Introduction:
By virtue of a memorandum signed by the COO last 15 August 2023 (with Ref.
No. MEM-LRMC-COO-0004), a Technical Working Group (TWG) was created to
conduct a Feasibility Study (FS) for the establishment of an IT assisted train
inspection system as part of the efficiency improvement program of
LRMC/ENG.
Objectives:
One area being explored is the digitization of inspection for the Light
Maintenance Section (LMS).
Deliverables:
Provide an outline of the various scenarios/assumptions, potential
challenges and approach based on the underlying requirements (as
described in the RSK wish list).
1
Gather information and investigate technical alternatives, with
corresponding positive or negative outcomes.
Identify actions on how to overcome major roadblocks.
Assess the risks vs. gains/rewards of moving forward with the project.
Recommend proceeding if it is feasible.
2 Upper CCTV units for Train Exterior (Left & Right Side) to focus on:
Carbody =>
o Detection of damaged and deformation
o Detection of outer cleanliness
o Detection of damaged paint/coating
o Detection of damaged window glass and window flops
o Detection of articulation side cover alignment
Pantograph =>
o Detection of Pantograph alignment
o Detection of damaged cable
o Detection of terminal temperature
o Detection of Carbon strip thickness
o Detection of Missing carbon strip
o Detection of Horn scratches
Roof =>
o Detection of Lightning arrester/ surge protectors condition
o Detection of roof linkage condition
o Detection of roof damage
o Detection of foreign object
o Detection of Abnormal noise on ACU
o Detection of Braking resistor damage for Gen 2, Gen 3 and
Gen 4
Doors =>
o Detection of door leaf condition/alignment
o Detection of door indicators
o Detection of open doors
2 Lower CCTV units for Train Exterior (Left & Right Side) to focus on:
2
ERCU (Earth Return Current Unit) =>
o Detection of ERCU mounting
o Detection of detached/broken cable
o Detection of terminal lugs temperature
o Detection of broken bracket
Wheel Sensor => what to check . . . c/o JDG . . . STS
Track Brakes =>
o Detection of track brake condition
o Detection of track brake clearances
o Detection of track brake hangers for G2
o Detection of track brake stopper for G1
1 CCTV unit for the underbody equipment to focus on:
Gearbox =>
o Detection of oil leak
o Detection of gearbox abnormal noise
o Detection of Gearbox temperature
o Detection of pneumatic line and hoses
o Detection of Bogie’s abnormal noise
Traction Motor =>
o Detection of missing traction motor cover for G1
o Detection of traction motor temperature
o Detection of traction motor abnormal noise
o Detection of traction motor physical condition
Axle & Brake Disc Hub =>
o Detection of axle temperature
o Detection of wheels’ abnormal noise and rotation
o Detection of damaged brake disc hub
o Detection of brake disc condition
o Detection of missing brake pads
Couplers =>
o Detection of lose coupler connections
o Detection of lose jumper connectors
NOTE: to place here a diagram of an LRV (Light Rail Vehicles) showing the
appearance of these equipment per generation . . . c/o Jayson DG.
3
Discussions of Key Points:
Viability c/o JS
Team focus
Identify opportunities.
Go/No Go decision.
Narrows the Alternatives
Valid reason to undertake the project.
Success rate => evaluating multiple parameters . . .
Reasons NOT to proceed.
In depth process to determine factors that will lead to the success of the
project and addresses: . . . c/o all
Technical feasibility
Legal
Operational Feasibility
Realistic Project Timeline
4
Economic Feasibility/Costing . . . c/o JDR and Diana
Relevant Issues & Questions
List of Underlying Assumptions
Project’s Expectations
Other Matters
-o0o-