Site Diary - 3-12-23

This document provides a summary of activities and manpower for the development of a 100MW solar photovoltaic plant in Terengganu, Malaysia from December 3rd to 7th, 2023. Key activities included site preparation works, cable termination, roof and drain installation by TNBIF. 40 subcontractors from TNBIF were allocated for manpower. The weather was expected to be cloudy in the mornings.

Uploaded by

lssmerchang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views2 pages

Site Diary - 3-12-23

This document provides a summary of activities and manpower for the development of a 100MW solar photovoltaic plant in Terengganu, Malaysia from December 3rd to 7th, 2023. Key activities included site preparation works, cable termination, roof and drain installation by TNBIF. 40 subcontractors from TNBIF were allocated for manpower. The weather was expected to be cloudy in the mornings.

Uploaded by

lssmerchang
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ACTIVITIES :

Site Preparation Works (WORK PROGRESS)


Cable termination works (TNBIF)
Housekeeping (TNBIF)
Roof installation (TNBIF)
Drain installation (TNBIF)
PROJECT : DEVELOPMENT OF LARGE SCALE SOLAR PHOTOVOLTAIC (LSSPV) PLANT OF 100MWac AT LOT 14020 KG Fencing installation (TNBIF)
JAMBU BONGKOK, MARANG, TERENGGANU

DATE : 3/12/2023 DAY : MON/TUE/ WED/ THU/ FRI/ SAT/ SUN


FROM : 8.00 AM TO : 7.00 PM
MANPOWER MACHINERY Mechanical & Electrical (WORK PROGRESS)

NO DESCRIPTION TOTAL NO DESCRIPTION TOTAL


1 Project Manager 1 1 Excavator 0
2 Construction Manager 0 2 Bulldozer 0
3 Project Engineer 1 3 Back pusher 0
4 Inspector of Works 1 4 Dump truck 0
5 Site Supervisor 1 5 Backhoe 0
6 Safety Officer 1 6 Compactor 0
7 Environmental Officer 0 7 Water browser 0
8 Surveyor 0 8 Crane 0
9 Chainman 0 9 Lorry Crane 0
10 Site Clerk 0 10 Piling machine 0 OTHERS (WORK PROGRESS)
11 Resident Engineer 0 11 HDD Machine 0
12 Machinery Operator 0 12
13 Security 2 14
14 Total Subcon Manpower 40 15
a) TNBIF 40 16
b) SPPIF 0 17
c) Chendering 0 18

WEATHER CONDITION
DOCUMENT ISSUED

AM PM

8.00am-5.00pm=Cloudy
MATERIAL DELIVERY

PREPARED BY ; CHECKED BY; VERIFIED BY ;

WAN IRSYAD WAN AZMI