Week 5 Module (CMPM, CMT, COSH and QS)
Week 5 Module (CMPM, CMT, COSH and QS)
SITUATION 1: Under normal conditions, the activities for a project and the corresponding
duration are as follows:
Duration Cost
Activity
(months) (Php)
0 – 1 (A) 7 6000
0 – 2 (B) 5 5500
0 – 3 (D) 11 12000
1 – 2 (C) 6 7500
2 – 3 (E) 7 6300
3 – 4 (F) 3 4200
2 – 4 (G) 8 10500
1. Which of the following routes will give the critical path?
a. A-C-E-F b. B-E-F
c. D-F d. A-C-G
3. What is the longest delay that activity G can have without causing delay in the overall
production?
a. 5 months b. 9 months
c. 8 months d. 2 months
SITUATION 2: Table – 2 Provides the PERT-CPM network diagram as shown in Figure 1. The
critical path is ABDGIK. Determine the following:
CE-4202 | CE-4208 Prepared by: Engr. C. M. U. Olano Jr., RCE, RMP, SO-2
CE 420 – CE Practice with Comprehensive Examinations
Week 5 Module (Construction Management Principles and Methods, Materials for
Construction, Construction Occupational Safety and Health; Quantity Surveying)
7. Given a substantial budget higher than the total normal cost, find the estimated savings from
the budget if the project will be completed 4 days ahead of schedule.
a. ₱ 6,500 b. ₱ 1,400
c. ₱ 3,900 d. ₱ 5,000
SITUATION 3: A concrete mix has a ratio of 1:2:4 by mass. Properties of the materials to be used
are tabulated below:
Specific
Materials
Gravity
Cement 3.33
Sand 2.65
Gravel 2.67
Cement weighs 40kg per bag. Use 24 liters of water per bag of cement.
9. Which of the following most nearly gives the volume of cement solids per bag of cement?
a. 0.1020 m3 b. 0.0120 m3
c. 0.2001 m3 d. 0.1201 m3
CE-4202 | CE-4208 Prepared by: Engr. C. M. U. Olano Jr., RCE, RMP, SO-2
CE 420 – CE Practice with Comprehensive Examinations
Week 5 Module (Construction Management Principles and Methods, Materials for
Construction, Construction Occupational Safety and Health; Quantity Surveying)
10. Which of the following most nearly gives the volume of concrete that can be produced per
bag of cement?
a. 0.1261 m3 b. 0.1162 m3
c. 0.1126 m 3
d. 0.1621 m3
11. Suppose the concrete mix will be used on isolated square footing, 1.5m wide and 0.4m thick.
Which of the following most nearly gives the required number of cement bags if there are 12
footings of the same size?
a. 78 bags b. 80 bags
c. 92 bags d. 86 bags
SITUATION 4: For a given project it is estimated that 150 kg of steel can be installed in one hour
using the following equipment and labor.
Reinforcing steel costs P 15/kg. For every 1 kg of reinforcing steel, 0.02 kg of tie wire is required
where 1 kg of tie wire costs P 26. The value added Tax is 10% of the material cost. The profit,
contingency, and miscellaneous cost is 40% of the labor and material costs. Determine the
following:
12. The cost of labor & equipment per kilogram.
a. ₱ 30.21 b. ₱ 15.52
c. ₱ 5.20 d. ₱ 9.55
CE-4202 | CE-4208 Prepared by: Engr. C. M. U. Olano Jr., RCE, RMP, SO-2