Construction Method Statement
Construction Method Statement
Wind Farm
May 2020
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 1 of 66
This document contains proprietary information belonging to Seagreen Wind Energy Ltd /or affiliated companies and shall be used only for the
purpose for which it was supplied. It shall not be copied, reproduced, disclosed or otherwise used, nor shall such information be furnished in whole
or in part to third parties, except in accordance with the terms of any agreement under which it was supplied or with the prior consent of Seagreen
Wind Energy Ltd and shall be returned upon request. © Copyright of Seagreen Wind Energy Ltd 2020
LF000009-CST-OF-MST-
002
Rev: 02
Page 2 of 66
Table of Contents
Consent Plan Overview ............................................................................................................................... 4
1. Introduction ............................................................................................................................................... 7
2. Project Background and Consents ............................................................................................................. 7
2.1 Project Overview ............................................................................................................................ 7
2.2 Consent and Licence Requirements............................................................................................... 9
2.3 Linkages with other consent plans and Consent Conditions .......................................................10
2.4 Updates and Amendments ..........................................................................................................13
3. Scope and Objectives of the OTA CMS .................................................................................................... 13
3.1 Scope and Objectives ...................................................................................................................13
4. Roles and responsibilities ........................................................................................................................ 14
4.1 Overview ......................................................................................................................................14
5. Seagreen Construction Management Framework .................................................................................. 18
5.1 Overview ......................................................................................................................................18
5.2 Industry Guidance ........................................................................................................................18
5.3 Construction (Design and Management) Regulations 2015 (CDM regulations)..........................20
5.4 Environmental management .......................................................................................................21
5.5 Training and Competence ............................................................................................................21
5.6 Contractor and sub-contractor obligations .................................................................................21
6. Construction procedures, mitigation and good working practices ......................................................... 22
6.1 Overview ......................................................................................................................................22
6.2 Mitigation and Good Working Practices ......................................................................................23
6.3 Construction Ports and Marine Coordination Centre ..................................................................24
6.4 Stage 1: Landfall installation up to MHWS ..................................................................................24
6.5 Stage 2: Subtidal seabed preparation ..........................................................................................32
6.6 Stage 3: OSP jacket foundation substructure assembly and installation ....................................33
6.7 Stage 4: OSP topside Installation .................................................................................................37
6.8 Stage 5: OSP interconnection cable installation ..........................................................................40
6.9 Stage 6: Subtidal export cable installation...................................................................................43
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 3 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 4 of 66
Purpose of the Offshore Transmission Asset (OTA) Construction Method Statement (CMS)
This Offshore Transmission Asset (OTA) Construction Method Statement (CMS) is submitted (i) by
Seagreen Wind Energy Limited on behalf of Seagreen Alpha Wind Energy Limited (SAWEL) and Seagreen
Bravo Wind Energy Limited (SBWEL) to address the specific requirements of the relevant conditions
attached to the OTA Marine Licence granted by the Scottish Ministers under the Marine (Scotland) Act
2010 and the Marine and Coastal Access Act 2009 on 10 October 2014, as amended by the revised
marine licence granted by the Scottish Ministers on 6 March 2019 (reference 04678/19/0) in respect of
the Seagreen Offshore Transmission Assets (OTA) associated with the Seagreen Alpha and Seagreen
Bravo Wind Farms (OWFs) (as varied, the OTA Marine Licence); and (ii) by Seagreen Wind Energy
Limited to address the specific requirements of the relevant conditions attached to the Marine Licence
granted by the Scottish Ministers under the Marine (Scotland) Act 2010 on 21 November 2019
(reference 07050/19/0) in respect of the Alternative Landfall Cable Installation Methodology
(Alternative Landfall Cable Installation Methodology Marine Licence).
The overall aims and objectives of the OTA CMS are to set out the construction procedures and good
working practices for the installation of the Seagreen OTA infrastructure. The OTA CMS demonstrates
that the construction procedures to be employed align with those set out within the Environmental
Statement (ES), ES Addendum and Environmental Report (ER) for the Alternative Landfall Cable
Installation Methodology, and that construction related mitigation measures detailed within the ES, ES
Addendum and ER will be applied during installation.
All Seagreen Contractors (including their Sub-Contractors) involved in the Seagreen OTA Project are
required to comply with this OTA CMS through conditions of contract.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 5 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 6 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 7 of 66
1. Introduction
This Offshore Transmission Asset (OTA) Construction Method Statement (CMS) is submitted to address the
specific requirements of the relevant conditions attached to the OTA Marine Licence granted by the Scottish
Ministers under the Marine (Scotland) Act 2010 and the Marine and Coastal Access Act 2009 on 10 October
2014, as amended by the revised marine licence granted by the Scottish Ministers on 6 March 2019
(reference 04678/19/0) in respect of the Seagreen Offshore Transmission Assets (OTA) associated with the
Seagreen Alpha and Seagreen Bravo Wind Farms (OWFs) (as varied, the OTA Marine Licence); and to address
the specific requirements of the relevant conditions attached to the Marine Licence granted by the Scottish
Ministers under the Marine (Scotland) Act 2010 on 21 November 2019 (subsequently amended on 24
February 2020) (reference 07050/20/0) in respect of the Alternative Landfall Cable Installation Methodology
(Alternative Landfall Cable Installation Methodology Marine Licence).
The overall aims and objectives of the OTA CMS are to set out the construction procedures and good
working practices for the installation of the Seagreen OTA infrastructure. The OTA CMS demonstrates that
the construction procedures to be employed align with those set out within the Environmental Statement
(ES), ES Addendum and Environmental Report (ER) for the Alternative Landfall Cable Installation
Methodology, and that construction related mitigation measures detailed within the ES, ES Addendum and
ER will be applied during installation.
A separate CMS (LF000009-CST-OF-MST-0001) has been prepared for the Seagreen OWF infrastructure.
LF000009-CST-OF-MST-
002
Rev: 02
Page 8 of 66
− Circa 55km of inter-array cables to connect strings of WTGs on piled foundations together
and to connect these WTG to the OSP; and
− Circa 3km of OSP interconnection cable to connect the two OSPs.
− Inter-array cables will be buried where possible and where burial is not possible cable
protection will be provided
• Three subsea export cables, totalling circa 190 km in length, to transmit electricity from the primary
OSP to the landfall at Carnoustie and connecting to the onshore export cables for transmission to the
onshore substation and connection to the National Grid network. The three subsea export cables will
be approximately 63.2 km, 63.2 km and 63.4 km in length respectively. Export cables will be buried
where possible and where burial is not possible cable protection will be provided.
LF000009-CST-OF-MST-
002
Rev: 02
Page 9 of 66
OTA Condition The Licensee must, no later than 6 months prior to the • The submission of the
Marine 3.2.2.4 Commencement of the Works submit a CMS, in writing, OTA CMS document
Licence to the Licensing Authority for their written approval satisfies the condition
(Licence
04678/19/ Such approval may only be granted following consultation • Consultation will be
0) by the Licensing Authority with the Joint Nature carried out by MS-LOT
Conservation Committee (JNCC), Scottish Natural as part of the approval
Heritage (SNH), the Scottish Environment Protection process
Agency (SEPA), the Maritime and Coastguard Agency
(MCA), the Northern Lighthouse Board (NLB), Angus
Council and any such other advisors or organisations as
may be required at the discretion of the Licensing
Authority.
The CMS must set out the construction procedures and • Section 5 - Seagreen
good working practices for constructing the Works. Construction
Management
Framework
• Section 6 -
Construction
procedures, mitigation
and good working
practices
The CMS must also include details of the roles and • Section 4 - Roles and
responsibilities, chain of command and contact details of responsibilities
company personnel, any contractors or sub-contractors • Appendix E – Pro
involved during the construction of the Works. Forma and contact
details
LF000009-CST-OF-MST-
002
Rev: 02
Page 10 of 66
• Appendix C -
Compliance with the
ES parameters and
processes
• Appendix D - Summary
of mitigation
commitments
Alternative 3.1.1 The Licensee must ensure that, where the Works • See Section 2.3 -
Landfall authorised by the licence are carried on as an alternative Linkages with other
Cable to nearshore cable laying operations under marine licence consent plans and
Installation number 04678/14/0, that the works authorised by the Consent Conditions
Marine licence are appropriately covered in the plans submitted • Section 5 - Seagreen
Licence under marine licence number 04678/14/0. Such plans are Construction
(Licence PEMP, EMP, DP, CoP, CMS, VMP, NSP, CaP, OMP, LMP Management
07050/19/ and PS, as required by conditions 3.2.1.1, 3.2.1.2, 3.2.1.7, Framework
0) 3.2.2.3, 3.2.2.4, 3.2.2.8, 3.2.2.9, 3.2.2.10, 3.2.3.2, 3.2.2.14, • Section 6 -
and 3.2.2.5 of marine licence number 04678/19/0. Construction
procedures, mitigation
and good working
practices
• Appendix D - Summary
of mitigation
commitments
LF000009-CST-OF-MST-
002
Rev: 02
Page 11 of 66
Reference Consent (condition in Linkage with the OTA CMS Cross-reference in this OTA
(consent plan parenthesis) CMS
title)
Environmental Marine Licence The EMP provides the overarching • Section 4 - Roles and
Management 04678/19/0 (3.2.1.2) framework for environmental responsibilities
Plan (EMP) management during the construction and • Section 6 - Construction
operational phases of the Seagreen OTA procedures, mitigation
Project. Environmental management and good working
measures have been integrated into the practices
construction procedures set out within • Section 9 - Compliance
this OTA CMS, with cross-reference to the with the ES, ES
EMP. Addendum and ER
• Appendix C -
Compliance with the ES
parameters and
processes
• Appendix D - Summary
of mitigation
commitments
Vessel Marine Licence The VMP sets out the number, types and • Section 6.3 -
Management 04678/19/0 (3.2.2.8) specification of vessels required during Construction Ports and
Plan (VMP) construction and operation, including Marine Coordination
vessel management procedures and Centre
vessel coordination, and location of ports • Section 7 - Compliance
and vessel transit corridors. with the ES, ES
Addendum and ER
Navigational Marine Licence The NSP addresses navigational safety • Section 6 - Construction
Safety Plan 04678/19/0 (3.2.2.9) measures, construction exclusion zones, procedures, mitigation
(NSP) Notice(s) to Mariners and Radio and good working
Navigation Warnings, anchoring areas, practices
temporary construction lighting and
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 12 of 66
Reference Consent (condition in Linkage with the OTA CMS Cross-reference in this OTA
(consent plan parenthesis) CMS
title)
Piling Strategy Marine Licence The PS is required in the event that pile • Section 6.6 - Stage 3:
(PS) 04678/19/0 (3.2.2.5) foundations are used, to include details of OSP jacket foundation
the proposed method and anticipated substructure assembly
duration of pile-driving, details of soft- and installation
start piling procedures and anticipated
maximum piling energy required, and
details of any mitigation and monitoring
to be employed during pile-driving.
Cable Plan Marine Licence The CaP provides details of the location • Section 6 - Construction
(CaP) 04678/19/0 (3.2.2.10) and installation techniques for the OSP procedures, mitigation
interconnection and export cables, the and good working
results of survey work to inform cable practices
routing, technical specification of the • Section 6.8 - Stage 5:
cables, a burial risk assessment, and OSP interconnection
methodologies for survey and monitoring cable installation
of cables during the operational phase. • Section 6.9 - Stage 6:
Subtidal export cable
installation
Lighting and Marine Licence The LMP provides the aviation and • Section 6 - Construction
Marking Plan 04678/19/0 (3.2.2.14) navigational lighting and marking procedures, mitigation
(LMP) arrangements for the OSPs. and good working
practices
Project Marine Licence The PEMP sets out the environmental • Section 6 –
Environmental 04678/19/0 (3.2.1.1) monitoring measures for the Seagreen Construction
Monitoring OTA Project, covering diadromous fish, procedures, mitigation
Programme benthic communities, seabed scour and and good working
(PEMP) local sediment deposition and sandeels. It practices
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 13 of 66
Reference Consent (condition in Linkage with the OTA CMS Cross-reference in this OTA
(consent plan parenthesis) CMS
title)
LF000009-CST-OF-MST-
002
Rev: 02
Page 14 of 66
4.1 Overview
This section sets out the key roles and responsibilities and chain of command in relation to the OTA CMS. It
identifies each key role involved in the construction phase of the Seagreen OTA Project and lists
responsibilities associated with each role in relation to the OTA CMS. It should be noted that there will be
two Main contractors responsible for the construction of the OTA; one with responsibility for the export cable
construction, and the other responsible for the OSP jacket, foundations and topside. The chain of command
below will be replicated for each Main contractor.
Figure 4.1 illustrates the key roles and chain of command in relation to the OTA CMS.
Document Reference
LF000009-CST-OF-MST-002
Rev: 02
Page 15 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 16 of 66
For full details of roles and responsibilities in relation to environmental management of the Seagreen OTA
Project construction phase please refer to the Offshore CEMP (LF000009-CST-OF-PLN-0014).
The Seagreen Marine Coordinator is responsible for the monitoring of people, vessels and offshore
structures with regards to the safe preparation and execution of offshore construction activities. The Lead
Marine Coordinator is supported by each of the Duty Marine Coordinators. The Duty Marine Coordinator is
the person responsible for the role when they are on duty.
LF000009-CST-OF-MST-
002
Rev: 02
Page 17 of 66
Consultant Archaeologist
The consultant archaeologist will provide advice in relation to marine archaeological matters during the
works.
LF000009-CST-OF-MST-
002
Rev: 02
Page 18 of 66
Contact Details
Contact details for key Seagreen personnel, contractors and sub-contractors will be provided to MS-LOT, in
line with consent conditions, when available and prior to engagement in the works through the submission
of the proforma included in Appendix E.
5.1 Overview
This section provides an overview of the overarching Seagreen construction management framework
within which the Seagreen OTA Project will be delivered. It details the industry guidance available to inform
the Seagreen construction management framework, highlights wider obligations under the Construction
(Design and Management) Regulations 2015 (CDM Regulation) and the Seagreen offshore CEMP, provides
details of training and competence requirements before summarising contractor and sub-contractor
obligations.
The Seagreen construction management framework will ensure the safe, compliant installation of the
Seagreen OTA Project components as described in this OTA CMS.
G+/DROPS, Reliable securing Provides information to help eliminate the risk of All of section 6
published booklet for dropped objects, explaining the requirement for worksite
through the offshore wind hazard management and illustrates good practice
Energy Institute recommendations. Information applies to all personnel,
(June 2019) tools, equipment and structures associated with design,
supply, transportation, installation, maintenance,
operation and dismantlement activities across the
industry.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 19 of 66
The G+, Working at height Describes how to reduce the need for working at height Sections 6.6 and
published in the offshore (WAH) and how to make suitable provision and 6.7
through the wind industry preparation for WAH. Covers design, construction,
Energy Institute (2nd Ed.) commissioning, operations, maintenance and
(July 2018) decommissioning phases. Gives topic guidance on
common requirements for WAH – training, fitness
requirements, PPE, responsibilities of those undertaking,
supervising and/or procuring work – and common
hazards with recommendations on how to reduce risk.
Also provides guidance on creating procedure flowcharts,
and national/ EU regulations and requirements.
RenewableUK Offshore Wind Guidelines consider health and safety risks in relation to All of Section 6
(Mar 2014) and Marine offshore wind and marine energy projects. Covers project
Energy H&S definition and design, construction, commissioning,
Guidelines operations, maintenance and decommissioning phases,
including supporting activities to these phases (e.g. survey
and geophysical). Covers most significant hazards and
activities relevant to offshore wind and marine projects.
RenewableUK H&S First Aid Guidance on how duty holders can assess provision of All of Section 6
(Dec 2013) Needs Assessment adequate and appropriate equipment, facilities and
personnel to ensure employees receive proper attention
if they are injured or taken ill at work. Sets out key issues
to consider when conducting a first aid needs assessment.
The G+, The safe Addresses small service vessels of less than 500GT, e.g. All of Section 6
published management of crew transfer vessels, guard vessels, survey vessels and
through the small service construction support vessels. Applicable to all offshore
Energy Institute vessels used in the wind farms globally; consistent with national
(Jan 2018) offshore wind requirements. Covers responsibilities for parties involved
industry (2nd Ed.) in management of service vessels, audit and inspection of
wind farm service vessels, operating procedures for
marine operations and vessel activities, management of
vessel traffic, training and competence of crew and
passengers, and vessel safety equipment.
RenewableUK Vessel Safety Guidance in the process of selection and management of All of Section 6
(2015) Guide vessels and interface of equipment to ensure all are Fit
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 20 of 66
The Crown Construction Provides guidance to developers and supply chain for the All of Section 6
Estate (Sep vessel guideline construction of a UK offshore wind farm project. Follows
2014) for the offshore on from ‘Vessel Safety Guide – Guidance for offshore
renewables renewable energy developers (Vessel Safety Guide)’
industry published by RenewableUK in 2012.
RenewableUK Guidelines for Guidelines for good industry practice to be followed for Section 6.4,6.6
(Nov 2013) Selection and selection and operation of jack-ups. Relevant to jack up and 6.7
Operation of Jack- owners/ operator’s technical staff and crews responsible
ups in Marine for the operation of jack-ups, and to project managers in
Renewable Energy the offshore renewables energy industry.
Industry
Fishing Liaison FLOWW Best Provides information to allow offshore renewables Sections 4 and
with Offshore Practice Guidance developers and the fishing industry to liaise on potential 6.2
Wind and Wet for Offshore impacts and/ or interactions in regard to the planning,
Renewables Renewables construction and operation of offshore renewables
Group Developments: projects.
(FLOWW) / The Recommendations
Crown Estate for Fisheries
(Jan 2014) Liaison
RenewableUK Safety Circular: Guidance on accepted scope and format for issuing Section 6.2
(Dec 2013) Notices to Notices to Mariners (NtoM).
Mariners.
Guidance for
Offshore Wind &
Marine Projects
LF000009-CST-OF-MST-
002
Rev: 02
Page 21 of 66
standards and risk management procedures. All contractors and sub-contractors will be expected to comply
with Seagreen Employer SHE Requirements (see LF000009-HSE-MA-STD-0001).
The Contractor’s Construction Environmental Advisors (CEAs), will ensure implementation of construction
management framework measures throughout the duration of the construction period. All contractors and
sub-contractors will ensure compliance with the Seagreen Employer SHE Requirements (see LF000009-HSE-
MA-STD-0001).
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 22 of 66
6.1 Overview
This section presents the construction methods and procedures for each component of the Seagreen OTA
Project. The construction process for the Seagreen OTA Project is comprised of seven broad stages, which
are summarised in Figure 6.1.
Anticipated Milestone
Commencement Date
1
Note: With reference to the Construction Programme Consent Plan (LF000009-CST-OF-PRG-0002), there may be a time gap
between the installation of the WTGs on suction bucket foundations and the WTGs on jackets with piled foundations. During this
gap, certain WTGs on suction buckets may be commissioned and begin generating. The installation of the second OSP may not be
sequential as outlined above but regardless, the process followed will be identical.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 23 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 24 of 66
• Reducing potential effects on the environment and other users of the marine environment are
minimised as far as reasonably practicable in line with the commitments made in the ES, ES
Addendum and ER.
Introduction
Export cable installation activities at landfall will be undertaken using one of the two methods – open cut
trenching or horizontal directional drilling (HDD) as described in the following sections.
LF000009-CST-OF-MST-
002
Rev: 02
Page 25 of 66
The key equipment and methodologies for cable installation at the landfall using HDD are presented in
Table 6.2 below
Table 6.2: Key parameters – landfall Installation up to MHWS utilising HDD approach.
Equipment/Vessels Methodology
HDD Launch Pit Site • Rectangular area (HDD launch pit) prepared
• HDD plant would access launch pit site
• Regular supply of fresh water provided for
mixing with the slurry/drilling mud
• Pit/settling pond excavated at site to contain
slurry and settle out tailings arising from HDD
bore.
HDD Drill Rig • Surveyors set out launch and reception points
and HDD rig would be manoeuvred to the
launch point
• Rig will be anchored in position.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 26 of 66
Equipment/Vessels Methodology
• HDD rig will undertake the pilot bore. (Does not
break out at offshore end).
• Borehole will then be reamed to the correct
diameter and break out at the seabed end on
final reaming pass.
• Duct pipe lengths (HDPE) are joined together
onshore and ends sealed and pulling head
fitted.
• Duct pipe (HDPE)is floated out to the offshore
exit point and pulled though the bore towards
the launch area by the drill rig
• Duct ends are temporarily sealed until cables
can be pulled in later.
Step 3: Demobilisation
LF000009-CST-OF-MST-
002
Rev: 02
Page 27 of 66
Figure 6.3: Aerial Photo of the Landfall Location Showing Carnoustie Golf Course behind the Rock Revetment
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 28 of 66
Figure 6.4: Overview of landfall installation up to MHWS utilising open cut trenching.
The key equipment and methodologies for cable installation at the landfall and up to MHWS utilising open
cut trenching are presented in Table 6.3 and Table 6.4. Three trenches (3 m x up to 360 m x 3 m) will be
excavated which will each contain one HDPE pipe and associated cable.
Equipment and materials are likely to be transported by sea (e.g. by barge) directly to the landfall
installation site, as access to the intertidal and rock revetment areas for vehicles and materials is limited by
tidal conditions. The total duration of activities including installation of the HDPE pipes from the onshore
joint pits through the rock revetment, intertidal and subtidal zones is expected to take up to four months
(excluding weather downtime).
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 29 of 66
Table 6.3: Key parameters – landfall Installation up to MHWS (open cut trenching).
Revetment
Number of trenches 1
Trench width x length x depth 70 m (includes working areas) at top and 30 m at base (trapezoid shape
to provide stability) x 32 m x 10 m
Number of trenches 3
Table 6.4: Installation methodology – landfall installation up to MHWS (open cut trenching).
Equipment/Vessels Methodology
Crawler crane and clamshell • Remove rock in layers to ensure effective reinstatement.
bucket/rock grapple • Stockpile material suitable for re-use. Transport remaining material to
a licenced onshore disposal site using a licensed waste carrier.
• Remove Geofabric rock under layer.
• Install sheet piles using vibro-piling.
Vibro-piling equipment
LF000009-CST-OF-MST-
002
Rev: 02
Page 30 of 66
Equipment/Vessels Methodology
Trench boxes
HDPE pipes • Install HDPE pull-in pipes if required to aid subsequent cable pull-in.
• Pipes will be fitted with concrete collars to weigh them down.
• If sea bed conditions permit, HDPE pipes may not be required in the
intertidal and subtidal sections.
• The seaward end of the pipes will be fitted with a messenger line and
temporarily capped to allow cable pull-in.
• Temporary ballast (e.g. concrete bags/clamps) may be attached to the
Source: Seagreen LF00009-CST-REP-0021) pipe ends for stabilisation.
• Concrete will be poured over the pipes for stabilisation underneath
the rock revetment.
Elevated backhoe excavator (see • Remove trench boxes and sheet piles.
Step 2) • Backfill excavated material.
• Site reinstated to original status.
LF000009-CST-OF-MST-
002
Rev: 02
Page 31 of 66
Equipment/Vessels Methodology
Source: mmaoffshore.com
Offshore vessel • Cable pulled through the HDPE pipes from the cable installation vessel
towards the onshore jointing bay.
• Burial of pipe ends to a depth of 2 m.
Source:
https://www.vanoord.com/activities/cable-
laying-vessel
N/A • Survey of HDPE pipe depth within revetment, intertidal and subtidal
zones.
• Topographical survey within revetment, intertidal and subtidal zones.
LF000009-CST-OF-MST-
002
Rev: 02
Page 32 of 66
Introduction
Seabed preparation activities may be required in advance of OSP foundation installation activities, OSP
interconnection cable installation activities and subtidal export cable installation activities to remove any
boulders. These activities may require further licensing. If a licence is required, this will be applied for by
Seagreen under the Marine (Scotland) Act 2010 for dredging and disposal activities within 12 NM of the coast.
The sequence of events and indicative durations for seabed preparation is illustrated in Figure 6.5
Equipment/Vessels Methodology
ROV:
• The ROV will survey the cleared path to identify any
remaining boulders.
Source: https://www.rovco.com/services/rov/
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 33 of 66
Equipment/Vessels Methodology
Source:
http://www.fisheroffshore.com/equipment/subsea-
tooling/recovery/boulder-grabs/
Introduction
Two OSP jacket substructures will be fixed to the seabed by piled foundations, each jacket shall have up to
12 post-installed piles (see Piling Strategy LF000009-CST-OF-PLN-0003). Delivery of main components will be
directly to the OSP installation sites by sea transport (Heavy Lift Vessel, HLV, or towed barge) from the site
of fabrication. The sequence of events and indicative durations for OSP piled foundation substructure
assemblies and installation is illustrated in Figure 6.6.
It should be noted that there may be a time gap between the installation of the WTGs on suction bucket
foundations and the WTGs on jackets with piled foundations. Prior to this gap the first OSP will have been
installed so that during the gap, certain WTGs on suction buckets may be commissioned and begin
generating.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 34 of 66
Figure 6.6: Overview of OSP jacket foundation substructure assembly and installation.
LF000009-CST-OF-MST-
002
Rev: 02
Page 35 of 66
Table 6.6: Key parameters – OSP jacket foundation substructure assembly and installation.
Parameter Value
Jacket Foundation
Equipment/Vessels Methodology
Source: http://www.fugro.com
Crane:
Source: www.crownestatescotland.com
LF000009-CST-OF-MST-
002
Rev: 02
Page 36 of 66
Equipment/Vessels Methodology
• The piles are driven into the seabed to the desired depth using a
suitable hydraulic impact hammer.
• A ‘soft-start’ process will be undertaken before ramping up to the
required hammer energy.
• Pile driving will be undertaken until pile refusal or the target
penetration depth is reached.
Source: ihciqip.com
Crane (see Step 2) • Relief drilling may be required prior to final pile driving to reach full
penetration (see Step 4 below)
• See Piling Strategy (LF000009-CST-OF-PLN-0003).
Step 4: Relief pile drilling (if required)
Reverse circulation drilling unit (subsea • The piling hammer is withdrawn and a reverse circulation drilling
drilling tool): unit deployed.
• A subsea drilling tool is lowered from the installation vessel and
fitted over the partially installed pile.
• Material inside the pile is drilled out with removed material
deposited on the adjacent seabed.
• Drilling continues until required depth is achieved or obstruction is
passed.
• Pile driving may resume.
Source: tms-supplies.nl
Step 5: Grouting
Grouting spread: • Grout will be mixed using fresh water on board the installation
vessel and stored in grout silos ready for use.
• Grout is pumped into the joint between the jacket and the pile.
• The grout cures and hardens.
• Temporary support is provided via pile grippers during the grout
curing duration
LF000009-CST-OF-MST-
002
Rev: 02
Page 37 of 66
Equipment/Vessels Methodology
Introduction
The OSP topsides will be delivered directly to site on either a barge or a HLV, direct from the location of
fabrication. There will be two OSP topsides which will contain transformers and associated switchgear and
which will be supported by the piled jacket substructures (see Stage 3 above). Total duration of OSP topside
installation is approximately eight days from arrival at OSP installation location. An illustration of a typical
OSP topside attached to a jacket foundation substructure is provided in Figure 6.7 below. The sequence and
indicative durations of events for OSP topsides installation is illustrated in Figure 6.8.
Figure 6.7: OSP at the Greater Gabbard OWF (source Seagreen Alpha and Bravo ES courtesy of Greater Gabbard OWF).
Again, it should be noted that there may be a time gap between the installation of the WTGs on suction
bucket foundations and the WTGs on jackets with piled foundations. Prior to this gap the first OSP will have
been installed so that during the gap, certain WTGs on suction buckets may be commissioned and begin
generating. The installation of the second OSP may not be sequential as outlined in this section but
regardless, the process followed will be identical.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 38 of 66
The key parameters of the OSP topsides are set out in Table 6.8, with the installation methodology and
equipment outlined in Table 6.9.
Table 6.8: Key parameters – OSP topsides.
OSP topsides 2
Height of topside structure including lightning protection Approx. 70.0m (including comms mast)
(relative to Lowest Astronomical Tide)
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 39 of 66
Equipment/Vessels Methodology
Source: http://www.fugro.com
HLV (see Step 1).
LF000009-CST-OF-MST-
002
Rev: 02
Page 40 of 66
Introduction
The OSP interconnection cable connects the two OSPs. The OSP interconnection cable will be trenched and
buried in the seabed, to a target depth of at least 1 m to provide protection to the cable. This will be carried
out by either a subsea jet trenching tool or an engineered rock placement solution where trenching to the
required depth has not been possible. An overview of the OSP interconnection cable installation process
and indicative durations is provided in Figure 6.9.
Key parameters for the OSP interconnection cable are set out in Table 6.10 with the installation
methodology and equipment set out in Table 6.11.
Table 6.10: Key parameters – OSP interconnection cable.
Width of trench 3m
LF000009-CST-OF-MST-
002
Rev: 02
Page 41 of 66
Cable protection
Material (type) Rock, armouring or concrete mattressing
Cable protection length x width x height Included in the 35.5 km x 7 m x 1 m cable protection volume assessed
for both Alpha and Bravo respectively
Equipment/Vessels Methodology
Grapnel assembly: • The cable route will be cleared of any remaining obstructions by
undertaking a pre-lay grapnel run (PLGR).
• The PLGR vessel will tow the grapnel rig along the centreline of the
cable route with a tolerance of +/- 5 m giving a 10 m corridor.
• The majority of debris encountered will be placed to the side of the
cable route. Larger debris (i.e. rock outcrops) will be left insitu and
the cable route diverted around it.
Source: http://eta-ltd.com/img/grapnels/tiger.jpg
• Any debris to be recovered and disposed of onshore in a licensed
Pre-lay Grapnel Vessel (PLGV) facility is anticipated to be limited to linear debris (abandoned
ropes) that would impede the burial tool as it tracks along the
seabed.
Step 2: Pre-lay survey
• An ROV deployed from the Cable Lay Vessel (CLV) will perform a
ROV:
pre-lay survey immediately prior to the cable installation operation.
Source: https://www.rovco.com/services/rov/
CLV:
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 42 of 66
Equipment/Vessels Methodology
Source:
https://www.vanoord.com/activities/cable-laying-
vessel
CapJet: • The OSP interconnection cable is trenched into the seabed to the
target depth.
• A jetting tool “CapJet” will inject water at high pressure onto the
sediment surrounding the cable.
• Where jet-trenching is not possible due to the presence of stiff
sediments, a hybrid tool capable of both chain cutting and jet
Source: Nexans Consent Requirements –
trenching will be used.
Construction Method Statement LF000009- • If target depth has not been reached, a second trenching pass will
NEX001-REP-K22-001-01 be completed to ensure the cable is adequately buried.
Jet trenching and chain cutting hybrid • An engineered cable protection solution will further protect any
tool: areas of cable not trenched to the required depth (armouring,
concrete mattressing, or rock placement).
• Rock protection is usually deposited by a fall pipe vessel.
Source: https://www.smd.co.uk/our-
products/qtrenchers/qtrencher-1400/
LF000009-CST-OF-MST-
002
Rev: 02
Page 43 of 66
Equipment/Vessels Methodology
Introduction
Prior to subtidal export cable installation, a pre-lay grapnel run (PLGR) will clear the seabed surface of
obstacles within the first half metre depth of the seabed along each cable alignment. The PLGR will
commence as close to MLWS as possible (minimum 10 m water depth). The three export cables will be
installed onto the seabed followed by burial (trenching) to a target depth of at least 1 m, to provide
protection to the cables. It should be noted that export cable installation will be completed at three
different discrete periods (see Construction Programme, LF000009-CST-OF-PRG-0002) and some of the
steps for the cable installation will be repeated 3 times (one for each cable) as outlined in Table 6.11.
An overview of the subtidal export cable installation process and indicative durations is provided in Figure
6.10
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 44 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 45 of 66
Equipment/Vessels Methodology
Cable testing will be performed at various stages during the cable lay
operations.
Step 3: Cable jointing if required (step to be repeated for each of the three cables
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 46 of 66
Equipment/Vessels Methodology
C/S Nexans Skagerrack (see Step 2) • 1st cable end is retrieved from the seabed to the C/S Nexans
Skagerrak.
• Cable jointing takes place on the vessel.
• The jointed cable will then be lowered to the seabed.
Step 4: Cable burial and cable protection (step to be repeated for each of the three cables)
• The export cable is trenched into the seabed to the target depth.
Jet trenching
• A jetting tool will inject water at high pressure onto the sediment
Fall pipe vessel for installation of any surrounding the cable to temporarily fluidise it allowing the cable to
rock protection sink to the required burial depth.
• If target depth has not been reached, a second trenching pass will be
completed to improve the first pass.
• An engineered contingency cable protection solution - rock
placement will be used where burial by jetting is not achieved with
up to 2 passes of the jetting tool. Rock will be deposited by a fall pipe
vessel.
Figure 6.11: Cable floating operation (source: Nexans Consent Requirements – Construction Method Statement
LF000009-NEX001-REP-K22-001-01).
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 47 of 66
Introduction
Following construction of the Seagreen OTA Project, the project will undergo commissioning and testing.
These steps complete the commissioning phase of the Seagreen OTA Project which is the handover of the
project from the construction phase to the operation phase.
LF000009-CST-OF-MST-
002
Rev: 02
Page 48 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 49 of 66
8. References
Table 8.1 sets out those documents for the Seagreen OTA project in relation to either Consent Plans or other
reference documents.
Table 8.1 Seagreen Document References
LF000009-CST-OF-REP-0021 Seagreen Alpha and Bravo Offshore Wind Farms: Alternative Landfall Cable
Installation Marine Licence Application – Environmental Report
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 50 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 51 of 66
https://cdn.ymaws.com/www.renewableuk.com/resource/resmgr/publications/reports/H&S_Jackup_Barg
es.pdf
Seagreen (2012) Environmental Statement (ES) for the Seagreen Alpha and Bravo Offshore Wind Farms.
September 2012.
Seagreen (2013) Addendum to the Environmental Statement for the Seagreen Phase 1 Offshore Project:
Alpha and Bravo Offshore Wind Farms October 2013.
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 52 of 66
Term Description
Alternative Landfall Marine Licence granted by the Scottish Ministers under the Marine (Scotland) Act 2010 on
Cable Installation 21 November 2019 (reference 07050/19/0) in respect of the Alternative Landfall Cable
Methodology Marine Installation Methodology
Licence
CaP Cable Plan as required under the Offshore Transmission Asset Marine Licence Condition
3.2.2.10
Offshore CEMP Construction Environmental Management Plan as required under the Offshore
Transmission Asset Marine Licence Condition 3.2.1.2
CM Compliance Manager
CMS Construction Method Statement as required under the Offshore Transmission Asset Marine
Licence Condition 3.2.2.4
commitments A register that sets out all commitments to manage and mitigate potential environmental
register impacts made by SWEL
(the) consents Collective term used to describe the Section 36 consents and Marine Licences issued to
SAWEL, SBWEL and SWEL
CEA SWEL’s Contractor are required to appoint a Construction Environmental Advisor (CEA).
The Construction Environmental Advisor will be a full-time resource for the duration of the
Contractor’s construction works and will be dedicated to delivering the requirements of
the SWEL consent conditions and wider environmental matters
CoP Construction Programme as required the Offshore Transmission Asset Marine Licence
Condition 3.2.2.3
LF000009-CST-OF-MST-
002
Rev: 02
Page 53 of 66
Term Description
DS Design Statement as required under the Offshore Transmission Asset Marine Licence
Condition 3.2.2.7
DSLP Design Specification and Layout Plan as required under the Offshore Transmission Asset
Marine Licence Condition 3.2.2.6
Diadromous fish Fish species that migrate between fresh and salt water
ECoW Ecological Clerk of Works as required under the Marine Licence Condition 3.2.2.12.
EMP Environmental Management Plan as required under the Offshore Transmission Asset
Marine Licence Condition 3.2.1.2 (see offshore CEMP above)
ER Environmental Report
ES Environmental Statement
FLO Fisheries Liaison Officer (SWEL) as required under the Offshore Transmission Asset Marine
Licence Condition 3.2.2.13
Landfall site The point above MHWS where the OTA export cables connects to the OnTW
Licensee Seagreen Wind Energy Ltd (Seagreen), a company with number 06873902 and having its
registered office at No1 Forbury Place, 43 Forbury Road, Reading, United Kingdom RG1
3JH, on behalf of SAWEL and SBWEL in respect of the OTA Marine Licence and Seagreen
Wind Energy Ltd a company with number 06873902 and having its registered office at No1
Forbury Place, 43 Forbury Road, Reading, United Kingdom RG1 3JH in respect of the
Alternative Landfall Cable Installation Methodology Marine Licence
LMP Lighting and Marking Plan, required under Condition 3.2.2.14 of the Marine Licence
Marine Coordination The management and surveillance of people, vessels and Offshore structures to ensure the
safe preparation and execution of Offshore activities, in order to minimise the probability
of an incident, and to provide effective response if an incident does occur
Document Reference
LF000009-CST-OF-MST-
002
Rev: 02
Page 54 of 66
Term Description
Marine Licence (ML) Either or both of the OTA Marine Licence or the Alternative Landfall Cable Installation
Methodology Marine Licence
MPCP Marine Pollution Contingency Plan, as required under Environmental Management Plan,
Condition 3.2.1.2 of the OTA Marine Licence
NSP Navigational Safety Plan, as required for approval under Condition 3.2.2.9of the OTA
Marine Licence
OMP Operation and Maintenance Programme required under OTA Marine Licence condition
3.2.3.2
OnTW Onshore Transmission Works, from landfall consisting of onshore buried export cables and
new transmission substation
OTA Offshore Transmission Asset, comprising the OSPs and the transmission cable required to
connect the Wind Farm Assets to the OnTW from the OSPs to the MHWS at the landfall at
Carnoustie
OTA Marine Licence Marine Licence granted by the Scottish Ministers under the Marine (Scotland) Act 2010 and
the Marine and Coastal Access Act 2009 on 10 October 2014, as amended by the revised
marine licence granted by the Scottish Ministers on 6 March 2019 (reference 04678/19/0)
in respect of the OTA
OWF the Wind Farm Assets
PEMP OWFs Environmental Monitoring Programme as required under the Offshore Transmission
Assets Marine Licence Condition 3.2.1.1
PS Piling Strategy, as required for approval under Condition 3.2.2.5 of the Marine Licence
LF000009-CST-OF-MST-
002
Rev: 02
Page 55 of 66
Term Description
SAWEL Seagreen Alpha Wind Energy Ltd (SAWEL) (company number 07185533) and having its
registered office at No.1 Forbury Place, 43 Forbury Road, Reading, United Kingdom, RG1
3JH
SBWEL Seagreen Bravo Wind Energy Ltd (SBWEL) (company number 07185543) and having its
registered office at No.1 Forbury Place, 43 Forbury Road, Reading, United Kingdom, RG1
3JH
Seagreen Seagreen Wind Energy Limited (SWEL), the parent company of Seagreen Alpha Wind
Energy Ltd (SAWEL) and Seagreen Bravo Wind Energy Ltd (SBWEL), (company number
06873902) and having its registered office at No.1 Forbury Place, 43 Forbury Road,
Reading, United Kingdom, RG1 3JH
Site The area outlined in black in the figure contained in Part 4 of the Marine Licence*
Toolbox talk A short presentation given to the project team members on an aspect of environmental
management
VMP Vessel Management Plan, required under Condition 3.2.2.8 of the Marine Licence
Wind Farm Assets Collective term to describe the WTGS, foundations and associated inter array cabling
LF000009-CST-OF-MST-
002
Rev: 02
Page 56 of 66
LF000009-CST-OF-MST-
002
Rev: 02
Page 57 of 66
Seabed preparation
Boulder clearance Scar plough and orange-peel grab Scar plough and orange-peel grab
Number of OSPs ≤5 2
Export cables
Maximum total length Original application - 530 km 63.2km, 63.2km and 63.4km
LF000009-CST-OF-MST-
002
Rev: 02
Page 58 of 66
Network of high voltage subsea power Circa 220 kV or above Circa 220 kV or above
cables providing inter connection
between OSPs
• Jet trenching
Cable installation techniques considered • Cable plough
• Mechanical cutter
• Jet trencher
• Mechanical cutter
OSP interconnection cable voltage Circa 220 kV or above Circa 220 kV or above
Environmental Project Description - Prior to installation of foundations and substructures a pre-installation seabed survey will be Section 6.5
Statement (ES) 5.126 required to confirm that no obstructions such as UXO, debris or large boulders are present.
Obstructions will be cleared and prepared for the intended installation or the foundation may be
micro-sited to avoid obstructions. In addition, there may be a need to microsite the foundations to
avoid identified sensitive ecological or archaeological features.
ES September Project Description – The pre-construction geophysical survey will ascertain the level of scour protection required for Section 6.6.2
2012 5.153 each location. Scour surveys will continue beyond the construction stage of the project and may
form part of the ongoing inspection regime and monitoring for the wind farm projects
ES September Project Description – If scour protection is required, this will be achieved by rock placement around the foundation and Section 6.6.2.
2012 5.154, 5.155. 5.156 the base of the substructures after installation. Rock placement will infill any scour pit which may
have developed after installation and will create a rock berm above seabed level. This will be
designed to remain stable for the full lifetime of the structure under all forms of predicted
environmental loading. The rock placement will be achieved using a fall pipe vessel or a vessel with
a side tipping system.
Environmental Project Description - The commissioning of Project Alpha and Project Bravo and the Transmission Asset Project, will be in Section 6.10
Statement (ES) 5.199 accordance with approved commissioning procedures. This will be managed by the principal
contractor(s) for construction of each project to the requirements of Seagreen and the OFTO, where
applicable. All commissioning activities will be subject to an approved safe system of work, including
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 02
Page 60 of 66
the Wind Turbine Generators (WTG) performance and reliability testing and compliance with the
Grid code standard.
ES September Physical Environment – Up to only two substructures/foundations will be installed simultaneously over any three-day period Section 6.6
2012 7.165, 7.192, 7.204 across all projects during the minimum 6 months annual construction period and therefore the
release of this material during construction activities will be phased over time.
ES September Physical Environment – Substructures/foundations will be installed over a minimum 6 month annual construction period, Section 6.6
2012 7.171, 7.174, 7.215 with no more than two substructures/foundations being installed simultaneously at any one time.
ES September Physical Environment – Where scour protection is adopted, visual ROV, drop video or dive surveys or bathymetric surveys Section 6.6
2012 7.259 will be undertaken at selected locations
ES September Physical Environment – Efforts will be made to optimize the length of cable that will achieve target burial depth and Section 6.9
2012 7.273 therefore the amount of cable protection required will be minimised.
ES September Sediment Quality - Site specific assessments will be made at each foundation location to determine the preferred Section 6.5
2012 8.142 foundation type and seabed preparation requirements and methods.
ES September Water and Sediment If the need for seabed preparation at any location is determined, a licence will be applied for under Section 6.5
2012 Quality - 8.142 the Marine (Scotland) Act 2010 for Dredging and Deposit of Solid Waste in the Territorial Sea and
UK Controlled Waters Adjacent to Scotland.
ES September Benthic Ecology and Best practice measures will be employed by Seagreen, based on lessons learnt from equivalent Section 6.4.5
2012 Intertidal Ecology - cable installations across sandy shores, to ensure that the significance of potential impacts remain
11.48 and 11.214 as negligible, these include:
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 02
Page 61 of 66
– Ensuring that any vehicle operations keep to designated areas of minimal practicable size
ES September Fish and Shellfish Placement of scour protection should reduce the amount of re-suspended material during Section 6.6
2012 Resources – 12.78, operation.
12.354, 12.367
ES September Fish and Shellfish However, burial depths of up to 3m and cable sheaths may mitigate some of the impacts of EMF for Section 6.9
2012 Resources – 12.376 the export cable.
ES September Marine Mammals – The export cables will be shielded to meet industry standards and will be buried to a minimum of Section 6.9
2012 13.516 0.5m.
ES September Commercial Fisheries - Export cables will be buried to a target depth of between 0.5 and 3m, where it is technically Section 6.9
2012 14.222 practicable to do so, which will reduce the risk to fishing vessels from snagging. In instances where
adequate burial cannot be achieved an appropriate cable protection will be used.
ES September Commercial Fisheries - The majority of export cables will be buried, although approximately 5% of the export cables may be Section 6.9
2012 14.203, 14.267; protected by other means (i.e. rock placement or concrete mattresses).
Shipping and
Navigation - 15.113,
15.145
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 02
Page 62 of 66
ES September Shipping and The following section presents mitigation measures which can be implemented for the OWF 6.6 and 6.9
2012 Navigation – 15.35, development to reduce the level of impact:
15.277
• Promulgation of information and warnings through Notices to Mariners, Kingfisher publications,
fisheries liaison, local recreation clubs and marinas and further appropriate media on
construction activities, cable installation works and other OWF matters;
• the use of guard vessels where appropriate to aid emergency situations and warn vessels;
• application for and use of safety zones to protect the construction/ decommissioning of the
sites;
• use of appropriate means to notify and provide evidence of the infringement of construction
safety zones;
• use of vessels that are ‘fit for purpose’ for the construction activities including marked in
accordance with International Regulations for the Prevention of Collisions at Sea (COLREGS) and
fitted with an Automatic Identification System (AIS) transponder to prevent them becoming a
risk factor;
• Aids to Navigation in line with International Association of Lighthouse Authorities (IALA) O-139
(IALA, 2008) and MCA/ NLB Requirements (which will include a system of routine inspection
and maintenance of lights and markings);
• additional buoyage if required to assist safe navigation (this would be based on guidance from
NLB);
• creation of an Emergency Response Co-operation Plan (ERCoP) with the relevant Maritime
Rescue Co-ordination Centre (MRCC) from construction phase onwards, including MCA
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 02
Page 63 of 66
standards and procedures for WTG shut -down in the event of a search and rescue, counter
pollution or salvage incident in or around an OWF;
• monitoring by radar, AIS and Closed Circuit Television (CCTV) or other agreed means;
• subsea cables will be buried or trenched where possible to provide protection from dragged
and dropped anchors and dropped objects;
• where burial/ trenching is not possible, cables will be protected by other means such as rock
dumping and concrete mattresses;
• any cables installed within the cable corridor will be notified to Kingfisher Information Services
and Cable Awareness (KISCA) for inclusion in cable awareness charts and plotters for the fishing
industry;
• consultation with fisheries stakeholders through the proposed regional Fisheries Working
Group (see Chapter 14: Commercial Fisheries) to ensure that the cable protection method does
not inhibit fishing activities; and
ES September Seascape, landscape Within the export cable corridor, the construction activities close to residential receptors would be Section 6.4 and 6.9
2012 and visual amenity - restricted to daylight or normal working hours. If there is night-time lighting less than approximately
16.216, Mitigation and 2 km to the shore, best practice measures would be applied to ensure the lighting is not directed
Monitoring - 22.32 towards the shore (e.g. using boats between the works and shore only).
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 02
Page 64 of 66
ES September Socio Economics, . For a temporary period within the construction phase, works to the coastal zone may prevent Section 6.4
2012 Tourism & Recreation - access to the beach and sea. Access would be prevented for safety reasons for a temporary period
19.141 of 3 months.
ES September Socio Economics, The export cables will be laid below the surface and hence will not result in any permanent change Section 6.9
2012 Tourism & Recreation - to the utilisation of the receptors as tourism or recreations resource.
19.143
ES Addendum Marine Mammals - Seabed preparation activities may require a licence under the Marine and Coastal Access Act (2009) Section 6.5
October 2012 3.138, 3.326; Fish and or Marine (Scotland) Act 2010 for Dredging and Deposit of Solid Waste in the Territorial Sea or UK
Shellfish - 4.120 Controlled Waters Adjacent to Scotland, depending on where the activity takes place.
Table D.2: Mitigation and good working practices specific to landfall installation.
Reference (this
Source Reference (ES Chapter) Details of commitment
document)
ER – alternative Table 4.1 Working and stockpiling areas would be kept to a minimum size during the construction phase. Section 6.4
cable landfall
ER – alternative Table 4.1 Excavation of material along each trench would be undertaken in separate sediment layers and Section 6.4
cable landfall material of different grades would be stored separately within temporary stockpile areas where
practicable. In intertidal areas, berms will be created to store the material which will be flattened to
ensure that the berms do not become too high where practicable.
ER – alternative Table 4.1 Reinstatement in the intertidal zone will be undertaken on a ‘layer by layer’ basis in reverse order to Section 6.4
cable landfall the excavation sequence.
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 02
Page 65 of 66
Reference (this
Source Reference (ES Chapter) Details of commitment
document)
ER – alternative Table 4.1 Rock that is used to replace any material on the rock revetment will be either imported from Section 6.4
cable landfall Norway or from a UK quarry. The quarried material will be transported dry to reduce the potential
risk of Invasive Non-Native Species.
ER – alternative Table 4.1 During cable installation works, working areas in the intertidal zone will be marked off to prevent Section 6.4
cable landfall public access, and advisory safety distances (of up to 500 m radius) will be recommended around
the cable installation works in the subtidal zone. Advisory safety distances will be notified via issue
of a Notice to Mariners.
ER – alternative Table 4.1 The rock revetment will be reinstated following completion of the works. Initial inspection has Section 6.4
cable landfall determined that some additional rock may be needed. Rock materials removed from the rock
revetment will, where practicable, be reused during reinstatement if this is possible. Rock that is
used to replace any material on the rock revetment will be either imported from Norway or from a
UK quarry. The quarried material will be taken from onshore and will be transported dry to reduce
the potential risk of Invasive Non-Native Species.
ER – alternative Table 4.1 A localised coastal flood warning system will be implemented during construction in consultation Section 6.4
cable landfall with SEPA to mitigate for flood risk. Where possible, works will not be carried out during a coastal
flood or storm event.
ER – alternative Table 4.1 A topographic survey will be carried out to identify and map the contours of the seabed, beach and Section 6.4
cable landfall rock revetment prior to construction. Following reinstatement, a repeat topographical survey will
be carried out to confirm that the original profiles and bathymetry have been restored.
ER – alternative Table 4.1 Selection of appropriate plant will reduce the potential for over excavation and reduce delays Section 6.4
cable landfall during construction
Document Reference
LF000009-CST-OF-PLN-0014
Rev: 01
Page 66 of 66
Appendix E – Pro-forma and contact details for key Seagreen personnel, contractors and sub-
contractors
PRO-FORMA
This pro-forma is for the notification to Scottish Ministers of any agents, contractors or sub-contractors that
will carry out any licensed marine activities (up to MHWS), as required under section 2.6 of Marine Licence
04678/19/0 and Section 3.1.3 of Marine Licence 07050/19/0.
This pro-forma should be completed prior to commencement of any licenced activity, and whenever there is
a change to agents, contractors or sub-contractors.
Complete the details in the table below.