NATSPEC National BIM Guide AIR Template 22-10-20
NATSPEC National BIM Guide AIR Template 22-10-20
October 2022
Project Reference:
Project name:
Project address/location:
Appointing party:
Version:
Date:
Copyright Notice
© Construction Information Systems Limited (NATSPEC) 2022. In keeping with NATSPEC’s commitment to encouraging the
availability of information, you are welcome to reproduce the material that appears in this publication for personal, in-house or
non-commercial use without formal permission or charge. All other rights are reserved. If you wish to reproduce, store or transmit
material appearing in this publication for any other purpose, a request for formal permission should be directed to
[email protected].
Disclaimer
This Document is intended for use by professional personnel competent to evaluate the significance and limitations of its content
and able to accept responsibility for the application of the material it contains.
NATSPEC and its contributors hereby disclaim all warranties and conditions with regard to this information and related graphics,
including all implied warranties, fitness for a particular purpose, workmanlike effort, title and non-infringement. In no event shall
NATSPEC be liable for any direct, indirect, punitive, incidental, special, or consequential damages or damages for loss of profits,
revenue, data, down time, or use, arising out of or in any way connected with the use of the Document or performance of any
services, whether based on contract, tort, negligence, strict liability or otherwise. NATSPEC disclaims any responsibility to update
any information, including with respect to any new legal, business, or technology developments. If you are dissatisfied with any
portion of the Document, or with any of these terms of use, your sole and exclusive remedy is to discontinue using the Document.
Document references
In this document:
The ‘AIR Template’ or ‘Template’ means the NATSPEC Asset Information Requirements (AIR) Template.
The ‘AIR’ means the asset information requirements for the nominated project.
The ‘BEP’ means the BIM Execution Plan for the nominated project.
The ‘National BIM Guide’ or ‘Guide’ means the NATSPEC National BIM Guide.
Acknowledgements
NATSPEC thanks the numerous individuals and organisations who contributed to the development of this document through
material they provided and/or comments they made on drafts.
Comments
NATSPEC welcomes comments or suggestions for improvements to this document and encourages readers to notify us
immediately of any apparent inaccuracies or ambiguities. NATSPEC also encourages users to share their experiences of applying
it on projects with us.
Contact us via email at [email protected].
Document control
Company/
Title/Role Name Email Tel. No. RACI
Organisation
Author
Owner
Appointing party
representative
Information
Manager
Key to responsibilities for developing AIR
R Responsible for undertaking activity
A Accountable for activity completion
C Consulted during activity
I Informed following activity completion
Role responsible for maintaining and updating AIR: [complete/delete]
Version history
3 COMMERCIAL
3.1 Procurement strategy
The project procurement strategy is shown in the Project procurement strategy table.
Project procurement strategy table
Information Manager
Project Manager
* Weeks before the key decision point ** Weeks before end of project phase
Asset management
AIM element
Models
Drawings
Documents
Data (object-based)
Drawings
Documents
Photographic images
Videos, animations
Data
Location
Geometrical
quantities
Function
Occupancy
Surface
finishes
Maintenance
Condition
Location
Parent system or
assembly
Classification or
category
Manufacture &
supply
Warranties
Temporal
Performance
Condition
Financial
4 MANAGEMENT
4.1 AIM quality assurance
AIM quality assurance requirements: [complete/delete]
Quality assurance standards: Conform to the standards documented in TECHNICAL, Standards and project
reference information.
4.2 Information security and privacy
Information security requirements: [complete/delete]
4.3 CDE management
CDE standards and procedures: [complete/delete]
5 TECHNICAL
5.1 Asset identification
Requirement: Provide all assets with a unique code for the purpose of identification and to facilitate the cross
referencing of information about assets in different information locations and formats within the AIM.