Guard House
Guard House
QUANTITIES
FOR
THE CONSTRUCTION OF
prepared by
Lelisa T
DUPLEX DWELLING HOUSE
SUMMARY
A.SUB- STRUCTURE
Sum 799,942.98
B.SUPER - STRUCTURE
3. Roofing 214,788.00
6.finishing 496,552.56
7.Glazing 11,956.00
8. Painting 113,229.66
9. Sanitary 58,032.30
10 Electrical 98,026.00
Sum 2,296,690.58
1
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE
A.SUB STRUCTURE
1.EARTH WORKS
1.1 Clear of the site to remove top soil to an average depth of 200mm m2 14.92 34.85 519.96
1.2 Bulk excavation in ordinary soil to a depth of 400mm m3 26.11 174.25 4,549.67
1.3 Excavate for footing trench to an average depth not exceeding
m3 0.00 85.00 0.00
1500mm below strips ground level.
1.4 Ditto as item 1.3, but depth 1.5 to 3.00m m3 0.00 95.00 0.00
1.5 Trench excavation in ordinary soil to a depth not exceeding 1500mm
m3 0.00 85.00 0.00
from reduced ground level
1.6 Fill under concrete footings & striped stone masonry foundations to
a required level with non expansive selected material out side the site m3 0.00 409.00 0.00
and well compacted in layer of 150mm thick.
1.7 Fill under hard core with non expansive selected material from site
m3 0.00 409.00 0.00
and well compacted in layer of 200mm thick.
1.8 Cart away excavated surplus material 5km away from the site,
m3 27.86 165.00 4,596.90
spread and level it as the site requires.
1.9 250 mm thick basaltic or equivalent stone hard core well rolled and
m2 0.00 416.59 0.00
consolidated and blinded with crushed stone.
2.CONCRETE WORK
Provide cut and fix in position swan zigba wood formwork to:
3. MASONARY WORK
3.2 Ditto, but 300 mm high exposed roughly dressed stone wall one side
m3 11.95 2,447.55 29,248.22
left for plastering above ground level
B.SUPER - STRUCTURE
1. CONCRETE WORK
Provide cut and fix in position swan zigba wood formwork to:-
2. BLOCK WORK
2.1 200mm thick HCB wall bedded in cement - sand mortar mix (1:3)
m2 260.00 537.32 139,703.20
both sides left for plastering.
2.2 Ditto, but 150mm thick partition & parapate Wall. m2 105.00 461.47 48,454.35
3.ROOFING
3.1 Supply & fix G-28 CIS metal sheet and painted one coat of anti-rust
m2 252.00 670.00 168,840.00
and two coats of synthetic paint.
3.2 Supply and fix metal coping ml 40.00 304.50 12,180.00
3.3 supply and fix G-28 galvanized flat metal sheet gutter within the the
ml 54.00 304.50 16,443.00
proposed concrete gutter support and coated with rustresisting paint
3.4 Supply and install110 mm PVC down pipes. Price includes fixing of
ml 75.00 231.00 17,325.00
pipes and bracing with metal bands.
4.4 plastic ceiling on and at 620mm centers both ways and fixed to truss,
m2 214.80 658.35 141,413.58
at corners shall be covered with sloped plastic ceiling cover fillet
4.5 Supply and fix 40 mm thick semi solid core flash wooden door
covered with 4mm thick woira ply wood decorated with and
including 3 coats of varnish paint. Price shall include all necessary
iron mongery and an approved type cylindrical door lock.
5. METAL WORKS
Supply and fix door and window made of Aluminium frames glazed
as shown the drawing including approved type hinges handles and
type cylindrical or equivalent .Price includes 5 mm thick clear/
patterned glass as required.
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE
DOORS
6. FINISHING
6.4 Apply with gypsum chack to internal wall surface to Satisfy fine Final
m2 256.00 230.00 58,880.00
finish.
6.5 Pointing in cement sand mortar mix ratio (1:3) to external stone
m2 41.83 131.25 5,490.19
masonry wall.
6.5 150x150x6 ceramic wall tile icluding cement mortar backing and
m2 10.80 656.25 7,087.50
white cement grouting.
6.6 48mm thick cement sand mortar, mix (1:3 ) and screed finished
m2 137.69 472.50 65,058.53
smooth.
6.7 2mm thick PVC tile flooring stuck down with approved adhesive
m2 56.27 500.00 28,135.00
type.
7. GLAZING
7.1 4mm thick quality clear glass fixed to LTZ profiles m2 17.08 700.00 11,956.00
7.2 4mm thick quality obsecured glass m 2
0.00 0.00 0.00
9. SANITARY INSTALLATION
9.4 Supply and fix low level white glazed vitereous china
wash down water closet,with all accessaries including
white plastic seat cover, white vitereous china flushing
cistern and lid fixing devices flexible pipes adoptors. Price shall no 2.00 1750 3,500.00
include all civil works
9.5 Supply and fix water heater complete with all water
proofing mounting and fastening matrial heat insulation
safety and none return valves with all required
accessaries
80 liter capacity no 2.00 8000.00 16,000.00
9.6 Supply and fix shower tray made of enameled cast iron
plate including chrome plated shower over head
complet with fitings and accessories.
size = 700x700 mm no 2.00 2656.5 5,313.00
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE
9.7 Supply and fix soap holder with of approved quality
complete with fixining screws for each shower and
bath tup room no 2.00 307.65 615.30
10 ELECTRICAL INSTALLATION
A. Distribution board
A.1 Supply and install main distribution board (MDB)for
wall mounting (recessed) with lockable doorbus
bar system of 3-ph 40 A rating earthing lead and
complete connecting accessories consisting of the.
following
1pcs main ACB of 32A/1 - ph
4pcs ACB of 10A/1 - ph
5 pcs ACB of 16A/1 - ph pc 2.00 3,300.00 6,600.00
B. Light points
B.1 Supply and install flush mounted light points fed
through 3x2.5mm2 copper conductors in thermoplastic
conduits of dia.13.5/16 mm in/under surface including
boxes with junction boxes with covers, insulating and
screw caps and flush mounted switches . No. 36.00 320.00 11,520.00
ITEM DESCRIPTION UNIT QTY U.PRICE TOTAL PRICE
D.2 RZB 331030.00x with A60 60w lamp No. 2.00 900.00 1,800.00
D.3 RZB 331092.00x with A60 60w lamp No. 4.00 900.00 3,600.00
D.4 RZB 331037.00x with A60 40w lamp No. 18.00 900.00 16,200.00
D.5 RZB 58132.002 with A60 40w lamp No. 10.00 900.00 9,000.00
D.6 RZB 22143.00x with A60 60w lamp No. 2.00 900.00 1,800.00
E.2 Bell call with transformer of 220/12v/25vA No. 2.00 661.5 1,323.00
F. Telephone systems
G. Television system
0.00 m3
1.75 1.2. Bulk excavation 0 0.25 Foundation column
3.73 0.25
4.00 26.11 m3 2.45
1.3. Footing pit excavation up 0.00 m3
0 1.70 to 1.5m depth. 0.00 Masonry trench
1.70 F1 0.50
1.50 2.20
0 m3 0.00 m3
0 1.7
1.70 1.4 .Ditto as item 1.3, but depth 0.00
0.80 0.00 1.5 to 3m.
0.00 0.00 Fill(m3)
1.5.Trench Excavation
Grade beam 0.00 1.8. Fill under hard core
0 19.00 0.00 Axis A 19.00
0 19.80 0.00 Axis B&C 12.80
0 14.00 0.00 Axis D 0.00 m3
0 9.80 0.00 Axis 1&5 0.00 grade beam areas
0 9.80 0.00 Axis2&4 -0.15 Deduction
0 12.80 0.00 Axis3 0
0.00 Total Grade beam length 0.00
124.60 0.25
0.35 0.00 m2
0.00
0.00 m3
For masonry trenches
0.00
15.40
2.20 0.00
0.00 m3
0.00 Total Excavation(m3)
4.00 1.8 cart away 2.6. 100mm ground floor slab.
3.73 1.75 112.05 see 1.7.
26.11 clearing 0.1
27.86 excav. Total 11.21 m3
0.00 less: - concrete volume zigba wood formwork for:
2.7. footing pads
18 1.20
0.00 - bulkage 0.25
27.86 4.00
86.4 m2
1.9 . Hardcoring
0.00 see item 1.7. 18 0.25 2.8. footing columns
2.45
2. Concrete works: 4.00
Lean concrete 44.10
1 3.15 2.1. Under conc.footings
2.93 124.60 2.9. grade beam
9.23 m2 0.80
99.68
11.36 2.2. Under masonry foundation
0.70
7.95 m2 2.10. Steel reinforcement bars
2.3. Under grade beam
11.36 1,141.47 2.10. Ø 8 mm deformed
0.20 370.72 2.11. Ø 12 mm deformed
2.27 m2 1,039.89 2.12. Ø 16mm deformed
T-3
9 4.10 36.90 Upper chord (12 Ф)
9 4.00 36.00 Lower chord (10 Ф)
9 2.00 18.00 Vertical member( 8 Ф)
9 3.20 28.80 Diagonal member (8 Ф)
T-4
2 2.80 5.60 Upper chord (12 Ф)
2 2.70 5.40 Lower chord (10 Ф)
2 1.50 3.00 Vertical member( 8 Ф)
2 2.70 5.40 Diagonal member (8 Ф)
T - 4'
4 2.50 10.00 Upper chord (12 Ф)
4 2.50 10.00 Lower chord (10 Ф)
4 0.90 3.60 Vertical member( 8 Ф)
4 1.50 6.00 Diagonal member (8 Ф)
T - 4"
4 1.60 6.40 Upper chord (12 Ф)
4 1.60 6.40 Lower chord (10 Ф)
4 1.50 6.00 Vertical member( 8 Ф)
4 0.50 2.00 Diagonal member (8 Ф)
Total
308.50 ml 12 Ф
304.50 ml 10 Ф
169.80 ml 8Ф
253.80 ml 8Ф
4.2. zigba purlins
352.00 ml
243.20 m2
4.5. Wooden Doors
2.00 Type D2, size 120x210
2.00 Type D3, size 90x210
2.00 Type D4 size 90x210
2.00 Type D6, size 70x210
6. FINISHING deduction (windows and doors)
Three coats plastering 1 3.4 W1(3.4x2.1)
6. FINISHING 2.1 -7.14
6.1. Two coats plastering to 4 2 W2(2.0x1.64)
External surfaces. 1.64 -13.12
9.40 Axis A 2 1.8 W3(1.8x0.6)
10.20 Axis C 0.6 -2.16
6.3 b/n Axis A &B, 2 & 4 2 1.2 D1(1.2x2.1)
6.3 b/n Axis C &D, 2 & 4 2.1 -5.04
9.65 Axis 1 & 5 4 2.10 D2(2.10 x 1.20)
41.85 1.20 -10.08
3 4 2.10 D3(2.10 x .90)
125.55 m 2
0.90 -7.56
deduction (windows and doors) 4 2.10 D4(2.10 x .90)
2 3.4 W1(3.4x2.1) 0.90 -7.56
2.1 -14.28 4 2.10 D5(2.10 x .90)
4 2 W2(2.0x1.64) 0.70 -5.88
1.64 -13.12 4 2.10 D6(2.10 x .70) (two Face)
2 1.8 W3(1.8x0.6) 0.70 -5.88
0.6 -2.16
2 1.2 D1(1.2x2.1) -64.42 m2
2.1 -5.04 521.12 m2(Internal plastering)
4 2.10 D5(2.10 x .90) 609.27 Total(int & ext)
0.70 -2.8
-37.4 6.2. Tyrolean rendering to
88.15 m2 (External plastering) external wall surface
1 4.60 4.60 Axis A
Internal surfaces. 1 4.85 4.85 Axis C
1 9.40 9.40 Axis A 1 4.80 4.80 Axis D
2 25.40 50.80 Axis b/n A & B 1 7.60 7.60 Axis 1
2 7.50 15.00 Axis B 1 4.20 4.20 Axis 2 & 3
1 9.40 9.40 Axis C 1 7.60 7.60 Axis 3
1 6.30 6.30 b/n Axis C & D 33.65
2 8.80 17.60 b/n Axis 1' & 2 3.00
2 9.65 19.30 Axis 1 100.95 m2
2 24.04 48.08 Axis 2 &4 deduction (windows and doors)
2 9.65 19.30 Axis 3 1 3.4 W1(3.4x2.1)
195.18 2.1 -7.14
3.00 4 2 W2(2.0x1.64)
1.64 -13.12
585.54 m2 1 1.8 W3(1.8x0.6)
0.6 -1.08
1 1.2 D1(1.2x2.1)
2.1 -2.52
1 2.10 D5(2.10 x .90)
0.70 -0.7
-24.56 m2
76.39 m2
7. GLAZING
6.4.Apply with gypsum Cement
plastering to internal wall surface
to Satisfy fine Final finish.
7.1. 4mm thick clear glass
521.12 m2
6.6. 48mm thick cementscreed 8.1. To all plstrd. both wall surfs.
142.00 ml
6 2.00 12 W2(2.0x1.64)
22.40 ml
.
31
335.72
304.72
119.50
1.33 5.70
1.20 6.24
0.80 5.04
3.34 0.72
3.8456
21.55
4
1
BAR SCHEDULE
TOTAL LENGTH 0.00 2,752.20 0.00 397.60 0.00 626.82 0.00 0.00
WEIHHT Kg/m 0.222 0.395 0.617 0.888 1.210 1.580 2.470
TOTAL WEIGHT 0.00 1,087.12 0.00 353.07 0.00 990.38 0.00 0.00
5% CONTINGENCY 0.00 54.36 0.00 17.65 0.00 49.52 0.00 0.00
GRAND TOTAL WEIGHT 0.00 1,141.47 0.00 370.72 0.00 1,039.89 0.00 0.00
BAR SCHEDULE
TOTAL LENGTH 0.00 288.00 0.00 741.44 0.00 272.00 0.00 0.00
WEIHHT Kg/m 0.222 0.395 0.617 0.888 1.210 1.580 2.470
TOTAL WEIGHT 0.00 113.76 0.00 658.40 0.00 429.76 0.00 0.00
5% CONTINGENCY 0.00 5.69 0.00 32.92 0.00 21.49 0.00 0.00
GRAND TOTAL WEIGHT 0.00 119.45 0.00 691.32 0.00 451.25 0.00 0.00
BAR SCHEDULE