Electrical Load Estimation - Part Two Electrical Knowhow
Electrical Load Estimation - Part Two Electrical Knowhow
In the previous topic " Electrical Load Estimation – Part One " , I explain the definitions of the most important terms in electrical load estimation and provides
download links for factors used in the electrical load estimation.
Also, I listed the (5) methods of electrical load estimations which were:
Note:
I will explain the (3) preliminary load estimation methods only in this course, and the two other methods, NEC load calculations and Final load calculations will be
explained later in course " EE-3: Basic Electrical design course – Level II " , because these two methods are applied in the final stages of design.
2 units are used interchangeably Units can’t used interchangeably. So, Hp will
because unity power factor is be converted to kVA; and kVA may be
assumed multiplied by the estimated power factor to
obtain kW if required
4 Demand and load factors values Demand and load factors values are Real
will be selected from tables based values that will document and reflect the
on the designer estimation and number, the type, the duty rating
they will be Used to calculate the (continuous, intermittent, periodic, short
transformer and service size. time, and varying), and the wattage or volt-
ampere rating of equipment supplied by a
common source of power, and the diversity
of operation of equipment served by the
common source.
5 The connected load will be Actual demand load will be calculated based
estimated based on area or on summation of individual building
population connected loads modified by suitable
demand and diversity factors
6 Easy and Fast calculations economical, cost effective calculations
insuring that items of equipment and
materials are adequate to serve existing,
new, and future load demands
Note:
A particular design may use one Preliminary load estimate method or a combination from two or even the three methods.
In the Space-by-Space Method, the building will be divided into different space based on its function like offices, conference halls, corridors and lobbies, shops,
parking areas, workshops and etc. The Load density in (W/ft2) or/and (VA/ft2) is prescribed for these different spaces, these load densities in addition to spaces
area will be used to estimate the preliminary electrical load of this building as described in below.
The Space-by-Space Method is used only for individual spaces in the building.
The Space-by-Space Method may be used for any building or portion of a building.
The square footage is measured from the outside surface of exterior walls to the centerline of walls between interior partitions of the spaces. The sum of the
Gross Interior Area equals the total Gross Area of the building.
First case: availability of grouped load density (i.e. one value covering all lighting, general power and power loads) in (W/ft2) or/and (VA/ft2) for each
space.
Second case: availability of individual load density (i.e. individual values for lighting, general power and power loads) in (W/ft2) or/and (VA/ft2) for
each space.
First case
Method of estimation by using Space-by-Space Method will be as follows: 1- Divide the building into different space based on its function (for example, office,
storage, mechanical, and corridor).
3- Determine the grouped load density for each space (from tables).
4- Multiply each space gross interior area by its grouped load density to get the estimated electrical load for this space.
5- Sum all the estimated electrical loads for all spaces to get the total preliminary electrical load for the whole building.
6- Multiply the total preliminary electrical load for the whole building by the power factor value (= 0.8) and a suitable load factor (for future extensions and
losses compensations) to get the main service size.
Example# 1:
For a high-rise office building with shopping arcade, the power supply has to be planned for a 10-story building (12 floors) with a floor area of approx. 25 m x 60
m.
There is a car park for customers in front of the building, the access way to the parking garage (levels -1 to -3 for employees) and a fountain (80 m x 20 m). (Fig.
1)
Real floor area approx. 1350 m2 (14 levels + technical equipment on roof level).
Floor heights of levels 00 to +10: 4 m, levels -1 to -3: 3 m Calculate main electrical service size for this building.
Fig (1)
The solution:
Consider first case: availability of grouped load density for each space. Hence, calculations will be as follows:
Parking garage / utilities areas (incl. roof area) Basement levels -1 to -3 with 1,350 m2 each + utilities areas ca. 210 m2 (areas between utilities hubs), Area = (3
x 1,350 m2 + 210 m2) = 4260 m2
Shopping center / bank Ground level 00 with 1,350 m2 Area = 1 x 1,350 m2 = 1350 m2
Table# 1
3- Determine the grouped load density for each space (from table#1) as follows:
4- Multiply each space gross interior area by its grouped load density to get the estimated electrical load for this space as follows:
Parking garage / utilities areas (incl. roof area) Estimated electrical load = (3 x 1,350 m2 + 210 m2) x 10 W/m2 = 42,600 W
Shopping center / bank
Estimated electrical load = 1 x 1,350 m2 x 120 W/m2 = 162,000 W
5- Sum all the estimated electrical loads for all spaces to get the total preliminary electrical load for the whole building.
Total preliminary electrical load for the whole building = 42,600 + 162,000 + 1,485,000 = 1,690 kW
The established total power demand determines the required transformer output. The determination is based on a cos phi = 0.85 and a transformer load level of
70%. Transformer output rating = 1,690 kW / (0.7 x 0.85) = 2,840 kVA
Second Case
1- Divide the building into different space based on its function (for example, office, storage, mechanical, and corridor).
3- Calculate the estimated lighting, small appliance and power loads for each space as follows:
Electric power loads shall include all loads other than lighting loads and those served by general purpose receptacles and comprise the environmental
system electric power requirements and the facility occupancy equipment electric power requirements.
HVAC Equipment
Use the same method for small appliance loads
These loads are related to the whole building and not related to the divided spaces. So, The Space-by-Space Method cann’t estimate the required
ratings for these loads and we must use the building method for this purpose.
4- After computing the preliminary electrical loads for each space, we must sum all of them to get the total preliminary electrical load for the whole building.
Example# 2 :
Consider the same building in example# 1 to be solved if individual load densities are known for each load type as follows:
Lighting 7
Parking Garage / Utilities Areas (Incl. Roof Area) Small Appliance 3
Power Load Inc. in building power
Lighting 28
Shopping Center / Bank Small Appliance 20
Power Load Inc. in building power
Lighting 28
Offices Small Appliance 20
Power Load Inc. in building power
The solution:
1- The following table summarizes the calculations steps.
Estimated
Load Estimated Electrical
Space Area Load
Density Load Load For
Space
Parking Garage /
Small
Utilities Areas 4,260 3 12,780 42,600 VA
Appliance
(Incl. Roof Area)
Small
Offices 13,500 20 270,000 648,000 VA
Appliance
HVAC –
Building Power Pumps –
14,850 60 891,000 891,000 VA
Load Elevators –
Others
Free download
In the next topic, I will explain Other methods for preliminary electrical load calculations. So, please keep following.
12 comments:
the best thing in your lessons is the examples , keep going and we with you .
Reply
Replies
thanks, medo88
Reply
Reply
Replies
Reply
but in calculation you used 110w/m2 and 120 w/m2 whats the logic behind this
Reply
Reply
Replies
Load level 70% means that the load of the transformer must be equal or less than 70% of the transformer rating . so, 1,690 KW must equal 70% of the transformer
rating. how much is the transformer rating? of course must be more than the load 1,690 KW and therefore, the load is divided by( the 70% multiplied by the
P.F=0.8.)
Reply
hi Ali,
Could you inform us fr average demand we can refer to IEC standard number ?
Reply
Reply
CONTACT FORM
Name
Email *
TRANSLATE
Message *
ቋንቋ ምረጥ
2 3 1 0 0 5 0 4
Send