PROPOSED SOUTH BEACH WELIGAMA
CONDOMINIUM DEVELOPMENT AT
WELIGAMA
METHOD STATEMENT
FOR
FORM WORKS
Method Statement for Form work
TABLE OF CONTENTS PAGE NO
1 Purpose ................................................................................................................................................ 2
2 Specification References ...................................................................................................................... 2
3 PPE Materials ...................................................................................................................................... 2
4 Materials ............................................................................................................................................... 2
5 Plant and Equipment ........................................................................................................................... 3
6 Resources and Manpower ................................................................................................................... 3
7 Methodology ......................................................................................................................................... 4
8. Inspection & approval ………………………………………………………………………………..8
Buildmart Lanka (Pvt) Ltd Page 1
Method Statement for Form work
1. Purpose
➢ This method statement is to explain how the form works applies in
foundations, walls, columns, slabs & beams
2. Specification References
➢ Structural Consultant’s guidelines and notes.
➢ BS standards and CIDA guidelines and specifications.
➢ Relevant / applicable construction drawings.
3. PPE Materials
➢ Following PPE (Personal Protective Equipment) should be provide in
order to all work.
• Safety Helmets
• Safety Boots
• Hand Gloves
• Safety Masks
4. Materials
• 15mm Plywood
• Wire nails
• Concrete Nails
• 2”x2” Timber
• 2”x4” Timber
• 4”x4” Timber
• “T” Jack
• “U” Jack
• Acro jack
• GI Pipes
• Form Tie
• Thread bar
• P cone
• Chains
Buildmart Lanka (Pvt) Ltd Page 2
Method Statement for Form work
• Turn Buckles
• Mould oil
• Scaffoldings
• Cross bracing
• Join pin
• GI clamps
5. Plant and Equipment
• Power Saw
• Electric Drill
• Hammer
• Nail Puller
• Auto Leveling Instrument
• Theodolite
• Staff
• Measuring Tape
• Set Square
• Plum bobs
• Marking boat
• Water level
• Spirit level
6. Resources and Manpower
➢ Site manager
➢ Site Engineer
➢ Assistant Engineer
➢ Supervisor
➢ Quality Assurance Inspector / Quality Control Inspector
➢ Survey Helpers
➢ Un Skill Labour
➢ Carpenter
Buildmart Lanka (Pvt) Ltd Page 3
Method Statement for Form work
➢ Health and Safety Officer
7. Methodology
➢ 7.1 Setting Out
• The detailed drawings will be used for setting out work.
• Erection of formwork shall be done in several stages accordingly.
• The Levels and line will be checked by supervisors before Erection of Formwork.
➢ 7.2 Preparation for Formwork
• Initially all the panels prepared at formwork fabrication yard and then directly install
and combine at the construction site.
• Foundation Perimeter formwork prepare by panels as shown in Figure 1.
Figure 1
Buildmart Lanka (Pvt) Ltd Page 4
Method Statement for Form work
• Wall form work as shown in figure 2
SECTION OF WALL FORMWORK
ELEVATION OF WALL FORMWORK
Figure 2
Buildmart Lanka (Pvt) Ltd Page 5
Method Statement for Form work
• Column form work as shown in figure 3
Figure 3
• Slab & beam form work as in figure 4
Buildmart Lanka (Pvt) Ltd Page 6
Method Statement for Form work
Figure 4
• Mould oil will be applied on the 15mm plywood board to improve the removal of
formwork.
Buildmart Lanka (Pvt) Ltd Page 7
Method Statement for Form work
➢ 7.3 Erection of Formwork
Erect the formwork by providing sufficient props and struts including necessary
bracing as per above figures. Seal gaps in formwork to avoid leakage of grout. Ensure
checking for the required shape and dimensions as per drawings.
➢ 7.3 Removal of Formwork
• Support removal will be carried out in such a way that no any damage occurred to a
concrete structure.
• Removal of form work will be done as fallows
Type of Form work Form work Removal Time
Foundation sides 16-24hrs
Walls 16-24hrs
Columns 16-24hrs
Beam sides 24hrs
Beam bottoms 14 days
Slab 14 days
• All the removed supporting materials will be stacked properly and all the debris
should be cleaned after removal of supports.
➢ 7.3.1 Removal of Plywood Panels
• Once the panels removed all the “P Cone” holes will be patched by construction grout as
per the specification
8.Inspections and Approvals
➢ On field site inspections and approvals sign off by team confirming
consulting Engineer and Contractor representative.
9.Health and Safety
➢ In accordance with the BML Health and safety guidelines.