Rigging & Lifting Handbook
Rigging & Lifting Handbook
· • PART OF ASCOWORLD
The International
RIGGING & LIFTING
Handbook
International English I 14th Edition
IMPORTANT NOTICE
This handbook is designed to give guidance aimed at reducing the risk of injury during
Rigging and Lifting operations.
The information contained in this handbook is intended to comply with and reflect the
guidance given in UK health and safety legislation current at the time of publication. The
users must always satisfy themselves, as to the relevant health and safety legislation
affecting the work site.
Lifting equipment, lifting operations, specific tasks and work sites have inherent
associated risks and hazards. While following the procedures and recommendations
contained in this book should reduce the risk of injury, it will seldom be possible to
eradicate risk completely.
This book contains general recommendations only. The users will require to satisfy
themselves that these recommendations are suitable for their particular circumstances
AND DO NOT CONTRADICT GUIDANCE GIVEN BY MANUFACTURERS FOR THEIR
PARTICULAR EQUIPMENT.
NSL
• PART OF ASCOWORLD
The International
Rigging & Lifting
Handbook
I
Details:
Name:
Address:
Tel:
Email:
Employer:
Workplace I Location:
Irrespective of your normal job designation or duties, the occasion may arise when
you have to operate lifting equipment.
The prime considerations are for the health and safety of personnel and then to
ensure that materials and cargo are handled with the minimum risk of damage.
This handbook reflects recognised policies and process of industries for safe lifting
practices and the guidance given by regulatory authorities. Statutory requirements
are the minimum standards acceptable and in many cases these practices will
exceed the minimum requirements.
The individual sections under the heading "Safe Use of Equipment" have
been compiled in general terms as the equipment can originate from various
manufacturers. Should any doubt exist as to the limitations of the equipment, the
manufacturer's technical and operational literature should be consulted.
Each lifting appliance or accessory should have an identification number and its
Safe Working Load (SWL) or Working Load Limit (WLL) clearly marked. Although
not required by law, it should also be colour coded to indicate its certification
status. Only use equipment marked with the current colour code which will be
prominently displayed at the worksite.
This handbook is issued in support of existing Health and Safety at Work Policies.
It provides information on lifting equipment and lifting operations which, if used
properly, will lead to safer working practices.
The handbook is aimed at any personnel involved in Lifting operations and those
working with lifting equipment.
The aim of this handbook is to alleviate "every day" mechanical handling problems.
It is not intended to solve complex rigging problems. These must be addressed
separately and individually.
British Standards
British Standards give guidance and recommendations and compliance is
not mandatory however we recommend the guidance contained within these
standards is followed as this will help you comply with your duties under Health &
Safety legislation. However, where standards have been revised I rewritten and no
longer contain the level of technical information or safety advice of the superseded
standards, reference to "withdrawn" standards technical information is made.
BASIC PRINCIPLES OF
RIGGING AND LIFTING
PAGE 10
SAFE USE
OF EQUIPMENT
PAGE35
SAFETY ADVICE
PAGE 160
WORKING LOAD
LIMIT TABLES
PAGE221
APPENDICES
PAGE232
BASIC PRINCIPLES OF
RIGGING & LIFTING
10
•
GLOSSARY
OF TERMS
2 .0 REGULATIONS
30 A~D
4.0 ELIXF~r:::
DEFINITION ATION OF
• LIFTING
PRINCIPLEEQSU?PMENT EQUIPMENT
50
•
SEL~~1:~~81~MENT
Lin
6• 0 SAFE APPROACH
TO LIFTING
1.0 GLOSSARY OF TERMS
1.7 Headroom
The maximum vertical distance between the item to be lifted and the point
of suspension of the hoisting machine, e.g . between the lifting eyes and
the underside of runway beams.
2.4 SI 1998 No. 2307 The Lifting Operations and Lifting Equipment
Regulations 1998 (This is backed by an approved code of practice).
These regulations came into force in December 1998. The parts of this
Statutory Instrument pertinent to this handbook and that affect you "the
user" are Regulations 4, 5, 6, 7, 8 and 9. Relevant information has been
extracted from these regulations and is shown here:
141CNSL1991 J nsl.ascoworld.com
3.0 DEFINITION AND PRINCIPLES OF LIFTING EQUIPMENT
Definition
Lifting Appliances
Mechanical device capable of raising or lowering a load, e.g.: Cranes,
Forklift Trucks, Lifts, Suspended Cradles, Powered Hoists, Manual Hoists,
Lever Hoists, Rope Hoists, Beam Trolleys, Beam Clamps, Sheave Blocks,
Winches, Runway Beams.
Lifting Accessories
Any device which is used or designed to be used directly or indirectly to
connect a load to a lifting appliance (see above) and which does not form
part of the load, e.g. Wire Rope Slings, Chain Slings, Man-made Fibre
Slings, Hooks and Fittings, Swivels, Shackles, Eye Bolts, Rigging Screws,
Wedge Sockets, Plate Clamps.
3.4 Many items are covered by British, European and International Standards.
Where applicable these are listed against individual types of equipment
(refer to Appendix 1).
3.5 Some lifting equipment (e.g. lifting beams) can be used in a variety of
ways. It is therefore important that information on the specific intended use
should be indicated by the manufacturer I supplier in such cases and the
advice sought before any change of use is attempted.
3.6 It will be apparent when reading specific sections of this handbook that
reference is made to the angle at which the equipment is used (e.g. the
angle between the legs of a multi-leg sling). It is most important that
allowance is made for the change in forces applied and resultant variation
in safe working load which can result from using the equipment at an
angle.
4.1 Companies and users of lifting equipment are required by law to have it
thoroughly examined periodically by a Competent Person (Examination
periods are referenced further within this section - "Periodicity of
Examinations"). The legal responsibility for ensuring this happens lies with
senior management who would normally delegate to supervisory staff.
4.4 Further details of what to check for during an examination are contained in
the "Safe Use of Lifting Equipment" section of this handbook as the details
vary according to the type of gear.
4.8 Hand splices on certified wire rope are not required to be proof load
tested.
fn\ Warning! Do not stow l1ft1ng tackle 1n lockers or tool boxes as the gear
~ could be missed during a statutory 1nspect1on and hence become uncert1f1ed
5.2 Once the weight has been established, another consideration is the
available "head-room''. This has a bearing on sling angles and increasing
tension in the sling legs.
~ Note: The weight of the selected ngg1ng must be added to the weight of
L::J the load to be lifted and the total weight considered when selecting the
ho1st1ng machine
5.3 Check the compatibility of the various components as sizes vary according
to materials used in manufacture.
5.4 Check suitability of hoisting equipment for specific tasks and environment,
e.g. you may wish to use it under water and not all types of equipment are
suitable for sub-sea use.
n
'!!!!'
u
6.1 Personnel Competence
Any person using lifting equipment must be trained in the safe use of
that equipment. The person must also have a working knowledge of its
capabilities and the defects likely to arise in service. This knowledge will be
of value when carrying out the pre-use examinations.
6.2 Never Exceed the Safe Working Load I Working Load Limit
In all lifting operations care should be taken to ensure that the load imposed
on any item of equipment or on part of any item does not exceed its SWL
I WLL. When there is any uncertainty about the weight of the load or the
load applied to a particular part of the equipment it is recommended that
load sensing devices be used. In addition, care should be taken to ensure
that the load remains in a stable condition through the duration of the lift. In
general the load may be unstable if at any time the centre of gravity of the
load is not vertically beneath the crane hook, or the centre of gravity of the
load is higher than the point of attachment of the slings to the load. There
are other causes of instability to be considered, e.g. liquid moving within a
vessel, etc.
~ Note: A spec1f1c nsk assessment must take place prior to travelling loads
~ ovw unprotected pressurised process pipework or suspending loads
from same
When planning a task, checks should be made to ensure that the lay-
down point is of adequate size and capable of taking the weight of the
load. It may be necessary to provide suitable landing packing, e.g. timber
bearers, to enable the slings to be removed from under the load. THE
LOAD SHOULD NEVER BE LOWERED SO AS TO TRAP THE SLINGS
AS THIS ACTION CAN CAUSE SEVERE DAMAGE TO THE SLINGS.
When lowering the load it should be brought to a halt a short distance
above the landing site to allow the operator to steady it, check the position
of the landing packing and ensure that all personnel have their fingers and
feet clear of the load. The load should then be inched down into position.
Before slackening off the slings check that the load is safe and stable. If
not, it should be lifted slightly (to allow the landing packing to be adjusted)
and lowered again. The trial landing procedure is very similar to the trial lift
procedure and should be repeated until the load is safely landed.
6.7 In the case of rigid loads, consideration should be given as to how many
lifting points will bear the load at any time as in practice the majority of
the load may be taken on only two lifting points. In such cases the safe
working load of each lifting point and its associated equipment should not
be less than half the total load.
Never attempt to repair any item of lifting gear or equipment as all repairs
must be carried out by properly trained personnel who are in possession
of approved repair procedures and have the relevant manufacturer's
reference literature. Should you come across faulty equipment, report it to
your supervisor who will take the necessary action.
6.9 When using pneumatic equipment ALWAYS check the pressure rating
as too high a supply pressure can cause the machine to overload. It is
recommended that you install an air service unit with a pressure regulator
as close to the unit as possible.
6.11 Planning
In addition. a "Lifting Operation Plan" which contains a list of possible
considerations is provided. Not all will be relevant to each task, but
the list will prompt you to address something you may have previously
overlooked.
-
,........... CJ ...CJ ...CJ..
-
1 ResjOdlleperscnldefaieslhalililln;i
--is!Dlll:e~ ·-ll ···C ···Q.......... ..
2 Thet1Jm11etenl?e1"11derl.!ieslill
:-'es':~~~control
~Wt!Olllnl*fsmld
Gl'll"IJ*'lasb."'*"""""'ti.utc;
*91ripraax:a.
--·
L.Jtlslhatin>dwelheUSlollmC
.....,
lllslhllart(lllki.t<Q:IOtlf.-... n...tWlsQ!o.fdlll:.,,.olOlll'tSll!Yell
categlliesblllwiOld.li<lnllfW>rlll,
: ,-:.": : '---· I
eo:~~~
olWuc!:S.tll;~~
··· · ···.•
-Mi.UWM ~
l =:.=::=bl I ~~ ~ ~ . .. ===-=-
.::. ===: ~.T~1 !~.:
~~di
=.:. . --·
~==~
atllr.~ Abasc ...,,,.,.~.....,.,.
=:.":~=tr ......
rislo.ISSll:ll'l'loMmusltlt .. _ ....... - . RISkAssmmelll ..... be
~=:*'" ~=*'II
s.,.ntlllll: !liroC*llDf
Kl~l)llllOrmingllt\111111<.
.__,_..._
.. Ell.. ..... 2.E<m ..... 3<S
_ . . . . . _ ... '-"l
~-·---
::::.c::::...-- --·
-~
~l'lrul"willl
!ecp.Jled.
....
~
Brief Description of Lifting Operation ~ndudng IOC&tlon) ·
Posstble Considerations (not exhaustive) - tick ti relevant Md edd1ess each poill n •step-by-step· plan sectloo below):
1 ~OllOadunmown ............. :J 7 Nodedlcatedriggiig ................D 13lrtlngthro'substantlalheights .... a
2 Hlghcentreofgrall1ty... ........ 0 8 loadhassharpedges ................O 14 Dynarrkfactorslnvctved ...........a
3 l..lnslabl91oad... ...... D 9 Extremetyheavybad .................O 15 Hazards to personnel ................a
Awkwardstza/shape .............. 0 10 Noiflpointaboveload .............O 16 Commt.nicatk>ns ....................a
Fmgllsload ............................. 0 11 Aestrlctedheadroom... ..... D 17 Tag lines needed ........................a
6 Nodedicatad8ftpclnts .......... 0 12 COnftnedw::irktw"ea................ 0 18 Poorlightcordillons .................0
Step by step plan of llftlng operation (lncUde any site clearance lf relevant) :
"'"*!'!*'*'•''
Risk Assessment perfonned: Written assessment a (attach copy to lllis plan)
;+meni!MM!ii! H'@!iiif.!*FH94fi
~~00nplam9dby: --
~+~
-'-''-;.,.,
-,---------<
!:!!· · mmp:mp
11 11 11!1if SMMM 111 m. _ u 11 'i?uM."ilifi t.t-M·' l@'tJCH!"·'
4. Has the load been checked and made ready for lifting
(e.g. sea fastenings released, hold down bolts and I or
weldments removed)?
1. Do you know the weight of the load and does the lifting operation
appear to be straight forward?
2. If the task is not a routine lift, do you have the relevant permission
and I or permit?
3. Is there a crane or certified support steelwork (e.g. runway beam or
lifting eye) directly above the load?
4. Does the load have certified lifting points (lifting eyes/collar eyebolts.
etc) fitted and if not. can slings be wrapped around easily (e.g. no
sharp edges.load not fragile etc)?
5. Is there ample headroom for the lifting appliance and slings?
6. Is the lift stable (e.g. centre of gravity below lifting points)?
7. Is the lift balanced (e.g. centre of gravity in the middle) or fitted with
special slings to compensate?
8. Is the work area restricted, e.g. inside a basket or open topped
container?
9. Is the removal route clear of any obstructions?
10. Can the removal (lift, transfer and landing) be performed without
cross-hauling?
11. Is there a suitable lay down area and does the load come within the
allowable load bearing capacity of the ground/deck?
12. Are you experienced in using all the lifting equipment and gear involved?
If you can answer "YES" to all the above, proceed with the hft.
STOP!
I
Due to further engineering and/or risk assessment being required.
PROCEED WITH CAUTION!
Operation must be performed by qualified rigging personnel only.
GO!
Proceed with lifting operation following the supervisor's guidance.
British and International Standards are quoted throughout but the dates of
issue have purposely been omitted to eliminate the need for revision each
time a standard is re-issued. It is to be understood that the latest issue I
revision complete with any amendments will apply to equipment supplied
to or used by the operating company.
The prime considerations are the safety of personnel and to ensure loads,
materials and cargo are handled with the minimum risk of damage.
6.15 When planning your lifting operation, remember that weather conditions
can have an adverse effect on the overall safety of the lifting operation.
6.16 Wind: High or gusting winds have the potential to affect the stability and I
or structural integrity of a crane. An indirect effect is that it can destabilise
a load or blow a load out of the safe working radius I safe operating
parameters of a crane and make the landing of a load hazardous as the
load can blow or swing and strike equipment or personnel. Wind can
cause loose material to fall from both the crane and the load. Crane
manufacturers indicate the maximum desirable wind speeds for safe
operation of their cranes. There are additional criteria to consider, e.g.
boom length, type of load (large surface areas can act as a sail) weight of
load (light loads are blown about more easily), etc. Most cranes have an
anemometer fitted so actual wind speeds will be readily available. If not,
hand-held anemometers can be used.
Fig 6.1
6.17 Wind at sea: Windy conditions have the effect of creating waves and a
swell. This increases the dynamics in lifting operations when lifting loads
from floating vessels using a crane on a fixed platform, e.g. if the vessel
drops just as the load is taken, it creates a "snatch" effect increasing the
actual loading and stresses through the crane. This is even worse when
lifting between vessels if one is rising as the other is falling.
6.18 Rain: Excessive rain can destabilise ground conditions which is critical
when positioning and setting up cranes. Rain can also adversely
affect visibility and interfere with communications especially visual
communications I hand signals. Radio clarity may also be affected by
adverse weather conditions unless they are suitably protected.
7•
0
CRANES
OF PERSO
(~NEL)
HOISTING
8 • 0 f HAIN HOISTS
PULLIFTS
10• 0 BEAM
CLAMPS
11• 0 BEAM
TROLLEYS
12 • 0 PLATE
CLAMPS
14 0•
WINCHES
(& HOISTIN:EL)
OF PERSON
16 0 WIRE ROPE
17• 0 MAN-MADE
FIBRE SLINGS
• SLINGS
19.0 SHACKLES
1 8 •0 ~~':.~ GRADEBO
SLINGS
2 2• 0 FALL ARREST
DEVICES
34 I 0 NSL 1991 I nsl.ascoworld.com
7 .0 THE SAFE USE OF CRANES
7.3 Crawler Cranes are also mobile and are usually found in construction
yards and project sites. They can travel with a load as long as the ground
is reasonably level. Usually these cranes have lattice booms but newer
models can have telescopic booms.
Fig 7.1
7.5 High Portal Cranes are less familiar. Their main feature is an elevated
control cab which allows the operator to see into the holds of ships. These
cranes are usually restricted to docksides where larger capacity models
are permanently installed and run on rails.
7.6 Finally there are Pedestal Cranes, again permanently installed, and usually
}
0
found on ships and offshore installations.
~
::>
·1_,.,~~--c::::::====:::.,_.
~'\,
Typical Pedestal Crane ~
Fig 7.2
36 I C NSL 1991 J nst.ascoworld.com
7.7 To work safely with cranes, it is important that you understand how they
function. The main six motions of the crane are:
Where relevant (e.g. Crawler Cranes} there are an additional two motions
which are Travel Forwards and Travel Backwards.
Boomup \
r r
Lower
Main hoist winch
Fig 7.3
1) When booming up, limits to prevent the boom coming into contact
with the back-stops.
2) When booming down, limits to prevent the boom angle becoming
less than approx 15° to the horizontal. (This limit can be over-ridden
to allow parking of the boom in the rest).
3) When hoisting, an over-hoist limiting device is used to prevent the
hook block being pulled through the sheaves (see fig 7.4 below).
4) When lowering, lower hoist limiting device I switch to prevent
running the hoist rope completely off the winch drum thus losing
the rope, hook block and possibly the load.
Note: Depending on manufacture and I or c rane type this activates
when there are 3 - 5 wraps of rope left on the hoist drum.
5) Slewing limits are sometimes fitted but care still has to be exercised
by the Crane Operator and the Banksman to avoid striking the
boom against obstructions (such as other cranes, buildings and
structures).
--- -- 'E-! ~
U1 0.
0 _ "-
________ co
F'ig 7.4
7.10 Certain cranes are fitted with additionaJ safety devices such as Gross Over-
moment (overload) Protection (GOP) or Ultimate Protection Systems (UPS), 'Aind
speed indicator (Anemometer) and wind direction indicator (Windsock).
7.11 If the crane is situated on an offshore installation, the operating cab should
contain a fire extinguisher, smoke hood and life jacket.
7.12 As with all lifting machines, cranes have a maximum safe working load I
working load limit but this depends on the number of wire rope falls reeved
up at the time. Obviously, the more falls, the greater the lifting capacity
but this decreases the hoisting speed. This in turn could affect the ability
to perform a lift from a vessel if the hoist speed is too slow to prevent the
load re-impacting on the vessel's deck as it rises on the next wave. The
SWL I WLL also reduces as the operating radius increases (see fig 7 .5
below). You must always refer to the load radius chart (and manufacturer's
instructions) which will be posted in the crane cab.
-~
'!
'
~~-,
~/1 ~
I
I
I
I Minradius I
i Max load 1 Max radius
r Min load
Fig 7 .5
7.14 The Crane Operator must also be fully conversant with rigging and slinging
of loads and their lifting arrangements. He is responsible for the condition
of the crane and for operating it within its safe limits. He must be able to
program the load indication system accordingly to reflect the environmental
conditions.
7.15 Prior to using the crane, he must perform pre start-up checks in
accordance with the daily check sheets. Under certain circumstances, he
may be assisted by the Crane Mechanic. Fuel, lubricant and coolant levels
have to be checked, and the structure itself must also be inspected. Once
the crane is started up, it should be left to run for approximately 5 minutes
to allow it to warm up. Then, all controls, brakes, instruments and safety
devices checked to ensure they are functioning correctly and set-up I
stability checked and monitored throughout operations.
6)
applicable).
Check that water is drainec from air reservoirs.
t
7) Check the boom structure for damage.
8) In the interest of safety and fire prevention, check that the crane
cabin is in a tidy condition and free from tins of grease and oil, rags,
tools, or materials other than those for which storage provision is
made.
9) Check the operating pressures in any air and I or hydraulic
system(s).
10) Check the operation of the crane through all motions with particular
attention to brakes to ensure that these are operating efficiently.
11) Check the operation of all limit switches or cut-outs (use caution in
making the checks in case of non-operation).
7.18 If a crane is working in a pipe yard or similar, there may be specific setting
up requirements at the work site. Ground conditions are crucial and ideally
the ground would be firm and even. Where ground conditions are not ideal,
special measures have to be taken to spread the load from the outriggers.
limber, steel or
fibre matting
Fig 7.6
7.19 The Crane Operator must ensure, as far as possible, that there are no
underground facilities such as drains, gas mains, or water pipes that might
collapse under loading.
7.20 Special care has to be taken when working near the edges of excavations,
or even quay sides. When the load is transferred through to an outrigger, it
could be disastrous if the edge collapsed (See Figs 7. 17 and 7. 18).
7.21 If a crane is involved in laying pipelines or similar in open countryside, the
operator must also be aware of potential danger overhead in the form of
electrical power cables. There is a recommended minimum distance to
operate from these power cables (refer to paragraph 7.41 & fig 7.11 for
further information).
7.23 Pedestal cranes working offshore do not have the hazards of overhead
power lines, however, the hazard of another crane working in close
proximity is common and the Crane Operator must be vigilant when
moving loads around the deck.
7.24 Ideally the Crane Operator should be able to see the load all the time but
as this is not always possible, he will need someone to guide and signal
to him. There will always be a designated and identifiable Banksman.
Recommended hand signals are contained in Appendix 3 of this ~
handbook. if
7.25 He must exercise great care when manoeuvring the crane up, down or f_,·
across an incline, e.g:
~~~~:
/
• .'
''
''
Normal operations on level ground
- :
''' -,
''
Downhill: Radius increases
In this example, the crane could tip forwards as the load
swings out of radius
..' .....mil''
Fig 7.7
The International Rigging & Lifting Handbook j 43
In these examples, the side loading inflicted on the boom could either tip the crane or
cause the boom to collapse.
Fig 7.8
7.27 The most important task the Slinger I Load Handler has is to prepare and
sling the load correctly. This includes the selection and fitting of appropriate
rigging, protection of the load, protection of the rigging where necessary
and to check the stability of the load (refer to section 24 for further
information on slinging).
7.28 Under normal circumstances, there is only one person nominated to signal
or guide the crane (Banksman). He must be in full view of (or in radio
communication with) the Crane Operator at all times and remain "hands-
off" the load.
7.31 If vessels are involved, radio communications between the crane, the
Banksman and the vessel must be established prior to lifting over the side.
7.34 On offshore installations, during periods of radio silence, all radios must
be isolated and no lifts shall take place either to or from vessels. Crane
operations will be restricted to onboard areas where the Banksman can be
clearly seen by the operator.
7.36 Special rigging may be necessary to suit the maximum variation in load
distribution and angular loading during the tandem lifting operation.
I/
(i1\ Warning! In a tarlrng operation, r e two cranes lrftrng a load and rotating
~ the load through 90 , the total weight wrll be transferred to and supported
by one or other of the cranes
Ideally, each crane should be capable of lifting the full load unless planned for accordingly
Fig7.10
7.41 Depending on the type of crane being used, certain precautions must be
observed to ensure the safety of the operators and any personnel in the
vicinity of the crane operations. When working onshore in close proximity
to overhead electric lines or cables supported by pylons, unless otherwise
agreed by the District Engineer of the local Electricity Power Company,
no part of the crane must come within 15 metres of the cable. To ensure
this minimum clearance, the crane should be positioned no closer to the
plumb of the nearest line or cable than a distance equal to the maximum
length of the crane jib fitted, plus 15 metres measured along the ground.
(This can be reduced to 10 metres if the cables are supported on wooden
or concrete poles). Failure to comply with these instructions could have
fatal consequences for people working in the vicinity of the crane as per fig
7.11.
'
I
'
I
~ism~·
Fig 7.11
7.43 If the machine makes electrical contact with a live overhead electric line
observe the following precautions:
Fig 7.12
7 .46 The dimensions of the goal posts and their distance from the nearest power
cable is to be decided in consultation with the District Engineer of the local
Electricity Power Company. Large notices should be posted stating:
7.47 Crossing routes should be located as close to the support tower or pole as
possible, in order to take advantage of the greater ground clearance.
7 .48 Finally, notices should be inserted in the driver's cab of all cranes likely to
operate in the vicinity of overhead electric lines and cables stating:
7.50 Ground conditions: i.e. the suitability of the ground to support the
crane's outriggers under fully loaded conditions. The ground should always
be firm and level. Care should be taken to ensure there are no dangers to
or from underground services such as gas mains, oil or chemical product
pipelines, electric cables, water mains, etc. Additional care has to be taken
when working near exposed edges such as quaysides· but even more
so, near the edges of excavations. Check that the type of ground can
withstand the bearing pressures transmitted through the outriggers when
the crane is lifting it's heaviest load (refer to table below).
iMMii!..!HWl!.!.H'i
,__
Dense gravel or dense sand and gravel >600 kN/m 2 >87 lbs f1n2
Loose gravel or loose sand and gravel <200 kN/m 2 <29 lbs /in 2
Medium dense sand 100 to 300 kN/ m2 14.5 to 43.5 lbs /in 2
Cohesive Soils
,....-
Very stiff boulder clays and hard clays 300 to 600 kN/ml 43.5 to 87 lbs !in'
Fig7.13
As the crane booms out, the bearing pressure in these outrigger foot
plates would increase due to the increased moment, generated by the
extended radius. This would give you a higher set of values.
Boomed out
~ Increase pressure on
this outrigger footplate
Fig7.14
As the crane slews round, the bearing pressure will decrease on one foot
plate and increase on the other, resulting in yet an even higher bearing
pressure value. Ideally, the crane manufacturer's tables for the various
bearing pressures in relation to loads I radii etc. should be consulted.
Fig7.15
In simple terms, the bearing pressure would be the total weight of the
crane + total weight of the load and rigging divided by area of ONE
outrigger foot plate.
d2 must be
greater than d1
Excavation
Fig 7.17
([]\ Warning! If the horizontal distance (d2) 1s less than the depth (d1), there 1s
\..V a danger of the side of the excavation c ollapsing
If d2 is
less than d1
Depth = d1
Load path
'
Excavation
Fig 7.18
7.55 When using a crane for heavier lifts, the maximum load capacity is
dependent on the number of line parts and this capacity decreases
as the operating radius increases. When preparing for a heavy lift,
confirm the weight of the load, determine the maximum radius
required for pick-up, transfer and laydown and then consult the crane
load I radius chart to ensure that it is adequately reeved.
7.57 Prior to any lifting operation, all slings and associated equipment should be
checked for security, fitting and balance. Should they require to be held in
place while slack is being taken up, a block of wood or Push I Pull Poles
should be used, i.e do not curl fingers round or grip the slings.
7.58 The person in charge should also consider whether a "tag line" is required
to control the load once it is in the air. This is recommended in the case of
long loads where tag lines should be attached at one or both ends so that
rotational movement may be controlled. The tag line should be of such
length that the operative(s) need not stand under the load during the lift. It
should always be connected to the load being lifted, not the rigging {see
fig 7].19).
7.59 All instructions to the Crane Operator (apart from emergency stop),
whether through radio contact or via the Banksman (refer to Appendix 3)
will only be given by the person controlling the lift.
Snagged on
handrail
Fig7.19
7.61 Most marine cranes are fitted with 'C' type hooks to prevent snagging on
protrusions such as handrails, etc., and in certain cases also have a safety
catch to prevent the eye of the lifting sling being accidentally displaced (see
fig 7 .20). Larger cranes however tend to be fitted with ramshorn type hooks
which could have an effect on the sling design (see fig 7.21) for options.
HardEye--+ _
7.63 Should the load swing when you cease travelling, the swing can be
eliminated by driving the crane into the swing, e.g. as the load swings to
the left, travel the same distance as the swing to bring the crane hook
back over the load's centre of gravity.
7.64 Further information on the safe use of cranes and other possible safety
restrictions can be found in BS 7121 HSE Technical Guidance on the Safe
Use of Lifting Equipment Offshore.
i) General
Radio messages should be used to convey work requirements only
and should not be used for general conversation. Under broadcasting
regulations, profane language is prohibited so refrain from swearing.
vii) Interference
When directing crane operations, ensure that personnel in the immediate
vicinity on the same channel, have their radios switched off to minimise the
possibility of your instructions being interrupted or distorted.
(Ensure you are familiar with the particular model you are using.)
Fig7.22
0 On-Off I Volume Control Turns the radio on I off and adjusts the loudspeaker volume.
e Transmit Button Push to talk, release to listen.
Warning! These radios transmit at a high output and should the antenna
fi1\ ever become damaged exposing the central core, the antenna must be
\_V 1mmed1ately replaced 1n order to ma1nta1n not only optimum performance
but to ensure user safety
x) Radio Silences
On an offshore installation, during periods of radio silence, the crane radios
will be isolated. No lifts shall take place either to or from vessels. Crane
operations will be restricted to platform areas where the lifting operations
and banksmen are clearly seen by the Crane Operator.
Fig 7.23
Yes No
1. Has it been established that no other viable option of carrying out
the work is available?
a a
2. Ive all the necessary certificates for the crane, crane
wire ropes, slings and other associated equipment current?
a 0
10. In the event of the primary brake system failing, can the load be
lowered manually to a position where the personnel can be a 0
recovered safely?
Once it has been established that the crane is suitable for hoisting personnel,
you must plan the actual operation you are about to perform anc carry out a risk
assessment in the normal manner.
If the risks have been minimised anc deemed acceptable. you can then carry
out the lifting operation in accordance wijh your generic procedures for hoisting
personnel as long as:
1. The workover basket I transfer basket complies with the current LOLER (SI
1998 No 2307) recommendations.
3. The Crane Operator has been trained and assessed as competent for this
type of basket I transfer operation.
Note:
This document provides guidance only.
Crane m anufacturer instructions and legislative requirements must be
followed at all times.
C NSL 2000
([]\ Warning! Avoid lifting loads below 10°0 of the ho1st's capacity and
\.V NEVER lift loads below 5°0 of capacity as the weight of the load may not
be enough to activate the friction brake
Check that:
8.6 When using a hook suspended hoist, the top hook should be attached to
its support in such a manner that the support fits freely into the seat of the
hook and does not exert any side thrust upon the point.
fli\ Warning! The hoist should be used for ra1s1ng and lowering only, 1e
I ~ loads should not be left suspended (unattended) from them for any length
of time
8.9 The length of the load chain should be checked to ensure that the bottom
hook will reach the lowest point required without running the load chain
fully out. If the load chain is permitted to run fully out, undue stress may
be placed on the slack end anchorage (which is not a load bearing
component).
~1 FigB.2
8.11 Never
Load the tips of the hook.
Never
T Fig 8.3
Note: Although chain hoists were ong1nally recommended for ve~1ca l use
only. tl11s was due to the ratchet pawls being purely gravity-operated. These
pawls are now held 1n pos1t1on by 0:1e or even two springs and therefore
chain hoists aro now suitable for use at up to '15 degrees from the vertical
e.g. 11 a "cross-l1auling" s1tuat1on. L.cvcr hoists can be usec11n <1 l1or:1ontal
oos1l•on. e.g. for pulling ilelTls togmr.er. such as welding.
·~
~ 8.14 Function test the hoist through its entire lifting height and check the
operation of the over-hoisting limits.
8.15 Check the pendant controls and ensure the operating buttons are not
sticky and that they return to neutral on release.
8.17 The preferred fittings to use for connecting hoses, etc. are the MacDonald
type couplings which are rated at 250 PSI. However, if you are using
crowfoot type fittings, they must be the type with the locking "R" clip (see
fig 8. 7 below). As additional backup in the event of failure or to prevent
accidental disconnection, they should also be fitted with a "whip check",
i.e. tied together with wire.
Fig 9.1
Pulling up an incline = Lifting as, if the hoist or rope fails, the load runs
down the slope, i.e. the load does NOT remain stationary.
Example 4
,,,,,,,,,,,,
- LI\
m
-
r---.
~---~
Cross hauling = Lifting as, if the hoist or rope fails, the load swings back,
i.e. the load does NOT remain stationary.
9.3 The hoists are supplied with a specially constructed rope to withstand the
gripping power of the jaws and to prevent "Bird-Caging". The standard
length of rope supplied is 20 metres but shorter or longer ropes are readily
available.
9.4 Wire rope hoists are normally manually operated but hydraulically
powered hoists can be procured to suit specific purposes such as extra
long lifts or pulls.
Manufacturer A
800 kg
,..
8.3mm Bmm
-- Bmm
1600 kg 11.Smm 11.2mm 11mm
• T508 - 55 mm approx.
• T516 - 55 mm approx.
• T532 - 32 mm approx.
~ Note: A longer stroke could 111d1cate 111tema/ wear. a sl101ie1 stroke could
~ 1nd1cate 111ter net! contarn1n2t•O 1 I dzimage
viii) Examine the rope ensuring it is the correct rope for the hoist
and it is free from kinks, corrosion and wear, etc.
ix) Ensure the hoist is well lubricated.
L2 V
• A
c
Fig9.3
Step 2 Remove the anchor locking pin and withdraw the anchor pin (C)
from the machine.
Step 3 To enable the rope to be inserted tilt the machine until it rests on
the anc hor pin end (B). With the left hand, turn the rope release
safety catch (V) forward. On models not fitted with the rope
release safety catch, insert a coin or screwdriver into the slot at
(V) and turn forwards. With the right hand, push the rope release
lever (P) firmly towards the anchor pin, until it locks into position.
Step 4 Ensure that both operating levers point in the same direction.
Insert the fused and tapered end of the Maxiflex rope through the
rope guide (A) at the opposite end from the anchor pin, until it
passes completely through the machine.
2 3a
Fig 9.4
l
machine is ready for either forward or reverse operating.
Step9 Move the operating handle backwards and forwards and the
'5 rope will pass through the machine.
~
~
Fig 9.5
(ii'\ Warning! Never attempt to operate both ho1st1ng and lowering levers
~ simultaneously as this could result 1n instantaneous release of load Never
use an extension pipe for extra leverage as this will overload the hoist
A
c___..
Fig9.6
Step 1 Uncoil the wire rope in a straight line to prevent loops which
might untwist the strands or form kinks when under tension.
Step 2 The following instructions assume that the machine anchor hook
points away from the operator.
With the right hand push in and maintain pressure on rope
release catch (V) on the side of casing by the hook, and, with the
left hand pull the rope release lever (P) away from the hook until
it is vertical. Release catch (V). Continue to pull back on the rope
release lever (P) until it locks into position. Both jaws are now
open.
Step 3 With the machine lying on the ground, insert the fused and
tapered end of the rope at (A). This is the best position for
feeding the rope between the jaws. Push the rope through until it
emerges at (B).
Fig 9.7
(ii\ Warning! The practice of "down-rating" a rope hoist for use 1n the above
~ circumstances is not an option No manufacturer will endorse this misuse
of their products
10.2 Selection
Beam clamps are available in two basic designs, the clip-on type (fig 10.1)
and the more popular adjustable type (fig 10.2).
The main consideration when selecting the clamp is the required SWL I
WLL, i.e. the load to be lifted plus the weight of the hoisting unit.
10.3 The width and thickness of the beam must also be considered and may
well lead to the selection of a clamp in excess of the desired SWL to be
compatible with the beam dimensions. The range and adjustability are
indicated on the clamp's identification plate.
10.4 The majority of clamps are designed for "in-line" use only, i.e. the line
of force must be at right angles to the flange of the beam to which it is
attached (see fig 10.3). It is therefore important to ensure that for "angled"
applications, a clamp of suitable design is selected (see fig 10.4).
F.@M·"11·&*•1§ 6 \1Mii•MMI
• • . • . . O" 1S' 30" 4S'
NIL 17% 34% SO%
Models WLL WLL WLL WLL
3t 2.St 21 1.St
4t 3.3t 2.61 2t
St 4.1 t 3.3t 2.S t
7t S.8t 4.6t 3.S t
6t St 4t 3t
101 8.3t 6.6t St
1S 1 12.41 10t 7.Sl
20 1 16.61 13.21 101
2S t 20.7 t 16.St 12.5 l
30 1 2S t 19.8t 1St
fO\ Warning! Clamp models S 1. S2 & S5 are not suitable for side loading as
\..V they are a lightweight design
~ Note: Where swivel jaws are fitted, ensure they are free to mtate.
vii) Operate adjusting bar and check straightness and function. Check
threads for wear and stretch.
viii) Examine female screwed spigots (in each clamp halq and ensure
they are not deformed due to over I under tightening of clamps on
the beam.
ix) Check "tommy bar" handle and ensure it is not bent or has any
damage which may be injurious to your hands.
10.7 Hand tighten the clamp onto the flange by means of the "tommy bar"
and ensure it has seated correctly. Do not use an extension pipe on the
tommy bar as over tightening causes undue pressure on the clamp
knuckles and can result in the clamp failing.
Fig 10.5
fi1\ Warning! Under tightening results 1n the load being transferred to clamp
\..V knuckles and can result 1n the clamp falling
10.8 Always
Ensure the correct clamp is selected to suit the beam flange and the
weight of the load to be lifted.
10.9 Ensure the beam or structure from which the clamp is to be suspended is
adequate for the loading (refer to 10.1 ).
10.10 Ensure the hoisting unit is correctly seated in the suspension shackle.
10.11 Never
Subject the clamp to side loadings outwith the manufacturer's
recommendation.
10.14 Universal side loading clamps are available which are designed to be
loaded at any angle including side loads.
86 I C NSL t 991 I nsl.ascowortd.com
11.0 SAFE USE OF BEAM TROLLEYS
11.1 Beam trolleys should not be used on any beam other than those designed,
tested and marked as a runway beam, with the exception that they may be
used on a beam forming part of a structure where a specific design check
for this purpose has been made and end stops or a suitable means
of preventing the trolley running off the end of the beam have
been fitted. The beam should also be sufficiently level under all loading
conditions such that the trolley will not run away under gravity.
11.2 Beam trolleys are in the main, adjustable to suit a specific range of beam
flange widths. Adjustment is achieved by means of a screwed adjusting
bar (see fig 11 . 1) or by the positioning of spacer washers on the load bar
between the side plates (see fig 11.2).
Threaded
Fig 11.2
11.3 There are two types of beam trolley available, push travel (see fig 11 .1 and
11.2) and geared travel (see fig 11.3). Push travel trolleys are normally used
for loads of up to 2 tonne and linear movement is achieved by pushing
against the load. Geared travel trolleys are preferred when loads in excess
of 2 tonne are to be handled or accurate positioning is required, e.g.
alignment of flanges, bolt holes, etc.
Fig 11.3
11.4 The SWL I WLL of the trolley must be adequate to take the load to be
lifted plus the weight of the hoist, and the operating chain (where fitted)
should be long enough to hang approximately half a metre above the
operating level.
Important
Check that, between the side plates, the adjusting washers are equally
disposed on both sides of the yoke or suspension plate(s) to ensure that
the loads imposed are directly in line with the web of the beam (see fig
11.5).
Fig 11.5
11.8 Remove one side plate, mount the trolley on the beam and reposition the
side plate taking care to tighten all bolts and locknuts. Should the trolley be
of the screwed adjusting bar type, open out to just over the beam flange
width, hook on one side of the trolley and close again until the desired
width is attained.
11.11 Ensure the operating chains will not foul or snag during travel.
11.12 Ensure the hoisting unit is correctly seated in the suspension yoke.
11.13 Never
Subject the beam trolley to side loadings.
11.16 Where curved beams require a beam trolley to be fitted, normal trolleys
may not be suitable (depending on radius of curve) and may foul and jam.
Specialist articulated trolleys are available for this.
Fig 11.6
Warning! Do not use beam trolleys on beams unless they are fitted with
{[]\ end stops or a suitable means of preventing the trolley running off the end
\.V of the beam Check the effectiveness of the end stops with the actual trolley
being used
0\ ...... Locking
Max 90°
LockHand:__d•
• • -
i 90' Plate
o "'·.·
Horizontal Clamps Universal (Vertical) Clamps
Fig 12.1
12.2 Selection
The first consideration when selecting the clamp is how the plate is to be
transported and stacked, i.e. horizontally or vertically.
12.3 The second consideration is the weight of the plate to be handled which
will determine the SWL I WLL of the clamps.
12.4 The third consideration is the plate thickness which will determine the
correct model of clamp with the appropriate jaw opening.
Vertical Clamps
viii) Examine hook ring and check for wear I distortion in the crown of
ring.
ix) Ensure the hook ring is not too slack in the clamp as this could
indicate internal wear.
x) Examine jaw pin and nut and ensure it is secure and not deformed.
xi) Check operation of cam-assembly locking lever I jaw spring.
xii) Examine serrated jaw and serrated pad and check for wear I
deformation.
xiii) Examine main body shell and check for wear, cracks or
deformation which may affect the operation of internal
components.
12_7 Position the clamp over the edge of the plate and ensure the plate butts against
the jaw stop (see fig 12.2). Should you be using two clamps to lift the plate,
they should be suspended from a spreader beam to prevent the clamps
canting over at an angle in excess of the allowable 10° (see fig 12.3).
12.8 Lock the jaw in the closed position and ensure the jaws have a firm bite on
the plate.
12.9 Always
i) Check that the plate is clean and free from mill scale, dirt, oil and
grease.
ii) Double check that the jaws are locked.
iii) Use an adequate number of clamps to balance the load.
iv) Lift slowly to allow the jaws to obtain a good grip.
12.10 Never
Attach clamps to the side of the plate.
Fig 12.4
fig 12.5
Fig 12.6
12.11 When using horizontal plate clamps, do not exceed the sling angles
indicated below and do not lift more than one plate at a time unless the
clamps are suitable, i.e. sheet bundle clamps.
Max 45'
Fig 12.7
12.12 Never
Use endless slings with clamp pairs as this practice can drastically
overload the clamps.
Fig 13.1
13.2 The main function of a single sheave block is to change the direction
of the hoisting or pulling rope whereas multi-sheave blocks reduce
the necessary pull required on the lead rope to lift the load, i.e. the pull
required reduces as the number of falls (sheaves) increases.
13.3 Selection
The main consideration when selecting single sheave blocks is the load
to be lifted and the resultant load on the head fitting, i.e. the load plus
the line pull {which will be slightly greater than the load, due to friction in
the sheaves). The resultant load increases as the angle between the ropes
decreases.
~ Note: If the sheave block 1s of the snatcl1 block variety, the design should
i.:=.J be such that the side plate securing bolt cannot be fully withdrawn
\ 30
40
1.93
1.87
130
135 0.76
0.84
To calculate the resultant load (R), firstly obtain the line pull (P) by
multiplying the load to be lifted (W) by 1.04 (bearing sheaves) or 1.08
(bushed sheaves). then multiply by the factors indicated in the table fig
13.2 according to the angle between the ropes.
(n'\ Warning! When using a single sheave block as a top block, the resultant
~ load imposed on the structure to which you attach the block can be more
than double the load being lifted, e g 1n the extreme cond1t1ons
t R=2W+F
(Where F = Friction)
R R R R
R R
t t t t t t
•
~
f
2.
{
p
l
"'
w
w w w w w
BRG BUSH BRG BUSH BRG BUSff BRG BUSH BRG BUSH B11G BUS!t
2.04W 2.08W 1.54W 1.58W l.38W 1.42W 1.29W 1.34W 1.24W 1.29W 1.21W 1.26W
1.04W 1.08W 0.54W 0.58W 0.38W 0.42W 0.29W 0.34W 0.24W 0.29W 0.21W 0.26W
Fig13.4
Conversely, divide your line pull capacity (P) by the load to be lifted (W)
and compare the factor with the table to establish block type and SWL I
WLL required.
The SWL I WLL of the block I head fitting is adequate for the
load.
ii) The colour coding (where applicable) is current and the block
has a plant number I ID mark.
iii) Examine sheaves for wear in the rope groove, cracks or
distortion.
iv) Try to lift sheaves to check bearings I bushes for wear.
v) Spin the sheaves to check bearings I bushes and ensure
smoothness of operation.
vi) Where applicable, ensure all grease ports are clean and
unblocked and the machine is well lubricated.
vii) Examine swivel head fittings and check for wear I stretch.
viii) Examine (if possible) thrust bearing I washer and ensure
smoothness of operation.
ix) Examine upper load pin I spigots and check for wear I
distortion.
x) If head fitting is of the shank type, check security of shank and
nut and examine for stretch I distortion. Examine cross-head
for wear.
xi) Examine head fitting shackle I eye checking for wear, stretch
or cracking.
xii) Examine side plates I straps and check for distortion, wear
or cracking (especially around main load pin hole and top
suspension hole).
xiii) Ensure there are no sharp edges or burrs in the side plates
which may be detrimental to the wire rope.
xiv) If fitted, examine becket and check for wear, stretch or
cracking.
xv) Check all spacers and tie bolts and ensure they are not
deformed.
xvi) Using sheave gauge, check rope groove for compatibility with
winch rope.
Fig 13.5
13.7 Safety
When attaching the sheave block to the support structure, ensure all split
pins, locking and secure pins are in place. Should the block be a "snatch"
block, ensure the side plate locking pin is replaced.
Fig 13.6
Always
i) Terminate the wire by means of an open wedge socket (see winch
section 14.12).
Never
ii) Form the termination by using wire rope grips as their use is
strictly prohibited in lifting applications.
iii) Overload the sheave block.
Manual Pneumatic
Fig 14.1
14.2 Selection
When selecting the winch, the most important consideration is the required
line pull. If you are operating in a multi-fall situation. refer to section 13.5
of the handbook to assist your calculations. It must be borne in mind that
the majority of manufacturer's line pull ratings are based on half drum
performance and that line pull decreases as the winch drum fills up.
Fig 14.2
..
with a snatch block and winch:
10 metres
Fig 14.3
35 te
(Should this amount be more than 36% of drum capacity
double check the line pull rating in the winch manufacturer's catalogue).
xiv) Check that the air supply is adequate for that particular model of
winch and is of the correct pressure.
xv) Connect air supply and function test the winch.
!
(For Breaking Loads and Wlls of wire, see table 1 at back of handbook)
Fig 14.4
14.7 When spooling wire rope from a wooden drum onto the winch drum, avoid
reverse bending which is detrimental to the lay of the rope.
Fig 14.5
Underwind Overwind
Left to Right Right to Left
Use Left Lay Rope Use Lett Lay Rope
Underwind Overwind
Right to Lett Left to Right
Use Right Lay Rope Use Right Lay Rope
Fig 14.6
Fig 14.7
Fig 14.B
14.10 The most popular winches have a long brake calliper and a short
brake calliper.
Check your rope winding in relation to the callipers as incorrect
spooling can:
"\Braking "\Braking
Long brake
...--- calliper
Hoisting
+---Hoisting
Fig14.9
Fleet Angle
~Angle of fleet
Ideal distances =
12 x width of grooved drum
I Pulley
Fig 14.10
14.12 In the majority of cases, the winch rope would have a ferrule secured
thimble eye but in certain circumstances (such as multi-reeving) this
eye will be removed and the rope has to be re-terminated on site. The
preferred method is by use of open wedge sockets especially in a lifting
situation. Refer to fig. 14.11 for the correct method of fitting.
Fig 14.11
~ Note 2: Sockets are now available which have an extended wedge with a
~ hole to accommo d ate the wire rope clip This design improves safety and
produces a neater term1nat1on (See Fig 14 1)
Fig 14.11a
The International Rigging & Lifting Handbook J 107
The ferrule secured thimble eye can either have a hook or a shackle
attached for connecting to the load. Most companies use a closed type
safety hook (e.g. BK type) or a safety type shackle. Safety shackles appear
to be the preferred fitting when using the winch for man-riding.
14.13 There are various wire rope clamps I grips available for terminating a rope
"in situ", the three most common being:
The above efficiencies are based on the catalogued breaking load of the
wire rope.
I Note: In general rrgg1ng s1tuatrons the use of any of the clamps I grips for
' ~ te11111nat1ng ropes 111 l1ft111g or pulling appl1cat1ons 1s forbidden They may
L:J only be used 111 'dead ending srtuatrons as rndrcated 111 fig 14 11 01 for
making up ·hold back lines e g for tongs, etc where 1111n1111al loads occur
I
Turnback
eJ.
-y- ...y,..-1
y,....-....:
Fig 14.13
~ Note: The t1ghte111ng torques quoted 111 the table apply to the threads having
l.:=J been greased
No mm Nm lbfl
5 5.8 4.3
6 14.6 10.8
6 17.8 13.1
10 2 8 29.4 21.7
11 8 29.4 21.7
13 10 68.6 50.6
14 10 68.6 50.6
16 12 112.8 83.2
18 12 112.8 83.2
19 4 12 112.8 83.2
20 4 16 276.6 204
22 4 16 276.6 204
24 20 540 398
26 20 540 398
Fig 14.14
Warning! The bolts supplied with the wirelocks are of a high quality to
meet the torque values and should NEVER be replaced with standard bolts.
Always use the correct torque tools.
\ Working part of
rope Qive end)
Thimble
, Turnback ,
1 1
()\-rr--y--
Fig 14.15
(ii'\ Warning! The saddle must always be fitted to the "live" part of the rope (the
\.V easiest way to remember 1s "You Don't Saddle A Dead Horse") The distance
between gnps should be six rope diameters
The quantity of grips required increases with the diameter of the rope. See
table on next page for both quantity and relevant torque values.
M!Mlil1M 3
Nm
2.0
Required Torque
lbft
1.5
6.5 3 3.5 2.6
8 6.0 4.4
10 9.0 6.6
13 33.0 24
16 49.0 36
19 68.0 50
22 107 79
26 147 108
30 6 212 156
34 6 296 218
40 6 363 268
Fig 14.16
~ Note: Refer to the Fist Gnp Table on the previous page for amount
~ of turnback
14.17 For intermediate nominal diameters of rope, the next largest grip size
should be used. The nominal size 5 grip should only be used on a 5mm
nominal diameter rope. For 11 mm diameter rope, use four 1Omm nominal
grips with a tightening torque of 14 Nm (10.3 lb.ft).
14.18 DIN standard bulldog grips applied in accordance with the above table will
have an efficiency of 80%, i.e. they will maintain their grip for up to 80% of
the breaking load of the wire rope.
14.20 Further periodic checking and re-torquing of the nuts is essential during
service, preferably more frequently during the early stages of operation to
ensure that a satisfactory terminal efficiency is being maintained.
Keep your hands clear of the rope spooling onto the drum.
ii) Keep other personnel clear of the hoisting rope.
iii) Check the brake efficiency prior to hoisting any significant height.
iv) Lower off slowly to avoid dynamic loadings on the winch and wire
rope.
14.22 Never
Warning! When using a winch with the wire rope running over a sheave
aloft, 1t is often necessary to attach a weight at the terminated end of the
CD wire to prevent it being overhauled by the weight of the wire running from the
sheave block back to the winch. This is particularly important when hoisting
and lowering personnel due to the lightness of load.
14.24 A detailed risk assessment must be carried out to identify hazards and
either eliminate risks or reduce them to an acceptable level prior to
operations commencing.
I
'l5
!
14.25 The winch operator and the personnel being transported by the winch
must be familiar with and work to the hand signals depicted in Appendix 4.
j 14.26 Ideally, the winch operator should be able to see the person being
transported by the winch at all times. Where this is not the case, e.g.
during a "'blind" lift where the operator does not have direct line of sight, it
is imperative that a suitable means of communication is established and
maintained. This would normally be via short wave radio.
14.27 All personnel involved with man-riding winch operations must at all times,
work within the guidelines of their company's "Safe Operating Procedures"
for such operations.
14.28 Unless marked otherwise, the man-riding winches can also be used as
utility winches as long as the (derated) capacity (for man-riding) is not
exceeded.
1141CNSL1991 I nsl.ascowor1d.com
15.0 THE SAFE USE OF HYDRAULIC JACKS I RAMS
15.1 Hydraulic lifting equipment is available in two basic formats, i.e. a ram
I plunger and cylinder with an integral pump unit (see fig 15.1) and a
ram and pump set which consists of a ram I plunger and cylinder with a
remote pump unit connected by a high pressure hose (see fig 15.2).
•
Fig 15.1 Fig 15.2
15.2 Selection
When selecting your hydraulic equipment, the most important
consideration is the "capacity".
15.3 The second consideration is the number of jacking positions and the
distance between them, i.e. should the positions be quite far apart, using
jacks, you will require one operator per unit whereas if you used rams with
remote pump units, the pumps could be brought together or connected to
a manifold and worked by one operator.
~ Note: When wo rking 1n conf1neo areas 1t 1s also preferable to use rams and
l.:=J oumps as o pposed to 1acks to ensure tl1e safety of the operator(s)
~ Note: Ensure the claw attacl1111ent rs the correct type for yoLr oar:rcu'ar
l..:=J n1odel of 1ack
15.5 Should you wish to monitor the loadings on the jacks or rams, they can be
fitted with pressure I load gauges.
15.6 Should the load have to be sustained, jacks I rams can be procured with
locking collars.
Fig15.4
15.7 As a safety measure, a lock off safety valve can be fitted to the ram to
maintain pressure in the event of a hose failure.
Ag15.5
15.10 As the load is jacked up. it must be followed by packing (to safe guard
against the jacks failing) and similarly when lowering a load, the packing
must be removed piece by piece.
15.11 A load must not be left supported solely by jacks/rams (i.e. packing must
be left in position) unless they are of the design with the locking collar.
15.12 Wherever possible, use non-slip packing between the ram head and the
load to be lifted.
15.14 Never
16.2 Selection
Wire rope slings are by far the most commonly used as they are versatile
and comparatively lightweight in relation to their strength.
They can be made up as single leg slings as shown in fig 16. 1 or as multi-
leg slings as in fig 16.2.
Effective length
~ Mechanical Splice
Thimble {)&a-------------0 Reeving Thimble
Endless (..,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _)
Fig 16.1
Fig 16.2
16.3 The majority of multi-leg slings are fitted with thimbles to utilise the strength
of the rope to best advantage as, with soft eye slings, the strength of the
sling is greatly reduced if the eye is supporting a load via a small diameter,
e.g. shackle pin or body.
Fig 16.3
Note: 'Tl1ere 1s 110 cMmc:1cc 1n WLI bcotwP.<m tlirme ancl fou· le:1 slings as
•o~· ca1culatio11 purposRs, it ·s c.s~;u·necJ that one leg 1r1 U-10 ·o~ir !eg s:·ng is
recl~nclant 1f the C o f G is offset or ti1e l leg lengths are r·ot uxilctly tr1e samo.
Typical Constructions
6 x36 6x19
122
•• More flexible
Less resistant to wear
16.6 When slings are fitted with hooks (e.g. crane pennants) the only types
permitted are the lockable "closed" design, i.e. use safety latch type.
+ BK Type
Fig 16.5
Safety Latch Type
The reason for this preference is that with both types, application of the
load closes the hooks (which lock in the closed position and will not
release on "no load") and their design is such that they do not snag on
protrusions, e.g. handrails, etc.
I
0
I
(i.e. the rope end should protrude slightly but no more than 1/3rd of
the dia.) unless the ferrule is of the longer tapered design which has
an internal step.
"j vi) The ferrule should be free from cracks or other deformities.
vii) Examine each thimble and check for correct fitting, snagging
damage and elongation. (Stretched thimbles I eyes could indicate
possible overload).
viii) Examine wire rope around thimbles as it is often abraded due to
sling being dragged over rough surfaces.
ix) If fitted, examine master link I quadruple assembly and check for
wear, corrosion and cracking.
x) If fitted with hooks, check for wear, corrosion, deformation and
cracking and ensure safety latch functions.
Fig 16.6
16.9 When using single slings in pairs or endless slings be aware of reductions
in sling capacity due to angles and sling configurations.
Refer to section 24 of this handbook for further guidance on safe
slinging.
Fig 16.7
fii\
Warning! A number of manufacturers do NOT recommend their cable grips
~ for lifting Always check the 1nstruct1ons and technical literature
16.12 Where used for overhead purposes, sensible additional safeguards, such as
safety nets, should be employed to protect personnel. If these cable grips
are permanently installed, e.g. suppcrting overhead cables, they should be
inspected on a regular basis.
16.13 For special applications, stainless steel wire can be used (particularly useful
for subsea operations). Non-conductive grips in man-made fibre are also
manufactured.
~ Note: Cable g11ps can be div ded into two main groups namely oull1ng grips
~ a,· d suppo1i grips
For light loads such as plastic tubes or ropes, etc. a grip made with a single
wire weave is sufficient but for heavy loads, particularly where long lengths
of overhead cables are to be installed, a combination of single, double and
triple weave grips are used with the single weave ensuring the initial grip but
the load being taken by the extra strands in the triple weave portion.
Fig 16.8
Using two cable grips ON TOP of each other is not advised as they
tend to damage each other and grip on the item being pulled cannot be
guaranteed.
The construction and application is the same as for pulling grips except
these more or less become part of an installation. They can be of a single
or double weave type according to the load to be supported and have one
or two supporting "eyes" dependent on the available anchoring points and
the disposition of the load.
1) To make fitting easier, the open end of the cable grips can be pushed down
on a fiat surface to make the wire ends of the lattice flare out. This will give
a slight funnel effect and make it easier to fit the open end over the cable.
2) Push the cable grip over the cable, pushing from the eye end towards the
open end. This will cause the cable grip to slightly expand and pass over
the cable.
For single eye grips the cable grip must be pushed onto the cable as far
as possible so as to ensure that the cable passes right to the end of the
cable grip.
For double eye grips the cable may be pushed through the cable grip
exiting between the eyes and for as far as your requirement needs.
3) Ensure that the cable grip is seated uniformally and firmly onto the cable by
positioning both hands around the cable's circumference.
For double eye start at the open end away from the pulling eyes.
Grasp the cable grip as firmly as possible and moving towards the other
end of the cable grip, slide your hands firmly over the woven lattice to
ensure that it sits firmly onto the cable.
Fig 16.9
ii) Use the cable grip if it shows any signs of damage or wear,
(this should be checked each time before use).
Warning! If at any time during the use of a cable grip any of the strands
fii\ 1n the braided woven (lattice) section break, stop the operation 1mmed1ately
\.V Broken strands are normally caused by overloading I uneven apphcat1on
of load
Lacing strands should be the same material I strength, e.g. single, double
or triple weave lace.
Single weave grips should be laced with single strand lacing: double
weave with double strand: triple weave with triple strand.
Laces of higher strength can be used on any cable grips, e.g. triple lace
on a double weave or double lace on a single weave. However, you must
never use a lower strength lace, e.g. single lace on a double weave or a
double lace on a triple weave.
Laces are supplied in manageable lengths. There may be more than 1 lace
per cable grip. You must use the lace(s) provided by the manufacturer.
1) Lay the lace out. Fold it in half and kink it at its mid point.
3) Start the lac ing at the lead or anchoring end of the grip.
Thread the lacing through the first two directly opposite loops of the split
and pull through until the lace is centred at this point.
For high load grips the first loop of the lace can be taken round the braid
wires twice to form a double loop before proceeding.
To make fitting easier, the grip can be compressed in its length, wrapped
around the cable and temporally tied at intervals to keep the adjoining
edges of the braid together, then continue as below.
4) Lace as you would your shoe, crossing the lacings before lacing the next
two loops.
Fig 16.11
5) Don't pull lacing too tight. Leave a space between adjoining loops
approximately equal to the width of one diamond of the mesh.
Fig 16.12
(If a multi length lace is used, tie off at the end of each section).
Fold the twisted tail back on itself to lie in line with the cable.
Start the new lace minimum of 2 braids (diamonds) back lacing over the
previous link and its tied off tail. Then continue as before.
7) Wrap the ends of the lacings once or twice tightly around the tail of the
grip, twisting the ends together securely. Excess lace can be cut off.
~ Note: Remember always remove all temporary ties (1f used before seating
~ the cable grip down and applying any load)
8) For added initial grip a bandit strap or Jubilee clip can be secured around
the cable grip, lace and tail at the open end, i.e. the end furthest away
from the pulling eyes and within two braids of the bottom. Apply load
slowly to allow the cable grip to contract and take up the grip.
~/ ·''~~-{~;:~.
/ / / .!
-... - - - -
Fig 16.13
10) The condition of the cable grip must be inspected before and after use.
Under no circumstances should a cable grip be used if it shows any signs
of damage.
Warning! Due to the nature of the sling material, strength 1s lost 1f there
([]\ are any cuts, tears, fraying or burst st1tch1ng For this reason, these slings
~ must be examined very closely pnor to use and they should only be re-
used 1f they are free from these defects
17.1 Man-made fibre slings (web slings and round slings) are available in five
basic formats as follows:
Format Application
With soft becketed eyes Multi-purpose
ii) With "D" links Straight or basket lifts
iii) With "D" link & reevable link Straight, basket I choke lifts
iv) Endless (Flat webbing) Multi-purpose
v) Endless (Round sling) Multi-purpose
'D' Links
Fig17.1
132 I C NSL 1991 I nsl.ascowor1d.com
17.2 Generally the width of a web sling governs the WLL and equates to 1
tonne capacity per 50mm of width of simplex slings (single thickness) and
1 tonne capacity per 25mm of width on duplex slings (double thickness).
17.3 When selecting the type of web or round sling, you must initially consider
the lifting mode as this affects the capacity of the sling, i.e. to calculate the
capacity of the sling, the SWL should be multiplied by the mode factor "M"
as indicated below.
Fig 17.2
17.4 For general use, soft eye, endless or round slings are more suitable due to
their versatility but if slings are going to be in constant use it is preferable to
use slings with "D" links which are more wear resistant.
17.5 For awkward or fragile lifts (such as valves, actuators, control panels,
etc.), it is advisable to use round slings as they are soft, flexible and when
choked, take a secure bite on the load.
Circumference
1When orderrng always order by circumference and not length or you
will end up with a sling half the length you actually require.)
Fig 17.3
(ii\ Warning! When checking round slings, should any cuts be found 1n
~ the outer protective cover, the sling should be removed from service and
quarantined, 1e do not use as the inner strength core could be damaged
17.7 Safety
Generally, man-made fibre slings are only suitable for use at the worksite
or on board the installation and should not be used for the transportation
of materials to and from the installation or worksite .
17.8 The vast majority of slings are made from polyester which is impervious
to sea water, crude oil and its products, and most acids (at room
temperature).
You must avoid using these slings in alkali conditions however as alkalis
cause the polyester to disintegrate.
I
The webbing will cut here
Fig 17.4
Always
Use packing around sharp edges. Refer to section 24 of this handbook for
further guidance on safe slinging.
18.2 Selection
Grade 80 chain slings, although approximately one third of the weight of
the high tensile type, are still strength for strength heavier than wire rope
slings but have three main advantages namely:
Fig 18.1
18.5 Chain slings fitted with shortening clutches are ideal for lifting loads with
an offset centre of gravity as the leg length can be adjusted to position the
lifting ring directly over the centre of gravity. This allows the load to be
lifted level.
Fig 18.2
i Loaded chain
Fig 18.3
18.8 Be aware that the capacity of the chain sling decreases when:
1381ONSL1991 j nsl.ascoworld.com
18.9 Always
Fig 18.4
18.10 Never
18.11 Refer to section 24 of this handbook for further guidance on safe slinging.
D!l JlJl
Screw pin
anchor shackle
Safety pin
anchor shackle
Screw pin
chain shackle
Safety pin
chain shackle
Fig 19.1
19.2 Selection
Shackles should be selected to suit the load being lifted allowing for any
increased loadings due to sling angles. The dimensions of the shackle will
often be governed by the hole diameter and the thickness of the material
of the lifting eye.
19.3 The selection between Bow type and Dee type will depend on the number
of components being connected.
Crown
Pin bearing PinbCrown
bearing bearing bearing
point point point point
Fig 19.2
Example:
A British Standard higher tensile shackle has approximately HALF the WLL
of an alloy shackle with the same physical dimensions.
Fig 19.3
Packing
Fig 19.4
19.7 Avoid using the shackle in such a manner that movement of the load
rope could unscrew the shackle pin.
If the load shifts. the sling will Shackle pin bearing on running
unscrew the shackle pin line can work loose
Fig 19.5
19.8 Never replace the shackle pin with an ordinary bolt as it will not be as
strong as the proper pin which is manufactured from a high grade material.
Fig 19.6
Fig20.1
([]\ Warning! Dynamo eye bolts are only suitable for an axial (vertical) lift and
\.V any angular loading will bend the screwed shank and lead to failure These
are considered unsuitable and their use 1s not recommended
I
20.2 Selection
The three main considerations when selecting eye bolts are:
Fig 20.2
Example:
Lift angle 0° (i.e. vertical) - collar eye bolts are rated 60% higher
than eye bolts with links.
ii) Lift angle up to 15° - both eye bolts have the same rating.
iii) Lift angle up to 30° - eye bolts with links are rated 28% higher than
collar eye bolts.
iv) Lift angle up to 45° - eye bolts with links are rated 56% higher than
collar eye bolts.
Fig 20.3
Note: Should equipment be supplied with INTEGRAL eye bolts I l1ft1ng eyes,
~ they should be removed and stored for later use and the remaining sockets
~ should be protected (e g screwed plugs) It 1s advisable to MPI eye bolts
prior to subsequent use and of course, the female socket has to be re-
examined (this applies to all eye bolt usage)
iv) The threads should be concentric and fit neatly in a standard nut. If
stretch is suspected, a thread gauge should be used to confirm the
condition.
v) Examine the eye of the bolt and check for wear I stretch I distortion
and look for hairline cracks at the crown of the rings. (This also
applies to the link if fitted).
vi) Check squareness of shank against shoulder.
vii) Examine tapped hole and check thread condition (i.e. depth I
corrosion, etc).
viii) Ensure that the thread (shank length) is suitable and has not been
modified I cut.
Plan
l~-
~w 5° maximum deviation
Fig 20.4
Shim washers
==:;;;...a!!='/
Fig 20.5
20. 7 When 20.6). NEVER use a sling in a basket format (see fig 20. 7), as this
can drastically overload the eyeballs.
20.8 Hoist rings are an alternative to eye bolts. The design of hoist rings is such
that they can be swiveled through 360" and pivoted through 90 - 180°
(dependent on manufacturer).
360'swivel
Fig 20.8
Fig 20.9
20.12 Tighten the bolt in accordance with the torque values given alongside the
safe working load in table 7 of this handbook.
(ii\ Warning! Never replace the bolt with a standard bolt as the assembly
I \V would likely fail thereafter
~ Note: Wliere different loading cond1t1ons (directions of use) are likely t l1e
~ padeye should be cert1f1ed to matcl1 (1e 111 the d1rect1ons of use)
+
Fig 20.10
20.14 These types of pad eyes should always be fabricated from steel to BS EN
10225 8355 G3+N to give the relevant cold weather properties. The profile
should be smooth, free from any flame cutting marks and the hole should
be line bored after the fitting of cheek plates.
~ i yI
0 ct
l
Jaw & Jaw Combination
0
~
~ Hook Clevis
(Has reduced I Jaw
capacity)
Eye Stub
"
0
Hook & Hook Combination
Fig 21.1
21 .2 Selection
The first consideration when selecting turnbuckles is the SWL which is
determined by the thread diameter (See table 8).
~ Note: This table does not apply to turnbuckles with hooks as they have a
' L:=J reduced rating (Refer to 111anufactu1er's l1teratu1e)
Fig 21.2
21.5 Safety
Turnbuckles must always have the threaded shank protruding into the
body to ensure that the load is borne over the correct length of the
threaded shank.
Fig 21.3
Particular care must be taken when using "Closed Body" type screws. It
may be necessary to dismantle the turnbuckle, measure the length of the
threaded shanks, reassemble and use measurement to ensure the above
"unsafe" case is avoided. A simple method of (non-destructive) marking
the threads will allow an easy visual indication of thread depth inserted.
fii\ Warning! When turnbuckles are to be left under load for any length of
\.V time. e g temporary hangers for pipe work, etc they should be visually
checked on a daily basis to ensure they are still secure
22.2 The use of fall arrest devices with an integral emergency winch is
recommended for certain vessel entries where retrieval I rescue from
restrictive areas may be necessary.
22.3 Fall arrest devices must always be used in conjunction with a safety
harness.
22.4 Selection
Fall arrest devices are available in various models, the most popular being
the range with galvanised wire rope (as opposed to the ranges which use
fibre rope or webbing). This rope is normally 15m long (50ft).
22.5 Within this range, there are two basic blocks, i.e. the standard block and
the retrieval block.
Pre-use Examination
Fig 22.3
22. 7 Prior to using the fall arrest device and associated equipment, it is the
responsibility of the individual to ensure that the device is in good working
order and a safe condition.
Referring to fig 23.3 for component identification, the following checks
should be made:
ii) Examine Saflok top hook and check for distortion or wear and
ensure the safety latch engages properly.
Safety Harness
~ Note: Only full body harnesses are acceptable for use with fall
[3 arrest devices
Suspension Trauma
22.9 Anchor your block as close as possible to your work place and if possible,
directly above you to reduce swing in the event of a fall.
22.10 In the event of a fall, the retrieval winch can be swiftly deployed by
removing the quick release pin (see fig 22.6 & 22. 7) and inserting it into the
handle to form part of the winding mechanism (see fig 22.8).
~
t
r' -,
Standard Position Winch In Operating Mode Winch In
For Normal Use (Ratche~ Winding Mode
Fig 22.6 Fig 22.7 Fig 22.8
22.11 Always
22.12 Never
23• 0 SLINGING
GUIDELINES
FORKCHLl~16cKS
REA
27.0 GUl~::scJNNEL
ON SFERS
TRAN
(BILLY PU GH AND FROG) 28.0 GUIDANCEV~~
LIFTIFNAGC?LITIES
29.0 HANDS-FREE
LIFTl~~AFE USE
LIVE
(INCLUDIN
OF TAG LINES)
23.0 SLINGING GUIDELINES
23.1 These are general guidelines, the majority of which are pertinent to all types
of slings whether constructed from wire rope, lifting chain or man-made
fibres. Whichever construction you are using, refer to the relevant section
in this handbook for additional information.
23.2 Storage
Wherever possible, all slings should be stored in a warm dry atmosphere
either coiled or hanging on purpose made racks. Wire ropes and chain
slings should be periodically lubricated to prevent corrosion.
Fig 23.1
1. 25% .1 J. 25% .1
Fig 23.2
Fig 23.3
23.5 If using Bulldogs only DIN 1142 type are acceptable for this particular
purpose.
Typical examples (SWLs shown below are for grade 1770 ropes):
CD Warning! Do not over-tighten the gnp as this could damage the wire rope
Fig 23.4
23.6 Always
Prepare your landing site to enable the bundles to be landed without
crushing the slings.
Ag 23.5
(i1\
Warning! When lowering off w ith the crane. beware of tubulars ro lling out
~ to flat position There may be a danger of limbs being trapped
Fig 23.6
23.8 Never
Flat bar
Different size
tubes
Fig 23.7
O'--
- 0.500 te each sling (0.5)
1 tonne load
Fig 23.8
For the above reason, the SWL of a pair of single slings decreases as the
angle between them increases as shown below:
or
Min45°
Fig 23.9
Multiply the SWL of one leg'by the mode factor - M to obtain the SWL of
the configuration. (The last four modes I ratings do not apply to "round"
slings - Refer to table 3 at back of handbook).
Typical application
Lilting sheet steel
Packing round
Cut to length as required
sharp corners
Fig 23.10
Slinging Slinging
Gable Reel (Wire Rope) Cable Reel (Electrical)
Protection for wire rope Protect the reel from collapsing and
and slings protect the sling from sharp edges
Protection for reel
and slings
Fig 23.11
/\
•
(Preferred}
Fig 23.12
EFIBCA provide guidance and information on the selection, safe use and
testing I certification of FIBCs.
FIBCs should be clearly and correctly labelled with all the information
stated in the Standard.
----
Integral certified
lifting straps
Data label
Warning! Reusable FIBCs must only be refilled with the same product
as the one for which 1t was designed, i.e. they are not suitable for the
transportation of concentrated solid loads such as scrap metal, scaffolding
components, etc. which could severely damage the bag if knocked against
something. They are not suitable for the transportation of extremely hot
items which could melt the fabric, or sharp items which could cut the fabric.
23.15 In the interests of safety, the use of FIBCs for the transportation of anything
other than the cargo for which they were designed must be prevented.
If FIBCs are to be stored for lengthy periods, preferably, they should be
stored indoors, in dry conditions and away from direct sunlight. Note: Their
condition can deteriorate if subjected to long-term static storage so it is
advisable to rotate stocks.
Not all FIBCs are suitable for outdoor storage but for those that are:
23.16 This section of the handbook should be read in conjunction with sections
6, 17, 18and 19.
1. Check that the inspection I test plate is up to date and there are 28
days I 1 Month left on the certification period (When dispatching
from the shore base).
Abbreviations you will find on the inspection I test plate:
T test (proof load tested).
V visual (examined only).
VN visual and NDT'd (usually MPl'd).
2. Ensure the overall structure is sound and there are no signs of
mechanical damage.
3. Check the function of the door locking mechanism and ensure the
doors close and lock without having to apply undue force.
4. Check that the lifting set is of the correct length for the size of the
CCU (i.e. the legs must be long enough to facilitate a lifting angle of
45° from vertical, or less).
5. Ensure the sling set is correctly fitted (i.e. no twists in the legs) and
is of adequate SWL I WLL.
6. If the CCU is a container, check efficiency of door seals.
7. If the CCU is of the open top design, ensure all drainage holes are
free from blockage.
CD Warning! The larger open top corta·ners with drainage ho.es blocked can
holo up to 18 tonnes of water
~ 4. Check slings
2. Check for
mechanical damage
Fig 24.1
24.3 Loading
The loading of CCUs must be carried out in strict accordance with your
procedures paying attention not to mix chemicals and I or gases which
when combined (possibly through transit damage) could become toxic,
highly fiammable or explosive.
Fig 24.2
Fig 24.3
Fig 24.4
24.8 Always
Exercise extreme care when opening container doors. Should there be
any hint of a dislodged load resting against the door (e.g. handle stiff
to operate), attach a rope to the handle and attempt to open the door
remotely.
24.9 Never
Load a CCU I place loads inside in such a way that there is no way of
unloading it at its destination.
1741ONSL1991 j nsl.ascoworld.com
Offshore - the handling of cargo units offshore is almost entirely done by
crane which means the units can be stored closer together to save room
on deck. However, stacking must be avoided if at all possible. Units may
only be stacked if:
;<
Gap to prevent
crushing slings
Fig 24.6
f Fig 24.7
25.1 Although the maintenance of the forklift I reach truck is normally carried
out by a trained mechanic, the day-to-day condition must be monitored
by the operator who, on finding any faults, should report them to the
mechanic and I or supervisor for remedial action.
Start Up Truck
ix) Check all lifting functions, i.e.: hoist, lower tilt, reach, sideshift (if
fitted), etc.
x) Check all transmission functions, i.e. drive, steering, footbrake and
parking handbrake.
xi) Ensure all safety devices and gauges work, e.g. horn, flashing
lights.
Fig25.1
25.4 Forklift trucks should always be parked with the tips on the ground and the
heels as close to the ground as possible. Therefore, before moving off, you
must tilt back the mast and raise the forks to give clearance for forward
travel. This clearance should be kept as low as reasonably practical with
slight back tilt but will be dictated by the ground conditions.
(The controls should be operated smoothly at all times).
25.5 Adjust the distance between the forks to the maximum that the load can
accommodate or to suit the fork pockets if fitted. Approach your load with
the forks low and parallel to the ground. Drive towards the load until it is
almost against the back face of the forks then stop, raise the forks to take
the load and tilt back to stabilise (retract reach if applicable). Travel with
the load as low as practicable ensuring your line of vision is not impaired.
Should your vision be impaired due to a tall or bulky load, travel in reverse
or have an assistant guide you.
...
1. Approach stack and stop 2. Raise load to desired height
+ "'ra-
place load
Fig 25.2
5. Move back slowly clear of stack 6. Lower load before moving off
fig 25.3
25.9 Forklift trucks are often narrow for manoeuvrability and hence tend to be
less stable laterally (side to side). For this reason, with or without load,
never travel across an incline.
25.10 Avoid using the forks through sling eyes to pick up pre-slung loads
especially lifting on a single fork. Special hook attachments are available for
this type of duty.
25.11 Always
Check your mast and load height when driving through doorways, areas
with restricted head room and be aware of other hazards or structures
such AC units, deluge systems, cable tray paths, etc.
25.12 Never
Allow personnel to ride on the truck or load.
25.13 Forklift trucks for use in a hazardous environment, if diesel or gas powered,
are required to meet EEMUA standards as a minimum. Electrically
powered forklift trucks are required to meet BASEEFA.
26.2 The problems associated with manual handling are widespread throughout
most industries. These problems are not only associated with industrial
work, but cover all areas where bodily force is used to move or support
loads.
26.3 The accepted approach to the potential risks from manual handling is the
"ERGONOMIC APPROACH", i.e. fitting the job to the person rather than
the other way around.
26.4 The Manual Handling Operations Regulations came into force on 1 January
1993. The guidance booklet produced by the Health and Safety Executive
is designed to interpret and explain the regulations and give guidance on
how the requirements can be met.
26.5 It is recommended that you obtain or have access to the HSE Guidance
booklet and also receive training I instruction in the safe manual handling
of loads.
Factors Questions
heavy?
bulky or unwieldy?
difficull lo grasp?
unstable, or with contents likely to shift?
sharp, hot or otherwise potentially damaging?
1841ONSL1991 I nsl.ascoworld.com
26.11 Regulations 3 (3) of the Management of Health and Safety at Work
Regulations 1999 requires employers to review their risk assessments.
The assessment should be kept up to date and reviewed if new
information comes to light or there has been a change in the Manual
Handling Operations, which in either case have a material affect on the
conclusion reached previously. The assessment should also be reviewed if
a reportable accident occurs.
26.12 Each employee while at work shall make full and proper use of any safe
system of work provided for his I her use by their employer in compliance
with regulation 14 of these Regulations.
26.13 Lack of knowledge and training on how to lift loads or how to use any
special equipment provided will increase the risks to an individual. Similarly,
lack of understanding in management and supervisory staff who are
lacking in the skills required.
26.14 The regulations state that employers must train, instruct and supervise
any personnel who are required to conduct a Manual Handling Operation.
but they themselves must have the knowledge and the skill to pass on the
training required.
This may be accomplished with the use of outside training bodies.
26.15 Kinetic Lifting - Lifting and Handling General Principles
26.16 In the United Kingdom, over 40,000 accidents per year reported by
industry are caused by the incorrect handling or carrying of goods.
The majority of these accidents occur in the construction and heavy
engineering industries.
26.17 The correct way to lift and carry is to lift with the legs and not with the
back, and to use the body weight.
Fig26.1
Faligue slrain can be prevented. Concentration Relaxing both knees to lower hands allows
of slress is the main cause of fatigue strain. feet to adjust for movemenl, better balance
Bending & IW1st1ng on a rigid leg concentrales adjustments and proper use of bodyweight.
stress mhip and lower back. Stress is distributed throughout body.
The International Rigging & Lifting Handbook I 1ss
26.18 If an object is too heavy, help must be obtained. Personnel must look out
for splinters, projecting nails, and sharp wire.
Harmful
Fig 26.3
26.21 When lifting, the chin should be held in and care taken not to drop the
head forwards or backwards.
26.22 The knees should be bent to a crouching position, keeping the natural
curvature of the spine, but not necessarily vertical.
26.23 A firm grip should be obtained with the palm of the hand and the roots of
the fingers. Using the finger tips means more effort and more chance of
dropping the object.
26.24 Arms should be as close to the body as possible so that the body takes
the weight instead of the fingers, wrist, arm and shoulder muscles. If
possible, the opposite corners of the object should be gripped.
26.25 Lifting should be with the thigh muscles, by straightening the legs, lift by
easy stages, i.e. from floor to knee, from knee to carrying position.
Progressive relaxation results from unlocking of both knees as hands are lowered. Looking up as
hands take the load automatically straightens back at the correct moment.
Fig 26.4
26.26 When carrying do not change grip. Rest the load on some firm support
and then change.
26.29 The consequences of a slip are likely to be greatly increased by the load
being carried as the hands cannot be used to soften the fall. It is therefore
essential to ensure that the route over which the load is being carried is
clear and free from obstructions.
26.30 When a load is lifted or carried by more than one person, the same
principles apply. Persons should work as a team and be given instructions
by one appointed leader only. Wearing rings on fingers is to be avoided.
Fig 26.5
26.34 Real strength depends upon skilful use of bodyweight, good balance
adjustment and elasticity of body structures.
Movements should start in knees and feet, not the head
and upper trunk.
Pushing
Pulling Down
Levering
Fig 26.6
Wroog Right
The basis of all harmful movement IS top The basis of all good movement is base
heavy bending (initial bending of head and action (initial relaxation of both knees)
upper trunk).
Lifting
Wrong Right
Stiffens legs and back so feet do not ad1ust for Legs and back relax for movement.
movement. Feet adjust to allow follow through with load -
Hands have to reach out excessively elbows tend to remain into the body
- elboWs jut out from body
- excessive finger end pressure
Fig 26.7
~ Note: Personnel who have not travelled previously by basket or PTC will be
L:J accompanied by a member of tl1e Deck Crew
27.4 The PTC comprises two main assemblies, an outer protective shell
consisting of a stainless framework that houses the buoyancy panels and a
central column seating assembly to provide shock absorption and support.
All components are designed for the marine environment.
27.5 The yellow coloured PTC buoyancy panels are manufactured from medium
density polythene. Depending on the model the PTC has a number of large
open access points to permit rapid entry and exit. It can withstand lateral
impacts of 2 mis.
27.6 The buoyancy distribution ensures the PTC will float upright in the event of
immersion. The central column supports a keel weight which ensures that
the PTC will also self right.
27.8 The PTC and passengers can safely withstand a maximum vertical impact
of4.5 mis.
1) A ladder
3) Good lighting
A suitable means of safely accessing the top and bottom parts of the
FROG or TOR0-4 is required. When using a step ladder or ladder it must
be securely fixed to prevent slippage whilst accessing the top of the unit.
The keel assembly can be visually checked from ground level using a
torch. Do not go underneath an active lift. Be aware that in some regions
"Working at Height" regulations may apply.
3) Back Up Lift-Eye
Check nut, split pin and tamper proof seal are fitted and in good order.
4) M48 Keel Boss and either Roll Pin (Type 1) or M10 Cross
Bolt (Type 2)
Check keel boss and either cross bolt or roll pin are in position c/w
split pin and tamper proof seals and anti-rotation fittings.
.I
TAMPER PROOF SEAL
I
I
Ml6 UFT1NG EYE BOLTS
WITH SPLIT P1NS AND
TAMPER PRCOF SEALS
@ j
KEEL PLATE
I
AOlLPlN
VIEW UNDER
order.
8) Check HANDLING EYE,
NUT, SPLIT PIN and
TAMPER PROOF SEAL are
fitted correctly and in good TOP CROSS
BEAM
order.
9) Check WIRE ROPE,
LIFTING ASSEMBLY is SEAT CROSS
correctly attached and BEAM M12 BOLTS
Check that all capsule fittings are in good order and within
certification. Ensure that the lifting sling and all shackles are
properly attached (with split pins in place).
ii) Ensure all passengers are wearing a survival suit and a life jacket.
Check passengers are seated and properly harnessed - use the
adjustment straps.
v) Check that tag lines and lifting sling is free and clear of any
J snagging hazards and check that the lift path is clear of any
obstructions.
f vi) Confirm that the passengers are ready for lift-oft then signal to the
Crane Operator to pick up slowly.
Guide the capsule into a suitable landing position using tag lines as
required.
ii) Upon touch down, the Crane Operator should immediately lower
the hook by another 3 metres I 1Oft.
1-J?-i Note: This will create slack "' t"e '1ghtwe1ght sling and preve,'t sra·ch1ng of
r=J the capsule due to vessel heave or loss of station
iii) Signal to the passengers to release their harnesses and step clear
of the capsule.
The capsule should be stored secured to the deck using soft line if
weather conditions dictate. It is recommended that a special cover
is fitted.
ii) Visually inspect the lifting point area prior to each use and ensure
the top nut is fully engaged.
In the event of the capsule being in the sea and disconnected from
the crane hook, an emergency recovery sling should be fitted to
the back-up eyebolt.
Stretcher opening
Fig '£7.2
Note: Tl1is model is not compliant with LOLER legislation and must only be
used as a last reso1i I in emergency circumstances. however other models
meet legislative requirements
Attachment to crane: The lifting sling sets fixed to the transfer baskets
will be fitted directly to the crane's whip line block (i.e. no pennant).
Lift off: The Crane Operator will hoist the transfer basket clear of any deck
obstructions, slew clear of the platform then lower (over the sea) to a level
clear of any vessel superstructure. When it is safe, he will slew the jib over
the vessel's open deck and lower the basket to the deck under instruction
from the vessel's Banksman.
The personnel transfer operation will be reversed for transfer from vessel to
platform.
The OIM I Vessel Master must be informed when the transfers are
completed.
Fig 27.3
After use, it must be rinsed with fresh water and stored in a shaded area,
i.e. out of direct sunlight.
2 Visually inspect safety load line when attaching the X-904 to the
crane hook. This includes the 4-part sling and all the hardware as
well as the load line and fabric covered stabiliser. Look for crimps,
broken wires or excessive wear or rust. If any of these problems
exist, take the unit out of service immediately and replace the sling.
Inspect crane hook positive locking device for function and physical
condition.
3 Visually inspect all of the load bearing areas of the X-904 for
excessive wear or damage paying close attention to the rigging
lines (inner and outer).
• Approach the device and place hand luggage into the netted baggage
area.
• Take hold of the outer rigging ropes and step in to the X-904.
• Position your feet as indicated by the footprints on the floor and clip in
using the fall restraint lanyard .
• The fall restraint lanyard prevents personnel from being able to reach or
step off the edge and is a feature which contributes to confidence and
stabilised positioning should the rider slip, faint or become ill.
• Boarding on a stable rig or platform is a simple matter, boarding from
a vessel or in rough seas may require the Crane Operator to raise the
basket slightly off the deck to reduce the pitch and roll and allow the
riders to attach the double action snap hook of the fall restraint lanyard.
• During transfer, personnel should keep their knees bent, hold on to the
centre ropes and keep the double action snap hook in one hand.
• When disembarking, the double action snap hook should be
disconnected to allow the rider to step away to a safe area.
• The rigid construction provides side impact and overhead protection
and allows the Crane Operator to slacken the crane wire further than
with a traditional net basket as the X-904 will remain upright and this is
an important feature in rough seas.
• Should it be required to transfer injured personnel this can be done
without any changes to the device, the injured person should be
secured in a stokes stretcher and the stretcher secured to the device
with suitable safety shackles at each end, at least one person should
accompany the injured person during transfer.
• The device should be washed with fresh water after use, allowed to dry
and then stored or covered in an area protected from the elements.
Routine Inspection:
For the purpose of this guidance, live facilities (process plant I equipment,
etc.) can be any of the following :
A competent person to create the lift plan and lead the operation.
A competent lifting team to follow the lift plan and operate the lifting
equipment.
To keep the load as low as possible, e.g. just high enough to clear any
obstructions but allowing for a margin of error.
The use of static back-up safety rigging (slings hooked up parallel with
the hoist to sustain the load in the event of a hoist brake failure).
i
Fig 29.1
29.2 While it is intended to make "hands-free" lifting the norm, there will be
exceptions, e.g. drill string related components, pipe handling equipment
and related rig floor tools. Some tasks necessarily require "hands-on"
lifting. Individual companies may find it useful to make a register of lifts
that cannot be performed "hands-free" along with the relevant safety
precautions to manage and minimise the risks.
29.3 The most hazardous parts of a lifting operation are the lifting off and
landing of the load. Therefore at these critical stages, personnel must
be as far away from the load as possible. To ensure this happens, it is
essential to adopt a "hands free" or "hands safe" lifting policy and it must
be rigidly adhered to.
29.4 Lifting-off:
When the strain is taken by the hoist or crane, any errors in the system will
manifest themselves as the loadings increase through the lifting appliance
and lifting accessories.
When landing a load, the hoist usually stops lowering to ensure the landing
site is ready to receive the load or to accurately orientate I position the
load for landing. These stop I start I slewing I booming activities can cause
a slight rocking motion through the crane which can result in:
In addition, if the landing site is not properly prepared, this can also cause
instability of the load. The majority of accidents and incidents happen
during lifting off and landing the load due to the changing dynamics of
the lifting operation and the close proximity of personnel. Personnel are
significantly less likely to be injured if they are outwith the vicinity of the
task, especially when environmental factors cause dynamics resulting in an
incident during the lifting operation.
Fig 29.2
210jCNSL1991 J nsl.ascoworld.com
29.6 What do we need to be able to achieve "hands-free" lifting?
Fig 29.3
Fig 29.4
It is also tempting to move towards a load as it is landing to manhandle it
into the final lay-down position. This is where hands and feet are liable to
crush injuries and can take focus away from your primary task.
Fig29.5
At these critical times you are at most risk, therefore you have to position
yourself at a safe distance from the load.
Fig 29.6
There will always be certain jobs which require "hands-on" for final
positioning but these should be treated as exceptions to the norm and as
such, be fully addressed in the risk assessment process paying special
attention to the risk of injury to fingers and hands, and toes and feet.
2 Tag Lines
Tag lines are "soft" lines made up from single I continual lengths of rope,
(usually polypropylene). The rope should contain no knots, frayed sections
or loops. Where possible, tag lines should be tied to the load and NOT the
rigging. The length of tag lines should be such that personnel using them
can stand well clear when guiding the load.
Although tagline use can introduce additional hazards such as snagging on
surrounding structures, their correct use will increase task safety.
Tag lines should only be used in normal operating conditions and not as
a control to enable lifting operations to be carried out in adverse weather
conditions.
:~
'
Fig 29.7
Tag lines should be held in such a manner that they can slip through the
hand if required. All sections of the line, including slack, must be kept in
front of the body, between the handler and the load.
Where two or more persons are handling the same line, ALL must work on
the same side of the line. Any slack must be kept in front of the group.
Particular care must be taken when using tag lines whilst wearing gloves to
ensure that they do not entangle the glove.
NEVER wrap tag lines around the hand.
NEVER tie tag lines off to a structure.
NEVER allow tag lines to coil around your feet.
ALWAYS keep non-involved personnel clear of the
lifting operation.
We recommend the use of tag lines is considered for all loads if ii helps
facilitate "hands-free" lifting, unless the use of tag lines introduces further
hazards and associated risk.
Fig 29.8
Push I Pull Poles are aluminium, wooden or fibre glass poles with a boat
hook at one end and a rubber or leather pad at the other. Ideally, these
should be about 2 metres/ 6 feet long.
- !Rll!l
Fig 29.9
The main point of hands free I hands safe lifting or pulling is to keep
personnel remote from the load, i.e. in a safe position. Just standing a few
metres or a few feet clear is not enough. Personnel must visualise what
could possibly go wrong with the actual lifting I pulling operation.
Work out where any falling, toppling or swinging load could end up.
Imagine where the boom would land if the boom hoist ropes failed.
Imagine where the winch would go if the anchorage failed.
Fig 29.10
Never position yourself between the load and another solid surface, for
example a bulkhead.
Fig 29.11
Always have a planned escape route and to ensure others remain safe,
never travel a load over personnel. Ensure barriers are in place on all levels
underneath I exposed to the route traveled by the load.
Apart from looking out for yourself, also look out for others who may enter
operational areas. While the work area will be cordoned off, barrier tape
doesn't always stop the person determined to have an accident!
Achieving "hands free" I hands safe lifting is not difficult. Where tasks
require "hands on", think about how you can change it by utilising special
tools or equipment to achieve "hands free". Discuss with your colleagues
and supervisor to determine a safer solution.
TABLE 1
WIRE ROPE
TABLE 2
WIRE ROPE
TABLE 3 SLINGS
MAN-MADE
FIBRE SLINGS
TABLE 4 ALLOY CHAIN
SLINGS
TABLE 5 ALLOY
SHACKLES
TABLE & EVE BOLTS
TABLE 7 HOIST RINGS
TABLE S TURNBUCKLES
220 I Cl NSL 1991 I nstascowor1d.com
•
Table 1: Wire Rope Breaking Loads •
(Refer To Section 14)
~ Note: For general l1ft1ng purposes. SWL = 1/5th of the MBL (1 e Fos = 5 1)
L::J For spec1f1c purposes, e g mooring towing etc, FOS can reduce to 3 1
Note: M1111111u111 breaking loads (MBLs) Working Load L11111ts (WLLs) and
~ Safe Working Loads (SWLs) can vary slightly between different 111anfacturers
~ and depend on 111anufactunng standards Always cl1eck with the sling
supplier for conf1r111at1011 of capacity
~ ~
Vertical Choker
[lD
Basket
@
Basket 90°
d~
Basket 120"
1.0 I 800 kg 2.01 1.41 1.0t
2.01 1.6! 4.0t 2.81 2.01
3.01 2.4 t 6.01 4.2 I 3.01
4.01 3.2 t 8.01 5.61 4.01
6.0t 4.8 t 12.0t 8.4t 6.0t
8.0 I 6.4 t 16.0t 11.2 I 8.0t
12.0t 9.6t 24.01 16.8t 12.01
~ Note: For duplex (two ply) and endless web slings, double the above values
Diameter
I 0 ,\ AIJ\
1 Leg Endless• 2Leg 3Leg&4Leg
7 1.5t 2.5t 2.12 t 3.151
8 2.0t 3.15 t 2.81 4.251
10 3.15 t 5.0t 4.25 t 6.71
13 5.3t 8.5 t 7.51 11.21
16 8.0t 12.5t 11.2 t 17.01
18 10.0 t 16.0t 14.01 21.2t
19 11.21 18.01 16.0t 23.6t
20 12.5 t 20.01 17.01 26.5t
22 15.01 23.61 21.21 31.5 t
23 16.01 26.51 23.6 t 35.5 t
25 20.01 31.51 28.01 40.0t
26 21.21 33.5 t 30.0t 45.0t
28 25.01 40.0t 33.51 50.01
32 31.51 50.01 45.01 67.0t
36 40.01 63.0t 56.0t 85.0t
40 50.0t 80.01 71.01 106.0t
45 63.01 100.0t 90.01 132.01
iMMil' Rated at 0 - 90°
~ Note: It 1s assumed that endless slings will ONLY be used 1n the choke
1 L:J hitch mode, hence the derated capac1t1es If single leg slings are used 111 the
choked mode, their capacities shown above must be reduced by 20%
The above load working load limits apply only to normal conditions of use in
straight configuration and are based on the "uniform load" method of rating.
Grade 10/100 Cham Slings (Coefficient of Safety 4:1}
ii3§.g 3&4Legs
·2mr=rn•·«H·••m·•·••·«i0i·•
mm Working Load Limit in tonnes
0-60 Deg
Anchor I bow shackle Safety anchor I bow Chain I 'D' shackle Safety chain/ ·o·
with screw pin shackle bolt type wilh screw pin shackle bolt type
.mm. . . . .
mm
.,tffflilrtnt·mfflfiMMFjMBlM
mm mm mm tonne mm
13 16 22 43 51 2t 32
16 19 26 51 64 3.25 t 43
19 22 31 59 76 4.75 t 51
22 26 36 73 83 6.5 t 58
26 28 43 85 95 8.5 t 68
28 32 47 90 108 9.5 t 75
32 35 51 94 11 5 12 t 83
35 38 57 115 133 13.5 t 92
38 42 60 127 146 17 t 99
45 52 74 149 178 25t 126
52 58 83 171 197 35t 146
64 70 105 203 254 55 t 185
i~
76 83 127 230 330 85 t 190
~i
90 96 146 267 381 120t 238
~i
Coefficient of Safety = 6: 1
f 48 10.0 t
~ 52 10.0 t 12.5 t
56 12.5t 16.0t
64 16.0t 20.0t
70 20.0t
72 25.0t
76 25.0t
All charts are provided for example only. Manufacturer dimensional and capacity values may vary
and manufacturers specifications should be referenced.
Metric Threads
Diameter (mm) SWL Torque (ft / lbs)
350 kg
10 450 kg 12
12 11 28
16 1.751 60
20 2.21 100
·20 2.71 100
24 3.5 I 160
30 4.2 I 230
Un1f1ed Threads
Diameter (inches} SWL Torque (ft / lbs)
% 454 kg 12
1il.
0. 'h 1.41 28
~~ % 1.82 I
~·~ 60
~::J 31, 2.27 I 100
*% 3.181 100
'Is 3.641 160
4.541 230
1-% 6.821 470
1- 1/4 10.91 I 800
13.61 I 800
II ~~
72 2S t
76
8S
30t
40t
0 ill \) ii!,
100 sot
~ Note: Tl1ese tables do not apply to units fitted w1tl1 hooks Refer to the
L::J manufacturer's literature
APPENDIXl
LIFTING GEAR
I LEGISLATION
MATRIX APPENDIX2
DENSITY OF
APPENDIX] MATERIALS
RECOMMENDED
HAND SIGNALS
FOR CRANE APPENDIX4
OPERATORS RECOMMENDED
HAND SIGNALS
APPEND1x5 FOR MANRIDING
LIFT WINCHES
CATEGORISATION
CHECKLIST APPENDIX6
GENERAL
APPENDIX7 PRE-LIFTING
BEAUFORT SCALE CHECKLIST
OF WIND FORCES
AND VISUAL
INDICATORS
AEQUJflEMEHTS
".o.BOYESWL ~~
MANUFACTURING
CODES/STANDARDS
102sso l 100300 s 10
. •.
2 CRANES(PEDESTAL/M081LE)(20l·SOI) BS1121/8SEN13001/Af'lSJMC2C&O • • • 0
• 0
•• . •
0
6 WINCH(OAVIT} SOL.AS/Onu.Approval
•• 0
•• • •
BSIS022915-<1/BSIS05766 ••
•• 0
0
......~·+-!-+-+-+-+-+-+-+-+.-'-!
*• 0
0
•
•• •• ••
0
13
1<1
POWERED HOISTS (ELECmlC)
POW!:R!OOHO!STS(PNEUMATIC) *•
*•
*.
*.
15 MANUAL HOISTS (CHA!N BLOCKS) 0 • 0
16 LEVERHOISTS(PULUFTS)
•
H-+.++-1H-++-IH--t=
0i
0
*• 0 • 0
17 WIRE ROPE HOISTS ("TIAFOAS1 0 • 0
18 WIRE~FORABOVE BSEN12385,BSIS043a9
•
H-+'+-+-1H-++-IH--t00 i
= •
• •
H-+:++-1H-++-IH--to~ : :
• •
22 SINGLESHEAVEBLOCKS(UPT0251)
• *• ••
23 $1NGLE$HEAVEBLOCKS(0VER25Q
• *• ••
2<1 MULT1-SHEAVEBLOCKSIUPT025t)
•• *•
• *•
25 MIJLTl-SHEAVEBLOCKS(OVER251)
26
27
CRANE HOOK BLOCKS (UP TO 251)
CRANE HOOK BLOCKS (OVER 251)
*•
>-+-+-+"•..._,.._.-+.+->-+.+-I *•
••
28
29
WINCH{PNEUMATIC)
WINCH (MAN·RIDINGJ
• *• •
•
30 WINOlfMANUALI
H-+.++-1H-++-IH--t"-'-i : e 0 0
BS2853(s1>11po!elJ
•• •
•• ••
0
0
33
:M
UFTINGBE.*.MS(UPTO&INC.31)
UFTING BEAMS(OVER 3 VP TO & INC. 6tJ
BSEN13155(aeenote1) '
BSEN13155(sHnole1)
•
•• ••
••
0
0
35 LIFTING BEAMS(OVER6tVPTO& INC. 20t) BSEN 13155(seenoto 1)
• . .. • •••• 0
0
•• ••
•• • *••
37 LIFTINGBEAMS{OVER•Ot) BSEN13155 (11HnotD1) 0
0
•• • 0 *•• • 0
>"
*+-+-+-+-+-<
0
0
••
•• •
0 *• •
•
!-".+-+-+-+-+-<
!-".+-+-+-+-+-<
0
0
BSEN13001(soenote 1)
•• • • •• 0
•
•••
BSIS0"30ll/BSEN12385/APl$ple.9
WIRE ROPE (ON PASSENGER LIFTS) *
48
•
• •
•••
58 $HACKLES - HIGHERTENSILE(VPT0251)
S!I
60
SHACKLES-HIQHERTI:NSIU:(OVER:!SI)
EYEBOLTS(BRmSH)
•• •
• ••
61 EYEBOLTS(V.S.J
62 RIGGING SCREWS (SRmSH)
•
•••
63 RIGGING SCREWS (fURNSVCKLES) (U.S.)
&4
es
OPEN WEDGE SOCKETS (SRmSHJ
~
• •
I 1
OPEN'NEOGESOCKETS(V.S.)
..
c
,,·-·-w
0
\l
•
*
Q
&
b,.
T
•
STATUTORV REQUIREMENTS
COMPANY POU CV INCLUDES UFTING Mo'.CHNES !N 6-MONTHLVS
REFERTOSPECIFICDESIGNCOOES
INITIALFACTOAVTEST
FUNCTIONTESTONLV
AMERICAN PATTERN BLOCKS
REFER TO L.R.0.S. /D.N.V. PROCEDURE
DESCENT RATE MUST M.SOFALL BETWEEN 90-180 FT /MIN I
Uhlngsup?OnsteelwctksuchesnlllW8)'beams,~ftlngfram"5,pedeyes,etc.wlth
nomovingpmnscenh1111otheb'periodocltyextendedto12monthseslongu:
1)Th9y&l9no1usedlo<suppo<llngpersonnel.
2)Thelr uw!s lnliwq1>1nt lo the Hlent that wear~ not an adverse fac:tor and ...
3)Th9y&l9ed9<1U1tel)'cDillted/protectedsothMccm>!llonlsnoten!ldvttsel11c:tcr.
NSL
-~~-
0
I
ATTHEDlSCAETIONOFTHEINSPECTIONBODV
• ACCEPTEOPAACllCE H.andsp~edlerminllllonsmustno1 bllsubjectedtoprocMoedtestinges
(X) 11 Harvest Avenue, D2 Business Park, Dyce,
....
0 MUSTBECALIBRATEDANNVALLV excess!Yeloadinge>tndamagoandwoal<onthosploco.
*
** SAMPLE TO BE OESTAUCTEO TO VERIFY MATERIALS
FOSVAAIES-REFERTOBS565S/PD6500
Aberdeen, AB21 080
+44 (0)1224 208988
I
Sl2ootino21M(mar!r>everslcnoflo~roquiresthet.llllship"s lltUngoqu1pmenl
0 * METAL END FITTINGS ONLV
nl\JS1blltestedby1compete~person ... erySyears
[email protected] nsl.ascoworld.com
"'
PLVSNDTAE?ORT
• APISPECIFICATIONCRANESONLY
C Copyright North Sea Lilting Limited 1989 {Aev.sed 2018)
234 I C NSL 1991 I nsJ.ascowor1d.oom
Appendix 2
Density of Materials
Note:
1. In some cases the above figures arc average only and n10 actJal weight
may vary according to the part1c1,,1ar composition I water conten'. . etc.
~ 2
3.
All figures have been rounded for convenience of use.
When dealing with a hollow body, check for any contents and whether
sucn contents are liable to move.
4. For calculation purposes:
Weight
-•.rn.11i111.1.u
US (Short) TON Ton
METRIC tonne te 1,000 Mid-weight
British (Long) Ton Tor Ton 2,240 1,016 Heaviest
..
rt
Stop
n
Emergency Stop
; ~
Take the strain (or) inch the load
(Clench and unclench fingers)
I •
Hoist Lower
'n
Slew in direction indicated
.ti I
Jib up
R Jib down Extend Jib Retract Jib
(Signal with one hand, other hand on head) (Signal with one hand, other hand on head)
+
To Raise: Extend arm horizontally palm up and move arm/hand up and down at your side.
To Stop: Extend arm horizontally outward, palm down and make a horizontal
slicing motion with hand/arm.
Point your ami and fingers downwards and make a circular motion.
Warning! Only trained personnel to operate winch & use riding belt.
These signals are also used by derrickmen when communicating with rig floor.
The object of the risk assessment is to identify and eliminate or reduce to an acceptable fevel, any
hazards in the lifting operation. It should also detennine the skill level of the personnel required to
perform that particular activity safely. This document will also highlight any needs for further training.
Dateoflift: - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Please complete the result table below once the relevant parts of the assessment have been completed.
If the lift is to proceed, please enter below, any special instructions and I or safety measures to
be taken:
Once the lift has been safety completed, please note in the box below any problems encountered and
how they were overcome, also any suggestions for doing the lift more efficiently I safely.
Job Co~etion Feedback:
i
Name: Position: Date:
Are you experienced with the procedure and all the lifting equipment and
gear to be used?
0 0
Has the load been checked and made ready for lifting
0 0
(e.g . sea fastenings released, hold-down bolts removed)?
6 Is the lift in an area free from obstructions and other possible hazards? 0 0
If the answer to all six questions above is "yes", proceed with the lifting operation in
accordance with the relevant procedure or the Rigging and Lifting Handbook.
If the answer to any of the above is "no", proceed with Part 2 of the assessment.
·-~-
(Can also be carried out by all personnel who have been suitably trained.)
Ive you experienced with the procedure and all the lifting equipment and
3 D D
gear to be used?
Has the load been checked and made ready for lifting
D D
(e.g. sea fastenings released, hold-down bolts removed)?
6 Is the lift in an area free from obstructions and other possible hazards? D D
Is the lift balanced (e.g. centre of gravity in the middle) or fitted with special
D D
slings to compensate?
Is the load free to be lifted (e.g. sea fastenings released, all hold-down
D D
botts removed, not jammed, etc)?
Is the removal route suitably controlled I cordoned off and clear of any
D D
obstructions?
Can the removal {lift, transfer and landling) be pertormed without cross-
10 D D
hauling?
Is there a suitable laydown area and does the road come within the
11 D D
allowable load bearing (laydown) capacity of the deck?
Are you experienced in using all the lifting equjpment and gear involved
12 D D
and do you have a Rigging and Lifting Handbook?
If you can answer "yes" to all the above, proceed with the lift.
If the answer to any of the above is "no", proceed with Part 3 of the assessment.
Note (l): to Supervisors: Jfyou can give solutions to the above negatives to allow the lift to proceed safely, write
the instructions in the box below and if you cannot supply a solution, seek guidance from the appropriate
Competent Person(s).
The table below shall be completed by the personnel abeut to perform the lifting operation .
Tick against factors which are applicable (APP) to the specific lifting operation and indicate
whether or not you have the relevant experience to deal with them.
·-·-
NSL
+Ji.ijiif,IMW
Comphcation
Load has centre of gravity above the Uting points or a high C of G. D D D
Load has an offset centre of gravity. D D D
Load has to be cross-hauled or restrained. D D D
Load does not have specific lifting attachments D D D
LoaCI if lrag~e. D D D
Load has a large sl.Xface area which may act as a sail. D D D
Load requires two sets of rigging or two appliances tor
tandem lifting.
D D D
Load has to be rotated (overturned). D D D
If you can answer "yes" to all the above, proceed with the lift.
If you have answered "no" to any of the above, check with your immediate supervisor.
Note (2) : to Supervisors: If you have the experience and can advise personnel how to deal with the complication,
alow lhe lifting operation to proceed but only under your guidance. Alternatively, you may have to
request the services of speciaWst persomel to corrplete the work.
Note (3) : to &Jpervisors: If you decide that the lifting operation is outwith the scope of your normal rigging and
lifting activities and merits a special work instruction or Job Pack, please indicate the reasons applicable
(APP) in the table in part 4 below before passing on to the engineering department.
Crane I Hoist
Crane I hoist pre-use inspected
Certification of crane I hoist is current
Adequate capacity for lifts
Adequate boom length I height of lift
Set up correctly for lifts (correct radius I adequate number of falls)
Set up correctly (level, on firm ground)
Set up correctly (outriggers fully extended and pinned)
Set up correctly (load spreaders I sleepers used under outriggers if required)
Set up correctly (clear of overhead power lines)
Set up correctly (clear of underground services)
Set up correctly (far enough away from excavations)
Certification of ancilliary equipment current (e.g. chain slings, hook blocks etc.)
Ancillary equipment - pre-use inspected
Banksman I Signaller
Qualified I experienced to direct crane I lifting operation
In good health, fit and capable to perform the tasks
Eyesight satisfactory
Knowledge of basic slinging
Knowledge of hand signals I radio comms
i
244 I C NSL 1991 I nsl.ascowoc1d.com
Load (Tubulars)
Correctly stacked for bundling
Thread protectors securely fitted where applicable
Casing checked for possible dropped objects
Each sling rated same as load (e.g. 5 tonne load - use 2 x 5 tonne slings)
Slings inspected prior to use (including colour code if applicable)
Slings positioned 25% in from either end
Slings double wrapped, choked, bulldogged and tie-wrapped (also applies
to singles)
Bundle tight and secure but NOT with slings hammered down
Loads (Various)
Load is of sound construction
Weight of load is known
Pad eyes I temporary lifting eyes currently certified
Pad eyes I temporary lifting eyes correctly installed
Load has central C of G or special slings to compensate
Load is balanced
Any wrap-around slings will remain in place during lifting operation
~ I Leaveslnconstantmotion,light ~~
ffi~
~0
8-12 6-11 3.6-5.5 GENTLE BREEZE Small waves 0.6 to tm high, scattered whitecaps beginning to fonn.
flag extended
~~
wo
Raisesdustandpapers,small
'5 13-18 11-16 5.6-8.4 MODERATEBREEZE I
brartehesstir
Waves 1.Sm high with numerous whitecaps beginning to form. "~
~z
.5
o; 19-24 I 16-21 8.5-10.8 FRESHBllEEZE I Small trees sway
Waves up to 2.Sm high with prominent wttile waves crests; spray begins lo be ~~
:I
<II
blown from the crests. ~
,,>c 25-31 21·27 10.9-14.2 STRONG BREEZE
I Largebranchesmove,useof
umbrella difficult
3 to 3.Sm waves with numerous streaks of spray blowing from foamy crests.
z0
~
Sm waves with white foam being whipped out In the direction of the wind
"'
<II
Cl>
32-38 77-33 14.3-17.3 MODERATE GALE I WholetreeslnmoUon
gusts.
!:! Tw1gsbrokenofftrees,d1fflcultto Extremely rough, violent sea with 6 to Bm waves; dense loamy streaks show
0 • 39 · 46 33-40 17.4-21.0 FRESH GALE
,,c
LL
47·f>4 21.1-24.5 STRONG GALE
driveacar
Slightstruch1raldamageoccurs
wind direction.
8to9mwaves:seabe9inslor0Uasheavyst1eaksofloamandsprayaresei!n
§ ' 40·46
on all sides
Trees uprooted, severe structural !I to 12m waves: sea 1s covered with white loam; v1s1b1hty allected by blown
0 10 55·63 46·54 24.6·28.5 WHOLE GALE
damage spray;shipisshockedbylorceofwaves.
Cl>
o; 11 64-73 54-63 28.6·32.6 STORM Widespread damage Can'tseethewaveslorbeingseasick!
0
I'- en
x ~ 12 AB0VE75 ABDVE63 JJ.7 HURRICANE Devastation Can'tseethewaves(hidingintheheads)!
_
'6
cQ)
~ NOTES: This table should be used for guldan.ce only. The safety of any lifUng operalian In windy conditions must be addressed lndMdually during the risk assessment process when all other relevant !actors are taken into
a.
a. "'Cl> J consideration.Average wind speeds reterredtoaboveareat10mabovesea level. Thlswlnd speed~s/!°!::::n:ttlanthewlndspeedat3mabovesea level.Allflguresaretalrlyaccurate buthawebnnrouoded I ~
<( Ill
....
ALWAYS:
I
The International Rigging & Lifting HandOOok I 247
Notes