0% found this document useful (0 votes)
403 views10 pages

Pre-Commissioning Matrix Guide

This document outlines the responsibilities for pre-commissioning and commissioning activities for the South Sembakung Development project in Simenggaris Block, North Kalimantan. It defines various roles like contractor, JOB P-MEPS, and third parties. An attachment provides the pre-commissioning and commissioning responsibility matrix that assigns scopes of work to different disciplines like mechanical, piping, instrumentation etc. Abbreviations are also defined to clarify terms used in the matrix.

Uploaded by

ono_cze
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
403 views10 pages

Pre-Commissioning Matrix Guide

This document outlines the responsibilities for pre-commissioning and commissioning activities for the South Sembakung Development project in Simenggaris Block, North Kalimantan. It defines various roles like contractor, JOB P-MEPS, and third parties. An attachment provides the pre-commissioning and commissioning responsibility matrix that assigns scopes of work to different disciplines like mechanical, piping, instrumentation etc. Abbreviations are also defined to clarify terms used in the matrix.

Uploaded by

ono_cze
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

( MEI )

INTER ‐ DISCIPLINE CHECK (IDC)

Project Title: SOUTH SEMBAKUNG DEVELOPMENT IDC No: MEI‐JOBSMN‐TR‐0366

Originator: KDY Date of Circulation: 02 Dec 21 Date to be return to DCC: 07 Dec 21

Document/Drawing No. Title/Description Current Rev. Status

SMN‐J‐PR‐00‐141 Pre‐Commissioning & Commissioning 02 Re‐IFI


Responsibility Matrix
Note.

CIRCULATION LIST
Date
No Discipline Initial Title/Comment Sign
Target Actual
1. Project Manager AZ

2. Engineering Sect. Head AMW 07‐12‐21 Review

3. Construction Sect. Head DPS 07‐12‐21 Review

4. Project Control Sect. Head PR

5. Project Engineer LS 07‐12‐21 Review

6. Process/Process Safety Engineer EHS/YS 07‐12‐21 Review

7. Mechanical Engineer AY/YAN Info

8. Piping Engineer AY/BP Info

9. Pipeline Engineer AY/AS Info

10. Instrument Engineer FAP/SW Info

11. Electrical Engineer SAF/SW Info

12. Civil Engineer LS Info

13. Construction Engineer KRH Info

14. QA/QC Engineer HY/MRY 07‐12‐21 Review

15. HSSE Engineer OS

16. Commissioning Engineer KDY 07‐12‐21 Owner

17. Project & Cost Control Engineer SP/AN/CAA Info

18. Contract Engineer CBO/RTH

19. Document Control ANH/AS

20. Technical Expert

The above document(s) have been reviewed and incorporate in the referenced document(s)/drawing(s) as appropriate

Final Review by: Approved by:

Dedy Parsaoran Sianturi Akhmad Zamroni


Construction Section Head Project Manager
File: Project Document Control: ANH / ASA
JOB PERTAMINA – MEDCO E&P SIMENGGARIS

PROJECT TITLE: SOUTH SEMBAKUNG DEVELOPMENT

DOCUMENT TITLE: Pre-Commissioning & Commissioning Responsibility Matrix

DOCUMENT NO.: SMN-J-PR-00-141

CONTRACTOR JOB P-MEPS


REV DATE DESCRIPTION
PREPARED CHECKED APPROVED APPROVED
X 4 Oct 21 Inter Discipline Check EMT DSL DSL
00 11 Oct 21 Issued for information EMT DSL DSL
01 05 Nov 21 Re-Issued for information EMT DSL DSL
02 30 Nov 21 Re-Issued for information
EMT EMT
DSL

UNAUTHORIZED COPYING OF THIS DOCUMENT IS NOT PERMITTED.

WO. No: REV.


JOB P-MEPS
3510006782 02
SIMENGGARIS BLOCK DISCIPLINE: Page
COMM Page 1 of 8
Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

COMMENT SHEET

Incorporated
Rev Section Page Comment (Y/N) Description

00 6 Please add abbreviation detail Y


00 4 Listed all attachment Y
00 9 Please add on test package CST as M Y
00 9 Please add on hydraulic oil flushing Y
PCC as W
01 10 CST add M Y

Doc. No: SMN-J-PR-00-141 Page 2 of 8


Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

TABLE OF CONTENTS

COMMENT SHEET ................................................................................................................. 2

TABLE OF CONTENTS .......................................................................................................... 3


1. INTRODUCTION ...................................................................................................................4
2. PURPOSE ..............................................................................................................................5
3. REFERENCE .........................................................................................................................5
4. DEFINITION AND ABBREVIATION ........................................................................................5
5. SCOPE ....................................................................................................................................5
6. WITNESSING LEVEL DEFINITION ........................................................................................5
7. THIRD PARTY SCOPE ...........................................................................................................6
8. ATTACHMENT ........................................................................................................................7
ATTACHMENT 1 – Pre-commissioning and Commissioning works Responsibility Matrix ..............7

Doc. No: SMN-J-PR-00-141 Page 3 of 8


Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

1. INTRODUCTION
JOB Pertamina - Medco E&P Simenggaris, hereafter known as COMPANY, is the operator of
South Sembakung Field located at Simenggaris Block, North Kalimantan. The South
Sembakung Field has a South Sembakung Gas Plant was designed to produce 30 MMscfd gas
for 20 years. Currently, there are 4 (four) wells which have been drilled; namely SSB-2 as
production well and three development wells namely SSB-4, SSB 5 and SSB-7, which are
currently under temporary suspension.
Based on the Gas Sales and Purchase Agreement (PJBG) to PT. PLN 8 MMSCFD and PT.
Kayan LNG 22 MMSCFD, the addition of 3 (three) development wells will be required, namely
SSB-8, SSB-9 and SSB-10.
COMPANY has initiated the new Project to accommodate produced gas from the new wells. The
project will consist of installation of : new wellsite facilities and its flowlines, LLP production
manifold and LLP production separator, new condensate handling system (heater, tanks,
pumps, custody meter and export line), new (future) compressor package during wells
pressure depletion and other repair and modifications required.

Figure 1 – South Sembakung Field Location


PT. Meindo Elang Indah has been awarded the Engineering, Procurement, Construction,
Installation & Commissioning of South Sembakung Gas Development

Doc. No: SMN-J-PR-00-141 Page 4 of 8


Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

2. PURPOSE

The foremost intention of this document is to ensure the proper demarcation of all Pre-
Commissioning and Commissioning works and responsibilities of all parties involved with CPY
witnessing and monitoring are properly identified and in place during pre-commissioning
preparation and execution phase of this project.

3. REFERENCE

Internal Document
SMN-J-PR-00-153 Pre-Commissioning and Commissioning
Execution Plan
SMN-J-PR-00-158 Punchlist Management Procedure

4. DEFINITION AND ABBREVIATION

MEI Meindo Elang Indah


ICAPS Integrated Commissioning and Progress System
AOC Achievement of Commissioning
RFC Ready for Commissioning
CST Construction
PCC Pre-Commissioning and Commissioning
OPR Operation
FCG Flooding, Cleaning and Gauging
Worksite Onshore Fabrication Yard

5. SCOPE

This document provided the scope for responsibility matrix for pre-commissioning and
commissioning works

6. WITNESSING LEVEL DEFINITION

The three levels at which the Pre-commissioning and the Commissioning activities will be
witnessed are as follow :

 Responsibility (R)
 Witness (W)

Doc. No: SMN-J-PR-00-141 Page 5 of 8


Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

 Monitor (M)

LEVEL 1 : RESPONSIBILITY (R)

RESPONSIBILITY points are defined as points within the project life cycle for which the formal
approval of the Company is obtained in order to proceed with the activities. Subsequent activities
directly linked to an RESPONSIBILITY Point are not carried out until an inspection/surveillance
activity is carried out by the Company.

RESPONSIBILITY points shall be subject to a minimum notification time of:

 24 hours for a Pre-commissioning activity

 24 hours for a Commissioning activity


LEVEL 2 : WITNESS (W)

WITNESS points are defined as points within the project life cycle that the Company may decide to
witness and approve progress to subsequent activities as applicable. Should Company not be
present at the appointed time for a WITNESS Point, then based on agreement with the Company,
the activity is permitted to proceed. Witness points shall be subject to a minimum notification time
of:

 24 hours for a Pre-commissioning activity

 24 hours for a Commissioning activity

LEVEL 3 : MONITOR (M)

MONITOR points are defined as points within the project life cycle for which the Company may
monitor activities, service, equipment or material, but specific approval is NOT REQUIRED for
Contractor proceed

7. THIRD PARTY SCOPE

There are activities during Pre-commissioning phase shall be held and witness by Third party such
as lifting equipment and PSV Pop Up testing. During Pre-commissioning and Commissioning phase
Contractor will coordinate with Third party inspection and/or classification party. The Certificate
issued by Third Party shall include in Pre-commissioning Dossier

Doc. No: SMN-J-PR-00-141 Page 6 of 8


Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

8. ATTACHMENT

ATTACHMENT 1 – Pre-commissioning and Commissioning works Responsibility Matrix

Doc. No: SMN-J-PR-00-141 Page 7 of 8


Doc. No.:
Pre-Commissioning &
SMN-J-PR-00-141
Commissioning
Responsibility Matrix
Revision : 02
SIMENGGARIS BLOCK
Date : 30 Nov 2021

ATTACHMENT 1 – Pre-commissioning and Commissioning works Responsibility Matrix

Doc. No: SMN-J-PR-00-141 Page 8 of 8


PRE-COMMISSIONING & COMMISSIONING WORKS RESPONSIBILITY MATRIX

FUNCTIONS
PREPARATION & EXECUTION WITNESSING & MONITORING
ITEM WORK /ACTIVITY DESCRIPTION COMPANY
CONTRACTORS JOB PERTAMINA EP-MEDCO
REMARKS
CERTIFYING
MEI VENDOR REMARKS CST PCC OPR
AUTHORITY
WORKSITE SIMENGGARIS
Engineering/Preparation
1 Planning and Scheduling R - - - - -
2 System and Sub-System List Preparation R - - - - -
3 System & Sub-System Marked Up Drawings Preparation R - - - - -
4 ICAPS Data Base Population R - - M M -
5 Dossier Preparation, handling and submission R - - M - - 02
6 Test Package preparation and handling R - - - - -
7 Work Execution R
7.1 Instument Calibration Test R - - W M -
7.2 Critical Valve Seat Leak and Stroke Test R - - - W
7.3 Flushing, Hydro Test and Re-Instatement R - - - W -
7.4 Gross Leak Test R - - - W -
7.5 Hydraulic Oil Flushing and Leak Test R R - - W -
witnessed & certified by
7.6 PSV Pop Up Test R - R W W M
third party (MIGAS)*
7.7 General conformity checks R - - W W -
7.8 Cable continuity and megger test R - - W M -
7.9 Tubing flushing and leak test R - - W W M
7.10 Vessel internal cleaning and final closure R - - M W W CPY Specialist
Vendor reuired during
FCG + C and Hydro Test (Pipeline) R R - Caliper pigging operation - W M
7.11 only
CTR Scope is for isolation / CPY to perform the actual
R - - H
de-isolation permit
7.12 Isolation / de-isolation isolation / de-isolation
7.13 SAT of selected packages R R - W M
7.14 General conformity checks R - - W W -
7.15 Cable continuity and megger test R - - W M -
7.16 Equipment function tests R R - - W -
7.17 Nitrogen Leak Test R - - - W -
Vendor for CPY supplied
7.18
Operational Test by System R R - - W M
items will be as required
7.19 Preservation R - - M W -
8 Punch List Management -
8.1 Clearing of FAT punch list at Meindo yard R R - W M -
8.2 Issuing of punch list prior to RFC and AOC R - - H H -
8.3 Verification/Validation of Punch List items entry to Data Base R - - H H -
8.4 Closing of Pre-Commissioning/Commissioning Punch Lists R A - Vendor assistance as required W W M
8.5 Approval/Clearance of Punch Lists - - - H H M

Note :
* : Third party or Certifying Authority in charge of the verification that the relevant standards and codes are met
Legend:
R - Responsibility
A - Assist
W - Witness
M - Monitor

You might also like