Partnership and Start-Up
Partnership and Start-Up
« Partnership and
start-up »
“ Industrial complex for the manufacture of ecological and innovative building materials
for the industrialization of construction"
summary
New BUILDING SYSTEM : 01
Industrialization of construction : 02
Location : 03
Project : 04
Implementation phases : 05
Our partnership needs : 06
Establishment of the partnership : 07
Schedule : 08
Partnership formula : 09
How do we organize ourselves ? 10
CONCLUSION AND ASSESSMENTS OF THE PARTNERSHIP : 11
Industrialization of construction. New BUILDING SYSTEM
« Downstream»
02
Location
Carrière
03
project
Features : Project profile and impact on the :
We will be the first to manufacture cellular concrete and fiber cement elements in
Small size Big size
Africa. I
Our implantation base for the project has a quarry of 08 Hectares (With mining title) Low stake high stakes
is an area of (+31 Hectares) for the establishment of production units as well as
M
exploitation. W Intangible deliverable Material deliverable P
The analyzes of its rock are excellent for the manufacture of glue cement (which is
E Low complexity High complexity O
used during the application of our products), as well as the MP for the manufacture
of other materials. A Low degree of innovation
R
High degree of innovation
Raw materials are totally local.
K T
Our supplier has significant experience and we have the guarantee and the certainty
Low battery life Strong autonomy
A
to accompany us in order to produce new products with CE standards (exportable).
The project fits in The organization is built N
Set up a new build system: the organization around the project
Cash flow negative Cash flow positive T
1- RESIDENTIAL & INDIVIDUAL 2- INDUSTRIAL & COMMERCIAL
Consistency of the project : The different investment headings of the initial project are summarized in the table below:
S/Total (€) 15 831 500 The production capacity of BCA 2000𝑀3 /D×300D×84.375€/𝐌 𝟑
elements is 2000𝑀3 /D. = 50 625 000€
Production line for BCA elements. 14 630 400 The adhesive mortar production 10T/H×20H×300D×50€/T
Phase II/III:
Total (€) 52 500 000 Phase III: Production line for concrete and BP elements.
From the 2nd year Fiber cement panel manufacturing lines.
04
Implementation phases :
- Phase I: (the beginning) Gisement a
Station
Gaz
d’eau
Need for phase I is: 15 831 500 €. (30%) exploiter
- cost. 12 631 500 €. (80%)
Feasibility : - Valuation report of the expert. 3 200 000 €. (20%)
In case the height of the
- The rest will follow the Leasing / Bail. credit is not answered.
GFmc
Fencing
Funding level
D
C Ordering and acquisition of equipment Assembly Testing and
- Phase I: (the beginning)
A Buildings B CV
machines/equipment production
(30%)
Fencing
02’
02
Production
Procedures for financing
Acquisitions
Preliminary studies and administrative procedures
Administrative procedures
01
Beginning Time
0 06 12 18 24 36 38 46 48 (month)
Pre-funding / » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » After-funding » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » 05
The different sections of our partnership needs for our project are summarized in the table below:
The project Amount (€) period 35% partnership(€) Sequences
1 120 000
Phase I 15 831 500 From the beginning ----------> 2nd month 5 541 025 2 951 025
1 470 000
1 141 308
Phase II 16 304 400 From the 12th month -------> 18th month 5 706 540 4 565 232
1 425 480
Phase III 20 364 000 From the 24th month -------> 30th month 7 127 400 5 701 920
Process and negotiate the partnership and define
Total 52 500 000 30 Month responsibilities (possibility to include ).
Phase I Acquisitions :
Phase I deliverables :
- Production of aggregates.
From the 1st year - Earthworks and distribution of platforms.
Phase II:
- Large works (civil engineering works and fence).
From the 2nd year - Design of a logistics platform and railway platform for transport.
Phase III:
- The civil engineering of the power station as well as the STEP
treatment station.
06
• My contact at NUROL: • What ? • How ? • When ?
Show my project.
An initial partnership of (65/35)%.,
After the establishment of the partnership NUROL will be From Sunday
Partnership with NUROL. 09/19/2022
Find a montage (realization) for my project. able to ensure its contribution with contributions in kind
Until...
An ideal installation solution. (equipment and achievements).
T1 - Schedule : o OP(1, 0) = Validate the scope of the project and reframe the schedule .
19/09/2022
T0
• Assembly and planning : N.B: the tasks are well defined, however the dates
o OP(0, 0) are not yet determined.
o OP(0, 1) Schedule
o OP(0,2)
T1
o OP(1, 0)
o OP(2, 0)
T2
o OP(2, 1)
o OP(2, 2)
T3
o OP(3, 0)
o OP(3, 1)
o OP(3, 2)
T4
o OP(4,0)
o OP(4,1)
o OP(4,2)
02 weeks o OP(4,3) T: Task
OP: Operation
07
25/10/2022
Schedule (Administrative implementation of the project)
• OP(0,1):
OP(0,1)a
Notary and Administration
o
o OP(0,1)b
o OP(0,1)c
o OP(0,1)d
• OP(0,2): Creation of the Sarl:
o OP(0,2)a BCA building
o OP(0,2)b
o OP(0,3)c
o OP(0,4)d
• OP(0,3):
o OP(0,3)a
• OP(0,4):
OP(0,4)a OP(0,4)b
o o
o OP(1,2)b
• OP(1,3):
o OP(1, 3)a
o OP(1, 3)b
• OP(1,4):
o OP(1, 4)a
o OP(1, 4)b
o OP(1, 4)c
• OP(1,5):
o OP(1, 5)a
o OP(1, 5)b
o OP(1, 5)c
o OP(1, 5)c Launch of phase I.
• OP(1,6):
o OP(1, 6)a
o OP(1, 6)b
o OP(1, 6)c
• OP(1,7):
o OP(1, 7)a
Filing of files
o OP(1, 7)b
• OP(1,8):
o OP(1,8)a
o OP(1,8)b
• OP(1,9):
o OP(1,9)a
o OP(1,9)b Have the funding.
• OP(1,10):
o OP(1,10)a
o OP(1,10)b
week 1
Création
08
T2 - load specifications (LS) for infrastructure :
o OP(2, 0) = Writing of the LS. o OP(2, 1) = Make a layout plan for the whole complex. o OP(2, 2) = Receipt of budget offers from NUROL.
- production units. - Power station. - Possible that the realization will be made by NUROL.
- Raw material area. Important :
The complex will contain : Take into account : - Small dam and STEP. - The constructions will be in reinforced concrete,
- Storage and shipping area. - Rail dock for shipping. prestressed, cellular and stone.
- Extraction and extension area. - Recycling plant. - Concrete, aggregate, stone, water on site.
T3 - Infrastructure enhancements :
Fence, Earthwork…. According to the cost of the market: 2400da/M²….
o OP(3, 0) = Reframing the project. Focus on results o OP(3, 1) = Start of works. o OP(3, 2) = Make an assessment of all the infrastructure.
Or : o OP(3,2)
The consistency of the project is 60 M€: 30% bank credit on the overall cost of 60% (BEDARNE Mokrane) 4,875 M€ 18,225+2,1 M€
Infrastructure €20m the project = 45% credit on 40% NUROL 2,625 M€ 9,975+4,2 M€
Production machines 40 M€ production equipment COSIDER (commercial partner) / o OP(4,0)
Or : o OP(3,2)
The consistency of the project is 60 M€: 30% bank credit on the overall cost of 55% (BEDARNE Mokrane) 4,875 M€ 18,225 M€
Infrastructure €20m the project = 45% credit on 30% NUROL 2,625 M€ 9,975 M€
Production machines 40 M€ production equipment 15% COSIDER / o OP(4,0) 6,3 M€
…
Or … :
09
Example : o OP(3,2)
The consistency of the project is 60 M€: 30% bank credit on the overall cost of 55% (BEDARNE Mokrane) 4,875 M€ 18,225 M€
Infrastructure €20m the project = 45% credit on 30% NUROL 2,625 M€ 9,975 M€
Production machines 40 M€ production equipment 15% COSIDER / o OP(4,0) 6,3 M€
Project cycle
• Level of effort » » » » » » » »
Execution / Realization
OP(0, 4)
Assembly
OP(4, 4)
o
OP(0, 2)
Definition project closure
o
o
Schedule Duration
• Draft part • » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » » Project part» » » » » » » » » » » » » » » » » » » » » » » » » » » » » » • Post-project part (production)
BEDRANE
NUROL
COSIDER
Base and tools to organize ourselves (essential):
• Implement PDCA,
strengths/weaknesses analysis.
Set goals: • Negotiate the deliverables with the
actors of the project thanks to the
triangle quality/costs/times.