01-07-2021
DOMEL GAYO
Philip Doctor
NHC-CGI-ASIR-MAT-CI-0164
DHP-2-IFC-TYPE B-AR-112
Follow manufacturer recommendations for storage and application of water proofing system. All materials to be inspected
by consultant & SAPL prior to use at site by submitting MIR
(Inspection & Test Plan (ITP ) to be Provided)
Mixed design and trial mix for for foam concrete to be officially submitted and approved prior to use.
Ensuring NO loose items, dust & deleterious items are present prior
to application.
Contractor to perform water leak test on entire roof system, no other work penetration to follow thereafter. A separate MS for repair if
needed shall be submitted if defect repairs are required.
Trial mix for light weight concrete, Density test for polyurethane foam and Polystyrene are required.
Check List for Roof Waterproofing
Checklist Number:
Program Title Developmental Housing Project of Saudi Arabia
Project Title ASIR-BISHA PROJECT
PD/PM Sadui Arabian Parsons Ltd. SAPL
Client National Housing Company
Engineer ASD
Contractor ASTRA
Drawing(s) No.(s)
ITP Number
Works Location
Building No.
Status
SN Description of checking to be carried out Remarks
Done Partially Done Not Done
1 Is the material Approved?
2 Is the sotrage & handling of material is ok?
3 Is the surface clean from dust and loose materials?
Is the slopes of foam concrete as per the approved Shop
4
drawings?
Is the thickness of polyurethane is as per the approved
5
shop drawings?
6 Is the surface is cleaned before applying acrilic paint?
7 Is the second coat is applied perpendicular to first coat?
Is the EPS thickness is as per the Standard and
8
specifications?
9 Is the Flood test is done before Screeding?
Remarks:
Accompanying document(s) :
Inspector Supervisor ASTRA Consultant PD/PM
Name
Signature
Date