0% found this document useful (0 votes)
116 views31 pages

Guard House

The document provides specifications and quantities for the construction of a duplex dwelling house at Arbaminch Substation. It includes two sections - the substructure and superstructure. The substructure includes earthworks, concrete works, and masonry works totaling nearly 800,000 Birr. The superstructure includes additional concrete works, block works, roofing, carpentry, metal works, finishing, and other components totaling over 2.2 million Birr. The total cost for the project is estimated at 3.4 million Birr including a 10% contingency.

Uploaded by

Lelisa Tarekegn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
116 views31 pages

Guard House

The document provides specifications and quantities for the construction of a duplex dwelling house at Arbaminch Substation. It includes two sections - the substructure and superstructure. The substructure includes earthworks, concrete works, and masonry works totaling nearly 800,000 Birr. The superstructure includes additional concrete works, block works, roofing, carpentry, metal works, finishing, and other components totaling over 2.2 million Birr. The total cost for the project is estimated at 3.4 million Birr including a 10% contingency.

Uploaded by

Lelisa Tarekegn
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 31

SPECIFICATIONS AND BILL OF

QUANTITIES

FOR

THE CONSTRUCTION OF

DUPLEX DWELLING HOUSE MAIN BUILDING


(ARBAMINCH SUBSTATION)

prepared by

Lelisa T
DUPLEX DWELLING HOUSE
SUMMARY

A.SUB- STRUCTURE

1. Earth work 9,666.53

2. Concrete work 482,473.73

3. Masonry work 307,802.72

Sum 799,942.98
B.SUPER - STRUCTURE

1. Concrete work 469,609.40

2. Block work 188,157.55

3. Roofing 214,788.00

4. Carpentry & joinery 373,576.71

5. Metal work 272,762.40

6.finishing 496,552.56

7.Glazing 11,956.00

8. Painting 113,229.66

9. Sanitary 58,032.30

10 Electrical 98,026.00

Sum 2,296,690.58

Total sum 3,096,633.56


10 % CONTINGENCY 309,663.36
GRAND TOTAL SUM 3,406,296.92

1
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE

A.SUB STRUCTURE

1.EARTH WORKS

1.1 Clear of the site to remove top soil to an average depth of 200mm m2 14.92 34.85 519.96
1.2 Bulk excavation in ordinary soil to a depth of 400mm m3 26.11 174.25 4,549.67
1.3 Excavate for footing trench to an average depth not exceeding
m3 0.00 85.00 0.00
1500mm below strips ground level.
1.4 Ditto as item 1.3, but depth 1.5 to 3.00m m3 0.00 95.00 0.00
1.5 Trench excavation in ordinary soil to a depth not exceeding 1500mm
m3 0.00 85.00 0.00
from reduced ground level
1.6 Fill under concrete footings & striped stone masonry foundations to
a required level with non expansive selected material out side the site m3 0.00 409.00 0.00
and well compacted in layer of 150mm thick.
1.7 Fill under hard core with non expansive selected material from site
m3 0.00 409.00 0.00
and well compacted in layer of 200mm thick.
1.8 Cart away excavated surplus material 5km away from the site,
m3 27.86 165.00 4,596.90
spread and level it as the site requires.
1.9 250 mm thick basaltic or equivalent stone hard core well rolled and
m2 0.00 416.59 0.00
consolidated and blinded with crushed stone.

Total to summary Birr 9,666.53

2.CONCRETE WORK

50mm thick lean concrete in C-5 with minimum cement content of


150kg/m3

2.1 Under concrete footings m2 9.23 326.00 3,008.82

2.2 Under masonry foundation m2 7.95 326.00 2,592.35

2.3 Under grade beam m2 2.27 326.00 740.67

Reinforced concrete in class C-25, with minimum cement content of


360 kgs/m3 filled into formwork and vibrated around steel
reinforcement and formwork shall be measured separately:

2.3 in footing pads m3 2.42 5,290.51 12,782.14

2.4 In footing columns m3 1.52 5,290.51 8,041.58

2.5 In grade beams. m3 13.18 5,290.51 69,728.92

2.6 In 100 mm thick ground floor slab m3 21.42 5,290.51 113,322.72

Provide cut and fix in position swan zigba wood formwork to:

2.7 footing pads m2 22.05 632.19 13,939.79


2.8 footing columns m2 26.73 632.19 16,898.44
2.9 grade beams. m2 99.68 632.19 63,016.70

Steel reinforcement according to structural drawing, price shall


include cutting ,bending, placing in position and tying wire.

2.10 Ø 6 mm deformed kg 0.00


2.11 Ø 8 mm deformed kg 1,163.24 90.59 105,377.91
2.12 Ø 10 mm deformed kg 0.00
2.13 Ø 12 mm deformed kg 268.53 90.59 24,326.13
2.14 Ø 14 mm deformed kg 0.00
2.15 Ø 16mm deformed kg 537.56 90.59 48,697.56

Total to summary Birr 482,473.73


ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE

3. MASONARY WORK

3.1 500 mm thick hard trachytic or equivalent stone masonry foundation


m3 119.50 2,331.00 278,554.50
wall bedded in cement sand mortar mix 1:4 below ground level

3.2 Ditto, but 300 mm high exposed roughly dressed stone wall one side
m3 11.95 2,447.55 29,248.22
left for plastering above ground level

Total to summary Birr 307,802.72

B.SUPER - STRUCTURE

1. CONCRETE WORK

i) on the ground floor

Reinforced concrete in class C-25, with minimum cement content of


360 kgs/m3 filled into form work and vibrated around steel
reinforcement and formwork shall be measured separately:

1.1 in elevated columns m3 3.75 5,290.51 19,839.41

1.2 Top tie beams and Gutter m3 15.89 5,290.51 84,066.20

Provide cut and fix in position swan zigba wood formwork to:-

1.3 in elevated columns m2 64.00 675.00 43,200.00

1.4 Top tie beam and gutter m2 145.00 675.00 97,875.00

Steel reinforcement according to structural drawing. Price shall


include cutting ,bending, placing in position and tying wire.

1.5 in elevated columns

a) Ø 8mm deformed kg 119.45 90.50 10,810.04


b) Ø 16mm deformed kg 451.25 90.50 40,837.94

1.10 In Toptie beams, Gutter and lintel

a) Ø 8 deformed kg 659.60 90.50 59,693.80


d) Ø 16mm deformed kg 1,251.79 90.50 113,287.00

Total to summary 469,609.40


ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE

2. BLOCK WORK

2.1 200mm thick HCB wall bedded in cement - sand mortar mix (1:3)
m2 260.00 537.32 139,703.20
both sides left for plastering.

2.2 Ditto, but 150mm thick partition & parapate Wall. m2 105.00 461.47 48,454.35

Total to summary 188,157.55

3.ROOFING

3.1 Supply & fix G-28 CIS metal sheet and painted one coat of anti-rust
m2 252.00 670.00 168,840.00
and two coats of synthetic paint.
3.2 Supply and fix metal coping ml 40.00 304.50 12,180.00
3.3 supply and fix G-28 galvanized flat metal sheet gutter within the the
ml 54.00 304.50 16,443.00
proposed concrete gutter support and coated with rustresisting paint
3.4 Supply and install110 mm PVC down pipes. Price includes fixing of
ml 75.00 231.00 17,325.00
pipes and bracing with metal bands.

Total to summary 214,788.00

4. CARPENTRY & JOINERY

4.1 Eucalyptus wood truss members

a) Ø12cm lower chord members ml 308.50 120.00 37,020.00


b) Ø10cm upper chord members ml 304.50 115.50 35,169.75
c) Ø8cm vertical members ml 169.80 94.50 16,046.10
d) Ø8cm diagonal members ml 253.80 94.50 23,984.10

4.2 50x70mm Zigba wood purlins m 352.00 204.00 71,808.00

4.4 plastic ceiling on and at 620mm centers both ways and fixed to truss,
m2 214.80 658.35 141,413.58
at corners shall be covered with sloped plastic ceiling cover fillet

4.5 Supply and fix 40 mm thick semi solid core flash wooden door
covered with 4mm thick woira ply wood decorated with and
including 3 coats of varnish paint. Price shall include all necessary
iron mongery and an approved type cylindrical door lock.

Type D2, size 120x210 No 2.00 7,805.70 15,611.40

Type D3, size 90x210 No 2.00 5,854.28 11,708.56

Type D4 size 90x210 No 2.00 5,854.28 11,708.56

Type D6, size 70x210 No 2.00 4,553.33 9,106.66

Total to summary Birr 373,576.71

5. METAL WORKS

Supply and fix door and window made of Aluminium frames glazed
as shown the drawing including approved type hinges handles and
type cylindrical or equivalent .Price includes 5 mm thick clear/
patterned glass as required.
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE

DOORS

5.1 Type D2, size 120x210 No 2.00 13,305.60 26,611.20


5.2 Type D3, size 90x210 No 2.00 9,979.20 19,958.40
5.3 Type D4, size 90x210 No 2.00 9,979.20 19,958.40
5.4 Type D6, size 70x210 No 2.00 7,761.60 15,523.20
WINDOWS: -

5.4 Type W1, size (340 x 210) No 2.00 37,699.20 75,398.40


5.5 Type W2, size (200 x 164) No 6.00 17,318.00 103,908.00
5.6 Type W3, size (180 x 60) No 2.00 5,702.40 11,404.80

Total to summary Birr 272,762.40

6. FINISHING

Finishing work shall included all surface pre cleaning, preparation


and application of the finishing, polishing and cleaning at the end of
finished works.

6.1 Apply 2 coats of plastering to external wall surface in cement mortar


m2 124.39 250.00 31,097.50
mix 1:3.

6.2 Apply 2 coats of plastering to internal wall surface in cement mortar


m2 251.84 250.00 62,960.00
mix 1:3.

6.3 ditto but to roof gutter m2 48.00 250.00 12,000.00

6.4 Apply with gypsum chack to internal wall surface to Satisfy fine Final
m2 256.00 230.00 58,880.00
finish.

6.5 Pointing in cement sand mortar mix ratio (1:3) to external stone
m2 41.83 131.25 5,490.19
masonry wall.

6.5 150x150x6 ceramic wall tile icluding cement mortar backing and
m2 10.80 656.25 7,087.50
white cement grouting.

6.6 48mm thick cement sand mortar, mix (1:3 ) and screed finished
m2 137.69 472.50 65,058.53
smooth.

6.7 2mm thick PVC tile flooring stuck down with approved adhesive
m2 56.27 500.00 28,135.00
type.

6.8 10 mm height plastic skirting m 57.4 380 21812

6.9 Porcelain tile flooring m2 130.00 1,044.75 135,817.50


0.00
6.10 Porcelain skirting m 86.70 220.50 19,117.35
concrete pavement around the building bedde on 10cm thick hard
m2 38.00 520.00 19,760.00
core
6.11 300x30mm marble window sill m 27.94 1,050.00 29,337.00

Total to summary Birr 496,552.56

7. GLAZING

7.1 4mm thick quality clear glass fixed to LTZ profiles m2 17.08 700.00 11,956.00
7.2 4mm thick quality obsecured glass m 2
0.00 0.00 0.00

Total to summary Birr 11,956.00


8. PAINTING
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE

Prepare and apply by brush three coats of plastic emulsion paints.

8.1 To all plastered/chacked internal m2 251.84 115.50 29,087.52


8.2 To all plastered ext. wall surfaces m2 124.39 280.00 34,829.20

8.3 Pointing to masonry wall m2 41.83 94.50 3,952.94


8.4 To roof anti rest m2 252.00 180.00 45,360.00

Total to summary Birr 113,229.66

9. SANITARY INSTALLATION

INTERNAL SANITARY INSTALLATION WORKS

9.1 Supply and install galvanized steel pipes for


cold and hot water distribution to all sanitary fixtures
from the main inlet according to the drawing,
complete with necessary accessories such
as bends, union etc,. the unit price shall include
all necessary assisstance to the installation works, such
as chiseling of walls, slabs, beams, floors etc., and
closing them with concrete or cement mortar to normal
condition.The installation shall be tested at installation
at a pressure of 10kg/cm2 at the expense of the
contractor
15mm m 18.00 320 5,760.00
20mm m 20.00 380 7,600.00

9.2 Supply and fix gate valves of approved


standards for every sanitary fixture, complete
with unions, elastic water proofing and hand
wheels,etc. before fixtures (itally made).
15mm no 8.00 175 1,400.00
20mm no 4.00 260 1,040.00

Sanitary fixtures and fittings


9.3 Supply and fix hand wash basins of approved quality
made of white vitreous china equipped with concealed
fixing bracket plug chains, smell traps, water tap
adaptors.
size 500x400mm no 2.00 4700 9,400.00

9.4 Supply and fix low level white glazed vitereous china
wash down water closet,with all accessaries including
white plastic seat cover, white vitereous china flushing
cistern and lid fixing devices flexible pipes adoptors. Price shall no 2.00 1750 3,500.00
include all civil works

9.5 Supply and fix water heater complete with all water
proofing mounting and fastening matrial heat insulation
safety and none return valves with all required
accessaries
80 liter capacity no 2.00 8000.00 16,000.00

9.6 Supply and fix shower tray made of enameled cast iron
plate including chrome plated shower over head
complet with fitings and accessories.
size = 700x700 mm no 2.00 2656.5 5,313.00
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE
9.7 Supply and fix soap holder with of approved quality
complete with fixining screws for each shower and
bath tup room no 2.00 307.65 615.30

9.8 Supply and fix towel hunger with of approved quality


complete with fixining screws for each shower and
bath tup room no 2.00 307.65 615.30

9.9 Supply and fix toilet paper holderof approved quality


for each toilet rooms. no 2.00 307.65 615.30

910 Supply and fix crystal glass mirror including chrome


plated brass mirrors, clips and screws with standard
shelves.
size = 500x400 mm no 2.00 1700 3,400.00

9.11 Supply and lay siol waste and vent


pipe in horizontal branches and vertical
stacks made of rigid plastic pipes (PVC)
of approved standard including the
necessary fittings such as bends, Y, T, clean outs, floor
drains, with water tight joints as shown on the drawing.
All horizontal branch pipes shall be laid in a
slope of 2%. The unit price shall include
all the necessary assistance works,such as chiselling
of walls, slabs , beams, floors, etc., and closing them with
concrete or cement mortar.
Diameter 50mm m 10.40 99.75 1,037.40
Diameter 100mm m 10.00 115 1,150.00

9.12 Supply and fix floor drains made of approved quality


and chrome plated. Surface with all required acessaries
such as removable stainer cap and smell traps
(Itally made)

Diameter 80mm no 2.00 293 586.00

Total to summary Birr 58,032.30

10 ELECTRICAL INSTALLATION

A. Distribution board
A.1 Supply and install main distribution board (MDB)for
wall mounting (recessed) with lockable doorbus
bar system of 3-ph 40 A rating earthing lead and
complete connecting accessories consisting of the.
following
1pcs main ACB of 32A/1 - ph
4pcs ACB of 10A/1 - ph
5 pcs ACB of 16A/1 - ph pc 2.00 3,300.00 6,600.00

B. Light points
B.1 Supply and install flush mounted light points fed
through 3x2.5mm2 copper conductors in thermoplastic
conduits of dia.13.5/16 mm in/under surface including
boxes with junction boxes with covers, insulating and
screw caps and flush mounted switches . No. 36.00 320.00 11,520.00
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE

C. Power and socket outlet


C.1 Supply and install flush mounted socket outlet
of 16A,1ph with earthing contact fed through copper
conductor of 3x2.5mm2 in PVC conduit F13.5/16
mm in /under surface including junction boxes with
covers insulating screw caps No. 20.00 320.00 6,400.00

D. Light fittings with lamp or equivalent


D.1 For living dinning room, ceiling mounted suspended with 4*18w No. 2.00 13500.00 27,000.00
D.1 RZB 331023.00x A60 60w lamp No. 2.00 900.00 1,800.00

D.2 RZB 331030.00x with A60 60w lamp No. 2.00 900.00 1,800.00

D.3 RZB 331092.00x with A60 60w lamp No. 4.00 900.00 3,600.00

D.4 RZB 331037.00x with A60 40w lamp No. 18.00 900.00 16,200.00

D.5 RZB 58132.002 with A60 40w lamp No. 10.00 900.00 9,000.00

D.6 RZB 22143.00x with A60 60w lamp No. 2.00 900.00 1,800.00

E. Bell call systems


E.1 Supply and install bell calling points, Use 2x0.8mm2
conductor size, thermoplastic conduits of F11mm
in/under surface including junction boxes with covers
and insulating screw caps as well as push buttons
for flush mounting. No. 10.00 451.5 4,515.00

E.2 Bell call with transformer of 220/12v/25vA No. 2.00 661.5 1,323.00

F. Telephone systems

F.1 Telephon out let type Legrand Décor 71545 or equivalent


fed through the appropriate RJ 12 telephone wire inside
conduit of dia.19mm and terminal box as per ETCo rules
and regulations. No. 8.00 462.00 3,696.00

G. Television system

G.1 TV out let point fed through OVC insulated conductor of


2x0.8mm.sq.(75 Ohm)in conduit of dia.13.5mm including
junction boxes with covers for flush mounting as well as
TV socket type LEGRAND Décor 71841 or equivalent. No. 6.00 462.00 2,772.00

Total to summary Birr 98,026.00


TAKE OFF SHEET
Welekite Substation
TAKE OF SHEET
PROJECT Guard House Page ____
LOCATION DD Regional office SUB STRUCTURE

SINGLE TOTAL SINGLE TOTAL


PIECES DESCRIPTION OF QUANTITIES PIECES DESCRIPTION OF QUANTITIES
QTY QTY QTY QTY

A. SUBSTRUCTURE 1.6. Fill under concrete footings


1. Earth works: striped stone masonry
Foundations
3.73 1.1. Site clearance(m2) 0 1.20 F1
4.00 1.20
14.92 m2 0.25

0.00 m3
1.75 1.2. Bulk excavation 0 0.25 Foundation column
3.73 0.25
4.00 26.11 m3 2.45
1.3. Footing pit excavation up 0.00 m3
0 1.70 to 1.5m depth. 0.00 Masonry trench
1.70 F1 0.50
1.50 2.20
0 m3 0.00 m3
0 1.7
1.70 1.4 .Ditto as item 1.3, but depth 0.00
0.80 0.00 1.5 to 3m.
0.00 0.00 Fill(m3)
1.5.Trench Excavation
Grade beam 0.00 1.8. Fill under hard core
0 19.00 0.00 Axis A 19.00
0 19.80 0.00 Axis B&C 12.80
0 14.00 0.00 Axis D 0.00 m3
0 9.80 0.00 Axis 1&5 0.00 grade beam areas
0 9.80 0.00 Axis2&4 -0.15 Deduction
0 12.80 0.00 Axis3 0
0.00 Total Grade beam length 0.00
124.60 0.25
0.35 0.00 m2
0.00
0.00 m3
For masonry trenches
0.00
15.40
2.20 0.00
0.00 m3
0.00 Total Excavation(m3)
4.00 1.8 cart away 2.6. 100mm ground floor slab.
3.73 1.75 112.05 see 1.7.
26.11 clearing 0.1
27.86 excav. Total 11.21 m3
0.00 less: - concrete volume zigba wood formwork for:
2.7. footing pads
18 1.20
0.00 - bulkage 0.25
27.86 4.00
86.4 m2
1.9 . Hardcoring
0.00 see item 1.7. 18 0.25 2.8. footing columns
2.45
2. Concrete works: 4.00
Lean concrete 44.10
1 3.15 2.1. Under conc.footings
2.93 124.60 2.9. grade beam
9.23 m2 0.80
99.68
11.36 2.2. Under masonry foundation
0.70
7.95 m2 2.10. Steel reinforcement bars
2.3. Under grade beam
11.36 1,141.47 2.10. Ø 8 mm deformed
0.20 370.72 2.11. Ø 12 mm deformed
2.27 m2 1,039.89 2.12. Ø 16mm deformed

Concrete C-25 3. Masonry works:


1 2.73
2.95 2.3. footing pads 3.1. Undeerground
0.30
2.42 m3 119.50 total length
2.4. footing columns 2.00
5 0.20 0.50
0.20 119.50
1.50
0.30 m3 119.50 3.2. Above ground
124.60 2.5. grade beams 0.20
0.25 0.50
0.40 11.95
12.46 m3
131.45
B. SUPERSTRUCTURE
1. Concrete works:
concrete in class C-25
a) on the ground floor deduction (windows and doors)
20 0.25 1.1. in elevated columns 2 3.4 W1(3.4x2.1)
0.25 2.1 -14.28
3.00 6 2 W2(2.0x1.64)
3.75 m3 1.64 -19.68
1.2. top tie-beams 2 1.8 W3(1.8x0.6)
1 19.00 19.20 TB A 0.6 -2.16
2 19.80 39.90 TB B&C 2 1.2 D1(1.2x2.1)
1 13.74 13.74 TB D 2.1 -5.04
2 11.60 19.40 TB 1&5 4 2.10 D5(2.10 x .90)
2 11.60 19.40 TB2&4 0.70 -2.8
1 12.80 9.70 TB3 -43.96
121.34 Total Length 183.29 m2
121.34 m2
0.25 3 5.6 16.8 Axis B
0.25 3 9.8 29.4 b/n Axis A & B, 2 & 4
7.58 m 3 3 2.3 6.9 Axis 1'
zigba wood formwork 3 8.8 26.4 b/n Axis 1' & 2, 1' & 5
1.3. in elevated columns 3 10.54 31.62 Axis 2,4
20 0.25 3 3.90 11.7 b/n Axis A & B, 1 & 2,4 & 5
3.00 122.82
4.00 240.00
121.34 1.4. Top tie beams deduction (windows and doors)
1.00 TB A,B,C,D,1,2,3 2 2.10 D2(2.10 x 1.20)
121.34 1.20 -2.4
reinforcement bars 2 2.10 D3(2.10 x .90)
1.5 . in elevated columns 0.90 -1.8
119.45 a) Ø 8 deformed 2 2.10 D4(2.10 x .90)
451.25 c) Ø 16 deformed 0.90 -1.8
1.6 . Top tiebeams 2 2.10 D6(2.10 x .70)
0.70 -1.4
193.73 a) Ø 8 deformed -7.4
869.68 c) Ø 16 deformed 115.42 m2

1.7.Roof slab 3. Roofing:


0.00 a) Ø 10 deformed
2. Block works: 3.1. G-28 CIS roof cover
14.00
2.1. 200mm thick HCB 18.00
3.00 9.40 28.20 Axis A 252.00 m2
3.00 8.60 25.80 b/n Axis A & B, 1 & 2 3.2. G-28 met.sheet down pipe
3.00 3.50 10.50 b/n Axis 1 &2, 4 & 5 ,A & B 10 4.00 40.00 ml
3.00 1.75 5.25 Axis B
3.00 10.20 30.60 Axis C 3.3. G-28 Ridge cover
3.00 6.3 18.90 b/n Axis C &D, 2 & 4 44.8 ml
3.00 9.65 28.95 Axis 1
3.00 3.80 11.40 Axis 2 3.3. G-28 met. Sheet Gutter
3.00 9.10 27.30 Axis 3
3.00 3.80 11.40 Axis 4 60.00
3.00 9.65 28.95 Axis 5 1.25
227.25 m2 75 m2
"
4. Carpentry & joinry:
5. Metal Works: -
4.1. Eucaliptus trusses Doors: -
T-1 2.00 Type D1, size 120x210
6 22.90 137.40 Upper chord (12 Ф) 4.00 Type D5, size 90x210
6 22.70 136.20 Lower chord (10 Ф)
6 13.00 78.00 Vertical member( 8 Ф) Windows: -
6 22.10 132.60 Diagonal member (8 Ф) 2.00 Type W1, size (340 x 210)
6.00 Type W2, size (200 x 164)
T-2 2.00 Type W3, size (180 x 60)
17 6.60 112.20 Upper chord (12 Ф)
17 6.50 110.50 Lower chord (10 Ф) Windows - Door-: -
Type WD1, size 80 x210 +
17 3.60 61.20 Vertical member( 8 Ф) 1.00 Type WD1, size 100 x 110cm
70 x(210 +45)cm
17 5.00 85.00 Diagonal member (8 Ф) 1.00

T-3
9 4.10 36.90 Upper chord (12 Ф)
9 4.00 36.00 Lower chord (10 Ф)
9 2.00 18.00 Vertical member( 8 Ф)
9 3.20 28.80 Diagonal member (8 Ф)

T-4
2 2.80 5.60 Upper chord (12 Ф)
2 2.70 5.40 Lower chord (10 Ф)
2 1.50 3.00 Vertical member( 8 Ф)
2 2.70 5.40 Diagonal member (8 Ф)

T - 4'
4 2.50 10.00 Upper chord (12 Ф)
4 2.50 10.00 Lower chord (10 Ф)
4 0.90 3.60 Vertical member( 8 Ф)
4 1.50 6.00 Diagonal member (8 Ф)

T - 4"
4 1.60 6.40 Upper chord (12 Ф)
4 1.60 6.40 Lower chord (10 Ф)
4 1.50 6.00 Vertical member( 8 Ф)
4 0.50 2.00 Diagonal member (8 Ф)
Total
308.50 ml 12 Ф
304.50 ml 10 Ф
169.80 ml 8Ф
253.80 ml 8Ф
4.2. zigba purlins
352.00 ml

4.3. 30x2.5cm tid wood facia board


63.60 ml
4.4. 8mm chip wood
(=horizontally measured roof area)

243.20 m2
4.5. Wooden Doors
2.00 Type D2, size 120x210
2.00 Type D3, size 90x210
2.00 Type D4 size 90x210
2.00 Type D6, size 70x210
6. FINISHING deduction (windows and doors)
Three coats plastering 1 3.4 W1(3.4x2.1)
6. FINISHING 2.1 -7.14
6.1. Two coats plastering to 4 2 W2(2.0x1.64)
External surfaces. 1.64 -13.12
9.40 Axis A 2 1.8 W3(1.8x0.6)
10.20 Axis C 0.6 -2.16
6.3 b/n Axis A &B, 2 & 4 2 1.2 D1(1.2x2.1)
6.3 b/n Axis C &D, 2 & 4 2.1 -5.04
9.65 Axis 1 & 5 4 2.10 D2(2.10 x 1.20)
41.85 1.20 -10.08
3 4 2.10 D3(2.10 x .90)
125.55 m 2
0.90 -7.56
deduction (windows and doors) 4 2.10 D4(2.10 x .90)
2 3.4 W1(3.4x2.1) 0.90 -7.56
2.1 -14.28 4 2.10 D5(2.10 x .90)
4 2 W2(2.0x1.64) 0.70 -5.88
1.64 -13.12 4 2.10 D6(2.10 x .70) (two Face)
2 1.8 W3(1.8x0.6) 0.70 -5.88
0.6 -2.16
2 1.2 D1(1.2x2.1) -64.42 m2
2.1 -5.04 521.12 m2(Internal plastering)
4 2.10 D5(2.10 x .90) 609.27 Total(int & ext)
0.70 -2.8
-37.4 6.2. Tyrolean rendering to
88.15 m2 (External plastering) external wall surface
1 4.60 4.60 Axis A
Internal surfaces. 1 4.85 4.85 Axis C
1 9.40 9.40 Axis A 1 4.80 4.80 Axis D
2 25.40 50.80 Axis b/n A & B 1 7.60 7.60 Axis 1
2 7.50 15.00 Axis B 1 4.20 4.20 Axis 2 & 3
1 9.40 9.40 Axis C 1 7.60 7.60 Axis 3
1 6.30 6.30 b/n Axis C & D 33.65
2 8.80 17.60 b/n Axis 1' & 2 3.00
2 9.65 19.30 Axis 1 100.95 m2
2 24.04 48.08 Axis 2 &4 deduction (windows and doors)
2 9.65 19.30 Axis 3 1 3.4 W1(3.4x2.1)
195.18 2.1 -7.14
3.00 4 2 W2(2.0x1.64)
1.64 -13.12
585.54 m2 1 1.8 W3(1.8x0.6)
0.6 -1.08
1 1.2 D1(1.2x2.1)
2.1 -2.52
1 2.10 D5(2.10 x .90)
0.70 -0.7
-24.56 m2

76.39 m2
7. GLAZING
6.4.Apply with gypsum Cement
plastering to internal wall surface
to Satisfy fine Final finish.
7.1. 4mm thick clear glass
521.12 m2

36.12 windows area


6.5. Pointing masonry walls. 2.30 doors area
Err:522 m2
59.76 m2
7.2. 4mm thick obscured glass
6.6. Ceramic wall tile
14.40 0.00 m2
1.50
21.6 m2 8. PAINTING

6.6. 48mm thick cementscreed 8.1. To all plstrd. both wall surfs.

243.20 m2 4.20 net wall area


6.7. 2mm thick PVC tile flooring -10.80 - toilet rooms ceramic wall area
2.80 9.40 26.32
3.35 8.80 29.48 -6.60 m2
55.80 m2
8.2. To plastered roof slab sofits
6.8. Pvc skirting
60.80 ml 7.20 m2
8.3.Pointing to masonry wall
6.9.Porcelain tile flooring
4.30 25.20 108.36 59.76 m2
1.80 9.20 16.56
1.20 8.80 10.56 8.2. To chip wood ceiling
2.20 5.60 12.32
563.40 m2 243.20 m2
6.10.Porcelain Skirting

142.00 ml

6.11.300x30mm marble window


sill

2 3.4 6.8 W1(3.4x2.1)

6 2.00 12 W2(2.0x1.64)

2 1.80 3.6 W3(1.8x0.6)

22.40 ml
.

31
335.72
304.72
119.50
1.33 5.70
1.20 6.24
0.80 5.04
3.34 0.72
3.8456
21.55
4
1
BAR SCHEDULE

PROJECT: STANDARD OPERATOR'S MAIN SINGLE DWELLING HOUSE PAGE.................


LOCATION: SUB / STRUCTURE

LOCA- BAR BAR f LENG


TION No SHAPE (mm) (m) No OF BARS f6 f8 f10 f12 f14 f16 f18 f20
F 1 12 1.42 20 14 397.60
FC 1 16 2.35 11 4 103.40
FC stirr. 1 8 1.00 12 14 168.00
GFS 8 4.80 91 1 436.80
GFS 8 4.40 91 1 400.40
GFS 8 2.80 30 1 84.00
GFS 8 18.00 25 1 450.00
GFS 8 18.00 23 1 414.00
GFS 8 13.00 15 1 195.00
GB A 16 39.2 2 1 78.40
GB stirr A 8 1.00 91 1 91.00
GB B&C 16 42.05 2 2 168.20
GB stirr B&C 8 1.00 95 2 190.00
GB D 16 29.18 2 1 58.36
GB stirr D 8 1.00 68 1 68.00
GB 1&5 16 20.1 2 2 80.40
GB stirr 1&5 8 1.00 47 2 94.00
GB 2&4 16 21.24 2 2 84.96
GB stirr 2&4 8 1.00 50 2 100.00
GB 3 16 26.55 2 1 53.10
GB stirr 3 8 1.00 61 1 61.00

TOTAL LENGTH 0.00 2,752.20 0.00 397.60 0.00 626.82 0.00 0.00
WEIHHT Kg/m 0.222 0.395 0.617 0.888 1.210 1.580 2.470
TOTAL WEIGHT 0.00 1,087.12 0.00 353.07 0.00 990.38 0.00 0.00
5% CONTINGENCY 0.00 54.36 0.00 17.65 0.00 49.52 0.00 0.00
GRAND TOTAL WEIGHT 0.00 1,141.47 0.00 370.72 0.00 1,039.89 0.00 0.00

BAR SCHEDULE

PROJECT: STANDARD OPERATOR'S MAIN SINGLE DWELLING HOUSE PAGE.................


LOCATION: SUB / STRUCTURE
TOP TIE BEMS
LOCA- BAR BAR Ф LENG
TION No SHAPE (mm) (m) No OF BARS Ф6 Ф8 Ф10 Ф12 Ф14 Ф16 Ф18 Ф20
C1 16 3.40 4 20 272.00

C1 stirr. 8 0.90 16 20 288.00

TOTAL LENGTH 0.00 288.00 0.00 741.44 0.00 272.00 0.00 0.00
WEIHHT Kg/m 0.222 0.395 0.617 0.888 1.210 1.580 2.470
TOTAL WEIGHT 0.00 113.76 0.00 658.40 0.00 429.76 0.00 0.00
5% CONTINGENCY 0.00 5.69 0.00 32.92 0.00 21.49 0.00 0.00
GRAND TOTAL WEIGHT 0.00 119.45 0.00 691.32 0.00 451.25 0.00 0.00
BAR SCHEDULE

PROJECT: STANDARD OPERATOR'S MAIN SINGLE DWEL………………………………………………………...PAGE...............


LOCATION.................................................…….. …………………………………………...SUB / SUPER STRUCTURE
TOP TIE BEMS
LOCA- BAR BAR Ф LENG
TION No SHAPE (mm) (m) No OF BARS Ф6 Ф8 Ф10 Ф12 Ф14 Ф16 Ф18 Ф20

TTB A 16 19.85 2 1 39.70


TTB A 16 19.35 2 1 38.70

TTB stirrup A 8 0.90 91 1 81.90


TTB B 16 21.90 2 1 43.80
TTB B 16 20.35 2 1 40.70

TTB stirrup B 8 0.90 100 1 90.00


TTB C 16 21.90 2 1 43.80
TTB C 16 20.35 2 1 40.70

TTB stirrup C 8 0.90 100 1 90.00

TTB D 16 14.84 2 1 29.68

TTB D 16 14.34 2 1 28.68

TTB stirrup D 8 0.90 70 1 63.00


TTB 1&5 16 10.30 2 2 41.20

TTB 1&5 16 9.80 2 2 39.20

TTB stirrup 1 & 5 8 0.90 47 1 42.30


TTB 2&4 16 10.87 2 2 43.48
TTB 2&4 16 10.37 2 2 41.48

TTB stirrup 2 & 4 8 0.90 50 1 45.00


TTB 3 16 13.40 2 1 26.80
TTB 3 16 13.15 2 1 26.30

TTB stirrup 3 8 0.90 61 1 54.90

TOTAL LENGTH (m)……. 467.10 0.00 0.00 0.00 524.22


WEIGHT ( Kg/ m)……… 0.222 0.395 0.617 0.888 1.208 1.580 2.000 2.47
TOTAL WEIGHT (Kg)………. 0.00 184.50 0.00 0.00 0.00 828.27 0.00 0.00
Add 5% Wastage (Kg)……….. 0.00 9.23 0.00 0.00 0.00 41.41 0.00 0.00
GRNAD TOTAL WEIGHT (Kg).. 0.00 193.73 0.00 0.00 0.00 869.68 0.00 0.00

You might also like