Mock Up Schedule - 09112023

The document contains a schedule for completing construction work on two types of flats - a 3BHK/E type flat and 2BHK/C type flat. The schedule lists 18 items of work required to complete the flats, including brick work, electrical work, plastering, tile fixing, plumbing and more. It specifies the duration and start and end dates for each item of work for both types of flats. The handover for both projects is scheduled for March 31, 2024.

Uploaded by

almamunmolla96
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views1 page

Mock Up Schedule - 09112023

The document contains a schedule for completing construction work on two types of flats - a 3BHK/E type flat and 2BHK/C type flat. The schedule lists 18 items of work required to complete the flats, including brick work, electrical work, plastering, tile fixing, plumbing and more. It specifies the duration and start and end dates for each item of work for both types of flats. The handover for both projects is scheduled for March 31, 2024.

Uploaded by

almamunmolla96
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Mock Up Schedule Block-D 3BHK/ E Type Flat 2BHK / C Type Flat

Sl No Description of iteam Duration Start Date End Date Duration Start Date End Date Remarks
1 Brick Work 11/15/2023 11/15/2023
2 Electrical Chase Cutting and Box Fixng including Toilet 7 11/16/2023 11/23/2023 7 11/16/2023 11/23/2023
3 Conduite Patching at Wall 3 11/24/2023 11/27/2023 3 11/24/2023 11/27/2023
4 Internal Plaster 10 11/28/2023 12/8/2023 10 11/28/2023 12/8/2023
5 Door frame fixing 3 12/9/2023 12/12/2023 3 12/9/2023 12/12/2023
6 Putty 7 12/13/2023 12/20/2023 7 12/13/2023 12/20/2023
7 Internal Toilet PHE Pipe Line and Pressure Testing 7 12/21/2023 12/28/2023 7 12/21/2023 12/28/2023
8 Waterproofing (Toilet and Balcony) 10 12/29/2022 1/8/2023 10 12/29/2022 1/8/2023
9 Screed concrete or protective plaster ay Toilet 2 1/9/2023 1/11/2023 2 1/9/2023 1/11/2023
10 S/D Window frame and shutter fixing 7 1/4/2023 1/11/2023 7 1/4/2023 1/11/2023
11 Tiles fixing 20 1/12/2023 2/1/2023 20 1/12/2023 2/1/2023
12 Door shutter fixing with Lock 8 2/2/2023 2/10/2023 8 2/2/2023 2/10/2023
13 Wire Pooling 10 2/11/2023 2/21/2023 10 2/11/2023 2/21/2023
14 Primer 10 2/22/2023 3/4/2023 10 2/22/2023 3/4/2023
15 Switch Scoket fixing 2 3/5/2023 3/7/2023 2 3/5/2023 3/7/2023
16 Toilet fitting and fixture 7 3/8/2023 3/15/2023 7 3/8/2023 3/15/2023
17 Desnaging 14 3/16/2023 3/30/2023 14 3/16/2023 3/30/2023
18 Handover 0 3/31/2024 3/31/2024 0 3/31/2024 3/31/2024