AR-MOS-1 - Wood Doors Installation
AR-MOS-1 - Wood Doors Installation
REV.00
Project Name
Ribat Shahata Al- Balad, Jeddah MOC Projects
1.0 PURPOSE
This method statement provides guidelines for the necessary works in the installation of
wood doors including accessories within the area of the REHABILITITATION OF
SHAHATA HOUSE and in accordance with project specification document and the project
schedule. To ensure efficient and safe installation. It outlines the necessary steps and
precautions to be taken during the installation process and guarantees that the quality of work
shall be carried out in full conformity with the project scope of work, applicable standards and
approved procedures to the satisfaction of the client.
2.0 SCOPE
This Method Statement describes the specific tasks required for the installation of wood
doors. It ensures that all activities are done in a safe and orderly manner. This meets the
requirements of the HSE manual, applicable quality standards and the manufacturer's
installation instructions for MOC Framework (Rehabilitation of SHAHATA House). It covers
the installation process from start to finish, including all necessary tools, equipment, and
safety precautions for the MOC Framework (Rehabilitation of SHAHATA House). In
accordance with approved shop drawings and materials.
This method statement covers the contractor’s responsibility, work execution procedure,
safety and quality control requirements as applicable for this particular work.
4.0 REFERENCES
a. Project Design
b. Approved Material
c. Project Quality Plan.
d. HSE Plan
e. Organizational Chart
5.0 RESPONSIBILITY
5.1. Project Manager - To ensure that the work described hereunder is executed in
accordance with all the contract requirements including this method statement and all
safety aspect of the installation
5.2. Construction Manager – Responsible for the verification of this method statement and of
any subsequent revision. He also responsible for ensuring that all works are performed
timely, properly, accurately and completely and aside from making sure that corrective
action is taken in case the work is not done correctly. Also ensures that all safety issues are
promptly addressed and remedied, and safety requirements and stipulation are met and
that all works are performed in accordance with well-established practices and procedures.
The Construction Manager reports to the Project Manager on the overall status of the site
execution works.
• Secures Work Permits to execute the job and ensures that a copy of the permit is displayed
in the work area.
• Ensure that all safety requirements to start the activity as listed in the work permit are in
place.
• Coordinates with the QC inspectors to ensure that all relevant inspections are completed
and approved to allow succeeding work to proceed.
• Supervises the execution of the work and ensures that it is being done as per approved
project specifications, drawings, material technical date sheet, and work procedure
• Ensures that all operatives involved in the performance of this work have been briefed
with this method statement and have the correct information as to the works that they are
required to perform
• Takes corrective actions required if any work has not been performed correctly
• Prepares and submits inputs to the daily report
• Reports directly to the Project Engineer
5.4. QA/QC Manager - Responsible for reviewing this procedure and also has the overall
responsibility of ensuring that works in the field are performed in compliance with all
applicable quality standards, stipulations and procedures in addition to ensuring that
corrective actions are taken in cases where are not performed correctly.
• Responsible for ensuring that all safety requirements necessary to start these activities is
provided by the construction group as per project HSE Manual and specification.
• Conducts inspection to ensure that all safety requirements are being maintained up to the
completion of this activity.
• Shall coordinate directly with the Project / Site Engineer regarding advisement on safety
issues and problems
• To report any safety violation to HSE Manager in order to take corrective action
5.6. HSE Manager – Responsible for reviewing this procedure to ensure systems of work are
in place/considered in each phase of the activities. He also has the overall responsibility of
ensuring, thought the safety supervisor/Safety Officer. Who works in the field are performed
safely and in compliance with all safety standards, stipulations functional responsibility to
the project manager.
• The foreman will out his duties by maintaining continuous with the site engineer on daily
basis, and ensure proper distribution of the workforce in the required and planned locations.
• To ensure that his assistance foreman/charge hand is aware of the job requirements and
they have enough information to carry out their duties properly.
• To ensure in consultation with the site engineer that the manpower involved the works are
moving as agreed and planned for the work
• To co-ordinate with the main contractor, MEP Coordinator and Safety Officer, for a safe
and proper execution of the works.
• To ensure full coordination with the safety officer to maintain safe work and proper
housekeeping of the site, following the approved safety measures and further ensure that all
his working team are aware of the same to prevent accident and loses.
• To inform the site engineer and of the areas ready for inspection
• Control of material shall be monitored by foreman and store keeping.
d. Inspection and Testing - Quality control inspection shall be conducted in accordance with
the approved inspection and Testing Plan (ITP)
10.0 Records - All records must be kept secure. Access to these records
should be limited to authorize personnel only. Records should be
regularly reviewed and updated.
ITP AS BUILT
MTS SD
WO MIR
WIP