Study About Relay & Meter Function & Reading
Study About Relay & Meter Function & Reading
Introduction:-
For successful operation of power system, the protection scheme provides an
important role . The Protection system mainly depends on his two powerful
hands.
1. Left hand:- Sensing element/equipments
2. Right hand:- Obeying element/equipments
Then protection scheme analyze the parameter and given command to ever time
obeying element circuit breaker.
If the parameters are abnormal / not safe for system then it means that
something is occurring wrong in system .Then next step of the protection Scheme
is to trace the section in which this type of critical situation has been created,
then next step to isolate the related part from the system to avoid any further
damage / collapse of system. So this whole phenomenon is completed through
the protection scheme. Now we discuss ... what are the abnormal condition and
what is meant by fault .
Then protection scheme analyze the parameter and given command to ever time
obeying element circuit breaker.
Actually circuit breaker isolates the faulty system from rest of the healthy
system and this circuit breakers automatically open during fault condition due to
its trip signal comes from protection relay.
But Remember :
The main philosophy about protection is that no protection of power system can
prevent the flow of fault current through the system, it only can prevent the
continuation of flowing of fault current by quickly disconnect the short circuit
path from the system.
In the picture the basic connection of protection relay has been shown. It is
quite simple. The secondary of current transformer is connected to the current
coil of relay. And secondary of voltage transformer is connected to the voltage
coil of the relay. Whenever any fault occurs in the feeder circuit, proportionate
secondary current of the CT will flow through the current coil of the relay due to
which mmf of that coil is increased. This increased mmf is sufficient to
mechanically close the normally open contact of the relay. This relay contact
actually closes and completes the DC trip coil circuit and hence the trip coil is
energized. The mmf of the trip coil initiates the mechanical movement of the
tripping mechanism of the circuit breaker and ultimately the circuit breaker is
tripped to isolate the fault.
Selectivity :-
The relay must be operated in only those conditions for which relays are
commissioned in the electrical power system. There may be some typical
condition during fault for which some relays should not be operated or operated
after some definite time delay hence protection relay must be sufficiently capable
to select appropriate condition for which it would be operated.
Sensitivity :-
The relaying equipment must be sufficiently sensitive so that it can be operated
reliably when level of fault condition just crosses the predefined limit.
Speed
The protective relays must operate at the required speed. There must be a
correct coordination provided in various power system protection relays in such a
way that for fault at one portion of the system should not disturb other healthy
portion.
Fault current may flow through a part of healthy portion since they are
electrically connected but relays associated with that healthy portion should not
be operated faster than the relays of faulty portion otherwise undesired
interruption of healthy system may occur. Again if relay associated with faulty
portion is not operated in proper time due to any defect in it or other reason,
then only the next relay associated with the healthy portion of the system must
be operated to isolate the fault. Hence it should neither be too slow which may
result in damage to the equipment nor should it be too fast which may result in
undesired operation.
Then...
Protection scheme self analyze the system by taking above two parameter by
comparing with present parameter (Formulas as set in software of relay).
If the parameters are abnormal/not safe for system then it means that something
is occurring wrong in system.
Then next step of the protection scheme is that to trace the section in which this
type of critical situation has been created then next to isolate that part from the
system to avoid any damage/collapse of system.
1. Pick up current.
2. Current setting.
In all electrical relays, the moving contacts are not free to move. All the
contacts remain in their respective normal position by some force
applied on them continuously. This force is called controlling force of
the relay. This controlling force may be gravitational force, may be
spring force, may be magnetic force.
For example>>>>
suppose, you want that, an over current relay should operate when
the system current just crosses 125% of rated current. If the relay is
rated with 1 A, the normal pick up current of the relay is 1 A and it
should be equal to secondary rated current of current transformer
connected to the relay.
Then, the relay will be operated when the current of CT secondary
becomes more than or equal 1.25 A.
As per definition,
The current setting is sometimes referred as current plug setting.
The current setting of over current relay is generally ranged from 50 %
to 200 %, in steps of 25 %. For earth fault relay it is from 10% to 70% in
steps of 10%.
Now, suppose fault current in the CT primary is 1000 A. Hence, fault current in
the CT secondary i.e. in the relay coil is, 1000 × 1/200 = 5A
The operating time of an electrical relay mainly depends upon two factors :
1.How long distance to be traveled by the moving parts of the relay for closing
relay contacts and
2.How fast the moving parts of the relay cover this distance.
But by adjusting only time setting multiplier, we can not set the actual time of
operation of an electrical relay. As we already said, the time of operation also
depends upon the speed of operation. The speed of moving parts of relay
depends upon the force due to current in the relay coil. Hence, it is clear that,
speed of operation of an electrical relay depends upon the level of fault current.
In other words, time of operation of relay depends upon plug setting multiplier.
The relation between time of operation and plug setting multiplier is plotted on a
graph paper and this is known as time / PSM graph. From this graph one can
determine, the total time taken by the moving parts of an electromechanical
relay, to complete its total travelling distance for different PSM. In time setting
multiplier, this total travelling distance is divided and calibrated from 0 to 1 in
steps of 0.05.
So when time setting is 0.1, the moving parts of the relay has to travel only 0.1
times of the total travelling distance, to close the contact of the relay. So, if we
get total operating time of the relay for a particular PSM from time / PSM graph
and if we multiply that time with the time setting multiplier, we will get, actual
time of operation of relay for said PSM and TSM.
For getting clear idea, let us have a practical example. Say a relay has time setting
0.1 and you have to calculate actual time of operation for PSM 10.
From time / PSM graph of the relay, we can see the total operating time of the
relay is 3 seconds. That means, the moving parts of the relay take total 3 seconds
to travel 100 % travelling distance. As the time setting multiplier is 0.1 here,
actually the moving parts of the relay have to travel only 0.1 × 100% or 10% of the
total travel distance, to close the relay contacts.
Hence, actual operating time of the relay is 3 × 0.1 = 0.3 sec. i.e. 10% of 3 sec.
In mechanical relay these closing and opening of relay contacts are done by
mechanical displacement of different gear level system.
3. Instantaneous relays.
5. Stepped characteristic.
6. Programmed switches.
2. Unbalance.
3. Neutral displacement.
4. Directional.
7. Distance schemes.
2. Voltage relays.
3. Frequency relays.
2. Backup relay.
2. Float type
a. Buchholz
b. OSR
c. PRV
d. Water level Controls etc.
3. Pressure switches.
4. Mechanical interlocks.
Voltage Ratio
and
SL Relays on HV Side Relays on LV Side Common Relays
Capacity of
Transformer
Differential Relay
3 nos Non-Directional
Overflux Relay
O/L Relay
220 /6.6KV 3 nos Non- Buchholz Relay
1 no Non-Directional
3 Station Directional O/L OLTC Buchholz Relay
E/L Relay
Transformer Relay PRV Relay
and/or standby E/F +
OT Trip Relay
REF Relay
WT Trip Relay
Differential Relay
Overflux Relay
3 nos Non- Buchholz Relay
Gen-volt/6.6KV 3 nos Non-Directional
4 Directional O/L OLTC Buchholz Relay
UAT O/L Relay
Relay PRV Relay
OT Trip Relay
WT Trip Relay
Buchholz Relay
OLTC Buchholz Relay
132/33/11KV 3 nos O/L Relay 2 nos O/L Relays
5 PRV Relay
upto 8 MVA 1 no E/L Relay 1 no E/L Relay
OT Trip Relay
WT Trip Relay
Differential Relay
Buchholz Relay
132/33/11KV 3 nos O/L Relay
3 nos O/L Relay OLTC Buchholz Relay
6 above 8 MVA & 1 no Directional E/L
1 no E/L Relay PRV Relay
below 31.5 MVA Relay
OT Trip Relay
WT Trip Relay
Differential Relay
3 nos O/L Relay Overflux Relay
132/33KV, 31.5 3 nos O/L Relay
7 1 no Directional E/L Buchholz Relay
MVA & above 1 no E/L Relay
Relay OLTC Buchholz Relay
PRV Relay
OT Trip Relay
WT Trip Relay
Differential Relay
220/33 KV, Overflux Relay
31.5MVA & 3 nos O/L Relay 3 nos O/L Relay Buchholz Relay
8 50MVA 1 no Directional E/L 1 no Directional OLTC Buchholz Relay
220/132KV, 100 Relay E/L Relay PRV Relay
MVA OT Trip Relay
WT Trip Relay
Differential Relay
3 nos Directional O/L
Overflux Relay
Relay 3 nos Directional
Buchholz Relay
(with dir.highset) O/L Relay
OLTC Buchholz Relay
400/220KV 1 no Directional E/L (with dir.highset)
9 PRV Relay
315MVA relay. 1 no Directional
OT Trip Relay
Restricted E/F relay E/L relay.
WT Trip Relay
3 nos Directional O/L Restricted E/F relay
Over Load (Alarm)
Relay for action
Relay
Depending upon time of operation, there are various types of Over Current
relays, such as,
In the graph above, it is also observed that, when actuating quantity is less than
OA, the relay operating time becomes infinity, that means for actuating quantity
less than OA, the relay does not at all actuate. This minimum value of actuating
quantity for which a relay initiates its operation is known as pick up value of
actuating quantity. Here it is denoted as OA.
It is also seen from the graph that, when actuating quantity approaches to infinity
along x axis the operating time does not approach to zero. The curve approaches
to an approximately constant operating time. This is approximately minimum
time required to operate the relay.
The inverse time relay, where the actuating quantity is current, is known as
inverse current relay.
In this type of relay, the inverse time is achieved by attaching some mechanical
accessories in the relay.
>>> Inverse time over current relay or simply inverse OC relay is again
subdivided as inverse definite minimum time (IDMT), very inverse time,
extremely inverse time over current relay or OC relay.
from trick value to certain range of faulty level, an inverse time relay shows exact
inverse characteristic. But after this level of fault, the CT becomes saturated and
relay current does not increase further with increasing faulty level of the system.
As the relay current is not increased further, there would not be any further
reduction in time of operation in the relay. This time is referred as minimum time
of operation.
In this typical situation there should be another alternate for protection . Hence,
back up relaying essentially have everything separate from main relaying scheme.
This is because backup relay must not fail to operate in the event of failure of
main relays.
But :-
As the back relaying is second line of protection , So it must be slow in action than
main relay so that it can only be operated when the main relaying scheme of the
system/equipment fails.
Trip Circuit Supervision Relay Concept
It is well known there are different contacts connected in series along a trip
circuit of an electrical circuit breaker.
At some situation when the circuit breaker should not trip even a faulty
current passes through its power contacts. Such situations are low gas pressure in
SF6 circuit breaker, low air pressure in pneumatic operated circuit breaker etc.
In this situation the trip coil of the CB must not be energized to trip the CB. So
there must be NO contacts associated with gas pressure and air pressure relays,
connected in series with breaker trip coil.
The above scheme is for supervision while circuit breaker is closed. This scheme is
called post close supervision.
The resistors are mounted separately from the relays and their values are chosen
such that if any one component is inadvertently short-circuited, a tripping
operation will not take place.
Note >>> The alarm circuit supply should be separated from main trip supply so
that the alarm can be actuated even the trip supply failed.
Differential Relay
The relays used in power system protection are of different types. Among them
differential relay is very commonly used relay for protecting transformers and
generators from localised faults.
Differential relays are very sensitive to the faults occurred within the zone of
protection but they are least sensitive to the faults that occur outside the
protected zone. Most of the relays operate when any quantity exceeds beyond a
predetermined value for example over current relay operates when current
through it exceeds predetermined value. But the principle of differential relay is
somewhat different. It operates depending upon the difference between two or
more similar electrical quantities.
These two currents meet at a junction point where a relay coil is connected.
According to Kirchhoff Current Law, the resultant current flowing through the
relay coil is nothing but summation of two currents, coming from two different
parts of the electrical power circuit. If the polarity and amplitude of both currents
are so adjusted that the phasor sum of these two currents, is zero at normal
operating condition. Thereby there will be no current flowing through the relay
coil at normal operating conditions.
But due to any abnormality in the power circuit, if this balance is broken,
that means the phasor sum of these two currents no longer remains zero and
there will be non-zero current flowing through the relay coil thereby relay being
operated.
In current differential scheme, there are two sets of current transformer each
connected to either side of the equipment protected by differential relay. The
ratio of the current transformers are so chosen, the secondary currents of both
current transformers matches each other in magnitude.
The polarity of current transformers are such that the secondary currents of
these CTs opposes each other. From the circuit is clear that only if any nonzero
difference is created between this to secondary currents, then only this
differential current will flow through the operating coil of the relay.
If this difference is more than the peak up value of the relay, it will operate to
open the circuit breakers to isolate the protected equipment from the system.
The relaying element used in differential relay is attracted armature type
instantaneously relay since differential scheme is only adapted for clearing the
fault inside the protected equipment in other words differential relay should clear
only internal fault of the equipment hence the protected equipment should be
isolated as soon as any fault occurred inside the equipment itself. They need not
be any time delay for coordination with other relays in the system.
In current differential relay two current transformers are fitted on the either side
of the equipment to be protected. The secondary circuits of CTs are connected in
series in such a way that the carry secondary CT current in same direction. The
operating coil of the relaying element is connected across the CT’s secondary
circuit. Under normal operating conditions, the protected equipment (either
power transformer or alternator) carries normal current. In this situation, say the
secondary current of CT1 is I1 and secondary current of CT2 is I2. It is also clear
from the circuit that the current passing through the relay coil is nothing but I1-I2.
As we said earlier, the current transformer’s ratio and polarity are so chosen, I1 =
I2, hence there will be no current flowing through the relay coil. Now if any fault
occurs external to the zone covered by the CTs, faulty current passes through
primary of the both current transformers and thereby secondary currents of both
current transformers remain same as in the case of normal operating conditions.
Therefore at that situation the relay will not be operated. But if any ground fault
occurred inside the protected equipment as shown, two secondary currents will
be no longer equal. At that case the differential relay is being operated to isolate
the faulty equipment (transformer or alternator) from the system.
In this type of relay, there are restraining coils in addition to the operating coil
of the relay. The restraining coils produce torque opposite to the operating
torque. Under normal and through fault conditions, restraining torque is greater
than operating torque. Thereby relay remains inactive.
It is clear from the above explanation, greater the current flowing through the
restraining coils, higher the value of the current required for operating coil to be
operated. The relay is called percentage relay because the operating current
required to trip can be expressed as a percentage of through current.
This simple thumb rule is that the current transformers on any star winding
should be connected in delta and the current transformers on any delta winding
should be connected in star. This is so done to eliminate zero sequence current in
the relay circuit.
There are some disadvantages in the voltage balance differential relay such as:-
The system is suitable for protection of cables of relatively short length otherwise
capacitance of pilot wires disturbs the performance. On long cables the charging
current will be sufficient to operate the relay even if a perfect balance of current
transformer achieved.
Distance Relay or Impedance Relay Working Principle
There is one type of relay which functions depending upon the distance of fault in
the line. More specifically, the relay operates depending upon the impedance
between the point of fault and the point where relay is installed. These relays are
known as distance relay or impedance relay.
The working principle of distance relay or impedance relay is very simple. There is
one voltage element from potential transformer and a current element fed from
current transformer of the system. The deflecting torque is produced by
secondary current of CT and restoring torque is produced by voltage of potential
transformer.
Hence clearly operation or working principle of distance relay, depends upon the
ratio of system voltage and current. As the ratio of voltage to current is nothing
but impedance a distance relay is also known as impedance relay.
The operation of such relay depends upon the predetermined value of voltage to
current ratio. This ratio is nothing but impedance. The relay will only operate
when this voltage to current ratio becomes less than its predetermined value.
Hence, it can be said that the relay will only operate when the impedance of the
line becomes less than predetermined impedance (voltage / current). As the
impedance of a transmission line is directly proportional to its length, it can easily
be concluded that a distance relay can only operate if fault is occurred within a
predetermined distance or length of line.
Restricted Earth Fault Protection of Transformer
An external fault in the star side will result in current flowing in the line current
transformer of the affected phase and at the same time a balancing current flows
in the neutral current transformer, hence the resultant current in the relay is
therefore zero.
So this REF relay will not be actuated for external earth fault. But during
internal fault the neutral current transformer only carries the unbalance fault
current and operation of Restricted Earth Fault Relay takes place.
This scheme of restricted earth fault protection is very sensitive for internal earth
fault of electrical power transformer. The protection scheme is comparatively
cheaper than differential protection scheme.
So it becomes essential to isolate only faulty section of busbar during bus fault.
All the CTs used for differential busbar protection are of same current
ratio. Hence, the summation of all secondary currents must also be equal
to zero
The quest for performance, security and reliability as tools for preventing
blackouts, has led to the wide spread use of numerical protection relays.
Numerical relays have gone a long way to meeting the challenges for security,
reliability, performance and compactness. However, numerical relays by necessity
embody a level of complexity and sensitivity, not encountered with previous
protection devices. Numerical relay having basic feature of distance protection &
other features are being installed in power system. It has complete scope of
protection of Power system.
Features:
Powerful 32 Bit Microprocessor system.
Fully numerical design
Biased differential protection
Restricted earth fault protection
Over fluxing protection
Integral CT Ratio & Vector group compensation
Remote transformer tap control
Measurement of phase, differential & bias current
Record of fault current & magnitude for the last fault
Relay flag details for the previous fault
The device incorporates the functions which are normally required for the
protection of an overhead line feeder & is therefore capable of universal
application. It may also be applied as time graded back up protection to all types
of comparison protection scheme used on line, transformers, generators, motors
& bus-bars of all voltage Levels.
Commonly used DPS in RVPN are as follows:
132 KV Feeder:
1. PD 521
2. D 30
1. KBCH 130
2.MICOM 632
Reading and Resetting of various Numerical Relays in RVPN
Note :- In this relay all contact are self reset hence breaker closing is possible
without resetting the relay/LED’s. Reset external trip Relay.
To read data in memory Press lower ‘ V ’ Key then move by pressing ‘ > ’ right
key. View record appears on the display then press lower ‘ V ’ Key again & again.
Fault No. Zero is latest fault. All parameters will be available one by one by
pressing ‘V’ down key.
(b) Trip contact:-Self reset.
Press ‘Book Marked Key’ again & again. Clear Fault will appear on display, then
press ‘C ‘ Key. The trip LED’s will stop glowing.
To reset alarm LED enter on View Records as above. Reset ‘NO’ will appear. Press
enter key. No start blinking , make ‘YES ’ by pressing up & down key & then enter
key. Then press ‘C ‘ Key again & again for normal display.
Note :- In this relay all contact are self reset hence breaker closing is possible
without resetting the relay/LED’s. Reset external trip Relay.
(c) Resetting of fault LED:- Press ‘LED ‘ Key. The trip LED’s will stop glowing.
Note :- In this relay all contact are self reset hence breaker closing is possible
without resetting the relay/LED’s. Reset external trip Relay.
(B) 132 KV Distance Scheme:
0396 Time
0397 Date
0421 Op-Time
0422 Fault Location KM
0427 Fault location percentage
3601 A Phase
3602 B Phase
3603 C Phase
3604 Ground Fault
0423 Fault Impedance
(c) Resetting of fault LED:- Reset ‘R’ Push Button. The trip LED’s will stop glowing.
Note :- In this relay all contact are self reset hence breaker closing is possible
without resetting the relay/LED’s. Reset external trip Relay.
(c) Resetting of fault LED:- Reset ‘O’ Key. The trip LED’s will stop glowing.
Note :-
(i) All contact are self reset hence breaker closing is possible without resetting
the relay/LED’s. Reset external trip Relay.
(ii) When ‘Clear fault record’ ‘=’0 available on display, do not press ‘O’ Key
otherwise all fault record will disappear from the memory.
Press ‘Book Marked Key’ again & again. Clear Fault will appear on display, then
press ‘C ‘ Key. The trip LED’s will stop glowing.
Electronic meter
Electronic meters display the energy used on an LCD or LED display, and
some can also transmit readings to remote places. In addition to measuring energy
used, electronic meters can also record other parameters of the load and supply
such as instantaneous and maximum rate of usage demands, voltages, power factor
and reactive power used etc. They can also support time-of-day billing, for
example, recording the amount of energy used during on-peak and off-peak hours.
Presently static meters have been introduced for metering in HV & EHV system.
The Electro-Mechanical Induction type meters are being replaces with static
meters for energy accounting. Static metres have installed by RVPN in place of
induction meters in its EHV system for inter /intra state metering as well as in LV
Side of power transformer. So the the performance of static energymeter as
compared to induction metre is concern, there is neither any problem in
performance of static meter nor any doubt about the technical superiority of
static meter over the electromechanical meter .
Digital Signal processor is used in static meter for electronic processing of voltage
& current signal collected from CT’s & PT’s.
The electronic metre consist of following parts:
1. Analog section
2. Analog to digital converter
3. Digital Signal processor
4. Microcontroller
5. Non Volatile memory
6. LCD
7. Power Supply
8. Real time Clock
9. Optical communication port
10. Metre software
B) Push Button-Display (with back scroll facility) Parameters for CT operated Static Meters:-
1. LED/LCD test
2. Date
3. Real Time
4. Rising Demand (KVA) with elapsed time
5. Phase to Neutral Voltages (R,Y,B)
6. Line Currents (R,Y,B) :
7. Supply Frequency
8. Instantaneous Power Factor
9. Instantaneous Load, Active, Reactive, Apparent
10. Cumulative Reset Count
11. Bill Point Active Energy (Kwh) : History 1
12. Bill Point Apparent Energy (Kvah): History 1
13. Bill Point Average Power Factor : History 1
14. Bill Point Power-on-hours : History 1
15. Bill Point Tamper Count : History 1
16. Bill Point TOD Active Energy (Kwh - REG 1,2,3) : History 1
17. Bill Point TOD Apparent Energy (Kvah REG 1,2,3) : History 1
18. Bill Point TOD Maximum Demand (KVA - REG 1,2,3) : History 1
19. Cumulative Power-on-hours
20. Cumulative Maximum Demand (KVA 0-24 HRS)
21. Cumulative Current Active Energy (Kwh)
22. Cumulative Current Reactive Lag Energy (Kvarh-Lag)
23. Cumulative Current Reactive Lead Energy (Kvarh-Lead)
24. Cumulative Current Apparent Energy (Kvah)
25. Cumulative Current TOD Active Energy (Kwh - REG 1,2,3)
26. Cumulative Current TOD Apparent Energy (Kvah REG 1,2,3)
27. Current TOD Maximum Demand (KVA - REG 1,2,3)
28. Indication of any existing Tamper
29. Cumulative tamper occurrence counts
30. Tamper information as mentioned in the relevant clauses of the specification should be recorded
and displayed in the push button display
31 Connection Check.
C) One high resolution display for Kwh & Kvarh suitable for easy dial testing of the meter.
Apart from the display parameters (Auto display & Push Button) as specified above and the standard
parameters as specified in the relevant clause of the guideline document, the meter should record in
addition the following parameters and all these parameters as well as the displayed parameters
should be retrievable/Calculable at the BCS end through CMRI/HHU:
1. Bill Point TOD Reactive Energies (Kvarh) Lag & Lead
2. Current TOD Reactive Energies (Kvarh) Lag & Lead
3. Current Maximum Demand (KVA) ( 0 –24 HRS)
4. Instantaneous power factors of individual phases
5. Bill Point Power factors of individual phases
6. Detail Tamper information
7. Detail historical data of all the parameters for at least 6 calendar months
8. Information regarding following failures:
a) Time & Calendar
b) RTC battery
c) Segment failure.
d) Self diagnostic details
e) Battery bad flag
TIME OF DAY (TOD) TARIFF / DEMAND
. The meter should be capable of registering time of day energy consumption on
stand-alone basis.
The meter shall be suitable to measure and record kW / kVA demand andactive
and apparent energies consumed during various time blocks of the day.
It should be actuated by an inbuilt real time clock which has the capability of being
set to indicate time zones in a 24 hour cycle with adjustable duration of time zone.
The registers shall indicate all parameters mentioned in this specification above for
every time zone.
It shall be possible to set minimum of 8 time zones in a 24 hour cycle and two
seasons in a year.
It shall be possible to change the time for TOD recordings through CMRI in
the meter itself with proper security.
Time of day register shall be provided for active energy/ apparent energy and
demand data (kW, kVA). Meter should indicate activeness through the current
time of day register on display.
This meter is designed for metering of HT/LT consumers feeders. The meter has
advanced data and tamper recording capabilities and is provided with
communication ports.
Software is available for data collection, load survey analysis and energy
management applications. The meter can be interfaced to a variety of
communication devices.
Features:
Dimention :