Mock Up Schedule Block-D 3BHK/ E Type Flat 2BHK / C Type Flat
Sl No Description of iteam Duration Start Date End Date Duration Start Date End Date Remarks
1 Brick Work 11/15/2023 11/15/2023
2 Electrical Chase Cutting and Box Fixng including Toilet 7 11/16/2023 11/23/2023 7 11/16/2023 11/23/2023
3 Conduite Patching at Wall 3 11/24/2023 11/27/2023 3 11/24/2023 11/27/2023
4 Internal Plaster 10 11/28/2023 12/8/2023 10 11/28/2023 12/8/2023
5 Door frame fixing 3 12/9/2023 12/12/2023 3 12/9/2023 12/12/2023
6 Putty 7 12/13/2023 12/20/2023 7 12/13/2023 12/20/2023
7 Internal Toilet PHE Pipe Line and Pressure Testing 7 12/21/2023 12/28/2023 7 12/21/2023 12/28/2023
8 Waterproofing (Toilet and Balcony) 10 12/29/2022 1/8/2023 10 12/29/2022 1/8/2023
9 Screed concrete or protective plaster ay Toilet 2 1/9/2023 1/11/2023 2 1/9/2023 1/11/2023
10 S/D Window frame and shutter fixing 7 1/4/2023 1/11/2023 7 1/4/2023 1/11/2023
11 Tiles fixing 20 1/12/2023 2/1/2023 20 1/12/2023 2/1/2023
12 Door shutter fixing with Lock 8 2/2/2023 2/10/2023 8 2/2/2023 2/10/2023
13 Wire Pooling 10 2/11/2023 2/21/2023 10 2/11/2023 2/21/2023
14 Primer 10 2/22/2023 3/4/2023 10 2/22/2023 3/4/2023
15 Switch Scoket fixing 2 3/5/2023 3/7/2023 2 3/5/2023 3/7/2023
16 Toilet fitting and fixture 7 3/8/2023 3/15/2023 7 3/8/2023 3/15/2023
17 Desnaging 14 3/16/2023 3/30/2023 14 3/16/2023 3/30/2023
18 Handover 0 3/31/2024 3/31/2024 0 3/31/2024 3/31/2024