0% found this document useful (0 votes)
71 views4 pages

Erosion Control Project Plan

This document outlines the construction schedule for erosion and flood control works in Adumu and Ogugu, Kogi State, Nigeria. It involves several phases including site mobilization, surveys, construction of temporary facilities, borrow pit development, and project construction activities over 568 days. The main work includes clearing, earthworks, construction of outfall drains 1 and 2, and other erosion control structures.

Uploaded by

kabiru isah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views4 pages

Erosion Control Project Plan

This document outlines the construction schedule for erosion and flood control works in Adumu and Ogugu, Kogi State, Nigeria. It involves several phases including site mobilization, surveys, construction of temporary facilities, borrow pit development, and project construction activities over 568 days. The main work includes clearing, earthworks, construction of outfall drains 1 and 2, and other erosion control structures.

Uploaded by

kabiru isah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

THE CONSTRUCTION OF EROSION/FLOOD CONTROL WORKS AT ADUMU / OGUGU EROSION SITE, OLAMABORO LGA, KOGI STATE

N ig e rp e t
s t r u c t u r e s l t d .

ID Task Name
2020 2021
July August September October November December January February March April May June July August September October November December January February March April May June July August
E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
1 THE CONSTRUCTION OF 568.63 days?
EROSION/FLOOD CONTROL WORKS AT
ADUMU / OGUGU EROSION SITE,
OLAMABORO LGA, KOGI STATE
2 SITE MOBILIZATION 139.88 days?

3 CONTRACT DOCUMENT / SITE POSSESSION


1/4
4 Site Handing over by client

5 Project Documents and Construction Drawings 90 days


Project Documents and Construction Drawings
6 PROCUREMENT AND SAFETY
1/4
7 Procurement and Logistics 71 days?
Procurement and Logistics
8 Placing Safety Bearers and Securing Site Location 15 days
Placing Safety Bearers and Securing Site Location
9 Training of Workers on Health and Safety 7 days
Training of Workers on Health and Safety
10 MOBILIZING EQUIPTMENTS TO SITE
1/4
11 Creating Access road on Project Site 14 days
Creating Access road on Project Site
12 Transporting Heavy Duty Equiptments to Project Site 15 days
Transporting Heavy Duty Equiptments to Project Site
13 CONSTRUCTION OF TEMPORARY FACILITIES
1/4
14 <New Summary Task> 60 days

15 Securing Yard Office and Construction of Other 60 days


Facilities Securing Yard Office and Construction of Other Facilities
16 Construction and Furnishing of Site Offices 30 days
Construction and Furnishing of Site Offices
17 Construction of sanitary Facilities for workers 15 days
Construction of sanitary Facilities for workers
18 Establishing Secured area for Storing Tools and 15 days
Equiptments Establishing Secured area for Storing Tools and Equiptments
19 Temporary Utilities Facilities and Portable Water 31 days
Temporary Utilities Facilities and Portable Water
20 SITE SURVEY
1/4
21 Site Survey to Establish Existing Base Lines and 15 days
Boundary Lines Site Survey to Establish Existing Base Lines and Boundary Lines
22 Demolition of Compensated Structures and Relocation of 15 days
Utilities Demolition of Compensated Structures and Relocation of Utilities
23 BORRROW PIT
1/4
24 Location of Borrow Pit 7 days
Location of Borrow Pit
25 Material Testing on Borrow Pit 30 days
Material Testing on Borrow Pit
26 Creating Access Road to Borrow Pit

27 PROJECT CONSTRUCTION / SITE ACTIVITIES 467.75 days?

28 SITE CLEARING

29 Site Clearing& initial earthworks in cut 90 days


Site Clearing& initial earthworks in cut
30 Earth filling of Roads to Sub Grade level 90 days
Earth filling of Roads to Sub Grade level
31 CONSTRUCTION OF OUTFALL DRAIN 1 & 2 276.88 days

Task Project Summary Inactive Summary Manual Summary External Milestone


Project: MOBILIZATION SCHEDULE F Split External Tasks Manual Task Start-only Progress
Date: Thu 11/19/20
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks

Page 1
THE CONSTRUCTION OF EROSION/FLOOD CONTROL WORKS AT ADUMU / OGUGU EROSION SITE, OLAMABORO LGA, KOGI STATE
N ig e rp e t
s t r u c t u r e s l t d .

ID Task Name
2020 2021
July August September October November December January February March April May June July August September October November December January February March April May June July August
E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
32 Site Survey to generate base line 15 days
Site Survey to generate base line
33 Clearing, Shaping and compaction of Exisitin gully 30 days
haed Clearing, Shaping and compaction of Exisitin gully haed
34 Setting out and Excavation of Outfall drain 40 days
Setting out and Excavation of Outfall drain
35 Concrete blinding, concrete base and construction of 90 days
concrete drain walls Concrete blinding, concrete base and construction of concrete drain walls
36 Installation of Reno Mattressess and Gabion baskets 60 days
Installation of Reno Mattressess and Gabion baskets
37 Construction of Conrete Toe Retaining Structures 20 days
Construction of Conrete Toe Retaining Structures
38 Backfilling of Drains and Side Slope Stabilization 40 days
Backfilling of Drains and Side Slope Stabilization
39 CONSTRUCTION OF ADUMU ROAD 396 days

40 CONCRETE WORKS
1/4
41 Setting out and Excavation of Side Drain Adumu Rd 90 days
Setting out and Excavation of Side Drain Adumu Rd
42 Concrete blinding, concrete base and construction of 150 days
concrete drain walls Adumu Rd Concrete blinding, concrete base and construction of concrete drain walls Adumu Rd
43 Concrete Drain Slab for Access Adumu Rd 80 days
Concrete Drain Slab for Access Adumu Rd
44 EARTHWORKS AND ROAD SURFACING
1/4
45 Shape and Compaction of Subgrade Adumu Rd 90 days
Shape and Compaction of Subgrade Adumu Rd
46 Earth Filling to Sub Base Level Adumu Rd 150 days
Earth Filling to Sub Base Level Adumu Rd
47 Stone Base to Road Base Level Adumu Rd 110 days
Stone Base to Road Base Level Adumu Rd
48 Bituminous Prime Coat Adumu Rd

49 CONSTRUCTION OF ADUPI-SABON GARI ROAD 316.38 days

50 CONCRETE WORKS
1/4
51 Demolition and Removal of Existing Concrete Drain 90 days
Sabon gari Demolition and Removal of Existing Concrete Drain Sabon gari
52 Setting out and Excavation of Outfall drain Sabon gari 90 days
Setting out and Excavation of Outfall drain Sabon gari
53 Concrete blinding, concrete base and construction of 150 days
concrete drain walls Sabon gari Concrete blinding, concrete base and construction of concrete drain walls Sabon gari
54 Concrete Drain Slab for Access Sabon gari 60 days
Concrete Drain Slab for Access Sabon gari
55 EARTHWORKS AND ROAD SURFACING
1/4
56 Shape and Compaction of Subgrade Sabon gari 90 days
Shape and Compaction of Subgrade Sabon gari
57 Earth Filling to Sub Base Level Sabon gari 90 days
Earth Filling to Sub Base Level Sabon gari
58 Stone Base to Road Base Level Sabon gari 80 days
Stone Base to Road Base Level Sabon gari
59 Bituminous Prime Coat Sabon gari 15 days
Bituminous Prime Coat Sabon gari
60 CONSTRUCTION OF ALASHA ROAD 403.13 days

61 CONCRETE WORKS
1/4
62 Demolition and Removal of Existing Concrete Drain 20 days
Alasha Rd Demolition and Removal of Existing Concrete Drain Alasha Rd
63 Setting out and Excavation of Outfall drain Alasha Rd 50 days
Setting out and Excavation of Outfall drain Alasha Rd

Task Project Summary Inactive Summary Manual Summary External Milestone


Project: MOBILIZATION SCHEDULE F Split External Tasks Manual Task Start-only Progress
Date: Thu 11/19/20
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks

Page 2
THE CONSTRUCTION OF EROSION/FLOOD CONTROL WORKS AT ADUMU / OGUGU EROSION SITE, OLAMABORO LGA, KOGI STATE
N ig e rp e t
s t r u c t u r e s l t d .

ID Task Name
2020 2021
July August September October November December January February March April May June July August September October November December January February March April May June July August
E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
64 Concrete blinding, concrete base and construction of 90 days
concrete drain walls Alasha Rd Concrete blinding, concrete base and construction of concrete drain walls Alasha R
65 Concrete Drain Slab for Access Alasha Rd 60 days
Concrete Drain Slab for Access Alasha Rd
66 EARTHWORKS AND ROAD SURFACING
1/4
67 Shape and Compaction of Subgrade Alasha Rd 35 days
Shape and Compaction of Subgrade Alasha Rd
68 Earth Filling to Sub Base Level Alasha 60 days
Earth Filling to Sub Base Level Alasha
69 Stone Base to Road Base Level Alasha Rd 60 days
Stone Base to Road Base Level Alasha Rd
70 Bituminous Prime Coat Alasha Rd

71 CONSTRUCTION OF OKEGBI ROAD A AND 396 days


ROAD B
72 CONCRETE WORKS
1/4
73 Demolition and Removal of Existing Concrete Drain 20 days
Okegbi Rd Demolition and Removal of Existing Concrete Drain Okegbi Rd
74 Setting out and Excavation of Outfall drain Okegbi Rd 60 days
Setting out and Excavation of Outfall drain Okegbi Rd
75 Concrete blinding, concrete base and construction of 120 days
concrete drain walls Okegbi Rd Concrete blinding, concrete base and construction of concrete drain walls Ok
76 Concrete Drain Slab for Access Okegbi Rd 60 days
Concrete Drain Slab for Access Okegbi Rd
77 EARTHWORKS AND ROAD SURFACING
1/4
78 Shape and Compaction of Subgrade Okegbi Rd 35 days
Shape and Compaction of Subgrade Okegbi Rd
79 Earth Filling to Sub Base Level Okegbi RD 40 days
Earth Filling to Sub Base Level Okegbi RD
80 Stone Base to Road Base Level Okegbi Rd 40 days
Stone Base to Road Base Level Okegbi Rd
81 Bituminous Prime Coat Okegbi Rd 10 days
Bituminous Prime Coat Okegbi Rd
82 CONSTRUCTION OF AMEKHU STREET 396.63 days

83 CONCRETE WORKS
1/4
84 Demolition and Removal of Existing Concrete Drain 20 days
Amekhu St Demolition and Removal of Existing Concrete Drain Amekhu St
85 Setting out and Excavation of Outfall drain Amekhu St 40 days
Setting out and Excavation of Outfall drain Amekhu St
86 Concrete blinding, concrete base and construction of 60 days
concrete drain walls Amekhu St Concrete blinding, concrete base and construction of concrete drain walls Amekhu St
87 Concrete Drain Slab for Access Amekhu St 40 days
Concrete Drain Slab for Access Amekhu St
88 EARTHWORKS AND ROAD SURFACING
1/4
89 Shape and Compaction of Subgrade Amekhu St 35 days
Shape and Compaction of Subgrade Amekhu St
90 Earth Filling to Sub Base Level Amekhu St 30 days
Earth Filling to Sub Base Level Amekhu St
91 Stone Base to Road Base Level Amekhu St 15 days
Stone Base to Road Base Level Amekhu St
92 Bituminous Prime Coat Amekhu St 15 days
Bituminous Prime Coat Amekhu St
93 CONSTRUCTION OF ALACHA ROAD 345.75 days

94 CONCRETE WORKS
1/4
95 Demolition and Removal of Existing Concrete Drain 20 days
Alacha Rd Demolition and Removal of Existing Concrete Drain Alacha Rd

Task Project Summary Inactive Summary Manual Summary External Milestone


Project: MOBILIZATION SCHEDULE F Split External Tasks Manual Task Start-only Progress
Date: Thu 11/19/20
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks

Page 3
THE CONSTRUCTION OF EROSION/FLOOD CONTROL WORKS AT ADUMU / OGUGU EROSION SITE, OLAMABORO LGA, KOGI STATE
N ig e rp e t
s t r u c t u r e s l t d .

ID Task Name
2020 2021
July August September October November December January February March April May June July August September October November December January February March April May June July August
E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E
96 Setting out and Excavation of Outfall drain Alacha Rd 40 days
Setting out and Excavation of Outfall drain Alacha Rd
97 Concrete blinding, concrete base and construction of 70 days
concrete drain walls Alacha Rd Concrete blinding, concrete base and construction of concrete drain walls Alacha Rd
98 Concrete Drain Slab for Access Alacha Rd 40 days
Concrete Drain Slab for Access Alacha Rd
99 EARTHWORKS AND ROAD SURFACING
1/4
100 Shape and Compaction of Subgrade Alacha Rd 35 days
Shape and Compaction of Subgrade Alacha Rd
101 Earth Filling to Sub Base Level Alcha Rd 60 days
Earth Filling to Sub Base Level Alcha Rd
102 Stone Base to Road Base Level Alacha Rd 60 days
Stone Base to Road Base Level Alacha Rd
103 Bituminous Prime Coat Alacha Rd 15 days
Bituminous Prime Coat Alacha Rd
104 ROAD WEARING COURSE 17.25 days

105 Preparing Road Surface for Wearing Course 7 days


Preparing Road Surface for Wearing Course
106 Laying of Asphalt Wearing Course on Roads 12 days
Laying of Asphalt Wearing Course on Roads

Task Project Summary Inactive Summary Manual Summary External Milestone


Project: MOBILIZATION SCHEDULE F Split External Tasks Manual Task Start-only Progress
Date: Thu 11/19/20
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks

Page 4