of composite
columns have been also developed (CDMC). They may include installation
of a precast concrete pile, reinforced concrete pile, or a steel pipe inside a
fresh DM column, or even execution of DM column inside a sand column
of comparatively large diameter. In Korea DCM has been developed since
mid-1980s and the use is increasing, especially for marine and harbour
works using special barges equipped with multiple mixing shafts (Kim
et al., 2009).
The hitherto development of different technologies and equipment
used in SM is dificult to follow without a certain generic classiication
system. Several similar systems have already been developed for this pur-
pose (FHWA 2000, CDIT 2002, and EN 14679). The classiication format
adopted herein is based on three fundamental operational characteristics.
The distinction between wet and dry technologies with respect to the form
of binder introduced into the soil is the most straightforward, and hence
the most widely used format. In the dry mixing methods the medium for
binder transportation is typically compressed air, while in the wet mix-
ing methods the medium of transportation is typically water. The second
key characteristic is related to the method used to mix the binder (i.e., by
342 Ground improvement
mechanical action of the mixing tool with the binder injected at relatively
low velocity), hydraulic action of the luid grout injected at high velocity
(jet grouting), or by a combination of both aforementioned techniques (so-
called hybrid mixing). The third basic characteristic relects the location
of mixing action at the end or along a speciic tool. The elaborated clas-
siication chart with the allocation of several operational methods, split
with account for the difference between systems involving rotation of the
cutting/mixing tool about vertical or horizontal axes or around the whole
cutting arm, is shown in Figure 9.6.
When comparing technical features of recently used DMM and SMM
machines and operational systems, it should be kept in mind that the afore-
mentioned methods have been developed while taking into account various
demands and constraints of regional markets, as well as soil conditions
prevailing in areas of potential application. Moreover, various operational
systems also relect different objectives of ground improvement and design
approaches. Consequently, not all SM methods can be regarded as equiva-
lents, although all are based on the same overall concept of in-situ soil
stabilisation. Despite these variations, the main technical goal of any SM
method is to ensure a uniform distribution of binder throughout the treated
soil volume, with uniform moisture content, and without signiicant pock-
ets of native soil or binder.
At the end of mixing tool Along tool At the end of mixing tool
c c c
Vert. axis rot. Vert. axis rot. Vert. axis rot. Vert. axis rot. Vert. axis rot.
- DJM Assoc. - CDM Assoc. - SMW - SWING (out of scope of
(Japan) (Japan) (Japan, USA) (Japan) this chapter)
- Nordic method - SCC - DSM - JACSMAN, Systems:
(Sweden, (Japan) (USA) CI-CMC - Single
Finland) - SSM - MULTIMIX (Japan) (grout)
- TREVIMIX (USA) (Italy, USA) - GEOJET - Double
(Italy) - Keller system - COLMIX (USA) (air+grout)
- SMM: Mass (USA, Europe) (France) - HYDRAMECH - Triple
stabilisation - MECTOOL - Bauer Triple (USA) (water+air
(Finland, Swe- (USA) Auger System - TURBOJET +grout)
den, USA) ..... (Germany) (Italy) - Super jet
.... ..... - Cross jet
....
Horiz. axis rot. Horiz. axis rot. Vert. trenching Horiz. axis rot.
- SMM: Mass - CSM - FMI - CT Jet
stabilisation (Cutter soil (Germany) (Cutter turbo
with mixing mixing, - TRD jet, Italy)
drums Germany, (Japan)
(Finland) France) - TRENCHMIX
(France)
Figure 9.6 General classiication of in-situ soil mixing based on (a) binder form, (b) mixing
principle, and (c) location of mixing action, with allocation of selected fully
operational methods developed in various countries, split with respect to
rotation characteristic of the cutting/mixing tool.
344 Ground improvement
(a) (b)
Upper mixing
blade
Section of
Nozzle
the shaft
Cutting bit
Figure 9.7 Mixing tools of the DJM method. (a) Construction scheme. (Redrawn from
DJM Association, 2002.) (b) Recently used single mixing tool of 1.0 m diameter.
In-situ soil mixing 345
(a) (b)
(c) (d)
Figure 9.8 Selected mixing tools. (a) SD 600 mm, (b) modiied SD 600 mm, (c) PB3 600
mm, (d) peat bore 800 mm. Note: changed location of binder outlow hole in
relation to the horizontal mixing blade in standard (a) and modiied (b) tool.
(Courtesy of LCM.)
sludges. In-situ mixing of the encountered soil mass with dry reagents to
the depth of a few metres can be economically carried out with large-diam-
eter single-axis augers, or with recently developed mass mixing tools imple-
mented in Finland and Sweden. In such applications it is also quite common
for the topsoil to be too weak to provide safe support for heavy mixing
machines. Therefore, it is best to use execution methods that employ mix-
ing tools suspended from the crane or mounted on elongated cantilever
arms, as they usually offer more lexible operation in the ield.
The shallow soil mixing (SSM) method, modiied for accommodation
of dry binders, utilises a crane mounted single auger tool 1.8–3.7 m in
In-situ soil mixing 347
Table 9.1 Mixing conditions for selected dry deep mixing methods
Selected dry DM methods
Technical speciication DJM Nordic method Trevimix
Number of mixing 2 (standard), 1 1 2 (more common), 1
shafts
Diameter of mixing 1.0 (standard) 0.5–1.0 possible 0.8–1.0
tool [m] 1.3 (modiied) 0.6, 0.8 standard (standard)
Realistic maximum 33 25 (30) 30
penetration
depth [m]
Penetration/Retrieval 0.5–3 (4), 7 (1 shaft) P: 2–15 P: 0.4
velocity [m/min] typically: R: 2–6 R: 0.6
P: 1.5, R: 0.7, 0.9 (R: 15–30 mm/
(R: 15 mm/rev.) rev.)
Penetration/Retrieval P: 24, 32 (Electr.) R: 100–220 10–40
rotation speed R: 48, 64 (Electr.) (150–180 P: 20 typically
[rpm] P/R 21–64 (Hydr.) typically) R: 30 typically
Injection during R R R
Penetration/Retrieval (P used: air/binder) (P possible) (P used: air/binder)
Footprint area of the 0.78 : 1 × 1.0 m 0.28, 0.5 (0.78) 0.78 : 1 × 1.0 m
mixing tool (max.) 1.56 : 2 × 1.0 m 1.56 : 2 × 1.0 m
[m2] 2.65 : 2 × 1.3 m
Amount of injected 100–400 70–150 150–300
dry binder [kg/m3] Cem.:sands 150–250 organic 250 typically
200–600 Cem.: peat soils
50–300 Lime: clay
Binder supply 25–120 standard, 40–230 around 100
capacity per shaft up to 200 mod.
[kg/min] version
Injection pressure P: 100–600 400–800 600–1,000
[kPa] R: 600–100
Productivity [m3/shift] 300–700 150–300 150–220
diameter (Jasperse and Ryan, 1992). The driver for the tool is a drilling
system. It can be a conventional hydraulic drill or a high-torque dual motor
turntable. The auger tool itself is specially designed to break up the soil
and/or sludge and mix it with dry reagent without bringing the material
to the surface. To suppress emissions from the mixing process and/or for
environmental applications, the mixing tool can be enclosed in a hood or
bottom-opened cylinder to control dust and airborne contaminants (Figure
9.9). Further components of environmental control may also include a
low pressure blower or vacuum pump to keep negative pressure inside the
hood during operation, a dust collector, a fume incinerator, or an activated
carbon scrubber, depending on site-speciic conditions and contaminants
(Aldridge and Naguib, 1992).
348 Ground improvement
Figure 9.9 SSM mixing tool diameter 3.7 m for the dry method. (Courtesy of Geo-Con
Inc.)
(a) (b)
Figure 9.10 Mass stabilisation using dry binders. (a) Mainly vertical mixing. (b) Vertical
and horizontal mixing.
In-situ soil mixing 349
which houses the pressurised binder container, compressor, air dryer, and
supply control unit. The operator injects the binder into the soil in such a
manner that it is equally distributed and mixed.
Different mixing tools have been tried in the past to treat very soft and
organic soils. The tools currently in use comprise cutting/mixing heads
equipped with blades rotating about a vertical axis, as shown in Figure
9.11, as well as very eficient cutting/mixing drums developed by Allu
Finland Ltd. (Powermixer systems PM and PMX) and suitable for large
mass stabilisation projects (Figure 9.12). The diameter of the mixing tool
rotating about a vertical axis is normally 600–800 mm, and the rotation
speed lies between 80–100 rpm. This method can be applied for soft clays
and organic soils with shear strength below 25 kPa. The more power-
ful PM/PMX mixing drums, with maximum torque of 7 and 23 kNm for
two drums, respectively, can be itted with different types of exchange-
able blades, teeth, or wings enabling enhanced mixing or cutting/break-
ing action in the treated soil. A typical mixing drum has plan width of
1.5–1.6 m and outside tooth to tooth diameter of 0.85–0.95 m. The work-
ing depth is 0–5 m. The novel aspect of the PMX system consists of drums
mounted on two inclined axes of rotation. This arrangement reduces the
distance between both drums and improves the homogeneity of mixing by
eliminating potential zones of unmixed soil which may appear behind the
mounting arm in case of the PM tools, especially when mixing soils with
higher shear resistance.
The mixing pattern of mass stabilisation is planned taking into account
site-speciic conditions and capabilities of the mixing machine and the
(a) (b)
Figure 9.11 Mass stabilisation of organic soil in Sweden. (a) Equipment. (b) Mass mixing
tool diameter 1.0 m. (Courtesy of LCM.)
350 Ground improvement
(a)
(b)
Figure 9.12 Mass mixing tools developed by Allu Finland Ltd. (a) Powermixer system PM
500, with cutting/mixing drums diameter 0.95 m, mounted on a horizon-
tal axis of rotation. (b) Powermixer system PMX 500, with cutting/mixing
drums diameter 0.85 m, mounted on two inclined axes of rotation.
353
Productivity per 100–200 m3 500–700 m3 100 m2 wall 250–750 m3: U 30–300 m3 100–200 m3 200–300 m2 100–300
shift (one rig) 400 m col. 75–200 m3: E wall linear m
354 Ground improvement
(a) (b)
Figure 9.13 Single-shaft mixing tools. (a) Diameter 0.8 m. (b) Diameter 2.4 m, with a
free-blade system. (Courtesy of Keller-Hayward Baker.)
Figure 9.14 Single-column mixing tool for double rotary drives (SCM-DH); column
diameter 1.8 to 2.4 m, max. depth 23.5 m. (From Bauer Maschinen GmbH.
(2010). Cutter Soil Mixing: Process and Equipment. Brochure No. 905.656.2.)
In-situ soil mixing 355
(a) (b)
(c) (d)
Figure 9.15 Multiple shaft mixing tools. (a) Standard CDM 2 × 1.0 m. (From Cement
Deep Mixing Association. (2002). CDM Cement Deep Mixing Bulletin as of
2002.) (b) CDM Land4, 4 × 1.0 m. (From Cement Deep Mixing Association.
(2002). CDM Cement Deep Mixing Bulletin as of 2002.) (c) SMW mixing pad-
dles 3 × 1.5 m. (d) Cutter head. (Courtesy of R. Jakiel.)
(a) (b)
Figure 9.16 DSM mixing tools. (a) Four blade-based mixing shafts. (b) Four discontinu-
ous, interlocking augers, diameter 0.9 m. (Courtesy of Geo-Con Inc.)
of the cement slurry with the soil. The unit is capable of treating harder
ground formations sandwiched between softer layers. The area of treatment
is 3.5 m2 and the required capacity of slurry supply is up to 1.0 m3/min.
The maximum depth of treatment is 40 m. This modern system not only
reduces the unit cost of soil treatment due to its very high productivity,
(a) (b)
Twin Triple
Quadruple
Direction of
rotation
during drilling
Figure 9.17 COLMIX mixing tools: (a) Possible arrangements. (b) Four discontinuous,
interlocking augers diameter 0.5 m. (Courtesy of Bachy-Soletanche.)
In-situ soil mixing 357
(a) (b)
Figure 9.18 Bauer mixing tool with three closely spaced, continuous augers, diameter
0.55 m. (Courtesy of Bauer Spezialtiefbau.)
(a) (b)
Figure 9.20 The cutter soil mixing heads. (a) Standard BCM 5, type 3-2 (three tooth hold-
ers in one row of teeth). (b) QuatroCutter. (Courtesy of Bauer Spezialtiefbau
GmbH.)
panel construction joints can be facilitated. For bigger depth, two standard
cutting and mixing heads attached at the bottom and at the top of a special
frame are used (Figure 9.20b). This system, known as QuatroCutter (Bauer
Maschinen, 2010), ensures intensive and homogeneous mixing as well as
high directional accuracy of CSM walls up to 60 m deep.
In relatively uniform soils, or for retaining structures up to about 20 m
deep, mixing is conducted during cutting (penetration) and withdrawal.
The backlow of soil and slurry is collected in a pre-excavated trench. For
deeper cut-off walls and for less uniform soils, a two-phase approach is
adopted for CSM using bentonite for temporary trench support during
cutting. As with conventional diaphragm wall construction, the bentonite
slurry is recirculated and cleaned by passing through desanding equipment.
Grout is injected during the withdrawal phase and mixed with remaining
soils. The speed of extraction and low of grout are adjusted to ensure that
the desired quantity of cement is blended with the soil.
The CSM system allows complete instrumentation inside the cutter gear-
box support frame to read and control in real time the coordinates of the
cutting head. This inclinometer system, coupled with the advantage of a
steerable tool, provides assurance of complete overlap between panels. In
favourable soil conditions the net productivity can reach about 40 m 2 of a
CSM wall/hour. However, a daily output is usually 100–200 m 2 (based on
70–90-tonne machines with power outputs of 260–300 kW) due to high
maintenance on the rig and cutter head. Wear rates are different for each
type of soil. For instance, in compacted sand and gravel re-welding of the
head was needed every 500–1,500 m 2 and the wear was 0.1–0.2 teeth/m 2 .
Changing of the head takes one day.
360 Ground improvement
(a)
(b)
Figure 9.21 TRENCHMIX equipment. (a) Rig in operation on a river dike. (b) Close-up
of cutting/mixing teeth. (Courtesy of Bachy Soletanche and Mastenbroek.)
362 Ground improvement
the soil with slurry injected at a controlled rate along the boom. Effective
and thorough mixing is ensured by the specially designed teeth
(Figure 9.21b) and high energy mixing process, controlled by a purposely
designed QC/QA system. The fact that the soil-mix material is drawn
to the surface allows also a good visual inspection of the eficiency of
mixing. Vertical mixed elements of about 0.4 m width to depths of typi-
cally 4–10 m (max 13 m) can be constructed. These elements can be used
to form cut-off walls to control pollution or groundwater in the ground,
or as improved ground foundation bearing elements when spaced close
together.
The trencher, despite its long boom, is highly manoeuvrable and capable
of operating in narrow and limited headroom spaces. This technique is
faster than sheet piling, produces signiicantly less spoil than convention-
ally dug walls and has no issues with noise and vibration. In favourable soil
conditions, the driving speed may reach 30–40 m/hour at the depth of 10
m and width of 0.4 m.
Mixing in the trench using dry binders is also possible given the right
conditions. The binder is placed in the shallow pre-trench and water is
added during mixing to achieve the required workability.
(a) (b)
Figure 9.22 Crane-mounted SSM tools for the wet method. (a) Diameter 2.4 m. (b)
Diameter 3.7 m. (Courtesy of Geo-Con Inc.)
(a)
(b) (c)
Figure 9.23 Shallow mixing equipment used at Fort Point Channel Site in Boston.
(Courtesy of R. Jakiel.)
(a) (c)
(b)
Figure 9.24 Spreadable wing (SWING) method. (a) Blade position during penetra-
tion. (b) Blade expanded. (c) Demonstration of jetting action. (Courtesy of
SWING Assoc.)
the blade and jetting action of water. Cement slurry is injected during with-
drawal, with the jetting energy supplemented by air pressure. Air is used
when the larger diameters are required or when the soils under treatment
are too stiff. This method also enables the installation of inclined or even
horizontal columns and therefore allows soil mixing in areas of dificult
access.
The JACSMAN system consists of two 10-bladed mixing tools, each
combined with a pair of jet grouting nozzles aligned for Cross Jet (XJET)
to ensure that over-cutting does not occur. As compared with the con-
ventional CDM method, JACSMAN offers signiicant improvements that
contribute to a more economical, high-quality product. Due to XJET cut-
ting with air-enveloped, high-velocity cement slurry during withdrawal,
the treatment area of single-stroke operation increases considerably and
equals 6.4 m2 for type A arrangement, with a 75% share of jet mixing, and
7.2 m2 for type B arrangement, with a 63% share of jet mixing, as shown in
Figure 9.25. Moreover, the diameter of the soil-cement column can be con-
trolled and changed over the column’s length through stopping and starting
XJET action, not affecting the surrounding soil due to the dissipation of jet
energy at the cross point (Figure 9.26). This allows for the adjustment of
the column’s diameter to soil stratiication, as well as for controlled mix-
ing operations close to structures or excavation walls. The main operating
parameters of JACSMAN are as follows: jetting pressure 30 MPa, jetting
slurry low rate 4 × 150 l/min, air pressure 0.7 MPa, grout low rate 2 × 200
l/min, grout pressure 5 MPa, and withdrawal speed of 0.5 and 1 m/min
for type A and B arrangement, respectively (Kawanabe and Nozu, 2002).
366 Ground improvement
(b)
(a) Conventional CDM method
Cross jet injected section
1.0
Improved area : 1.5 m2
1.8 m
Jacsman
Type A Type B
3.3 m 3.7 m Mechanical section
1.0 0.65 1.3 0.5
2.3
Mechanical
1.0 1.4
section Single-rod installation
Improved area : 6.4 m2 Improved area : 7.2 m2
Figure 9.25 The JACSMAN method. (a) Comparison of treatment areas. (b) Exposed sin-
gle column. (Redrawn from Kawanabe, S. and Nozu, M. (2002). Combination
mixing method of jet grout and deep mixing, Proceedings from the Deep
Mixing Workshop 2002, Port and Airport Research Institute & Coastal
Development Institute of Technology, Tokyo, Japan.)
(a) (b)
Figure 9.26 JACSMAN mixing tool. (a) Twin head assembly (note grout nozzle in front
of the tool). (b) XJET demonstration with increased pressure. (Courtesy of
R. Essler.)
In-situ soil mixing 367
occurs smoothly in the centre of the column, and chunks of material are
forced to the perimeter, where they are disaggregated by the jets. Treatment
with jets can be switched on and off throughout the column length to cre-
ate plugs of treated soil. Realistic maximum penetration depth is 20 m.
Penetration/retrieval velocity is 1–3 m/min, with 5–20 rpm during pen-
etration and 10–30 rpm during retrieval (additional mixing). Industrial
productivities are in the range of 250–500 m3/shift. The main objective
for developing this method was to improve on current jet grouting tech-
nologies that can create subsurface problems with the use of compressed
air. HYDRAMECH can create an extended diameter soil-cement column
without the injection of compressed air and still provide the continuous
overlap that is a very positive aspect of jet grouting systems, particularly
when installing horizontal barriers.
TURBOJET (GEOJET in the US) combines mechanical mixing with
single luid jet grouting technology. Jetting is used during insertion of the
tool to increase penetration velocity while extraction is carried out solely
with mechanical mixing. A specially designed mixing tool (or processor),
itted at the end of a tubular Kelly bar, consists of two levels of inclined
blades and is furnished with several 4–8 mm diameter high-pressure nozzles
mounted along the shaft and tip (Figure 9.27). The exact nature and com-
position of the processor can be varied, depending on soil conditions. Grout
can be pumped with a discharge rate of 450 l/min at 30 MPa, although lower
lows rates and pressure (15 MPa) are the norm. Tool diameters range from
0.6–1.5 m, usually 0.9–1.2 m, and the practical available depth of treat-
ment is 25 m (Lebon, 2002). Instantaneous rates include 2–12 m/min (6 m/
min typical) during penetration and 15 m/min during withdrawal. Computer
control of the equipment during column formation is therefore required. The
computer analyses the rate of tool rotation and penetration, slurry pressure,
torque, crowd force, and soil-mix volume and density as a function of depth.
The system also reacts to changing parameters and automatically adjusts to
maintain speciied soil-cement properties, even in varying subsurface soils.
Because of the additional mixing energy supplied, restroking is not required.
Industrial production rates in excess of 150 m/h and 1100 m/shift are possi-
ble. The system produces low waste volumes (20%–30% of ground treated).
(a) (b)
Figure 9.27 TURBOJET deep soil mixing equipment and processor. (Courtesy of M.
Siepi.)
Depth Depth
Figure 9.28 Typical execution procedures of deep soil mixing. (a) Without or with bot-
toming. (b) With reversal(s) during penetration. (c) With bottom restrok-
ing. (d) With stepped restroking during withdrawal. (e) With full-depth
restroking.
In-situ soil mixing 369
The position and verticality of the shaft is checked irst, and zero adjust-
ments of the logging system are conducted. For on-land application optical
survey devices are normally used, whereas for marine operations the use of
the GPS has become common. The GPS is also advantageous in the case of
large on-land projects, especially those involving treatment of very weak
supericial soils.
During penetration the mixing tool is delivered to the required depth. In
this phase compressed air (dry method), or slurry (wet mechanical mixing),
or high-velocity jetting with slurry or water and air (hybrid mixing) is used
to support mechanical drilling. Mechanical penetration may be dificult
when the tool hits a hard layer or when the improvement depth is relatively
deep, leading to possible damage or deadlock of the tool in the ground.
This danger may be reduced with partial restroking to minimise rotation
resistance along the shaft (Figure 9.28b), or by means of pre-boring with
an auger machine.
After the basal treatment depth is reached, the mixing tool remains
on the bottom rotating about 0.5–2 minutes for complete mixing. This
phase is often called ‘bottoming’ and serves to ensure suficient contact of
the column(s) with the bearing subsoil. Penetration into the bearing layer
should be conirmed by a rapid change of penetration velocity of the tool,
required torque, and rotation speed. At this stage the tool can be raised
about 0.5–1 m and lowered again to treat more effectively the transition
zone between soft and bearing soils (Figure 9.28c). Withdrawal may be
conducted as a continuous upstroke, but can include stepped or even full
restroking if needed (Figure 9.28d and e). Full restroking is beneicial in the
case of interchanged soft/stiff layers and stratiied soils, leading to more
uniform properties of stabilised soil across the depth of treatment.
The accompanying delivery of the stabilising agent to the subsoil is oper-
ator/computer controlled and linked to the energy of mixing in the speciic
layers of treated soil. In general, injection of the stabilising agent can take
place during penetration, withdrawal, and restroking; however, two main
injection methods are distinguished—the penetration injection method,
which is a top-bottom process, and the withdrawal injection method,
which is a bottom-top process. Penetration injection is typically used for
on-land applications of the wet method because the slurry helps to lubri-
cate the mixing tool and assists in breaking up the soil into smaller pieces.
Normally, 80%–100% of the total slurry volume is used in this stage. This
method is also beneicial to the homogeneity and strength of the manufac-
tured column because the native soil is mixed twice with the binder.
Withdrawal injection is typically used for the dry method, usually
with the whole amount of binder delivered to the soil during this phase.
However, if very high binder concentration is needed to reach the design
strength, part of the stabiliser may be injected during penetration phase
and the rest during withdrawal of the mixing tool. Withdrawal injection
370 Ground improvement
also prevails for marine operations with the CDM method, but not for all.
For on-land applications with the wet method, withdrawal injection is also
possible, but usually at a reduced low rate to minimise the volume of spoil
(except of the CDM-LODIC method where withdrawal injection is a stan-
dard installation process).
The sequence of mixing operations will need to be adjusted to suit each
site’s speciic conditions, but in general the most eficient sequence is to
work the stabilisation machine within its radius of operation as much as
possible before it is moved.
(a) complete injection during penetration and outlet located below the
blades:
T = ΣM × (Rp / Vp + Rw / Vw ), (9.1)
In-situ soil mixing 373
(b) complete injection during withdrawal and outlet located above the
blades:
T = ΣM × (Rw / Vw ), and (9.2)
(c) partial injection during penetration and main injection during with-
drawal, with the lower outlet active only during penetration and the
upper outlet active during withdrawal:
T = ΣM × (Rp / Vp × Wp / W + Rw / Vw ) (9.3)
The total number of mixing blades, ΣM, is assessed by counting all cut-
ting/mixing blades that are effective in the mixing process, taking into con-
sideration the method of injection and position of the injection outlet(s) in
relation to the blades. A full-diameter blade is counted as two blades. For
example, when the outlet port is located beneath two levels of blades and
when injection is carried out during penetration, as is common for the wet
methods, the total number of mixing blades is ΣM = 4 and Equation 9.1
is used to evaluate T. In case of the withdrawal injection method and the
outlet port located above all blades, as is common for the dry methods, ΣM
is also four but only the withdrawal stage is considered (Equation 9.2). This
example demonstrates that higher rotational speeds are required for the
withdrawal injection method to obtain a comparable degree of mixing. In
case multiple restroking along the whole depth is used, as shown in Figure.
9.27e, the resulting blade rotation number is a sum of T values calculated
for each penetration/withdrawal cycle of the mixing tool.
The blade rotation number is used for mechanical mixing only, and the
soil conditions are included indirectly (i.e., through selection of appropri-
ate input values), taking into account accumulated experience and techni-
cal speciications of the equipment. Based on ield data obtained in loose
sands (Mizuno et al.) and clays, the blade rotation number of 360 has been
recommended in Japan for the wet method to ensure reasonably low value
of the coeficient of variation, ν, of the unconined compressive strength
(CDIT, 2002). Field tests using wet mixing in silty/sandy clay in Poland
revealed T = 430 to satisfy ν ≤ 0.3 (Topolnicki, 2009). For the dry mixing
methods the blade rotation number is typically 274 or 284 for the DJM
and 200 to 400 for the Nordic method, noting that dry binders are injected
mainly only during withdrawal. For special mixing tools using cutting/mixing
374 Ground improvement
blades that rotate in opposite directions on a single shaft, like for instance
the Bauer SCM-DH and the CDM Column 21 methods, there is a need to
conceive a new guideline for the quality of mixing.
(a) (b)
Pressurised tank Feeding wheel
Main
air
Air for
Binder
rubber
valve
Bypass
Air
air
Cell feeder
Rubber Outlet
To mixing tool valve
Figure 9.29 Binder feeding systems. (a) Cell feeder used in the Nordic method (cour-
tesy of LCM). (b) Impeller used in the DJM method. (Redrawn from Aoi,
M. (2002). Execution procedure of Japanese dry method (DJM), Proceedings
of the Deep Mixing Workshop 2002, Port and Airport Research Institute &
Coastal Development Institute of Technology, Tokyo, Japan.)
Figure 9.30 Examples of deep soil mixing patterns. (a), (b) Column-type (square and
triangular arrangement). (c) Tangent wall. (d) Overlapped wall. (e) Trench/
CSM wall. (f) Tangent walls. (g) Tangent grid. (h) Overlapped wall with but-
tresses. (i) Tangent cells. (j) Ring. (k) Lattice. (l) Group columns. (m) Multiple
trenches/CSM walls. (n) Block.
open cuts and protect structures with shallow foundations surrounding the
excavation, and as a measure against seepage. They are also constructed to
increase the bearing capacity of improved soil against horizontal or sliding
forces, with column rows installed in the direction of horizontal loading or
perpendicular to the expected surface of failure. Walls can be constructed
with tangential or overlapping columns, joint panels, or as trench struc-
tures. Overlapping is particularly important when executing cut-off walls
or environmental barriers. In the case of DM machines equipped with
linearly arranged multiple shafts, walls are usually executed using inter-
secting primary and secondary panels, with partial or even full-column
diameter overlap. Groups of columns can be utilised to support embank-
ments and foundations in order to reduce settlements and/or increase the
bearing capacity. Various combinations of columns or panels are also used
to build grid, U-formed, cellular, or circular installations with tangential
or overlapping elements to improve the interaction with the untreated soil.
Lattice-type improvements are considered an intermediate, cost-effective
system between the wall-type and the block-type improvement. Full blocks
are used to create large, highly stable volumes of stabilised soil, which act
as gravity structures.
Next Page
378 Ground improvement
The upper limit of the ratio of area improvement for a square grid of tan-
gential columns is 78.5%, and for equilateral triangular grid it is 90.7%.
For columns spaced at 2 diameters ap is 19.6% and 22.7% for square and
triangular patterns, respectively; and for columns spaced at 3 diameters it
is 8.7% and 10.1%. The spacing of 3 diameters, usually recommended to
minimise interaction between piles, can be considered as a practical lower
limit of the area improvement ratio. Numerous embankments in Japan
have been stabilised with ap usually 30%–50% (due to seismic excitations),
while in Scandinavia area ratios 10%–30% have been typically applied in
case histories. Statistical evaluation of about 2,770 embankment projects
in Japan revealed a distinct difference between ap values used for settlement
reduction and stability problems, being about 20% higher for the latter
cases (Terashi et al., 2009).
Column/panel installation patterns may not only vary in plan view but
also with respect to the depth of treatment. In the wall-type improvement,
short and long walls can be alternately installed in the soft soil to reduce
the costs of soil mixing (Figure 9.32a). The long walls transfer the loads
exerted by the superstructure and external excitations to the bearing stra-
tum, while the intermediate short walls provide connection between the
long walls, increasing the rigidity of the total improved soil mass. This
type of improvement has been commonly applied in port and harbour con-
structions in Japan (e.g., Kansai Airport man-made island; CDIT, 2002).
Another example is the variation of column/panel lengths in transition
and/or purposely determined zones of soil treatment, as shown in Figure
(a) L1 (b) L
L2 B
Ac Aci
A
A = L1 × L2 , At = Ac A = B × L , At = ¦ Aci
Figure 9.31 Evaluation of the ratio of area improvement. (a) Regular grid of columns. (b)
Foundation slab.
Chapter 10
CONTENTS
435
436 Ground improvement
10.1 INTRODUCTION
Dry soil mixing (DSM) methods are the only techniques which directly
mix soils with dry binder materials where the soil moisture is suficient
to hydrate the resulting in-situ mix. A range of binders can be used, but
the most common are cement, lime-cement, and other cementitious blends
which undergo beneicial chemical reactions with the soils into which they
are mixed. These dry materials are fed into the ground using compressed
air where they are comprehensively mixed, using purpose-designed tools,
with the soils to be improved to the depth range identiied.
Early development of in-situ dry mixing methods appears to have arisen
simultaneously in Japan and Sweden during the late 1960s in order to
deal with soft silts and clays. Since then the approaches have markedly
diverged to address the differing technical and commercial demands of
their respective markets. This chapter deals speciically with the Swedish
method, sometimes dubbed the ‘Nordic method’ (Holm, 2002). By the end
of the 1980s the method was widely established in Sweden, Finland, and
Norway, and by the early 2000s was being used in the US and in several
other European countries, notably Poland and the UK. At the time of writ-
ing the method is also being used in the Far East and Australia. The his-
tory and development of both Nordic and Japanese methods are covered in
more detail in Chapter 9 (Section 9.2) of this book.
Single-axis column mixing is the simplest and most widely used form
of construction using the Nordic method. The mixing tool is irst rotated
into the ground down to the depth previously identiied for the toe of
the column. The tool is then withdrawn at a high rate of rotation, dur-
ing which the dry binder is injected through ports in the mixing tool at a
controlled rate according to the design. This creates appropriate mixing
of the binder with the soil contained within the blade diameter and shape
of the tool. Typical equipment for column construction is a purpose-built
hydraulic base machine with low ground pressure, suitable for traversing
soft ground, carrying a mast, rotary head, hollow-stem Kelly bar and the
mixing tool. A separate pressurised container is used to store and transfer
the binder to the Kelly, and is either self-propelled or towed behind the
base machine.
Dry soil mixing 437
Dry soil mixing is applied in inorganic soft soils in which the natural
moisture content is close to or above the liquid limit, and is increasingly
being used in highly organic soils and peats. The main applications are for
foundation bearing or settlement control and providing stability for slopes,
embankments, and excavations. Other applications include reduction of
vibrations, provision of liquefaction resistance, and solidiication of con-
taminated soils and mud. The technique has continued to spread worldwide
due to its advantages of avoiding the need to pre-mix materials with water
before injection and the high rate of construction, leading to low costs per
metre of column relative to other forms of soil mixing. Typical column
diameters are 0.5–1.0 m and depths of treatment are often 5–17 m with
deeper treatment available with special equipment.
10.2.1 General
Dry soil mixing is a general term for mechanical in-situ mixing of soil by
adding a dry additive (commonly called binder) distributed by air low. The
mechanical mixing is done by either vertical or horizontal mixing by rotat-
ing impellers of paddles see Figure 10.1 or by cylinders with cutting heads
as in Figure 10.2.
The binder is transported from rig-mounted silos or from silos mounted
on a separate unit (which could be either on a so-called shuttle or distrib-
uted directly from a bulk silo). The DSM process with the in-situ mixing of
a dry additive into the soil by compressed air is referred to by several differ-
ent terms, such as lime/cement columns, deep stabilisation, dry jet mixing
PF Pressure feeder
Excavator
Peat,
2-5 meters
Mass stabilished peat,
mud,
mud or soft clay
soft
clay
Figure 10.4 Installation sequence for mass mixing with rotated cylinders and cutter
heads. (Courtesy of Allu Finland.)
speed of the mixing tool. Typical penetration speed is 100 mm/rev. and
typical rotation speed of the mixing tool is <100 rev/min. The binder is sel-
dom injected during penetration. In mass mixing using cutter heads there
is no initial penetration—instead the mixing and dispersion of binder take
place directly.
r The mixing tool design and the drilling rig site–speciic adjustments
r Air pressure delivery and amount of air entrained into the ground
ρsoil
ρsoil − (1 + w )
w/c = N
(10.1)
mbinder
where
ρsoil = bulk density of unstabilised soil (t/m3)
wN = natural water content in unstabilised soil
mbinder = binder content (t/m3)
Graphs on the relationship between w/c ratio and strength from labora-
tory investigations and from literature studies are valuable information in
the pre-design stage. However, mixing soil samples with different amounts
Dry soil mixing 443
Shear strength
kPa
300
Clayey mud
28 days
250
200
Cement
150
Lime cement
100
50
0
0 4 8 12 16
wcr-wctr
Figure 10.5 Relation between shear strength and water cement ratio (w/c) in a clayey mud
from Sweden. (From Åhnberg, H., Johansson, S.E., Retelius, A., Ljungkrantz,
C., Holmqvist, L., and Holm, G. (1995). Cement och Lalk för Djupstabilisering av
Jord – En Kemisk Fysikalisk Studie av Stabiliseringseffekter (Cement and Lime for
Stabilisation of Soil at Depth – a Chemical Physical Investigation of Soil Improvement
Effects), Report No. 48. Linköping, Sweden: Swedish Geotechnical Institute.)
Mixing energy is, in its more general sense, measured as mixing cycles
per metre of a column T (Yoshizawa et al., 1997):
N d N u
T = ∑ M × V + (10.2)
d Vu
where:
ΣM = number of mixing tool blades
Nd = rotation speed of mixing tool during penetration (rev/min)
Vd = mixing tool penetration velocity (m/min)
Nu = rotation speed of mixing tool during retrieval (rev/min)
Vu = mixing tool retrieval velocity (m/min).
For DSM, by the Nordic method, the uplift rate (mm/rev) of the mix-
ing tool is used as a measure of the mixing time since mixing does not
occur during penetration. The mixing energy is speciied as the blade
rotation number (BRN; see Figure 10.6) and the number of cycles per
column metre T is calculated as:
1
T = ∑ M × s × 1000 (10.3)
Strength magnitude and variability
Strength
Coefficient of variation
Figure 10.6 Principal changes in strength and coeficient of variation due to the variation
in blade rotation number T. (From Larsson S. (2005). Keynote lecture: state
of practice report – execution, monitoring and quality control. Proceedings of
the International Conference on Deep Mixing Best Practice and Recent Advances,
May 23–25, 2005, Stockholm, Sweden, pp. 732–785.)
Dry soil mixing 445
where
M = number of mixing tool blades
s = retrieval rate of mixing tool during withdraw (mm/rev).
of cement and slag. In other European countries, the UK, and the US,
the most commonly used binders are cement only or cement and slag.
However, blended mixtures of cement and quicklime are moderately used
in Poland.
10.2.4.3.1 Cement
Cement used as binder in a DSM process is predominately standard
Portland cement. When cement is mixed with a soil it reacts with the water
content and instantly the hydration process commences in which a hard
cement paste forms of calcium silicate hydrate Ca3Si2H4 (CSH-gel). The
CSH-gel is formed on the cement particles and increases in size, illing the
voids between the particles. With time the porosity decreases, the particles
bind together, and the mass becomes stronger and more dense. Initially, the
rate of strength gain is controlled by the temperature; the higher the tem-
perature, the more reactions that take place leading to better strength gain
(Timoney et al., 2012). The reaction process of 100g cement and 25g H2O
can be expressed as:
10.2.4.3.2 Lime
Lime used as binder is mainly calcium oxide (CaO), known as quicklime or
burnet lime. When quicklime is mixed with water slaked lime or hydrated
lime, Ca(OH)2 , is formed:
CaO + H 2O → Ca(OH)2
100g 32g → 132g
448 Ground improvement
The reaction is instant, and reaches its maximum within 5 minutes while
generating a great deal of heat. The reaction also results in the pH increas-
ing to ~12.5, which is a condition for the secondary pozzolanic reaction.
During soil stabilisation, hydration dewaters the soil giving a rapid gain in
stability (Janz and Johansson, 2002). The primary reaction is not gaining
any strength. The strength gain in stabilised soil is due to the secondary
pozzolanic reactions with other additives or with the surrounding soils:
10.2.4.4.3 Temperature
Soil masses stabilised with lime and/or cement generate heat during the
cement and pozzolanic reactions; Halkola (1999) reports a temperature
of 70°C in lime and Åhnberg et al. (1995) reported that cement increases
the ground temperature by 5–10°C and lime can increase the ground
temperature 40–50°C, and locally it can even generate temperatures up
to 100°C. Binders like GGBS produce less heat during exothermic reac-
tions, and are therefore more susceptible to temperature changes of the
soil being stabilised, thus often resulting in less reaction and lower initial
strength (Timoney et al., 2012). Admixtures with lime or cement increase
the ground temperature, which activates any secondary binder such as
GGBS or ly ash.
* von Post is a classiication system for peat on a scale between H1 to H10 based on its physi-
cal properties.
450 Ground improvement
600
500
Shear strength (kPa)
400
300
Lime
200 Lime/cement
100 Cement
0
0 50 100 150 200 250 300
Time (days)
Figure 10.7 Strength gain over time for different binders. (From Åhnberg, H.,
Johansson, S.E., Retelius, A., Ljungkrantz, C., Holmqvist, L., and Holm,
G. (1995). Cement och Lalk för Djupstabilisering av Jord – En Kemisk
Fysikalisk Studie av Stabiliseringseffekter (Cement and Lime for Stabilisation
of Soil at Depth – a Chemical Physical Investigation of Soil Improvement
Effects), Report No. 48. Linköping, Sweden: Swedish Geotechnical
Institute.)
loading on DSM columns in clay has also have a positive effect on the
strength gain, but less than in peat.
3
Linköping clay
y = 0.305ln(x) – 0.04
Löftobro clay
R2 = 0.94
Holma gyttja
Trend Nagaraj et al. (1996)
2
qt/q28
0
0 200 400 600 800 1000
Time after mixing t, days
Figure 10.8 Increase in unconined compression strength over time for cement-stabilised
clay and sludge. (From Åhnberg, H. (2006). Strength of Stabilized Soils – A
Laboratory Study on Clays and Organic Soils Stabilised with Different Types of
Binder. PhD Thesis, Lund University, Sweden.)
452 Ground improvement
Prediction on strength gain for cement-stabilised soil has also been investi-
gated by Horpibulsuk et al. (2003) by using a modiication of Abram’s law*.
Predictions of strength gain by time for cement-stabilised clays are dif-
icult and the presented methods are empirical methods that can be used
as an indication of the strength gain over time. However, these can only
provide indications while site-speciic tests are the most reliable method.
10.3.1 Equipment
One machine unit consists of a drilling rig and a shuttle carrying the binder
tank (some machines have the binder tank on the drilling rig). The drilling
rig is constructed with wide tracks for low ground pressure (40–60 kPa).
Such rigs are 4–5 m long and 3.0–3.5 m wide and are commonly the
base units of excavators or a piling rig, see Figure 10.9. The mast is nor-
mally 15–17 m high, but can be extended up to about 27 m. The machine
equipment and shuttles are commonly manufactured by the contractors
themselves.
* Abram’s law is an empirical model to predict strength gain extensively used in concrete
technology.
Dry soil mixing 453
Figure 10.9 DSM machine unit, drilling rig, and shuttle. (Courtesy of dmixab.)
The shuttles carrying binders have a storage capacity of 10–15 tons and
are pressurised to 5–10 bar. The pressures applied to the ground by the
shuttle are similar to those from drilling rigs. The binder is fed from the
shuttle to the top of the drilling shaft and blown out by the outlet hole at
the mixing tool via air pressure, see Figure 10.1. Drilling can generally, with
equipment today, be carried out to approximately 25 m depth; however, in
the majority of projects drilling length is 15 m or less. Rotation speed of the
drilling shaft is in the interval of 100–200 rpm, depending on the ground
conditions. Downward penetration is usually controlled manually by the
operator and corrected due to ground conditions and the risk of hitting
obstacles. Typical downward movement is 100 mm/rotation. During down-
ward movement, the shaft is pressurised by air to prevent water and soil
from entering. During upward movement, the binder is fed out by air pres-
sure. The amount of binder is regulated by feed-out valves in the shuttle.
The upward movement is generally 15–30 mm/rotation, depending on the
required mixing work. The blowout of binder into the surrounding soil is
stopped at 0.5 m beneath the ground surface to prevent release into the
open air. In urban areas a protection head can be used to avoid clay splash
and blow outs of binder into open air.
Mass mixing equipment is similar to DSM equipment with a drilling unit
(rig and shuttle). The drilling rigs are commonly smaller than a DSM rig
and have lower ground pressure (30–40 kPa), see Figure 10.10. Shuttles are
in many cases not used for binder delivery due to limited storage capacity
454 Ground improvement
(a) (b)
Figure 10.10 (a) Mass mixing drilling rig and shuttle. (Courtesy of LCM.) (b) Storage sup-
ply in bulk silos. (Courtesy of LCM.)
(large amount of binder is commonly the case in mass mixing). The binder
is delivered directly from bulk silos by compressed air in tubes or supplied
by bulk trucks behind the drilling rig.
The mixing tool is an important part of the equipment. There are some
well-established shapes of mixing tools. The three most commonly used
are (1) standard mixing tool (the irst developed mixing tool, Figure 10.11);
Figure 10.11 Standard mixing tool, Pinnborr (shown in Figure 10.1), and Allu rotary head
(shown in Figure 10.2).
Dry soil mixing 455
(2) Pinnborr, a three-level blade mixing tool (the most common in Nordic
countries today); and (3) Allu rotary head (mass mixing tool).
Since the turn of the century, industrial mixing has made progress as a
new technique based on knowledge gained from DSM experience. Industrial
mixing is predominately used for dredge material pumped into the machine
where it is mixed with different types of binder and thereafter transported
to a land reclamation area (a lagoon) for hardening.
r Column name
r Machine name
r Responsible operator
r Used mixing tool
r Time and date of installation
r Drilling time
r Retrieval rate (mm/r)
r Speed of rotation (rpm)
r Drilling length and/or stabilising length
r Amount of binder along the column
r Weight of the binder tank
r Position of the column (GPS)
r Machine name
r Responsible operator
r Date of installation
r Column name
456 Ground improvement
Monitoring data is part of the quality assurance (QA) and quality control
(QC) for the stabilisation work. The information is commonly delivered
from the contractor to the client on a daily or weekly basis. Adjustments to
the installation process and decisions for in-situ testing can be made from
the printouts of the installation data. It is important not to focus solely on
performing in-situ tests on apparently less good columns, as it is the mass
properties that will often be most relevant.
The production capacity is dependent on a number of factors and site-speciic
conditions such as stiffness in the unstabilised soil, magnitude of obstacles,
length of columns, rotation speed and restrictions in vertical movement (special
installation pattern etc.), access to the area and transportations roads, distance
to binder storage, and amount of binder in the columns. Typical production
capacity for 10-m long columns is 40–80 stabilised metres per hour per unit.
10.4.1 Applications
There are a number of applications using DSM columns and mass mixing
for permanent and temporary works either on land or in marine environ-
ment. Some of the main applications include
r Reduction of settlement
r Improvement of stability
r Reduction of ground vibration
r Foundations of structures and houses
r Mass mixing of organic soils and dredged sediments
r Solidiication and stabilisation of contaminated soils
r Increase passive earth pressure for sheet pile walls in soft clay
r Reduce active earth pressure on retaining/sheet-piled walls in soft clay
r Preventing liquefaction in seismic hazard areas
r Creating geohydrological barriers
DSM columns and mass mixing is sometimes combined with other soil
improvement techniques in order to design the most technical and eco-
nomical solution:
Exposure of col.
Section
Panels 6–8m
longitudinal
Panels 4–6m
perpendicular
Single col.
settlements
Plan
Figure 10.13 Column layout for reduction of vibration connected to high-speed train
phenome.
and culverts, the adjoining embankments are also usually stabilised with
DSM columns. By improving the soil underneath the structure, a system
with small differential settlements is obtained. An example of column lay-
out is shown in Figure 10.14. The ratio of improvement is increased under-
neath the structure and at the adjacent embankment, but further from the
embankment the ratio of improvement decreases. Columns in panels are
installed to increase the stability toward the passway. Panels along the road
are installed to increase the stability during excavation and foundation
works. This type of layout takes care of the permanent situation as well as
the temporary excavation and foundation works.
Buildings, warehouses, and residential homes built in soft clay and silt
areas have been supported by DSM columns as an economical alternative
to piling. When it comes to warehouses, a combination of DSM and piling
has been used in areas with soft clay deposits. The warehouse framework
structure is supported on piles taken to a irm bearing soil layer, and the
loor is supported by DSM columns.
Designing DSM for supporting structures means that small settlements
and restrictions of differential settlements are critical. Hence the static load
Dry soil mixing 461
(a)
Bridge
(b)
Figure 10.14 (a) Column layout applied on small bridges and culverts. (b) Interlocking
panels for slope stability at Skepplanda, Sweden (Courtesy of Johnny
Wallgren.)
Dahlström and Eriksson (2005) have reported two projects using mass
stabilisation and DSM columns for road embankments in Sweden. Jelisic
Road level
0.5-1m
MS-soil
DSM
Figure 10.15 Mass mixing combined with DSM for a road embankment.
Dry soil mixing 463
and Leppännen (2005) and Forsman et al. (2008) have reported experi-
ences of mass stabilisation in contaminated dredge mud.
10.4.2 Design
The design of the Nordic method and the Japanese method differ in their
basic philosophy. This chapter only presents the Nordic method as it has
been developed alongside the DSM processes.The original design was
developed for lime columns and was irst presented by Boman and Broms
in 1975 at the Nordic Geotechnical Conference, NGM-75, in Copenhagen.
Only minor changes and complementary theories have been developed since
the irst paper regarding the design method was published. In 2005 Álen
et al. (2005a) presented a new design method to determine the compres-
sion strength in the columns. Today, both the original design philosophy
developed by Boman and Broms and the new design model for determining
the compression strength and bearing capacity of a column is used in the
Nordic countries. The original design philosophy is still the most com-
mon design method. Design guidelines such as EuroSoilStab (2002) and
SGF (2000) are based on Boman and Broms’ design philosophy. Stability
failure has been investigated and presented in numerous papers, including
Kitazume et al. (1996), Kivilö and Broms (1999), Terashi (2005), and Filz
et al. (2012).
DSM columns and mass mixing are inhomogeneous to varying degrees,
with an irregular structure and varying properties. The columns and mass
mixing are primarily intended to interact with unstabilised soil at axial
loading. For other load situations such as horizontal loading (direct shear-
ing) or uplifting (tensile stresses), shear strength can be signiicantly lower
than measured. Columns subjected to tensile stresses shall be avoided.
DSM columns and mass mixing structures are designed for ultimate limit
state (ULS) and serviceability limit state (SLS).
464 Ground improvement
Acol
a" (10.5)
Atot
where Acol = area of the column; Atot = total area, which can be calculated
from the effective diameter (De) according to column layout and spacing
between columns (s); Atot = πDe2 /4.
Soil characteristics such as the shear strength, settlement modulus, and
permeability of the improved soil volume are calculated based on the ratio
0.866s
s
s s
70
60
Undrained shear
50 strength in DSM and soil
40
30
Design shear
20 strength
10
0
0 25 50 75 100 125 150 175 200
Effective stress (kPa)
τfu τfd τfud τf,dimA τf,dimD
Figure 10.17 Critical shear strength due to in-situ stress situation in the stabilised soil
volume; the bold line is the calculated shear strength used in the stability analysis.
of improvement. The improved soil volume can be divided into three zones,
A, B and C, see Figure 10.17 (Álen et al., 2005a), which are:
A. Upper zone of 0.5–2 m, transition zone. In the top part of the col-
umns, the homogeneity and strength can vary considerably. Hence,
the column shall not be treated as a full-strength column. Spacing
between columns due to arching in the embankment ill needs to be
evaluated. Column spaces greater than 3 times the column diameter
should be used with caution.
B. Stabilised volume. Column and soil are assumed to have full
interaction.
C. Unimproved soil underneath the stabilised volume. Soft soil under-
neath the columns is considered according to basic soil mechanics.
For time-settlement analysis the drainage length has to be adjusted
due to the fact that DSM columns have higher permeability than
unimproved soil.
these situations full interaction between column and soil can be assumed.
When columns are installed in natural slopes, excavations, or embank-
ments with a very low factor of safety in unstabilised conditions where
full interaction between column and soil is uncertain, columns need to be
designed and checked in undrained, drained, and combined shear strength.
where
a = ratio of improvement, see Equation 10.5
τf,col = shear strength in a column
τf,soil = shear strength in unstabilised soil.
where
C u,col = UCS/2, (unconined compression strength).
Undrained shear strength greater than 150 kPa is not recommended for use
in the design guidelines.
where
τ fd ,col = c ´col + σ ´× tan(φ ´col ) (10.9)
β = 0 to 0.5
φ´col = 30–35 deg.
Combined analysis means that the drained shear strength in the columns
and undrained shear strength in unstabilised soil are used in calculations of
shear strength in the stabilised soil volume.
Combined shear strength is often the most critical factor in the stability
analysis for slopes and excavations, due to limited axial load on the col-
umns. In stability analysis the most critical shear strength in the stabilised
soil is due to the stress situation on the columns and the shape of the slip
surface (evaluation of columns in active, direct and passive shear zone).
Figure 10.17 shows an evaluation of the critical shear strength due to the
in-situ stress for the active shear zone and direct shear zone.
where:
q u,col = UCS (unconined compression strength) ~2*C u,col
1 + sin φ '´col
K P = Coeficient of passive earth pressure, K P =
σ = Initial total overburden pressure 1 − sin φ '´col
v0
msoil = Factor of stress increase into the unstabilised soil due to applied
weight from unit loads (e.g., embankment). The ratio of stress
increase msoil = 0 to 0.5. The stress increase depends on the load
distribution on the unstabilised soil
∆σv = Applied unit load on the columns (e.g., embankment)
ucol = Pore water pressure.
The ultimate bearing capacity increases with depths and the UCS in a
column.
Creep strength is a commonly used term in design of DSM columns. The
creep strength is a function of the expected homogeneity of the column
depending on the mixing work, the virgin soil properties and type of binder.
For instance, organic soils and peats are more dificult to mix to achieve
high homogeneity in the column. Creep strength of a column is estimated at
65%–90% of the ultimate bearing capacity.
The creep strength can be calculated as:
where:
mcreep = 0.8–0.9 (columns in clayey silt, silty clay and sandy clay)
mcreep = 0.7–0.8 (columns in clay)
mcreep = 0.65–0.7 (columns in organic clay, peat and contaminated
soils).
where:
Ecol = 50–300*C u,col
M soil = compression modulus of the unstabilised soil and depends on
the stress applied on the soil and the preconsolidation pressure
in the unstabilised soil between the columns.
h × σv
sMS = ∑ MMSl
(10.16)
where:
M MSl = 50–100*C u,MS
2 × cos(φ ´) 1 + sin(φ ´)
σ ´col = × c ´+ × σ ´h − σ ´v0 (10.17)
1 − sin(φ ´) 1 − sin(φ ´)
where:
σ'col = maximum increase of stress in a column
σ'h,0 = horizontal effective stress in-situ conditions
∆σ'h,soil = increased horizontal stress in unstabilised soil
∆σ'v,soil = increased vertical stress in unstabilised soil.
Stress distribution from the columns to the unstabilised soil has been
reported by Álen et al. (2005a). The investigation showed that the load distri-
bution from trial embankments on loating columns (columns not installed
to irm ground) was similar to load distributions in unstabilised soil. Álen et
al. (2005a) presented a modiied Boussinesq’s stress distribution with depth.
The authors also presented a load split model (see Figure 10.18) where part
of the total applied load is divided into two loads, q = q1 + q2. Load (q2) is
applied at top of the columns and load (q1) is transferred to the toe of the
columns. Stress distribution by depth is thereafter calculated for the two
cases. In applications with loating columns and large deposits of soft clay
(commonly the case in Sweden) this model has been successfully used.
−2 × c × t
U = 1 − exp 2 vh (10.19)
R × f(n)
where:
U = degree of consolidation
cvh = coeficient of consolidation in unstabilised soil with respect to lat-
eral drainage, normally assumed to be equal to 2*cvv
Dry soil mixing 471
q = q1 + q2
q2
A
1:X
1:X
B
q1
1:2
C 1:2
Figure 10.18 Conceptual zones, principle of load split model and stress distribution from
a stabilised soil volume.
When columns are installed at distance c between the centre in a square grid,
the inluence radius can be expressed as R = 0.56*c. If the columns are installed
in a triangular grid, the inluence radius can be expressed as R = 0.53*c.
n2 1 1 n2 − 1 1 k
f (n) = × ln(n) − 0 .75 + × 1 − 2
+ 2 × 2 × soil × L2D
n −1
2
n 2
4n n r kcol
(10.20)
where:
n = R/r
r = column radius
472 Ground improvement
Investigations in Finland and Japan show that the permeability in the col-
umns decreases with increasing cement content. The equation for consolida-
tion time shall be used as a qualiied guess due to the uncertainties of the
permeability in the columns. Long-term settlements and creep settlements
have been discussed in numerous publications; however, this area needs more
investigation together with studies of the increasing strength over time in
DSM. Therefore, creep settlements in DSM columns are left out of the design
today.
B
Section A-A
(d-5)
A
B (mm) d (mm)
400 20
500 15
A 600 15
d
φ 36–44 mm
φ 50 mm
Figure 10.19 Column penetration test (the lime column probe). (From Svenska
Geotekniska Förening (Swedish Geotechnical Society). (2000). Lime and lime-
cement columns. Guide for design, construction and control, Report 2. , Linköping,
Sweden (in Swedish).)
The vane is pressed down into the column with a penetration rate of 20
mm/sec and the push-down force is recorded. The method was developed
from the Iskymeter method from the late 1930s and the mid-1950s. The
Iskymeter, which was developed for penetration tests in very soft clays, was
calibrated with respect to vane tests and fall cone tests. A semi-empirical
relation was developed where the undrained shear strength τfu can be evalu-
ated according to Equation 10.21. In 1979 Boman presented a simpliied
equation to evaluate the undrained shear strength in a lime column.
The equation to determine the shear strength in soft soils using the
Iskymeter method:
1
0.06 × γ × h × 1 −
0.092 × P St
τ fu = + (10.21)
2 2
1 + S × A 1 + S
t t
where:
P = penetration force
γ = density of the soil
A = area of the probe
St = sensitivity of the soil.
F
τ fu = (10.22)
N×A
N is a bearing factor equal to 10 (empirical value) for a probe with the
area 100 cm 2 , according to the Swedish guideline SGF (2000). There is,
however, continued discussion about the bearing factor and, according to
EuroSoilStab, a bearing factor of 10 to 15 can be used.
The test method evaluates a mean value of the shear strength along the
column. The method is suitable for columns <10 m due to the risk of the
vane deviating out of the column. This deviation tendency can be overcome
by predrilling a small centre hole in the column. Columns with greater
shear strength than 300 kPa can in many cases be dificult to penetrate.
The test is regarded as a nondestructive method for embankments where
the tested column is surrounded by a great number of other columns and
support for the embankment is assured. However, for structural founda-
tion works, test columns should be used with reduced bearing capacity in
the inal construction.
For evaluation of the test result, the mantle friction along the probe shall be
taken into account. In recent years the method has been improved by attaching
a CPT (Cone Penetration Test) device to measure the penetration resistance
without the friction. In the CPT device an inclinometer has also been added for
verticality control (Forsgren and Ekström, 2002). A minimum of 5%–10% of
the total tested columns shall be taken in unstabilised soil in order to compare
the shear strength and to evaluate the mantle friction along the probe.
(a)
a
15–20 mm
a a-a
(b)
Figure 10.20 (a) Reverse column penetration test. (From Holmqvist, L. (1992). The lime
column method. Bygg and Teknik, 7–8:40–44, in Swedish.) (b) Picture of
installation of the probe. (Courtesy of LCM.)
mean value and standard deviation can be identiied. The shear strength in
a column can be evaluated according to Equation 10.23:
qc − σ v 0
τ fu = (10.23)
Nc
where:
qc = measured cone resistance
σv0 = total overburden stress
Nc = Bearing factor 10 to 25 (according to EuroSoilStab Nc = 10–13)
τ fu = N v × Mmax (10.24)
Dry soil mixing 477
where:
Nv = Vane factor (345)
M max = Maximum torque.
Extraction of the whole column (Figure 10.23) has been used in some
large projects and in research projects. Extraction is performed by a spe-
cial designed casing, pressed down around the column and extracted by a
mobile crane. This is an expensive test and seldom used.
Core sampling has frequently been used as a test method for wet mixing
columns. In Japan core sampling is a standard test method and the samples
are collected after 5 or 6 days. Typical sample equipment is a Denison sam-
pler, double core tube, and triple core tube. Diameters of the sample tubes
are 86–150 mm. For DSM columns, undisturbed core sampling is dificult
to perform because of the risk of cracks in the samples. It is recommended
that the samples be tested with consolidated-undrained triaxial tests.
MOSTAP sampling is a core sampling method and has been used in a
number of projects in the UK. The method uses standard CPT equipment
and consists of a cone and cutting shoe at the base of the sampling tube. The
sampling method is easy to use, and samples of 36–65 mm in diameter can
be obtained. The samples lengths are 1.20 m and are retained within a stock-
ing in a UPVC liner. The liner is sealed within airtight end caps. Samples are
478 Ground improvement
32
3
6
65
20
132
Figure 10.22 Finnish vane test. (From Halkola, H. (1983). In-situ investigation of deep
stabilized soil. Proceedings of the 8th European Conference on Soil Mechanics
and Foundation Engineering, May 23–26, 1983.)
preferably taken in fresh columns (soon after installation) and stored in labo-
ratory for hardening. After hardening the sample tube is split and laboratory
tests can be performed on the samples. This method has shown good results
especially for visual inspection as well as for chemical testing.
Soil/rock sounding and total sounding are common Swedish and
Norwegian methods. These methods are commonly used for predrilling
a centre hole in the columns before the column penetration tests are per-
formed. The penetration resistance can be roughly estimated by adding a
bearing capacity or a correlation factor to the results from column pen-
etration tests, which identiies the undrained shear strength. However, this
method alone is not reliable.
(1) Exposure of column head and survey of the column position and level.
(2) Documentation of the column head (e.g., photo documentation).
(3) Predrilling with a soil/rock sounding. During drilling, registration
of penetration force, rotation speed (if necessary), and torque. Spoil
water shall not be used.
(4) Execute column penetration test, with or without the CPT device.
(5) Taking short notes (e.g., if the probe tends to deviate out of the col-
umn) or other observations that could be of interest to the designer.
The test result is best presented graphically for each column as well as for
the penetration force of the predrilling. All the tests from one test session
Dry soil mixing 479
Dry soil mixing also referred to as the Nordic method was rarely used
outside the Nordic countries until the late 1990s. After this the number of
projects has signiicantly increased and today the method is well accepted
and used successfully in numerous countries around the world. Four case
histories from different countries are presented in this chapter.
DSM columns were selected to increase the stiffness of the soft soil in
order to reduce settlements and provide a new foundation for the access
road. DSM columns with diameters of 800 mm were selected. These
were formed in a rectangular grid with 1.1 m spacing, giving a replace-
ment ratio of 0.41. The selected binder was Cement CEM I with a dosage
rate of 200 kg/m3. The amount and type of binder to be used was based
upon evaluation of the soil characteristics from the site investigations
together with the geotechnical engineer’s local knowledge of soil mix-
ing. Soil samples from the site were collected for laboratory mixing tests
in order to verify the stabilisation effect. A pretest was conducted to
demonstrate the performance of the improvement. Column penetration
testing was carried out after 5–7 days and 14–16 days according to the
ield test scheme (Figures 10.25 and 10.26). The preselected binder and
amount of binder demonstrated good increase in shear strength, and the
design shear strength of 150 kPa (28 days’ strength) was demonstrated
within 7 days test.
Installation of production columns started after inalising the pretest,
which demonstrated the performance of the DSM columns, with binder
content of 100 kg/m column (200 kg/m3) and mixing energy of 350 BRN.
In total, some 7,500 columns were installed at an average depth of 7.8 m.
Testing was performed using CPT, column penetration tests (KPS tests)
and reverse column penetration tests (pull-out test, FOPS). The column
penetration tests showed the most reliable test results and were selected
as the main test method. Evaluation of column shear strength at 7–14
days testing showed a wide range of strength. The evaluated average shear
strength was 2–3 times design shear strength.
This case study demonstrates that DSM columns can be used in peaty
soils with high organic content and high moisture content, which report-
edly are dificult to improve.
Figure 10.25 Field test with column penetration tests. (Courtesy of Keller Géotechnique.)
Figure 10.26 Exposed columns for visual examination. (Courtesy of Keller Géotechnique.)
for supporting lood levees and loodwalls after Hurricane Katrina and
Hurricane Rita devastated parts of the southern United States.
The project Jewish Creek is located in Key Largo, Florida (Table
10.4). The existing road was extended by 12m in width and 8km in
length, see Figure 10.27. A typical mass-mixing setup is illustrated in
Figure 10.28. Field test methods are illustrated in Figures 10.29 and
10.30. As an alternative to traditional solutions, such as removing and
replacing the soft mangrove material, surcharge or installation of piles
with structural platform in-situ treatment with mass mixing (Figure
10.31) was selected.
Conversion between psi and kPa, 1psi ≈ 6.89 kPa
(a) (b)
Figure 10.28 Mass mixing equipment. (a) Mixing rig. (b) Blending station. (Courtesy of
Hayward Baker.)
(a)
(b) 20
15
Relative frequency (%)
10
0
0 50 100 150 200 250 300
Unconfined compressive strength (psi)
Figure 10.29 (a) Typical core samples. (b) Compression strength from core samples
taken. (Courtesy of Hayward Baker.)
Dry soil mixing 485
(a)
Date
(b)
12/26/05
1/16/06
1/23/06
1/30/06
2/13/06
2/20/06
2/27/06
1/2/06
1/9/06
2/6/06
3/6/06
0.00 30
0.05 25
0.10 20
Settlement (ft)
0.20 10
Location of the project is in the Göta Älv River Valley (see Figure 10.32).
The geological formation in the valley is characterized by large clay depos-
its with highly sensitive clays (quick clays) overlying bedrock. Slope stabil-
ity is a major issue along the Göta Älv River, and two major slip failures
with human loss have occurred in the area (the Surte failure 1950 and the
Göta failure 1957). In addition, there have been a large number of failures
resulting in material losses.
The soft clay deposits are stabilised by approximately 9 million linear
DSM columns (Figure 10.33). Columns are installed to increase stability,
reduce settlements, and prevent mitigation of ground vibrations connected
to high-speed trains. Other applications are foundations of structures such
as bridges (see Figures 10.14a, b and 10.15).
Before the project started (5–7 years), test embankments were installed
and monitored. Field and laboratory tests were performed in order to
determine binder combination, amount of binder, and mixing param-
eters for the total project before construction started. This is, however, an
unusual way of designing because all contractors are restricted to certain
parameters. In construction, pretesting is performed for each part of the
project. Pretesting of DSM columns is carried out in test areas to verify the
predesigned installation concept. Field testing is performed on two occa-
sions, 12–16 days and 28–34 days. No other time periods are allowed for
testing.
Dry soil mixing 487
Uddevalla
Railway
Highway 44
Trollhättan
Stenröset
Velanda
Torpa
E15
Upphärad
Alvängen
Alingsas
Nol
Kungälv
Nödinge
Bohus
Surte
Agnesberg
E20
Marieholm
Olskroken
Göteborg 40
Figure 10.32 Site map of the project. (From Banaväg in Väst website, http://www.
traikverket.se/banavag.)
(a) (b)
PEAB Förprovning 12-16 dygn
Kontrollobjekt 7
Sammanfattande diagram 30 kg/m, 20 mm/r
Sektion 000+000 Tvärmatt: ±Xm
Skjuvhällfasthet [kPa]
0 50 100 150 200 250 300 350 400 450
0 Cu förväntad
undre fraktil 15%
Cu förväntat
1 medel
Cu, medel
Cu, undre fraktil 15%
2 520C105
520C109
3 520C113
520C117
4 520C121
Djup under arbetsysta [m]
524C54
5 524C106
524C107
524C111
6
524C114
524C115
7
524C118
524C119
8
524C122
524C123
9
10
11
12
Figure 10.33 (a) Testing of DSM columns. (b) Printout of KPS tests. (Courtesy of dmixab.)
488 Ground improvement
14.9 m
New 2.5 m 2.5 m Rehab.
track track
Working
Embankment platform
22.9 m
Figure 10.34 Typical cross-section of the railway embankment and treated zone. (From
Raju, V. R., Abdullah, A. and Arulrajah, A. (2003). Ground treatment using
dry deep soil mixing for a railway embankment in Malaysia, Proceedings
of the 2nd International Conference on Advances in Soft Soil Engineering and
Technology, July 2–4, 2003, Putrajaya, Malaysia.)
(a) (b)
0 2 4 6 8
0
qs [MPa]
2
10
12
z [m]
Figure 10.35 (a) Typical CPT log. (b) The LCM machine at work. (From Raju, V. R.,
Abdullah, A. and Arulrajah, A. (2003). Ground treatment using dry deep
soil mixing for a railway embankment in Malaysia, Proceedings of the 2nd
International Conference on Advances in Soft Soil Engineering and Technology,
July 2–4, 2003, Putrajaya, Malaysia.)
Dry soil mixing 489
Kentledge blocks
6
s [mm]
8
Load cycle-1 Load cycle-2
Figure 10.36 Control static loading test over an area of 3 × 3 m, 4 columns. (From
Raju, V. R., Abdullah, A. and Arulrajah, A. (2003). Ground treatment using dry
deep soil mixing for a railway embankment in Malaysia, Proceedings of the 2nd
International Conference on Advances in Soft Soil Engineering and Technology, July
2–4, 2003, Putrajaya, Malaysia.)
490 Ground improvement
REFERENCES
Boman, P. (1979). Quality Control of Lime Column. Part 2: Results from Investigations
at Sollentunaholm. Stockholm, Sweden: Royal Institute of Technology (in
Swedish).
Bredenberg, H. (1999). Keynote lecture: equipment for deep soil mixing with the dry
jet mix method. Proceedings of the International Conference on Dry Methods for
Deep Soil Stabilization, October 13–15, 1999, Stockholm, Sweden, pp. 323–331.
Bredenberg, H., Holm, G., and Broms, B., eds. (1999). Dry Mix Methods for
Deep Soil Stabilization: Proceedings of the International Conference on
Dry Methods for Deep Soil Stabilization, October 13–15, 1999, Stockholm,
Sweden.
Broms, B. (1984). Stabilization of Soil with Lime Columns – Design Handbook, 3rd
ed. Kungsbacka, Sweden: Lime Column Method AB.
Broms, B. (1999). Keynote lecture: Design of lime, lime/cement and cement columns.
Proceedings of the International Conference on Dry Methods for Deep Soil
Stabilization, October 13–15, 1999, Stockholm, Sweden, pp. 125–154.
Dahlström, M. and Eriksson, H. (2005). Mass stabilisation in Smista Allé (2002)
and Moraberg (2003) by cell and block stabilisation methods. Proceedings
from the International Conference on Deep Mixing Best Practice and Recent
Advances, May 23–25, 2005, Stockholm, Sweden, pp. 425–429.
Dahlström, M. and Wiberg, D. (2012). Dry soil mixing and vibro replacement in com-
bination for a high embankment. Proceedings from the International Conference
on Grouting and Deep Mixing, February 16–18, 2012, New Orleans, Louisiana,
United States.
EuroSoilStab. (2002). Development of Design and Construction Methods to Stabilise
Soft Organic Soils: Design Guide Soft Soil Stabilisation, CT97-035I, European
Commission Project BE 96-3177.
EN14679:2005 (2005). European Standard, Execution of Special Geotechnical
Works – Deep Mixing. Publisher information
Filz, G., Adams, T., Navin, M., and Tempelton, A.E. (2012) Keynote lecture: Design
of deep mixing for support of levees and loodwalls. Proceedings from the
International Conference on Grouting and Deep Mixing, February 16–18,
2012, New Orleans, Louisiana, United States.
Forsgren, I. and Ekström, J. (2002–2012). Personal communication.
Forsman, J., Maijala, A., and Järvinen, K. (2008). Case stories, harbours – mass
stabilisation of contaminated dredging mud in Sörnäinen, Helsinki. Proceedings
of the International Mass Stabilisation Conference 2008, October 8–10, 2008,
Lahti, Finland.
Halkola, H. (1983). In-situ investigation of deep stabilized soil. Proceedings of the
8th European Conference on Soil Mechanics and Foundation Engineering,
May 23–26, 1983, Helsinki, Finland.
Halkola, H. (1999). Keynote lecture: quality control for dry mix method. Proceedings
of the International Conference on Dry Methods for Deep Soil Stabilization,
October 13–15, 1999, Stockholm, Sweden, pp. 285–294.
Hansbo, S. (1979). Consolidation of clay by bandshaped prefabricated drains,
Ground Engineering 12(5): 21–25.
Hayashi, H., Nishikawa, J., Ohishi, K. and Terashi, M. (2003). Field Observation
of Long-Term Strength of Cement Treated Soil, ASCE Geotechnical Special
Publication No. 120, pp. 598–609.
492 Ground improvement
Hebib, S. and Farrell, E.R. (2003). Some experience on the stabilisation or Irish
peats, Canadian Geotechnical Journal 40:107–120.
Holm, G. (1999). Keynote lecture: applications of dry mix methods for deep soil
stabilization. Proceedings of the International Conference on Dry Methods for
Deep Soil Stabilization, October 13–15, 1999, Stockholm, Sweden, pp. 3–14.
Holm, G. (2002). Nordic dry deep mixing method – execution procedure, Proceedings
of the Deep Mixing Workshop 2002, Port and Airport Research Institute &
Coastal Development Institute of Technology, Tokyo, Japan.
Holm, G., Andréasson, B., Bengtsson, P-E., Bodare, A., and Eriksson, H. (2002).
Mitigation of Track and Ground Vibrations by High Speed Trains at Ledsgård,
Sweden, Report No. 10. Linköping, Sweden: Swedish Deep Stabilization
Research Centre.
Holmqvist, L. (1992). The lime column method. Bygg and Teknik, 7–8:40–44 (in
Swedish).
Horpibulsuk, S., Miura, N. and Nagara, T. (2003). Assesment of strength develop-
ment in cement-admixed high water content clay with Abrams’ law as a basis.
Géotechnique 53(4): pp. 439–444.
Janz, M. and Johansson, S.E. (2002). The function of different binding agents in deep
stabilization, Report No. 9. Linköping, Sweden: Swedish Deep Stabilization
Research Centre.
Jelisic, N. and Leppännen, M. (1999). Mass stabilization of peat in road and railroad
construction. Proceedings of the International Conference on Dry Methods for
Deep Soil Stabilization, October 13–15, 1999, Stockholm, Sweden, pp. 59–64.
Jelisic, N. and Leppännen, M. (2005). Remediation of contaminated land
of Sörnäinen, Helsinki, by using mass stabilization. Proceedings of the
International Conference on Deep Mixing Best Practice and Recent Advances,
May 23–25, 2005, Stockholm, Sweden, pp. 353–356.
Kitazume, M., Tabata, T., Ishiyama, S. and Ishikawa, Y. (1996a). Model tests on
failure pattern of cement treated retaining wall, In: Yonekura R., Terashi M.,
and Shibazaki M. (eds.) Grouting and Deep Mixing: Proceedings of the 2nd
International Conference on Ground Improvement Geosystems, May 14–17,
1996, Tokyo, Japan, pp. 509–514.
Kivilö, M. and Broms, B. (1999). Mechanical behavior and shear resistance of lime/
cement columns. Proceedings of the International Conference on Dry Methods for
Deep Soil Stabilization, October 13–15, 1999, Stockholm, Sweden, pp. 193–200.
Lawson, C.H, Spink, T.W, Crawshaw, J.S. and Essler R.D. (2005). Veriication
of dry soil mixing at Port of Tilbury, UK. Proceedings of the International
Conference on Deep Mixing Best Practice and Recent Advances, May 23–25,
2005, Stockholm, Sweden, pp. 453–462.
Larsson, S. (1999). The mixing process at the dry jet mixing method. Proceedings
of the International Conference on Dry Methods for Deep Soil Stabilization,
October 13–15, 1999, Stockholm, Sweden, pp. 339–346.
Larsson, S. (2003). Mixing Process for Ground Improvement by Deep Mixing,
Doctoral Thesis, Royal Institute of Technology, Stockholm, Sweden.
Larsson, S. (2005). Keynote lecture: state of practice report – execution, monitor-
ing and quality control. Proceedings of the International Conference on Deep
Mixing Best Practice and Recent Advances, May 23–25, 2005, Stockholm,
Sweden, pp. 732–785.
Dry soil mixing 493
Rogers, C.D.F., Glendinning, S. and Holt, C.C. (2000a). Slope stabilization using
lime piles – a case study, Ground Improvement 4(4):165–176.
Rogers, C.D.F., Glendinning, S. and Troughton, V.M. (2000b). The use of additives
to enhance the performance of lime piles. Proceedings of the 4th International
Conference on Ground Improvement Geosystems, June 7–9, 2000, Helsinki,
Finland, pp. 127–134.
Svenska Geotekniska Förening (Swedish Geotechnical Society). (2000). Lime and
lime cement columns. Guide for design, construction and control, Report 2,
Linköping, Sweden (in Swedish).
Terashi, M. (2003). The State of Practice in Deep Mixing Methods, ASCE
Geotechnical Special Publication No. 120, pp. 25–49.
Terashi, M. (2005). Keynote lecture: design of deep mixing in infrastructure applica-
tions. Proceedings of the International Conference on Deep Mixing Best Practice
and Recent Advances, May 23–25, 2005, Stockholm, Sweden, pp. K25–K45.
Timoney, M.J., McCabe B.A., and Bell, A.L. (2012). Experiences of dry soil mixing in
highly organic soils, Proceedings of the Institution of Civil Engineers – Ground
Improvement 165(1):3–14.
Yoshizawa, H., Okumura, R., Hosya, Y., Sumi, M. and Yamada, T. (1997). Japanese
Geotechnical Society Technical Committee Report: factors affecting the qual-
ity of treated soil during execution of DMM. In: Yonekura R., Terashi M.,
and Shibazaki M. (eds.) Grouting and Deep Mixing: Proceedings of the 2nd
International Conference on Ground Improvement Geosystems, May 14–17,
1996, Tokyo, Japan, pp. 931–937.