PEMBANGUNAN TEPI JALAN-scribd

The document discusses guidelines for roadside development applications in Malaysia. It was issued by the Public Works Department's Road Maintenance Branch Small Committee through the Main Committee. It outlines the application process which involves obtaining approval at the state and district levels, including land surveys, development plans, and ensuring utilities are properly arranged. Safety and technical reports are also required. The application is then reviewed and a decision is made within 14 working days.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views15 pages

PEMBANGUNAN TEPI JALAN-scribd

The document discusses guidelines for roadside development applications in Malaysia. It was issued by the Public Works Department's Road Maintenance Branch Small Committee through the Main Committee. It outlines the application process which involves obtaining approval at the state and district levels, including land surveys, development plans, and ensuring utilities are properly arranged. Safety and technical reports are also required. The application is then reviewed and a decision is made within 14 working days.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

PEMBANGUNAN TEPI JALAN

Arahan Teknik Jalan (ATJ):


Garis Panduan Permohonan
Pembangunan Tepi Jalan
❑ Diterbitkan oleh Jawatankuasa
Kecil Cawangan Senggara
Fasiliti Jalan melalui
Jawatankuasa Induk
Cawangan Jalan
❑ Bermula April 2019 dan draf
akhir dibentangkan kepada
Mesyuarat Pengurusan
Tertinggi pada 20 Januari 2022

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
TARIKH
KUATKUASA
❑ SAKPKR 14/22
❑ 25 Ogos 2022

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
PUNCA KUASA
❑ Akta Pengangkutan Jalan 1987
(AKTA 333)
➢ Seksyen 85 – Pembinaan
Akses, dan Parit dan
Penyusunan Pemasangan
Utiliti Awam Ke Jalan – Jalan
Yang Ada.
❑ Akta Pewakilan Kuasa 1956
(AKTA 358)
➢ Seksyen 5 – Pewakilan Kuasa

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
AKTA BERKAITAN
Akta Perancangan Bandar dan Desa
1976 (AKTA 172)
❑ Seksyen 19 – Larangan terhadap
pemajuan tanpa kebenaran
merancang
❑ Seksyen 20A – Kewajipan untuk
berunding
❑ Seksyen 21 – Permohonan untuk
Kebenaran Merancang

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
PERINGKAT KELULUSAN (JKR)
PERINGKAT NEGERI PERINGKAT DAERAH
PERMIT

KEBENARAN
MERANCANG (KM)

PELAN KERJA
TANAH (KT)
Input:
Permohonan
daripada pemaju
PELAN JALAN NOTIS MULA KERJA
DAN PARIT (J&P) (NMK)

PENYUSUNAN Penyenggaraan
UTILITI jalan dilaksanakan PERAKUAN SIAP
oleh Pemaju DAN PEMATUHAN

Nota: SIJIL SIAP BAIKI


Mengikut skala KECACATAN
pembangunan

Output:
Penyerahan
kepada KKR/JKR

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
POLISI

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
PROSEDUR
NO CARTA ALIR TINDAKAN TEMPOH BORANG

ATJ3/85 [PTJ]Pin.2020 (01)


M

PEMBANGUNAN TEPI
– Lampiran 1

ATJ3/85 [PTJ]Pin.2020 (02)


– Lampiran 2
Terima permohonan secara rasmi* PP/PSP/SP
ATJ3/85 [PTJ]Pin.2020 (03)

JALAN
– Lampiran 3
Urus setia OSC,
Serahan dokumen oleh
Pihak Berkuasa Mengikut jenis permohonan
urus setia OSC
Tempatan

JABATAN KERJA RAYA

1. Objektif
1 Daftar dan rekod permohonan Pembantu Tadbir 2 hari

2. Skop
TIDAK
2 Semak dan sedia
KU/JJ/STA/TA 8 hari

3. Rujukan
Laporan yang pengesyoran
dikemukakan tidak
menepati kriteria
semakan teknikal
YA

4. Definisi 3 Mesyuarat Pembangunan PKRN/KBJ/KU/


1 hari
Tepi Jalan JD/JJ/STA/TA

5. Singkatan 4 Keputusan permohonan PKRN/JD** 2 hari

6. Proses Kerja dan Tanggungjawab 5 Hantar ulasan teknikal/keputusan


permohonan kepada OSC
Pembantu Tadbir 1 hari

• Carta alir proses kelulusan T 14 hari

permohonan Kebenaran Merancang


(KM)/ Tukar Syarat/ Pecah Sempadan/ *INPUT
· Pelan Ukur Tanah
PETUNJUK

PKRN Pengarah Kerja Raya Negeri

Pengeluaran Hasil Bumi ·


·
·
Pelan Tataatur
Laporan Cadangan Pemajuan (LCP)
Reka bentuk Awalan/Konsep
KBJ Ketua Bahagian Jalan

· Laporan TIA* JD Jurutera Daerah/Jajahan


· Laporan RSA Peringkat 1 dan/atau Peringkat 2*

7. Rekod · Laporan Geoteknik/Kejuruteraan Cerun*


*Sekiranya berkaitan
KU

JJ
Ketua Unit

Jurutera Jalan/Awam

STA Pen. Jurutera Kanan

8. Lampiran M Mula T Tamat


TA Pen. Jurutera

**Mengikut surat wakil kuasa

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
PROSEDUR
NO CARTA ALIR TINDAKAN TEMPOH BORANG

M ATJ3/85 [PTJ]Pin.2020 (04)

PEMBANGUNAN TEPI
– Lampiran 4

ATJ3/85 [PTJ]Pin.2020 (05)


Terima permohonan secara rasmi* PP/PSP/SP – Lampiran 5

JALAN
Mengikut peringkat
Urus setia OSC, permohonan
Serahan dokumen oleh
Pihak Berkuasa
urus setia OSC
Tempatan

JABATAN KERJA RAYA

1. Objektif 1 Daftar dan rekod permohonan Pembantu Tadbir 2 hari

2. Skop 2 Semak status kelulusan KM dan


keperluan teknikal
KU/JJ/STA/TA 2 hari

3. Rujukan 3
TIDAK Semak dan sedia
pengesyoran
KU/JJ/STA/TA 3 hari
Laporan yang
dikemukakan tidak

4. Definisi menepati kriteria


semakan teknikal YA

5. Singkatan
Mesyuarat Pembangunan PKRN/KBJ/KU/
4 4 hari
Tepi Jalan JD/JJ/STA/TA

5 Keputusan permohonan (Deposit PKRN/JD** 2 hari

6. Proses Kerja dan Tanggungjawab


Keselamatan – jika berkaitan) JJ/STA/TA

6 Hantar ulasan teknikal/keputusan Pembantu Tadbir 1 hari

• Carta alir proses kelulusan


permohonan kepada OSC

permohonan Kerja Tanah /Jalan dan T 14 hari

Parit *INPUT PETUNJUK


· Laporan Penyiasatan Tanah (S.I Report) PKRN Pengarah Kerja Raya Negeri

7. Rekod
· Reka bentuk Terperinci
· Pelan Pemetaan Utiliti & Pengalihan KBJ Ketua Bahagian Jalan
· Laporan RSA Peringkat 3*
· Laporan ICE* JD Jurutera Daerah/Jajahan
· Kajian semula reka bentuk/Verifikasi Reka bentuk/
Validasi Reka bentuk* KU Ketua Unit

8. Lampiran
· Laporan Geoteknik/ Kejuruteraan Cerun*
*Sekiranya berkaitan JJ Jurutera Jalan/Awam

STA Pen. Jurutera Kanan

M Mula T Tamat TA Pen. Jurutera

**Mengikut surat wakil kuasa

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
PROSEDUR PEMBINAAN
NO CARTA ALIR TINDAKAN TEMPOH BORANG

DAN PENYENGGARAAN 1 Terima permohonan secara rasmi* PSP/SP ATJ3/85 [PPJ]Pin.2020 (01)
– Lampiran 1

JALAN 2 Daftar dan rekod permohonan Pembantu Tadbir 1 hari

1. Objektif 3 Semak status kelulusan* STA/TA 4 hari

2. Skop 4
Dokumen
Lengkap?
TIDAK

3. Rujukan YA
KU/JJ/STA/TA 5 hari

5 Permohonan Pemeriksaan Tapak ATJ3/85 [PPJ]Pin.2020 (02)

4. Definisi
PSP/SP
(RFI) – Lampiran 2

5. Singkatan 6
TIDAK
Pemeriksaan
Tapak
JJ/STA/TA 4 hari ATJ3/85 [PPJ]Pin.2020
(02A) – Lampiran 2A

6. Proses Kerja dan Tanggungjawab YA

ATJ3/85 [PPJ]Pin.2020 (03)


7 Serahan Notis Mula Kerja JJ/STA/TA 1 hari

• Carta alir proses Notis Mula Kerja


– Lampiran 3

Penyenggaraan Rutin Jalan ATJ3/85 [PPJ]Pin.2020 (04)


8 PP/PSP/SP

7. Rekod
dilaksanakan oleh PP* – Lampiran 4

14 hari

8. Lampiran *INPUT
PETUNJUK
KU Ketua Unit

· Kelulusan Kebenaran Merancang (KM) JJ Jurutera Jalan/Awam


· Kelulusan Pelan Kerja Tanah (KT)
· Kelulusan Pelan Jalan dan Parit (J&P) STA Pen. Jurutera Kanan
· Laporan RSA Peringkat 4 Bahagian 1**
· Deposit Keselamatan (Bon Jaminan Bank)** TA Pen. Jurutera
· Mengikut skala pembangunan**
**Sekiranya berkaitan PP Pemilik Projek

PSP Principal Submitting Person


M Mula T Tamat
SP Submitting Person

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
PROSEDUR PEMBINAAN
NO CARTA ALIR TINDAKAN TEMPOH BORANG

DAN PENYENGGARAAN 1 Terima permohonan secara rasmi* PSP/SP ATJ3/85 [PPJ]Pin.2020 (05)

JALAN
– Lampiran 5

2 Daftar dan rekod permohonan Pembantu Tadbir 1 hari

1. Objektif
3 Lawatan tapak dan ATJ3/85 [PPJ]Pin.2020

2. Skop
pengesyoran JJ/STA/TA 15 hari
TIDAK (05A) – Lampiran 5A

YA

3. Rujukan 4 Mesyuarat Pembangunan Tepi


JD/KBJ/KU/JJ/STA/TA 8 hari
Jalan (sekiranya terdapat
keperluan)

4. Definisi ATJ3/85 [PPJ]Pin.2020 (06)


5 Pengesahan teknikal CCC KBJ/JD 5 hari
– Lampiran 6

5. Singkatan 6 Hantar pengesahan teknikal CCC 1 hari


Pembantu Tadbir
kepada urus setia OSC dan SP/PSP

6. Proses Kerja dan Tanggungjawab Penyenggaraan Rutin Jalan


7 PP/PSP/SP

• Carta alir proses Perakuan Siap dan


dilaksanakan oleh PP*

Pematuhan (CCC) T 30 hari

7. Rekod *INPUT
· Permohonan dikemukakan sekurang-kurangnya dua (2)
PETUNJUK
KU Ketua Unit
bulan sebelum tarikh CCC

8. Lampiran
· Laporan RSA Peringkat 4 Bahagian 3** JJ Jurutera Jalan/Awam
· Laporan Kecacatan/Kerosakan
· Log Aduan STA Pen. Jurutera Kanan
· Mengikut skala pembangunan**
**Sekiranya berkaitan TA Pen. Jurutera

PP Pemilik Projek
M Mula T Tamat
PSP Principal Submitting Person

SP Submitting Person

SKhadijah@TJ-Ogos22
[email protected]
PEMBANGUNAN TEPI JALAN
NO CARTA ALIR TINDAKAN TEMPOH BORANG

PROSEDUR PENERIMAAN
· ATJ3/85 [PP]Pin.2020
(01) – Lampiran 1
M · ATJ3/85 [PP]Pin.2020
(02) – Lampiran 2

TANGGUNGJAWAB OPERASI
· ATJ3/85 [PP]Pin.2020
(03) – Lampiran 3
1 Terima permohonan secara rasmi* PSP/SP · ATJ3/85 [PP]Pin.2020
(04) – Lampiran 4

DAN PENYENGGARAAN ASET


· ATJ3/85 [PP]Pin.2020
(05) – Lampiran 5

2 Daftar dan rekod permohonan Pembantu Tadbir 1 hari

1. Objektif
3 Audit Penerimaan dan ATJ3/85 [PP]Pin.2020

2. Skop
pengesyoran JJ/STA/TA 15 hari
TIDAK (05A) – Lampiran 5A

YA

3. Rujukan 4 Mesyuarat Pembangunan Tepi


JD/KBJ/KU/JJ/STA/TA 8 hari
Jalan (sekiranya terdapat
keperluan)

4. Definisi ATJ3/85 [PP]Pin.2020 (06)


5 Pengesahan CMGD KBJ/JD 5 hari
– Lampiran 6

5. Singkatan 6 Hantar pengesahan CMGD kepada 1 hari


Pembantu Tadbir
urus setia OSC dan SP/PSP

6. Proses Kerja dan Tanggungjawab


7 Serahan kepada KKR/JKR PP/PSP/SP

• Carta alir proses Penyerahan dan


Pengambilalihan Jalan T 30 hari

7. Lampiran *INPUT
· Permohonan dikemukakan sekurang-kurangnya tiga (3)
PETUNJUK
KU Ketua Unit
bulan selepas tarikh CCC
· Laporan RSA Peringkat 5** JJ Jurutera Jalan/Awam
· Laporan Kecacatan/Kerosakan
· Log Aduan STA Pen. Jurutera Kanan
· Mengikut skala pembangunan**
**Sekiranya berkaitan TA Pen. Jurutera

PP Pemilik Projek
M Mula T Tamat
PSP Principal Submitting Person

SP Submitting Person

SKhadijah@TJ-Ogos22