1 Civil and Finising Works To NRB LINE 1 Civil and Finising Works To NRB LINE

1. The document outlines the schedule for a civil and finishing works project to the NRB LINE from October 2023 to February 2024. 2. Key activities include dismantling and demolishing works from October to November 2023, sub-structure works like excavation and foundations from November to December 2023, and super-structure works from November 2023 to February 2024. 3. Super-structure works involve civil works like steel structure fabrication from November to December 2023, and MEP works from December 2023 to January 2024 including first fixed installations, ductwork, and finishing works.

Uploaded by

Mutasem Hamad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views1 page

1 Civil and Finising Works To NRB LINE 1 Civil and Finising Works To NRB LINE

1. The document outlines the schedule for a civil and finishing works project to the NRB LINE from October 2023 to February 2024. 2. Key activities include dismantling and demolishing works from October to November 2023, sub-structure works like excavation and foundations from November to December 2023, and super-structure works from November 2023 to February 2024. 3. Super-structure works involve civil works like steel structure fabrication from November to December 2023, and MEP works from December 2023 to January 2024 including first fixed installations, ductwork, and finishing works.

Uploaded by

Mutasem Hamad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Classic Schedule Layout 24-Nov-23 18:59

Activity ID Activity Name Original Start Finish Total November 2023 December 2023 January 2024 February 2024
Duration Float
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11
1 Civil and finising works to NRB LINE 105 28-Oct-23 09-Feb-24 -15 09-Feb-24, 1 Civil and finising work

1.1 Dismantling and Demolishing 11 28-Oct-23 07-Nov-23 -3 07-Nov-23, 1.1 Dismantling and Demolishing
A1000 Dismantling of MEP fittings (Fire pipes, Ducts, Cables ..etc) 4 28-Oct-23 31-Oct-23 -1 Dismantling of MEP fittings (Fire pipes, Ducts, Cables ..etc)
A1010 Dismantling of aluminum Partitions, windows and alcabound 6 28-Oct-23 02-Nov-23 -3 Dismantling of aluminum Partitions, windows and alcabound
A1020 Dismantling steel ladder and steel column 6 28-Oct-23 02-Nov-23 -3 Dismantling steel ladder and steel column
A1030 Dismantling ground stainless steel trench 6 28-Oct-23 02-Nov-23 -3 Dismantling ground stainless steel trench
A1040 Demolishing of Ceramic Walls, gypsum board walls and cement board walls 6 28-Oct-23 02-Nov-23 -3 Demolishing of Ceramic Walls, gypsum board walls and cement board walls
A1050 Demolishing of existing SOG 5 03-Nov-23 07-Nov-23 -3 Demolishing of existing SOG
1.2 Sub-Structure 23 08-Nov-23 30-Nov-23 -3 30-Nov-23, 1.2 Sub-Structure
A1060 Excavation around all foundations 10 08-Nov-23 17-Nov-23 -3 Excavation around all foundations
A1070 Casting foundations (New foundations) 9 18-Nov-23 26-Nov-23 -3 Casting foundations (New foundations)
A1080 Reinforced concrete columns necks and installing the anchor bolts 2 27-Nov-23 28-Nov-23 -3 Reinforced concrete columns necks and installing the anchor bolts
A1090 backfilling around foundations 2 29-Nov-23 30-Nov-23 -3 backfilling around foundations
1.3 Super-Structure 75 26-Nov-23 08-Feb-24 -14 08-Feb-24, 1.3 Super-Structure

1.3.1 Civil Works 27 26-Nov-23 22-Dec-23 34 22-Dec-23, 1.3.1 Civil Works


A1100 Hollow block walls to close the existing windows opening 1 01-Dec-23 01-Dec-23 55 Hollow block walls to close the existing windows opening
A1110 Fabrication works of steel structure 20 26-Nov-23* 15-Dec-23 -15 Fabrication works of steel structure
A1120 Installing of steel structure 7 16-Dec-23 22-Dec-23 -15 Installing of steel structure
A1140 Installation sandwich panels of roof 5 18-Dec-23 22-Dec-23 -15 Installation sandwich panels of roof
A1190 Rebar works of SOG 2 11-Dec-23 12-Dec-23 -3 Rebar works of SOG
A1200 Casting concrete of SOG 3 13-Dec-23 15-Dec-23 -3 Casting concrete of SOG
1.3.2 MEP Works 56 01-Dec-23 25-Jan-24 0 25-Jan-24, 1.3.2 MEP Works
A1160 First Fixed in wall MEP (power conduits, drain vent) 4 01-Dec-23* 04-Dec-23 -3 First Fixed in wall MEP (power conduits, drain vent)
A1161 Plumbing works under slab (pipe draings, trenches and testing) 6 05-Dec-23* 10-Dec-23 -3 Plumbing works under slab (pipe draings, trenches and testing)
A1162 Plumbing works with slab works (concrete & steel PVC conduits) 4 23-Dec-23* 26-Dec-23 30 Plumbing works with slab works (concrete & steel PVC conduits)
A1163 First Fixed @H.L (lighting, fire alarm, soft water..etc) 16 23-Dec-23* 07-Jan-24 7 First Fixed @H.L (lighting, fire alarm, soft water..etc)
A1164 Duct work inside @H.L fabricate and installion 10 08-Jan-24* 17-Jan-24 7 Duct work inside @H.L fabricate and installion
A1165 First fixed in second ceiling (Lighting, F.alarm,cctv..etc) 5 23-Dec-23 27-Dec-23 -15 First fixed in second ceiling (Lighting, F.alarm,cctv..etc)
A1166 Main panels and secondary panels, cabling ..etc 4 28-Dec-23 31-Dec-23 -15 Main panels and secondary panels, cabling ..etc
A1167 Install equibments (MCCB, isolators, sprinkles , grills..etc) 14 01-Jan-24 14-Jan-24 -15 Install equibments (MCCB, isolators, sprinkles , grills..etc)
A1168 Finishing installation MEP (testing & connection and comissioning for equipments and fixture
11 15-Jan-24
units) 25-Jan-24 -15 Finishing installation MEP (testing & connection and com
1.3.3 Finishing Works 55 16-Dec-23 08-Feb-24 -14 08-Feb-24, 1.3.3 Finishing Works
A1210 Installing of PV walls or sandwich panel wall 8 16-Dec-23 23-Dec-23 33 Installing of PV walls or sandwich panel wall
A1220 Installing of stainless steel kerbs 2 18-Dec-23 19-Dec-23 37 Installing of stainless steel kerbs
A1230 Epoxy coating of SOG 2 26-Jan-24 27-Jan-24 -15 Epoxy coating of SOG
A1270 Installing Aluminum partition 5 04-Feb-24 08-Feb-24 -15 Installing Aluminum partition
1.3.4 Roof Works 9 01-Dec-23 09-Dec-23 47 09-Dec-23, 1.3.4 Roof Works
A1240 Concrete screed fill to the edge of existing dome slab 2 01-Dec-23 02-Dec-23 47 Concrete screed fill to the edge of existing dome slab
A1250 Installing of waterproofing membrane 7 03-Dec-23 09-Dec-23 47 Installing of waterproofing membrane
1.5 Handing over 15 26-Jan-24 09-Feb-24 -15 09-Feb-24, 1.5 Handing over
A1255 Testing and finishing of mechanical equipment and electrical equipment 3 26-Jan-24* 28-Jan-24 -4 Testing and finishing of mechanical equipment and
A1260 Handing over of the project 1 09-Feb-24 09-Feb-24 -15 Handing over of the project

Actual Level of Effort Remaining Work Milestone Page 1 of 1 ARAB BUISNESS CONTRACTING