Week 5 Module (CMPM, CMT, COSH and QS)

This document contains 14 multiple choice questions assessing knowledge of construction management principles including critical path analysis, concrete mix design, cost estimation, and scheduling. Questions assess identifying critical paths, project durations and costs, volume calculations for concrete mixes, and unit costs for installing reinforcing steel based on labor, equipment, material and overhead costs.

Uploaded by

JAMES Panaligan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
133 views

Week 5 Module (CMPM, CMT, COSH and QS)

This document contains 14 multiple choice questions assessing knowledge of construction management principles including critical path analysis, concrete mix design, cost estimation, and scheduling. Questions assess identifying critical paths, project durations and costs, volume calculations for concrete mixes, and unit costs for installing reinforcing steel based on labor, equipment, material and overhead costs.

Uploaded by

JAMES Panaligan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

CE 420 – CE Practice with Comprehensive Examinations

Week 5 Module (Construction Management Principles and Methods, Materials for


Construction, Construction Occupational Safety and Health; Quantity Surveying)

SITUATION 1: Under normal conditions, the activities for a project and the corresponding
duration are as follows:

Duration Cost
Activity
(months) (Php)
0 – 1 (A) 7 6000
0 – 2 (B) 5 5500
0 – 3 (D) 11 12000
1 – 2 (C) 6 7500
2 – 3 (E) 7 6300
3 – 4 (F) 3 4200
2 – 4 (G) 8 10500
1. Which of the following routes will give the critical path?
a. A-C-E-F b. B-E-F
c. D-F d. A-C-G

2. Which of the following gives the duration of the critical path?


a. 21 months b. 23 months
c. 22 months d. 25 months

3. What is the longest delay that activity G can have without causing delay in the overall
production?
a. 5 months b. 9 months
c. 8 months d. 2 months

4. How much is the total cost of the project?


a. ₱ 55,000 b. ₱ 50,000
c. ₱ 52,000 d. ₱ 53,500

SITUATION 2: Table – 2 Provides the PERT-CPM network diagram as shown in Figure 1. The
critical path is ABDGIK. Determine the following:

CE-4202 | CE-4208 Prepared by: Engr. C. M. U. Olano Jr., RCE, RMP, SO-2
CE 420 – CE Practice with Comprehensive Examinations
Week 5 Module (Construction Management Principles and Methods, Materials for
Construction, Construction Occupational Safety and Health; Quantity Surveying)

5. The cost of the project.


a. ₱ 92,700 b. ₱ 104,500
c. ₱ 97,200 d. ₱ 105,400

6. The cost of the project when accelerated to the minimum duration.


a. ₱ 92,700 b. ₱ 104,500
c. ₱ 97,200 d. ₱ 105,400

7. Given a substantial budget higher than the total normal cost, find the estimated savings from
the budget if the project will be completed 4 days ahead of schedule.
a. ₱ 6,500 b. ₱ 1,400
c. ₱ 3,900 d. ₱ 5,000

8. The activity that is cost effective to accelerate.


a. Activity A b. Activity B
c. Activity K d. Activity I

SITUATION 3: A concrete mix has a ratio of 1:2:4 by mass. Properties of the materials to be used
are tabulated below:
Specific
Materials
Gravity
Cement 3.33
Sand 2.65
Gravel 2.67

Cement weighs 40kg per bag. Use 24 liters of water per bag of cement.
9. Which of the following most nearly gives the volume of cement solids per bag of cement?
a. 0.1020 m3 b. 0.0120 m3
c. 0.2001 m3 d. 0.1201 m3

CE-4202 | CE-4208 Prepared by: Engr. C. M. U. Olano Jr., RCE, RMP, SO-2
CE 420 – CE Practice with Comprehensive Examinations
Week 5 Module (Construction Management Principles and Methods, Materials for
Construction, Construction Occupational Safety and Health; Quantity Surveying)

10. Which of the following most nearly gives the volume of concrete that can be produced per
bag of cement?
a. 0.1261 m3 b. 0.1162 m3
c. 0.1126 m 3
d. 0.1621 m3

11. Suppose the concrete mix will be used on isolated square footing, 1.5m wide and 0.4m thick.
Which of the following most nearly gives the required number of cement bags if there are 12
footings of the same size?
a. 78 bags b. 80 bags
c. 92 bags d. 86 bags

SITUATION 4: For a given project it is estimated that 150 kg of steel can be installed in one hour
using the following equipment and labor.

1 bar bender ……………. P 50/hr


1 bar cutter ……………… P 80/hr
1 Foreman ……….............. P 50 / hr
8 Skilled workers ……….. P 40 / hr
8 Unskilled workers …. P 35/hr

Reinforcing steel costs P 15/kg. For every 1 kg of reinforcing steel, 0.02 kg of tie wire is required
where 1 kg of tie wire costs P 26. The value added Tax is 10% of the material cost. The profit,
contingency, and miscellaneous cost is 40% of the labor and material costs. Determine the
following:
12. The cost of labor & equipment per kilogram.
a. ₱ 30.21 b. ₱ 15.52
c. ₱ 5.20 d. ₱ 9.55

13. The cost of materials per kilogram.


a. ₱ 30.21 b. ₱ 15.52
c. ₱ 5.20 d. ₱ 9.55

14. The unit cost of the project per kilogram.


a. ₱ 30.21 b. ₱ 15.52
c. ₱ 5.20 d. ₱ 9.55

CE-4202 | CE-4208 Prepared by: Engr. C. M. U. Olano Jr., RCE, RMP, SO-2