Drilling Operations Module 1 Introduction To Drillingg
Drilling Operations Module 1 Introduction To Drillingg
MODULE 1
INTRODUCTION TO DRILLING
i
INTRODUCTION TO DRILLING - MODULE 1
TABLE OF CONTENTS
1. Module Objectives 7
3.1 Overview 18
2
INTRODUCTION TO DRILLING - MODULE 1
4.1.14 Fuel Tanks
29
4.1.15 Electrical Control Room 29
4.1.16 Mud Pumps 30
4.1.17 Mud Components 30
4.1.25 Accumulator 33
34
5. Rig Crew Familiarisation
34
5.1 Drilling Team
34
5.1.1 Roughneck
34
5.1.2 Derrickman
34
5.1.3 Assistant Driller
35
5.1.4 Driller
35
5.1.5 Tool Pusher
36
5.2 Deck Crew or Marine Team 36
5.2.1 Barge Engineer
36
5.2.2 Crane Operators
36
5.2.3 Roustabout
37
5.3 Maintenance Team 37
5.3.1 Rig Maintenance Supervisor (RMS) 37
5.3.2 Rig Electrician 37
5.3.3 Motorman or Rig Mechanic 38
5.3.4 Electronics Technician
38
5.4 Administrative Team
38
5.4.3 Medic 39
5.5.2 Cementer 40
Rig Systems 42
7.3.2 Hammer 49
7.4 Drilling 50
7.9 Liners 54
4
INTRODUCTION TO DRILLING - MODULE 1
TABLE OF FIGURES
5
INTRODUCTION TO DRILLING - MODULE 1
igure 45 - Shale Shakers............................................................................................................... 31
igure 46-Choke Manifold ............................................................................................................... 32
igure 47 - Vee Door and Catwalk................................................................................................... 32
igure 48 - Pipe Racks.................................................................................................................... 33
igure 49 - Accumulator .................................................................................................................. 33
igure 50 - Roughnecks .................................................................................................................. 34
igure 51 - Derrickman ................................................................................................................... 34
igure 52 - Assistant Driller ............................................................................................................. 34
igure 53 - Driller ............................................................................................................................ 35
igure 54 -Tool Pusher ................................................................................................................... 35
igure 55 - Barge Engineer ............................................................................................................. 36
igure 56 - Crane Operator ............................................................................................................. 36
igure 57 - Roustabout ................................................................................................................... 36
igure 58 - Rig Maintenance Supervisor.......................................................................................... 37
igure 59 - Rig Electrician ............................................................................................................... 37
igure 60 - Motorman or Rig Mechanic............................................................................................ 37
igure 61 - Electronics Technician................................................................................................... 38
igure 62-OIM................................................................................................................................. 38
igure 63 - Safety Officer ................................................................................................................ 38
igure 64- Medic ............................................................................................................................. 39
igure 65 - Radio Operator.............................................................................................................. 39
igure 66 - Camp Boss ................................................................................................................... 39
igure 67 - Catering Personnel........................................................................................................ 40
igure 68 - Mud Engineer................................................................................................................ 40
igure 69 - Cementer ...................................................................................................................... 40
igure 70- Mud Logger .................................................................................................................... 41
igure 71 - Wireline Engineer .......................................................................................................... 41
igure 72-MWD, PWD, LWD ........................................................................................................... 41
igure 73 - Hoisting System Diagram .............................................................................................. 42
igure 74- Kelly ............................................................................................................................... 43
igure 75-TDS ................................................................................................................................ 43
igure 76 - Circulating System ........................................................................................................ 44
igure 77 - Solids Control Equipment .............................................................................................. 44
igure 78 - Simple Rig Power System Diagram ............................................................................... 45
igure 79 -Typical BOP Configuration ............................................................................................. 46
igure 80 -Typical Well Design ........................................................................................................ 47
igure 81 - Casing Joint .................................................................................................................. 48
igure 82-Spudding the Well ........................................................................................................... 49
igure 83- Drill Bit ........................................................................................................................... 50
igure 84 - Cementing Diagram ...................................................................................................... 51
igure 85 - Surface and Subsea BOP's ........................................................................................... 52
igure 86 - Well Schematic ............................................................................................................. 53
igure 87 - Perforation .................................................................................................................... 54
igure 88- Dry Tree Surface Wellhead ............................................................................................ 55
6
INTRODUCTION TO DRILLING - MODULE 1
1. MODULE OBJECTIVES
This is a self-study course designed to teach the key terms and concepts that are essential to the oil
and gas drilling industry. Topics include cable-tool and rotary drilling, rig types and components, land
and offshore drilling operations. This module is the first in a series of modules and will teach you the
following basic lessons:
The Chinese have used oil and gas for many centuries. There is no record of when Chinese began
using natural gas, but clearly in Szechuan the local people were drilling down hundreds of feet into
the earth to get natural gas and brine before the start of the Han Dynasty, before 400 B.C.
The Chinese used bamboo pipelines to carry natural gas and mix it with air to yield a usable source of
fuel for fires.
The initial discovery of natural gas may have come as a serendipitous by product of the search for
brine and salt, and the natural gas fires were certainly used on brine taken from wells to evaporate
the water and recover salt. Natural gas wells were called fire wells.
Edwin Drake is often mentioned for digging a modern oil well in Pennsylvania in 1859, starting a
boom in the modern petrochemical and mining industries, but people had been drilling wells in China
over two thousand years before him.
8
INTRODUCTION TO DRILLING - MODULE 1
2.2. Advancement of Chinese Drilling
The first drilling technique developed in China was the Spring Pole Technique seen in Figure 2,
which harnessed the motion of a wooden pole to lower and raise a drill bit into the ground. The
broken rock would then be lifted out with a separate bailing tool.
By the first century B.C., the technology of well-drilling had advanced to the use of a derrick and
cable tools.
Chinese engineers were able to dig down over 800 feet, and commonly did so as part of a brine
industry in Szechuan.
9
INTRODUCTION TO DRILLING - MODULE 1
2.3. Development of Early Drilling Tools
The percussion drilling method on its own is impressive, especially when considering that the rest of
the world had nothing comparable in the earlier centuries.
But even more impressive are all the techniques the Sichuan drillers developed to overcome common
drilling problems such as cave ins, lost tools, deviated wells, and so on. A huge variety of tools and
techniques evolved to handle well repair issues and some examples can be found in Figure 3.
Figure 4 - Traditional
Chinese Drilling
Equipment
Pictured in Figure 4 is the the "Fish Tail" drill bit, a long and very heavy bit used to create the
initial large diameter hole at the wellhead. This was made of Iron and attached to a Bamboo pole
with a stabilizer wrapped around the top.
10
INTRODUCTION TO DRILLING - MODULE 1
2.4. The Development of Spring Pole Drilling in the USA
Drilling knowledge which started in China eventually made its way to the rest of the world. In the
United States the Spring pole technique was being used successfully to drill for "Brine" so that
Salt could be extracted.
There was money to be made from brine wells. The rapidly growing number of settlers in the
frontier needed a lot of salt to preserve food. However, Often Brine wells were fouled with the
intrusion of unsought and unwanted oil.
While repeatedly kicking down a stirrup was primitive and slow, the spring pole's rope and chisel
were still practical drilling technologies.
In 1802 in what is now West Virginia, salt brine drillers David and Joseph Ruffner took 18-months
to drill through 40 feet of bedrock to a total depth of 58 feet using a spring pole.
The well's historic significance rests on the "development of well drilling tools and practices, which
became almost immediately standard equipment used by many other well drillers in the new salt
industry."
The rainbow sheen and pungent smell of oil was bad news to brine drillers.
11
INTRODUCTION TO DRILLING - MODULE 1
2.5. The Derrick and Cable Tool Drilling (Percussion Drilling)
The advent of cable-tool drilling introduced the wooden derrick into the changing American
landscape. Using the same basic notion of chiseling a hole deeper and deeper into the earth.
Frequent stops were needed to remove the chipped-away rock and other material, bail out water- and
sharpen the bit.
Bull wheels and hemp rope repeatedly hoisted and dropped heavy iron drill strings and a curious
variety of bits deep into the borehole.
Oil was still an adversary to those in search of either fresh water or brine. When Yale chemist,
Benjamin
Silliman, found that oil could be distilled into a kerosene illuminant, the world changed forever.
Inspired entrepreneurs with the idea of using cable tool drilling to extract oil quickly got to work.
12
INTRODUCTION TO DRILLING - MODULE 1
Edwin L. Drake's 1859, discovery of commercial quantities of oil at 69. 5 feet in Titusville,
Pennsylvania, brought America's first drilling boom — and virtually created an industry over night.
Drake was the first to use large diameter pipe to case the hole.
Soon, cable-tool rigs were everywhere, pounding into the earth, searching for oil.
In 1860 steam engines were introduced to power rigs and the drilling operation became much more
efficient.
As wells got deeper, some drilling experts found resistant rock strata that made progress far more
difficult using the percussion drilling method. Sometimes the drilling tools got stuck threatening the
well.
13
INTRODUCTION TO DRILLING - MODULE 1
2.6. Development of Rotary Drilling
Instead of the repetitive lift and drop of heavy cable-tool bits, rotary drilling introduced the hollow drill
pipe that enabled drilling fluid to be circulated down through the drill pipe and then cuttings would be
washed out of the borehole while the rotating drill bit cut deeper.
By applying downward pressure, the drilling fluid also stops an oil well from kicking unexpectedly.
This was achieved by using a fluid weight that was greater than the anticipated reservoir pressure.
Archaeological records show that as early as 3000 BC the Egyptians may have been using a similar
technique.
Leonardo Di Vinci, as early as 1500, developed a design for a rotary drilling mechanism that bears
much resemblance to today's technology.
14
INTRODUCTION TO DRILLING - MODULE 1
Drillers would grind their way through layers of rock rather than pounding, and the heavy fishtail bits
made history.
Rotary rigs soon became the preferred means of drilling after the efforts of Captain Anthony Lucas
and Patillo Higgins in drilling their 1901 "Spindletop" well in Texas for oil, although to this day they still
share the oil patch with a few cable-tool rigs.
The new oil field at Spindletop in Texas soon produced more than 100,000 barrels. The record depth
recorded for a cable-tool rig is 11,145 feet. On Russia's Kola Peninsula, a rotary rig reached more
than 40,000 feet after ten years of drilling.
15
INTRODUCTION TO DRILLING - MODULE 1
2.7. Offshore Drilling Rigs
In 1896, as enterprising businessmen pursued California's prolific Summerland oilfield all the way to
the beach, the lure of offshore production enticed Henry L. Williams and his associates to build a pier
300 feet out into the Pacific - and mount a standard cable-tool rig on it.
By 1897 this first offshore well was producing oil and 22 companies soon joined in the boom,
constructing 14 more piers and over 400 wells within the next five years. The Summerland offshore
field produced for 25 years - fueling the growth of California's economy.
By 1921, steel piers were being used in Rincon and Elwood (California) to support land-type drilling
rigs. In 1932, a steel-pier island (60 x 90 ft with a 25-ft air gap) was built V* mile offshore by a small oil
company, Indian Petroleum Corp., to support another onshore-type rig. Although the wells were
disappointing and the island was destroyed in 1940 by a storm, it was the forerunner of the steel-
jacketed platforms of today.
16
INTRODUCTION TO DRILLING - MODULE 1
2.8. Offshore Floating Rigs
The first truly offshore Semi-Submersible Drilling Rig was the Mr. Charlie, designed and constructed
from scratch by Ocean Drilling and Exploration Co. (ODECO), headed by its inventor and president,
"Doc" Alden J. Laborde. The Mr. Charlie was a purpose-built submersible barge built specifically to
float on its lower hull to location and, in a sequence of flooding the stern down, ended up resting on
the bottom to begin drilling operations. When the Mr. Charlie went to its first location in June 1954,
Life magazine wrote about the novel new idea to explore for oil and gas offshore. The Mr. Charlie was
rated for 40-ft water depth.
Another semi-submersible resulted from an unexpected observation in 1961. Blue Water Drilling
Company owned and operated the four-column submersible Blue Water Rig No.l in the Gulf of Mexico
for Shell Oil Company. As the pontoons were not sufficiently buoyant to support the weight of the rig
and its consumables, it was towed between locations at a draught mid-way between the top of the
pontoons and the underside of the deck. It was noticed that the motions at this draught were very
small, and Blue Water Drilling and Shell jointly decided to try operating the rig in the floating mode.
17
INTRODUCTION TO DRILLING - MODULE 1
3. TYPES OF DRILLING RIGS
3.1 Overview
The most commonly used rigs in the industry are Jack-ups, used to drill in shallow water, Semi-
Submersible, used to drill in deep water and Land rigs which are moved on trailers and spotted on
concrete bases on land.
Fixed Platforms and Drill Ships are other types which can have drilling facilities on board. The most
expensive to run is the Drill ship followed by the Semi, then the Jack-up and finally the Land rig.
This is all down to the size, equipment differences and also the difficulty with logistics to and from the
rig. Each rig will have similar drilling equipment on board but some will vary due to the nature of the
rig.
Figure 14 below depicts from left to right; Land Rig, Fixed Platform, Jack-Up, Semi-Submersible and
Drill Ship.
18
INTRODUCTION TO DRILLING - MODULE 1
3.2 Semi-Submersible Drilling Rigs
These rigs sit on pontoons and float high above the water. The ballast tanks can be adjusted to raise
or lower the rig and they can be moved under their own power or towed into place.
Once in place the rig will deploy its six anchors and they will be tensioned accordingly to move the rig
over the drilling location. Semi-Submersible rigs can be used in water depths from 200 ft - 10,000 ft
(60 m - 3000 m).
The main difference with drilling from a Semi is that the rig is not static and is constantly moving with
the swell, therefore the drill pipe moves up and down with the swell.
Therefore the rig is fitted with heave compensators which keep the drill pipe firmly at the bottom whilst
drilling. When the rig moves upwards the heave compensators push down the drill pipe and vice
versa.
19
INTRODUCTION TO DRILLING - MODULE 1
3.4 Jack Up Drilling Rigs
These rigs are towed into location and then jack their 3 legs down until the legs reach the sea bed.
Some larger rigs can have up to 5 legs. The rig will then raise itself out of the water to the desired
height. Jack-ups are good in water depths of up to 400 ft (120 m) and can be found most commonly in
the North sea because of the seas shallow nature. Once settled the Jack-up rig has a static base in
which to drill from. When their legs are not deployed, jack ups float, and are transported from one
drilling location to another. While some are capable of self-propulsion, most jack ups are transported
via tug boats.
There are two ways to mount the drilling equipment on the hull.
• Cantilever decks. Mount the drilling derrick on an arm that extends outward from the main deck.
With a Cantilever deck, drilling can be performed through existing platforms, as well as without
them. Most jack ups built in the last 10 years have been cantilevered jack ups.
• The other type is the Slot Type jack up, also known as the key way jack up.This is basically a
large opening in the hull with the derrick positioned over it.
20
INTRODUCTION TO DRILLING - MODULE 1
3.5 Land Drilling Rigs
The land-based drilling rig is the most common type used for exploration. These type of rigs come in
a variety of sizes depending on the type of well you will be drilling.
The rig breaks down into many parts so that it can be transported with trucks and trailers. First a
concrete base will be laid at the location of the well and a pit will also be dug next to the location for
the cuttings from the well to be temporarily dumped into.
These rigs can be assembled very quickly usually within 3-7 days and can be transported in as little
as 12 truck loads.
The depth that a rig can drill to depends on the power of its drawworks which lowers and raises the
drill pipe from the well.
21
INTRODUCTION TO DRILLING - MODULE 1
3.6 Fixed Drilling Platforms
Today they're usually used to tap shallow, long term oil deposits and have multiple wells drilled from
one location. These platforms are permanently anchored directly to the seabed with the use of a steel
structure known as a "jacket". This rises up from the seabed to support a surface deck which is above
the ocean. The jacket provides the rig's sturdy base and holds everything else out of the water, while
the drilling modules and crew quarters are located on the surface deck. They can drill to depths of
about 1,500 feet below the surface, but are expensive to build, so they usually require a large oil
discovery to justify their construction.
It has a broadly conventional ship's hull, but also feature a large aperture, known as a "moon pool",
through which drilling takes place. Either purpose built, or converted from some other use, drill ships
can be moved easily between locations. They can carry large stocks of supplies, but are not as stable
as semi-submersibles. Drill ships use either anchors or dynamic positioning to maintain station. The
latest drill ships can operate in 1,500 meters of water. Drill ships are differentiated from other offshore
drilling units by their easy mobility. While Semi Submersible rigs can also drill in deep waters, drill
ships are able to propel themselves from well to well and location to location, unlike Semi subs, which
must rely on an outside transport vessel to transfer them from place to place.
22
INTRODUCTION TO DRILLING - MODULE 1
3.8 Coil Tubing Drilling Rig
Coil Tubing technology is best suited to re-entering existing wells, and when multiple casing wells are
unnecessary. In some cases, coiled tubing technology can replace the typical drill string with a
continuous length of pipe stored on a large spool. This approach has many benefits, including
reduced drilling waste and minimized equipment footprints, so it is especially useful in environmentally
sensitive areas. No drill pipe connections means that tripping in and out of the hole operations
become very fast compared to conventional drilling practices. Some old vertical wells can be re-
entered with coil tubing and kicked off in a horizontal direction to allow more of the reservoir to flow
into the well bore. A down hole motor is used to transfer rotation to the drill bit.
23
INTRODUCTION TO DRILLING - MODULE 1
4. RIG EQUIPMENT ORIENTATION
The diagram shown is of a land rig but the principles are the same for an offshore rig. The following
lessons will describe in detail what each piece of equipment is used for.
1. Crown Block
2. Catline Boom and Hoist Line
3. Drilling Line
4. Monkeyboard
5. Traveling Block
6. Top Drive
7. Derrick or Mast
8. Drill Pipe
9. Doghouse or drillers shack
10. Blowout Preventer
11. Water Tank
12. Electric Cable Tray
13. Engine Generator Sets
14.Fuel Tanks
15. Electrical Control Room
16. Mud Pump
17. Bulk Mud Components Storage
18. Mud Pits
19. Waste Pit
20. Mud Gas Separator
21. Shale Shakers
22. Choke Manifold
23. Vee Door and Catwalk
24. Pipe Racks
25. Accumulator
24
INTRODUCTION TO DRILLING - MODULE 1
4.1.1 Crown Block
25
INTRODUCTION TO DRILLING - MODULE 1
4.1.4 Catline Boom and Hoist Line
A structural framework erected near the top of the derrick for lifting
heavy material around the rig floor and pipe ramp. The hoist line is
attached to a mechanical air driven winch.
The top drive rotates the drill string without the use of a kelly and
rotary table. The top drive is operated from a control console on
the rig floor.
26
INTRODUCTION TO DRILLING - MODULE 1
4.1.7 Mast or Derrick
Figure 31 - Derrick
The heavy seamless tubing used to rotate the drill bit and circulate
the drilling fluid. Joints of pipe of 30 feet long are coupled together
with tool joints. Usually three pipes are joined and this makes a
"stand". Drill pipes come in different sizes and standards which I
will later cover in another article.
27
INTRODUCTION TO DRILLING - MODULE 1
4.1.10 BOP (Blowout Preventer)
Supports the heavy electrical cables that feed the power from the
control panel to the rig motors.
28
INTRODUCTION TO DRILLING - MODULE 1
4.1.13 Engine Generator Sets
Large storage tanks that hold the fuel supply for the rig generators
and other rig equipment.
Most rigs have 3 electrically powered triplex fluid pumps that pump
the drilling fluid (mud) down the drill pipe and into the well. Each
pump can supply high volume, up to 500 gpm and high pressures
of up to 7500 psi. The volume and pressure depends on the size
and length of the pump liners which can be changed.
These are large tanks which can hold up to 400 barrels each and
the entire pits will be made of of many of these tanks. The mud is
blended into these tanks and kept at a constant weight and
viscosity ready to be circulated into the well and returned back to
the pits.
30
INTRODUCTION TO DRILLING - MODULE 1
4.1.19 Reserve Pit
Any pit not part of the active (circulatory) system. The reserve pit
may be used to store spare or waste mud, base oil or brine. In
operations on land, the reserve pit is usually a plastic-lined,
earthen pit, in which waste mud is stored until final disposal.
The primary and probably most important device on the rig for
removing drilled solids from the mud. This vibrating sieve is simple
in concept, but a bit more complicated to use efficiently. A wire-
cloth screen vibrates while thedrilling fluid flows on top of it. The
liquid phase of the mud and solids smaller than the wire mesh
pass through the screen, while larger solids are retained on the
screen and eventually fall off the back of the device and are
discarded.
31
INTRODUCTION TO DRILLING - MODULE 1
4.1.22 Choke Manifold
The upside down V-shaped opening in one side of the derrick that
enables long pipes and tools to be lifted into the interior of the
derrick. This opening is aligned with the slide and catwalk of the
rig. The Cat walk is a long, rectangular platform about 1 m high,
usually made of steel and located perpendicular to the vee-door at
the bottom of the slide. This platform is used as a staging area for
rig and drillstring tools, components that are about to be picked up
and run, or components that have been run and are being laid
down.
32
INTRODUCTION TO DRILLING - MODULE 1
4.1.24 Pipe Racks
4.1.25 Accumulator
Figure 49 - Accumulator
33
INTRODUCTION TO DRILLING - MODULE 1
5. RIG CREW FAMILIARISATION
5.1.1 Roughneck
Also know as floor hands who do the jobs on the rig floor. The job
of the roughnecks is to make connections in the drill pipe using
pipe tongs or an automatic device known as an "iron roughneck".
Roughnecks "trip pipe" joints of drill pipe into and out of the hole
when drill bits, etc, need to be changed.
Figure 50 - Roughnecks
5.1.2 Derrickman
Figure 51 - Derrickman
Runs the work crew and takes information from the driller and give
it to their crew. While the assistant driller acts in a predominately
supervisory role, they may also work alongside the roughnecks to
run machinery. AD's train roughnecks to recognize abnormal well
conditions in order to prevent leaks and rig blowouts.
34
INTRODUCTION TO DRILLING - MODULE 1
5.1.4 Driller
Figure 53 - Driller
On a land drilling rig the tool pusher may be the rig manager and
responsible for all operations, but on drill ships and offshore oil
rigs, tool pushers are in charge of the drilling department and
report to the Offshore Installation Manager (OIM).
35
INTRODUCTION TO DRILLING - MODULE 1
5.2 Deck Crew or Marine Team
5.2.3 Roustabout
The job of roustabout is about the easiest entry level job to get. It
involves a lot of hard manual labor and long work hours.
Roustabouts typically are involved on the main deck with painting
and sandblasting, unloading pipe and other kinds of physical work.
During breaks they also fill in for the roughnecks on the rig floor.
Figure 57 - Roustabout
36
INTRODUCTION TO DRILLING - MODULE 1
5.3 Maintenance Team
37
INTRODUCTION TO DRILLING - MODULE 1
5.3.4 Electronics Technician
The OIM is the overall responsible for the rig and its personnel.
His/her position is equivalent to the Captain position on board a
ship and he/she must take an extensive series of safety,
environmental and leadership courses to build up the necessary
theoretical knowledge to lead a crew of up to 180 members.
Overall responsible for all safety of personnel onboard, and he/she
ensures that all operations onboard are performed in line with all
rules and regulations. He/she also ensures that the client's
representative is kept informed about all activities and operations
on board the rig-
Figure 62 - OIM
The Safety Officer assists the rig management in ensuring that the
health, safety and environmental (HSE) work on the unit complies
with the applicable HSE rules and regulations. He/she heads
campaigns, initiatives, audits, inspections and investigations
concerning work safety, with particular emphasis on rules and
regulations concerning emergency preparedness. They control the
rigs permit to work system and chair regular HSE meetings
onboard.
38
INTRODUCTION TO DRILLING - MODULE 1
5.4.3 Medic
The Camp Boss is responsible for all hotel services on the rig and
leads the catering crew. He/she is responsible for the safety, work
schedules, job content and work allocation of catering personnel,
and for maintaining the food stocks.
39
INTRODUCTION TO DRILLING - MODULE 1
5.4.6 Catering Personnel
Responsible for testing the mud at a rig and for prescribing mud
treatments to maintain mud weight, properties and chemistry within
recommended limits. The mud engineer works closely with the rig
supervisor to disseminate information about mud properties and
expected treatments and any changes that might be needed. The
mud engineer also works closely with the rig's derrickman, who is
charged with making scheduled additions to the mud during his
work period.
5.5.2 Cementer
Figure 69 - Cementer
40
INTRODUCTION TO DRILLING - MODULE 1
5.5.3 Mud Logger
Figure 70 - Mud Logger
Mud Logging Technicians in an oil field drilling operation determine
positions of hydrocarbons with respect to depth, identify downhole
lithology, monitor natural gas entering the drilling mud stream, and
draw well logs for use by oil company geologist. Rock cuttings
circulated to the surface in drilling mud are sampled and analyzed.
Mud loggers connect various sensors to the drilling apparatus and
install specialized equipment to monitor or "log" drill activity. This
can be physically and mentally challenging, especially when
having to be done during drilling activity. Much of the equipment
will require precise calibration or alignment by the mud logger to
provide accurate readings.
Runs a single strand wire, or a multi-strand wire, into the gas or oil
well. This may be done to set flow control on various devices. It
may also be performed for processes of clean out, or to place
instruments that will gather readings of temperature, pressure or
seismic surveys in order to establish an accurate monitoring of the
situation within the well.
41
INTRODUCTION TO DRILLING - MODULE 1
6. RIG SYSTEMS
Used for raising and lowering the drilling assembly, and for running casing, completion equipment and
other tools in and out of the hole. The Hoisting system is made up of the following components:
• Crown Block
• Drilling Line
• Travelling Block
• Hook
• Derrick
• Drawworks
• Supply Reel
42
INTRODUCTION TO DRILLING - MODULE 1
6.1 Rotating System
The Rotating System is used for rotary drilling. Two different types of rotary drilling are available.
A hexagonal or square pipe is connected to the topmost joint of the drill string. The rotary table and
Kelly drive bushing impart rotation to the drill string while allowing it to be moved up or down.
Figure 74 - Kelly
As an alternative to the Kelly and rotary table, most modern rigs employ a Top Drive system for
rotating the drill string. A powerful electric or hydraulic motor is suspended from the travelling block.
Figure 75-TDS
43
INTRODUCTION TO DRILLING - MODULE 1
6.2 Circulating and Solids Control System
During drilling, fluid is continuously pumped down the drill string, through the bit, and up the annular
space between the hole and the drill string. Its main purpose is to bring up the cuttings, cool the bit,
maintain hole stability, and prevent formation fluids from entering the wellbore.
Mud Pits
• Pumps
• Standpipe
• Drill Pipe
• Bit
• Shale Shaker
• Desilter
• Desander
• Degasser
• Centrifuge
F
i
g
ure 77 - Solids Control Equipment
44
6.3 Power System
Most modern rigs are electric. Generally, large diesel engines are the primary source of power.
Electric power generated by the engines is first converted from AC to DC in the SCR unit. DC motors
supply power to the drawworks, rotary, and pumps. AC power is still used for auxiliary equipment.
45
INTRODUCTION TO DRILLING - MODULE 1
6.4 Well Control System
Primary control of wellbore pressure is maintained by ensuring that the hydrostatic pressure of the
drilling fluid in the well is always slightly higher than the highest formation pressure exposed to the
open wellbore. Primary control is lost if a kick is taken due to imbalance of pressures.
The BOP (Blow Out Preventer) is the secondary barrier used to control the well if the primary barrier
is lost. The BOP is made up of a series of preventers that can close a well in.
Annular Preventer- Rubber element that can close around any size of drill pipe.
Blind Rams - Steel rams that close together sealing off the well when no drill pipe is in
the hole.
Pipe Rams (Fixed and variable sizes) - Rubber rams that close around drill pipe
Shear Rams - Rams that can cut through drill pipe and seal off the well.
Choke and Kill lines- If the preventers above are closed circulation is achieved through
the choke line.
HCR valve - A hydraulically operated remote valve on the choke line.
Accumulator - Stores hydraulic power to operate the BOP.
The Well Control System comprises of the following components:
46
INTRODUCTION TO DRILLING - MODULE 1
7. WELL DESIGN AND COMPLETEIONS
A typical Oil and Gas well is drilled in several phases with different size holes gradually getting smaller
until total depth is reached. Design of the steel casing strings is a key part of the well design and a
key factor in well success, including assurance of zonal isolation and wellbore integrity. Casing design
and running are carefully executed technical processes.
• Conductor casing
• Surface casing
• Intermediate casing
• Production casing
Cement
Conductor Casing
Surface Casing
Intermediate Casing
Production Casing
47
INTRODUCTION TO DRILLING - MODULE 1
7.2 Casing Joints
Casing is threaded on each end, and has a coupling installed to join it to the next pipe. When several
joints of casing have been screwed together they form a continuous "string" of casing that will isolate
the hole. When screwing together a casing connection, applying the proper amount of torque is
important. Too much torque overstresses the connection and can result in failure of the connection.
Too little torque can result in a leaky connection.
Casing joint
Casing joint
48
INTRODUCTION TO DRILLING - MODULE 1
7.3 Spudding the Well
The first step is to 'Spud' in a large diameter conductor, typically a 36" steel tube, into the surface.
This conductor will form the top of the well that sits proud on the ground. It will provide the casing
head-the base for the well head and all well control equipment e.g. the BOP to seal to.
Dependent on the composition of the ground, be it hard or soft, the conductor can be spudded in in
one of two ways.
7.3.1 Jetting
Used if the ground composition is of soft sediment. Either water or environmentally friendly drill fluid is
jetted though the drill bit, moving any sediment up and out the top of the conductor, allowing the
conductor to continue further through the ground.
7.3.2 Hammer
If the composition is a harder makeup, then the conductor will be hammered into the ground.
Once the conductor has been spudded into the depth required as per the well engineers design,
drilling will start.
49
INTRODUCTION TO DRILLING - MODULE 1
7.4 Drilling
The driller will start drilling from the bottom of the conductor casing going deeper into the ground.
Drilling fluid know as 'mud' will be pumped down through the inside of the drill pipe and out through
nozzles in the drill bit. This will force any cuttings up and out of the top of the conductor in the same
way as in the jetting process. Most surface holes are drilled using sea water if offshore. Forcing the
cuttings up and out of the bore will keep the drill string from getting jammed and keep the wellbore
clean.
In drilling, the mud is referred to as the primary barrier from a hydrocarbon release or blowout.
50
INTRODUCTION TO DRILLING - MODULE 1
7.5 Running and Cementing Surface Casing
Once the driller has bored to the required depth on the well engineers plan, the drill string will be
pulled out of the well bore, allowing a smaller steel 'surface' casing typically around 13 3/8', to be
lowered into the bore.
Cement can then be pumped down into the casing until it reaches the bottom of the bore. The
pumping will continue pushing the cement out of the bottom of the casing and up between the sides of
the casing and the sides of the bore hole.
Once the calculated amount of cement has been pumped, a drillable plug is inserted into the casing,
allowing mud to be pumped in order for the cement to continue being pushed out and up the sides of
the casing. The cementing operation is continued until the cement has completely sealed the casing
in place.
51
INTRODUCTION TO DRILLING - MODULE 1
7.6 Installing the BOP
At this point, although possibly still a great distance from the target depth and reservoir, the pressure
in the well can become too great to control safely by water based drilling fluid / mud alone, also there
could be uncertainty about the possibility of hitting unknown pockets of hydrocarbons. Either of these
could cause an uncontrolled kick or blowout.
To alleviate this risk, a blowout preventer (BOP) will be installed. This can either be a surface BOP or
typically in deepwater drilling operations- a subsea BOP. When you drill with a surface BOP stack,
you must install the BOP system before drilling below surface casing. If needed in a blowout situation,
the BOP can shear the drill pipe and seal in the well by a succession of hydraulic rams.
The BOP will be lowered and attached to the casing head, at the top of the conductor casing that was
originally spudded in. The BOP will then be connected to the drill floor by a pipe called a riser or bell
nipple. The riser will allow mud to be pumped backup from the well bore to the rig flow line.
• The mud can be cleaned once back at the rig and reused.
• Having a closed circuit of mud makes it easier for mud engineers and well engineers to assess
the composition of the bore.
• The mud can safely use additional additives to further increase its weight to counteract the risk of
a blowout.
52
INTRODUCTION TO DRILLING - MODULE 1
7.7 Intermediate Casing
It is often set in the transition zone from normal to abnormal pressure. The casing cement top must
isolate any hydrocarbon zones. Some wells require multiple intermediate strings. Some intermediate
strings may also be production strings if a liner (A type of casing that hangs off another and does not
reach surface) is run beneath them.
Production Casing or Liner is used to isolate production zones and contain formation pressures in the
event of a tubing leak. It may also be exposed to:
A good primary cement job is very critical for this casing string.
5650 w
53
INTRODUCTION TO DRILLING - MODULE 1
7.9 Liners
A Liner is a casing string that does not extend back to the wellhead, but is hung from another casing
string. Liners are used instead of full casing strings to:
• Reduce cost
• Improve hydraulic performance when drilling deeper
• Allow the use of larger tubing above the liner top
• Not represent a tension limitation for a rig
Liners can be either an intermediate or a production string. Liners are typically cemented over their
entire length.
7.10 Perforation
Cased-hole completions require casing to be run into the reservoir. In order to achieve production, the
production casing and cement are perforated to allow the hydrocarbons to enter the wellstream.
This process involves running a perforation gun and a reservoir locating device into the wellbore,
many times via a wireline, slickline or coiled tubing. Once the reservoir level has been reached, the
gun then shoots holes in the sides of the well to allow the hydrocarbons to enter the wellstream. The
perforations can either be accomplished via firing bullets into the sides of the casing or by discharging
jets, or shaped charges, into the casing.
While the perforation locations have been previously defined by drilling logs, those intervals cannot be
easily located through the casing and cement. To overcome this challenge, a gamma ray-collar
correlation log is typically implemented to correlate with the initial log run on the well and define the
locations where perforation is required.
Figure 87 - Perforation
54
INTRODUCTION TO DRILLING - MODULE 1
7.11 Wellhead Installation
The last step in completing a well, a wellhead is installed at the surface of the well. Many times called
a Production tree or Christmas tree, the wellhead device includes casingheads and a tubing head
combined to provide surface control of the subsurface conditions of the well.
While both onshore and offshore wells are completed by production trees, offshore wells can be
completed by two different types of trees: dry and wet trees.
Similar to onshore production trees, dry trees are installed above the water's surface on the deck of a
platform or facility and are attached to the well below the water.
On the other hand, are installed on the seabed and encased in a solid steel box to protect the valves
and gauges from the elements. The subsea wet tree is then connected via electronic or hydraulic
settings that can be manipulated from the surface or via ROVs.
55
INTRODUCTION TO DRILLING - MODULE 1