The document outlines requirements for various contractor deliverables including a job-specific contractor site safety program, plans for contractor camps and project support facilities, a hazard identification plan, worksite medical facilities, requirements for short service employees, quantity of safety staff, and safety training for site personnel.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100%(1)100% found this document useful (1 vote)
580 views4 pages
Csi Deliverable Checklist
The document outlines requirements for various contractor deliverables including a job-specific contractor site safety program, plans for contractor camps and project support facilities, a hazard identification plan, worksite medical facilities, requirements for short service employees, quantity of safety staff, and safety training for site personnel.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4
CSI DELIVERABLE CHECKLIST
DELIVERABLE SUBMITTAL REFERENCE SPECIFIC REQUIREMENTS
1.1 Availability and submission of CSSP (for long form capital project or as CSAR 5.2(A) requested by SAPO) from SAPO to ALPD for additional review. 1.2 Concurrence of CSSP from SAPO considering the review comments of CSAR 5.2(B) ALPD 1.3 Availability of copy of concurred CSSP at the jobsite (e.g., at satellite CSAR 5.2(B) site office, strategic location) accessible within worksite, and likewise CSAR5.4 1. Job-specific Contractor Site provided to subcontractor(s). Safety Program 1.4 Periodic review of CSSP's implementation conducted by contractor’s top management three (3) months after contract execution and every six (6) months thereafter. SCHEDULE D Note: Requirement applies to new contracted projects under revised schedule D – 2020. CSAR 5.1 1.5 Field implementation of SA-concurred CSSP at the jobsite. 2.1 Review of comprehensive plans (design drawing, site plan & specifications) for contractor's Camp and Project Support Facilities from concerned SA Organizations (ALPD, FrPD, EPD & where CSAR 10.3 applicable JHAH and ID) and approval from SAPO, including future CSAR 11.1(C) expansion, if any. GI 298.010(5.17- 5.21) Note: 2. Plans for Contractor Camps GI 298.010-5.22 1. Design, review/approval and pre-occupancy inspection of and Project Support GI 2.718-3.1.4 accommodation camp were completed and satisfactorily complied Facilities with as per GI 298.010. 2. Project Support facilities: Site Offices, Laydown yard, warehouse/storage area. CSAR 11.1(H) 2.2 Pre-occupancy inspection conducted at the contractor’s camp and GI 298.010 project support facilities by the above concerned SA organizations (5.20-5.21) and SAPO, and any concerns resolved prior to occupancy. GI 298.010(5.18, 2.3 SAPO approval of the contractor’s camp as per GI 298.010. 5.20) 3.1 Availability and submission of HIP from SAPO to ALPD for additional CSAR 6.3 review 3.2 Concurrence of HIP from SAPO considering the review comments of 3. Hazard Identification Plan CSAR 6.4 & 6.5 ALPD and amended or updated where necessary. (HIP) 3.3 Availability of concurred HIP at the jobsite (e.g. site offices) and CSAR 6.1 & 6.4 likewise provided to Sub-contractor(s). CSAR 6.1 3.4 Implementation of SA-concurred HIP at the jobsite. 4. Worksite Medical Facilities GI 298.010(5.17- 4.1 Inspection and acceptance of the clinic from JHAH that includes and Related Requirements 5.20) ambulance whether from the camp or worksite. CSAR 9.3(E) & 11.1(H) Note: Dedicated full-size ambulance in roadworthy condition shall be CSAR 9.5(B, C & available at each clinic that meets MMSR. To verify its compliance, D) check the MMSR-Survey & Compliance Review Report (Standard 6, MMSR-Standard Ambulance Service).
Saudi Aramco: Company General Use
6 MMSR– 4.2 JHAH approval of CV's of Medical Staff (Doctor, Nurse) and Standard 2, Ambulance Driver. Figure 2-3 & 2-4 4.3 Availability of valid copies of licenses and MMSR-specific required training certificates such as but not limited to the following:
- MOH License-Saudi Council for Health Specialist (SCFHS) – (Doctor,
Nurse) - Driving License (Ambulance Driver) CSAR 9.4(B) - Advance Cardio Life Support (Doctor) CSAR 9.4(E) - Advance Trauma Life Support (Doctor) CSAR 9.4(G) - Basic Life Support (Doctor, Nurse, Ambulance Driver) – Renewal CSAR 9.5(G) Every Two (2) Years MMSR-Standard - First Aid (Doctor, Nurse, Ambulance Driver) - Renewal Every Two (2) 2 Years - Infection Control (Doctor, Nurse, Ambulance Driver) – Annual Renewal - Fire Safety (Doctor, Nurse, Ambulance Driver) – Annual Renewal - Disaster/Emergency Response (Doctor, Nurse, Ambulance Driver) - Annual Renewal CSAR 9.5(E) 4.4 Implementation of Ambulance Daily Maintenance Inspection and Log MMSR–Figure 6- as follows: 2 - Daily Ambulance Checklist MMSR–Figure 6- - Ambulance Condition Report-Daily Checks with daily test run record 3 (mileage/KM) 4.5 Prior to start-up and periodic (semi-annual) independent CSAR 9.3(G, H) inspection/audit of each clinic conducted by medically qualified personnel from contracted MDF/HCP. CSAR 9.3(H) & 4.6 Correcting of deficiencies noted during the pre-occupancy/initial and 11.1(H) periodic inspections/audits on the clinic conducted by JHAH/HCP. CSAR 8.3(A) 5.1 Availability of Contractor’s SSE Program. 5.2 Implementation of Contractor’s SSE Program such as: CSAR 8.3(D, F & - Wearing of SAPO- approved SSE visual identifier while at the jobsite 5. Short Service Employee G) - Training of SSE - Supervisors SSE’s work performance evaluation 5.3 Communication of the maximum ratio of SSEs to experienced workers CSAR 8.3(E) to SAPO. 6.1 Adequate Quantity of active SA-concurred Contractor’s Safety Staff as per CSAR Table 4.1. (e.g., Safety Staff to employees ratio). CSAR 4.5(A, F & 6. Quantity of SA-concurred H) Note: A copy of the SA-concurred document of safety staff will be the Contractor's Safety Staff basis in counting the number of active safety staff 6.2 Availability of contractor’s SA-concurred site safety personnel at the CSAR 4.5(L) jobsite while work is on-going at any given time. 7. Safety training for Site CSAR 8.6(A) 7.1 Provision of formal safety training for all contractor’s Site Supervision Supervision and Safety Staff and Safety Staff on OSHA (24-Hrs. min.), NEBOSH, NSC or other SAPO-
Saudi Aramco: Company General Use
approved equivalent safety training program. 7.2 Provision of job-specific safety training for Site Supervision and Safety Staff such as but not limited to the following: - Job-specific CSSP & HIP - Contract’s safety requirements - Specific hazards & safe work practices associated with the job CSAR 8.6(B) - Relevant sections of the SA Safety Handbook & the SA Construction Safety Manual (CSM) - Injury/incident reporting and investigation - Applicable emergency response procedures - First Aid & Basic Life Support (BLS) with valid certificates CSM I-4.3.2 & 8.1 Availability of SAPO approved Contractor’s Work Permit System CSM I-6.3.4 (Procedure) for grassroots project CSM I-4.4.1 8.2 Availability of contractor’s valid permit issuers and receivers 8. Work Permit System CSM I-4.4.2 certificates (SA/Contractor’s Certification as applicable). 8.3 Implementation of SAPO-approved Contractor’s Work Permit System CSM I-4.3.2 for all hazardous work activities. 9.1 Availability of Contractor’s Incident Reporting and Investigation CSAR 4.21(A) Procedure. 9. Incident Reporting CSM I-2.3.5 9.2 Submission of all contractor’s on-job incident reports to SAPO that Procedure CSAR 4.21(C) properly identify the root causes and effective corrective actions. 9.3 Availability of tracking of corrective actions closure and evidence of CSAR 4.21(C) implementation follow-ups. 10.1 Availability of human-machine interface (HMI) plan submitted to SAPO that addresses the following: - Vehicle Back-up Alarms 10. Human / Machine - Pedestrian and vehicle only zones Interface (HMI) Plan for CSM III-2.3.6 - High visibility clothing Heavy Equipment - Identifying low-visibility areas Operation - Use of spotters - Proximity detectors-PWAS (as indicated in the contract/Schedule B) - Blindspot cameras CSAR 8.1(B) 10.2 Availability of documented training for assigned flagmen/spotters. 11. Site Specific Steel Erection 11.1 Availability of SAPO approved site-specific steel erection plan that CSM II-7.3 Plans includes the requirements outlined in CSM II-7.3.1. 12. Heat Stress Program (HSP) CSAR 4.17(C & 12.1 Availability of SAPO-concurred contractor’s heat stress management D) program that addresses the requirements outlined in CSAR 4.17(D). CSAR 4.17(E & 12.2 Provision of heat stress management program training for site F) management, supervision and their employees. 12.3 Conducting periodic (e.g. weekly) safety meetings/toolbox talks CSM I-13.2.1(D) during hot weather emphasizing heat stress hazards and precautions. CSAR 4.17(C) 12.4 Availability of adequate resources on site to support the implementation of the HSP such as but not limited to the following: - Calibrated weather monitoring equipment to determine the actual heat index periodically (e.g. hourly). - Communication of current heat stress danger category to
Saudi Aramco: Company General Use
employees thru color-coded flagging or mass distribution of SMS mobile phone text messages to site supervisors. - Educational information / signs related to heat stress conditions, illness/symptoms and preventive measures displayed on bulletin boards and break/recovery areas. - Local ventilation (e.g. fans, portable air movers) are provided when the air temperature is less than 37 ˚C (99˚F). - Portable blowers with built-in chillers as needed or where required (e.g. when confined spaces and enclosed work areas have ambient temperatures exceeding 43˚C (110˚F). CSAR 4.18(A & 13.1 Availability of an appropriate site-specific ERP (worksite, project B) support facilities and camp) reviewed by SAPO. 13.2 Availability of MEDEVAC Procedure (where required) that is 13. Site-specific ERP CSAR 9.6 incorporated in the SA-reviewed ERP. (Worksite, Project Support 13.3 Provision of ERP training for ERT (other than CS rescue personnel as Facilities, camp) and CSAR 4.18( C ) mentioned in deliverable item #15) at the worksite, project support MEDEVAC Procedure facilities and camp on their specific roles. CSAR 4.18(C & 13.4 Conducting periodic emergency drills at the worksite, project G) support facilities and camp. 14.1 Availability of contractor’s documented risk-based PPE needs 14. PPE Needs Analysis CSM I-3.3.2 analysis in line with CSM I-3.3.2. 15.1 Provision of appropriate training for CS rescue personnel as specified CSM I-6.10.4 15. Documented Training in in CSM I-6.10.4. Confined Space Entry CSAR 8.1(E) & 15.2 Provision of training for workers involved in excavation including (CSE), Excavation and 8.4 nominated excavation competent person. Work at Height-Fall CSM II-1.3.1 Protection CSAR 8.4 15.3 Provision of training and periodic refresher courses for personnel CSM II-sec. 5.7 performing work @ heights including their supervisors. 16.1 Availability of contractor’s fall protection plan specific to the work @ CSM II-5.3.7 heights (including high elevation rescue procedure) performed by 16. Fall Protection Plan for their personnel in accordance with CSM II-5.3.7. specific work at heights 16.2 Availability of documented appropriate design of horizontal lifeline and related requirement(s) (calculations, drawings and material specifications) prepared by a CSM II-5.6.2(C) degreed structural engineer and reviewed by SAPO prior to installation. GI 6.036 CSAR 4.15(L) 17.1 Availability of SAPO-approved contractor’s journey management SMG-06-009- program (JMP) for remote travel and oversize/heavy loads that 17. Journey Management and 2019, sec. includes a detailed response plan. Off-road Driving 5.1.1.1 17.2 Provision of specific training in off-road driving and survival CSM I-8.6.1 techniques to off-road vehicle operators. CSM I-8.6.3 17.3 Implementation of JMP including time-out/time-in logging system.