ENA ER G12 Issue 4 Amendment 2 2022
ENA ER G12 Issue 4 Amendment 2 2022
www.energynetworks.org
PUBLISHING AND COPYRIGHT INFORMATION
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system
or transmitted in any form or by any means, electronic, mechanical, photocopying, recording
or otherwise, without the prior written consent of Energy Networks Association. Specific
enquiries concerning this document should be addressed to:
Operations Directorate
Energy Networks Association
4 More London Riverside
London
SE1 2AU
This document has been prepared for use by members of the Energy Networks Association
to take account of the conditions which apply to them. Advice should be taken from an
appropriately qualified engineer on the suitability of this document for any other purpose.
Amendment 2 January 2022 Reference to EREC G83 and EREC G59 updated to EREC G98 and
EREC G99 respectively.
A version of this document which tracks all the changes is available from
ENA on request.
Contents
Foreword ................................................................................................................................ 6
1 Scope............................................................................................................................... 7
2 Normative references ....................................................................................................... 7
3 Terms and definitions ....................................................................................................... 8
3.1 Aerial Bundled Conductor (ABC) ............................................................................. 8
3.2 Branch .................................................................................................................... 8
3.3 Caravan .................................................................................................................. 8
3.4 Distributing Main* .................................................................................................... 8
3.5 Distributor* .............................................................................................................. 9
3.6 Electric Line* ........................................................................................................... 9
3.7 Exhibition** ............................................................................................................. 9
3.8 Marina** .................................................................................................................. 9
3.9 Mobile/transportable Unit** ..................................................................................... 9
3.10 Basin of fountain** .................................................................................................. 9
3.11 Protective multiple earthing (PME)** ....................................................................... 9
3.12 Protective neutral bonding (PNB) ............................................................................ 9
3.13 Residual current device (RCD)** ............................................................................. 9
3.14 Service line* .......................................................................................................... 10
3.15 Show** .................................................................................................................. 10
3.16 Stand** ................................................................................................................. 10
3.17 Street electrical fixture* ......................................................................................... 10
3.18 Supplier* ............................................................................................................... 10
3.19 TN system** .......................................................................................................... 10
3.20 TN-C system** ...................................................................................................... 10
3.21 TN-S system** ...................................................................................................... 10
3.22 TN-C-S system**................................................................................................... 10
3.23 TT system** .......................................................................................................... 10
4 Requirements for PME Networks ................................................................................... 11
4.1 General ................................................................................................................. 11
4.2 Substation earthing ............................................................................................... 11
4.3 Supply Neutral Conductor ..................................................................................... 11
4.3.1 Cross-sectional area ................................................................................. 11
4.3.2 Maintaining integrity .................................................................................. 11
4.4 Earthing of supply neutral conductor ..................................................................... 11
4.4.1 Location of earth connections.................................................................... 11
4.4.2 Service line requirements .......................................................................... 12
4.5 Underground cable networks ................................................................................ 12
Figure 4.4 Installation of electrodes along branches of distributors ............................ 13
Figure 4.5 Typical application of PME to networks with SNE and CNE cables ........... 14
4.6 Overhead networks ............................................................................................... 15
4.7 Values of earth electrode resistance ..................................................................... 15
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 4
Foreword
This Engineering Recommendation (EREC) is published by the Energy Networks Association
(ENA) and comes into effect from 24 January 2022. It has been prepared under the authority
of the ENA Engineering Policy and Standards Manager and has been approved for publication
by the ENA Electricity Networks and Futures Group (ENFG). The approved abbreviated title
of this Engineering document is “EREC G12 issue 4”, which replaces the previously used
abbreviation “ER G12/3”.
1 Scope
This Engineering Recommendation sets out the requirements to be adopted when Protective
Multiple Earthing (PME) is applied to DNO (Distribution Network Operator, including
Independent Distribution Network Operator) overhead and underground low voltage
distribution systems and to other public distribution systems connected to those systems under
the Distribution Code. These requirements may be supplemented by each Company's own
PME code of practice in respect of the detailed engineering and technical requirements of PME
application. The requirements in this Engineering Recommendation aid compliance with
certain aspects of the requirements of the Electricity Safety, Quality and Continuity Regulations
2002, as amended. The document also considers situations where PME should not normally
be used.
2 Normative references
The following referenced documents, in whole or part, are indispensable for the application of
this document. For dated references, only the edition cited applies. For undated references,
the latest edition of the referenced document (including any amendments) applies.
This document makes reference to, or should be read in conjunction with, the following
documents:
Statutory publications
The Electricity Safety Quality and Continuity Regulations 2002 (SI 2002 No. 2665), as
amended
The Electricity at Work Regulations 1989 (SI 1989 No. 635), as amended
Standards publications
BS 7375: Code of practice for distribution of electricity on construction and building sites
BS 7430: Code of practice for earthing
BS 7671:2008 (2011) Requirements for electrical installations. IET Wiring Regulations.
Seventeenth Edition
BS 7870-5: LV and MV polymeric insulated cables for use by distribution and generation
utilities. Part 5: Polymeric insulated aerial bundled conductors (ABC) of rated voltage 0.6/1kV
for overhead distribution
BS 7909: Code of practice for temporary electrical systems for entertainment and related
purposes
BS EN 50122-1: Railway applications. Fixed installations. Protective provisions relating to
electrical safety and earthing
BS EN 50122-2: Railway applications. Fixed installations. Protective provisions against the
effects of stray currents caused by d.c. traction systems
BS EN 62305: Protection against lightning
IEC/TS 60479-1: Effects of current on human beings and livestock. General aspects
ENA Publications
TS 41-24: Guidelines for the design, installation, testing and maintenance of main earthing
systems in substations
TS 43-13: Aerial bundled conductors insulated with cross-linked polyethylene for low voltage
overhead distribution
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 8
EREC C93: Type approval tests for mechanical connections to metallic sheaths of cables
EREC G14: PME. Recommended principles of testing to ensure correct polarity
EREC G98, Requirements for the connection of Fully Type Tested Micro-generators (up to and
including 16 A per phase) in parallel with public Low Voltage Distribution Networks on or after
27 April 2019
EREC G99, Requirements for the connection of generation equipment in parallel with public
distribution networks on or after 27 April 2019
EREC G87: Guidelines for the provision of low voltage connections to multiple occupancy
buildings
EREC P24: AC traction supplies to British Rail
EREC S34: A guide for assessing the rise of earth potential at substation sites
EREP 123: Guidelines for managing the interfaces between utility services and light rapid
transit systems
For the purposes of this document, the following terms and definitions apply.
NOTE: Definitions marked with an asterisk are taken from the Electricity Safety, Quality and Continuity Regulations
2002, as amended. Those with a double asterisk are taken from BS 7671:2008 (2011).
3.2 Branch
A sub-division of a distributing main from its end furthest from the source of voltage to its
junction with the distributing main.
• it connects no more than four consumers’ installations, of which one or more has a
PME earthing terminal and:
• it is no more than 40 metres in length from its point of connection to the distributing
main.
3.3 Caravan
A trailer leisure accommodation vehicle, or:
A mobile home or residential park home if certain conditions apply; namely, if any metalwork
connected to the earth terminal is within reach of a person in contact with the general mass of
earth or they are not permanently sited or not permanently connected to water/sewerage
services.
NOTE: "Caravan" is a legally defined term which includes tents.
3.4 Distributing Main*
A low voltage electric line which connects a distributor’s source of voltage to one or more
service lines or directly to a single consumer’s installation.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 9
NOTE: A distributing main supplying a single consumer may, in other contexts (e.g. charging, planning consent for
OH service) be described as a service.
3.5 Distributor*
A person who owns or operates a network, except for a network situated entirely offshore or
where that person is an operator of a network within the meaning of Part I of the Railways Act
1993 or an operator of a tramway, a trolley vehicle system or guided transport.
a) any equipment connected to any such line for the purpose of carrying electricity;
b) any wire, cable, tube, pipe, insulator or other similar thing (including its casing or coating)
which surrounds or supports, or is associated with, any such line".
3.7 Exhibition**
Event intended for the purpose of displaying and/or selling products etc., which can take place
in any suitable location, either a room, building or temporary structure.
3.8 Marina**
Facility for mooring and servicing of pleasure craft with fixed wharves, jetties, piers or pontoon
arrangements capable of berthing one or more pleasure craft.
3.15 Show**
Display or presentation in any suitable location, either a room, building or temporary structure.
3.16 Stand**
Area or temporary structure used for display, marketing or sales.
3.18 Supplier*
A person who contracts to supply electricity to consumers.
3.19 TN system**
A system having one or more points of the source of energy directly earthed, the exposed
conductive-parts of the installation being connected to that point by protective conductors.
3.23 TT system**
A system having one point of the source of energy directly earthed, the exposed-conductive-
parts of the installation being connected to earth electrodes electrically independent of the
earth electrodes of the source.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 11
In the case of single phase two wire or two phase three wire distributing mains and services
the cross-sectional area of the supply neutral conductor shall be not less than the equivalent
cross-sectional area of the phase conductor, with recommended minimum values of:
NOTE: The terms “single phase three wire” and “split phase” are commonly used to describe a two-phase, three
wire, phase angle 180° system according to BS 7671 Section 312. The term “two phase three wire” is commonly
used to describe a two phase, three wire, phase angle 120° system according to BS 7671 Section 312.
The design of conductors, cables, joints and terminations shall be such as to minimise the risk
of an open circuit of the neutral.
Wherever possible, CNE cables shall be used for reinforcement, diversions, and repairs to
existing systems. The neutral to sheath bonding and neutral earthing requirements of such
systems shall be in accordance with paragraphs 4.4.1, 4.4.2, Figure 4.4 and any additional
requirements shown in Figure 4.5. Details of the appropriate size of conductor for neutral to
sheath bonds and neutral earth connections may be found in paragraph 4.9.
An earth electrode shall be provided at the end of the section of CNE cable most remote from
the distribution substation. The neutral of each section of CNE cable shall be bonded to the
neutral/sheath of the adjacent SNE cable. The whole of the distributing main between the
substation and this earth electrode will then be suitable for PME.
PME can be applied to the remote sections of SNE distributing mains by bonding the earth
and neutral conductors at the end of the SNE distributing main and where necessary installing
an earth electrode.
A suitable length of metallic sheath of an SNE cable laid direct is considered to be an earth
electrode (see paragraph 4.8).
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 13
C
B >4 customers Neutral
≤4 customers
A Earth Electrode required
≤40 metres length
at C
> 4 customers Neutral No Neutral Earth
Earth Electrode Electrode required at B
required at A
E
D
No maximum length
Service Line
Associated Branch
Distributing Main
Non-PME customer
PME customer
TERMINOLOGY:
S/S = Substation
L/B = Link disconnecting Box (phase normally open, neutral solid)
CNE = Combined Neutral Earth cable
SNE = Separate Neutral Earth cable
= PME neutral earth electrode
= Bond between sheath of SNE cable and Neutral of CNE cable
PME facilities
Examples
available
S/S
SNE CNE Along whole length
1
of distributor
Earth electrode
where necessary
S/S
CNE SNE On CNE section
2
only
S/S
SNE Between S/S and
7
service joint position
Earth electrode
where necessary
Figure 4.5 Typical application of PME to networks with SNE and CNE cables
When a new CNE service, or an existing service replaced by a CNE cable, is connected to an
SNE distributing main which does not already form part of a PME system, the consumer may
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 15
be provided with a PME earth terminal provided that an earth electrode is connected to the
neutral at the service joint.
When converting systems with a separate earth conductor to PME, all overhead sections of
associated main and any other main likely to be used as an alternative supply, between the
supply substation and the connection to the consumer being offered PME, shall meet the
requirements of this Engineering Recommendation.
Additional neutral earth electrodes may be required at intervals along the line in order to
maintain the neutral to earth resistance below the required value (see 4.7).
NOTE 1: It is found that neutral earth electrodes installed at intervals not greater than 8 spans will generally achieve
this value.
NOTE 2: Overhead systems are more exposed to the elements so are more likely to lose an earth connection.
On poles supporting cable terminations, the sheaths and metallic termination boxes shall be
bonded to the neutral conductor.
Undereaves wiring should be considered as part of the distribution network and the definitions
of service line and distribution main applied.
The combined resistance of all LV neutral earth electrodes shall not exceed 20 ohms (before
the connection of consumers' earthing terminals to the neutral).
Where several driven rods are used to form an electrode system, and space is available, the
mutual separation should not be less than twice the depth to which the rods are driven.
NOTE: Metallic joint boxes, link disconnecting boxes or non-insulated metallic cable sheaths of SNE cables which
are electrically continuous and in direct contact with the general mass of earth for a minimum length of 5 to 20
metres may be suitable earth electrodes dependent upon local soil conditions.
The minimum size of earthing and bonding connections for copper conductors shall be as
shown in Table 4.9a. For non-copper conductors or copper alloys, the cross sectional area
shall be such as to give a conductance (or continuous rating) equivalent to that of copper.
Currents in PME earthing conductors may flow for an extended duration. In calculating the
‘copper equivalent’ cross sectional area of a conductor it is therefore not appropriate to use
short-time equivalent ratings such as are typically quoted for protective conductors.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 16
To assist with the sizing of earthing and main protective bonding conductors, the copper
equivalent cross-sectional areas of the supply line and neutral conductors for a range of typical
DNO incoming cables are listed in Table 4.9b.
The LV neutral conductor shall be connected to an earth electrode at a point remote from the
transformer, between the transformer and the supply terminals of the consumer(s). The
distance between the connection to earth and the consumers’ intake shall be 40m or less;
however in order to minimise the risk of voltage rise in the event of a broken neutral this
connection should be made as close as is practicable to the consumers’ supply terminals. The
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 17
metallic sheaths of any LV cables shall also be connected to the earth electrode. The
resistance of the earth electrode shall not exceed 40 ohms.
The transformer tank and associated HV metalwork will be connected to a HV earth electrode.
All uninsulated parts of this electrode shall be separated from any part of the LV earth electrode
and any earthed metalwork connected to it.
PNB can apply to both three phase and single phase connections.
Earth terminals provided using PNB shall be treated in all respects as PME earth terminals.
5. Consumers Installations
5.1 Consumers on existing networks
Where consumers' installations use SNE earth terminals all reasonable precautions shall be
taken to ensure that the safety of these consumers is not adversely affected by modifications
or additions to existing networks.
Where CNE cable is introduced into SNE networks, existing SNE consumers' installations may
retain an SNE earth provided that:
• a continuous metallic earth return path exists to the source substation and:
• they are connected to a length of electrically continuous non-insulated metallic sheath
cable, sufficient to control the rise of potential to acceptable levels under open-circuit
neutral conditions, having considered the requirements of IEC/TS 60479-1. By
experience this criterion will be met provided the resistance to earth of the metallic
sheath is 10 ohms or less or an individual earth electrode is provided with a
resistance of less than 10 ohms. Where in specific circumstances the 10 ohm value
cannot be achieved, a value up to 20 ohms is acceptable where it can be shown by
calculation that any voltage rise on the neutral conductor of the 3-phase cable is
limited to 100V.
If these conditions cannot be met there should be discussions with existing SNE consumers
who may wish to convert to PME provided their bonding complies with paragraph 5.2.1.
Alternative earth fault protection may be provided if the consumer operates an installation
forming part of a TT system by installing a separate earth electrode and fitting appropriate
protection in accordance with BS 7671 (eg an RCD). Alternatively, SNE earths may be
maintained by running a separate earth cable along with the section of CNE cable. Where this
option is chosen the neutral and earth should remain separate and be so constructed as to
minimise the risk of deterioration or damage.
On overhead networks containing continuous earth wires (CEW) when the 5 wire sections are
replaced by CNE cable, or 4 wire ABC, it is preferable from a technical point of view for all
existing SNE consumers to be converted to PME provided their earthing and bonding complies
with paragraph 5.2.1. If not, a suitable earth electrode and appropriate protection in
accordance with BS 7671 (eg an RCD) should be installed to provide earth fault protection.
Existing consumers beyond the CNE or ABC insert may retain their SNE earth provided the
earth is connected to a sufficient length of SNE cable such that the resistance to earth of the
metallic sheath is 10 ohms or less. Where in specific circumstances the 10 ohm value cannot
be achieved, a value of up to 20 ohms is acceptable where it can be shown by calculation that
any voltage rise on the neutral conductor of the 3-phase circuit is limited to 100V.
At the junction of the 5 wire system and the CNE or ABC section, the neutral of the CNE or
ABC must be bonded to the neutral and earth of the 5 wire system and an earth electrode
installed.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 18
Where none of these solutions can be applied, a 4-core metallic sheathed cable or separate
earth conductor should be installed. The sheath or earth conductors shall be connected to the
SNE cable sheath or CEW earth conductor at each end with the neutral and earth remaining
separate.
Where service cables with a concentric neutral are used, the concentric neutral and any
separate earth conductor shall be connected to the earthing terminal, neutral terminal or
neutral connector block, as appropriate.
6. Special Situations
6.1 General
A PME earthing terminal provides a satisfactory means of protection for the majority of
installations. There are, however, a number of special situations where PME is not a suitable
method of earthing: in such situations, if a PME earth terminal is utilised, the rise of voltage on
a consumer’s earth terminal in the event of an open neutral may pose an unacceptable risk. In
these cases the consumer must utilise an additional or alternative form of fault protection such
as a TT system earthing arrangement by installing a separate earth electrode and fitting
appropriate protection in accordance with BS 7671 (eg an RCD).
Where the use of PME is precluded in any consumer's installation or part thereof the earthed
metalwork of the TT system associated with the use of an RCD or other protection must be
segregated from any metalwork associated with the PME system.
It is not acceptable in these situations to provide an SNE service from a PME main since any
rise of voltage on the neutral of the main will be transferred to the consumer’s earth terminal.
NOTE:Specific requirements for various specialised installations can be found in BS 7671.
6.2.1.1 General
For any supply with a PME earth terminal:
a) All installations shall comply with the requirements of BS 7671, including equipotential
bonding under PME conditions;
b) The housing at the intake position shall not expose a member of the general public to
dangerous touch potentials.
c) Metal housings containing LV equipment are not permitted at the intake position or where
they may expose a member of the general public to dangerous touch potentials.
The above measures do not necessarily provide full protection against touch potentials for
railway personnel. It is the responsibility of the railway operator to assess and control such
risks.
NOTE: These standards include BS EN 50122-1 and the Railway Group Standard GL/RT1255.
Therefore, more stringent limits than those set by these standards are required to ensure that
dangerous voltages are not exported to DNO LV networks through a PME earth conductor.
PME supplies may be made available subject to the railway operator confirming that their
design standards will ensure that:
i. In the case of traction supply faults the earthing standards will limit the rise of earth
potential to the following values as specified by TS 41-24 :
• 430V for faults with a duration greater than 0.2s, but not greater than 3s;
• 650V for faults with a duration not greater than 0.2s.
ii. The rise of voltage on the traction rail due to traction return current shall not exceed
25V under frequent traction peak starting or running current conditions.
These requirements are set in place in order to minimise the risk of electrolytic corrosion of
earthing systems due to stray DC currents. They are based on a recognition that, if stray
currents exist, there will be paths electrically closer to the traction system which will take larger
stray currents than will flow through a DNO LV earthing system. In this case corrosion of cable
sheaths, structures and earthing systems, which are subject to regular inspections, will quickly
become apparent to the railway operator.
These measures will also ensure that for PME systems no external voltage is impressed on
the neutral/earth conductor.
In the case of Light rapid transit systems, reference should be made to EREP 123.
In addition to the arrangements shown in 6.2.2.1 and 6.2.2.2, if the site does not have a
dedicated transformer, ie the transformer supplies other consumers or other parts of the LV
network, it is still possible to provide a TN-S earthing system within the boundary of the site
via a suitable isolating transformer.
The transition from a temporary to a permanent supply must be taken into account, and both
supplies should be considered during the design and planning stages. Refer also to BS 7375.
Construction site
DNO secondary
DNO Consumer
substation
HV : LV
L1 L1
L2 L2
L3 L3
N N
E E
The supply must be protected in accordance with BS 7671; this will usually include a residual
current device (RCD) on the consumer’s side of the cut-out. There shall be no exposed-
conductive-parts before and/or enclosing the RCD.
The earth electrode must be separated from any PME earth electrode or metallic cable sheath.
Construction site
DNO secondary
DNO Consumer
substation
HV : LV
RCD
L1 L1
L2 L2
L3 L3
N/ E N
E
Other consumer
supplies
• The permanent building is complete and there are no reasonable grounds to believe
that the installation does not meet the requirements of BS 7671;
• Any scaffolding is not bonded to the construction site TT system earth.
PME shall not be offered for a dedicated supply to a mobile or transportable unit except as
permitted by BS 7671:
Examples of these situations are outside broadcast vehicles, medical services vehicles/cabins,
transportable catering units, technical/facilities vehicles for fire fighting etc. The definition does
not include caravans, pleasure craft, mobile machinery and generating sets and traction
equipment of electric vehicles.
• Damp locations
• Possibility of contact of the body with true Earth potential
• Presence of livestock
NOTE: In addition to normal electric shock hazards to persons, livestock are sensitive to small potential differences
and may experience low level shocks or tingles from voltages imported via the neutral/earth conductor of the DNO
TN-C-S system.
BS 7671 notes that PME (TN-C-S) earthing is not recommended where a metal grid cannot be
laid in the floor and included in the installation’s equipotential bonding. In this case each
building should be provided with its own earthing installation as part of a TT system by installing
a separate earth electrode and fitting appropriate protection in accordance with BS 7671 (eg
an RCD).
NOTE: In practice this means that the main service position can be provided with a PME terminal.
The consumer’s electrician:
• may use the PME terminal to earth the farm house / offices/ shop etc.
• may use the PME terminal to earth the farm buildings where a metal grid is installed in the floor and
included in the equipotential bonding of the installation.
• may segregate the earthing conductor / wire armouring of each circuit and install a separate earth electrode
for each building where the full equipotential bonding provision of BS 7671 Section 705 cannot be fully
applied.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 24
• Should, in accordance with Guidance Note 5 to BS 7671, advise the consumer that if PME is to be used
and the metal grid in the concrete floor cannot be bonded or does not exist, the small voltage differences
referred to above may adversely affect livestock feeding and milking.
Where segregation is not possible then the alternative of converting the whole of the installation
to form part of a TT system should be considered.
Locations containing swimming pools and other basins are considered to be ‘Special locations’
within BS 7671. Section 702 of that standard sets out requirements and recommendations
relating to the use of supplementary equipotential bonding and RCDs in electrical installations
in such locations.
BS 7671 recommends that where PME (TN-C-S) earthing is adopted, an earth mat or electrode
should be installed for Zone 2.
• Wet locations
• Possibility of contact of the body with true earth potential
• Presence of wet barefoot persons
NOTE: In addition to normal electric shock hazards, persons may experience low level shocks or tingles from the
out of balance voltages imported via the neutral/earth conductor of the DNO TN-C-S system.
Competent persons enquiring about the suitability of PME for swimming pool supplies should
be advised:
• The main service position can be provided with a PME terminal. It is the electrician’s
decision whether or not to utilise the PME terminal for all or part of the installation.
• Where the pool is in separate building or outdoors the consumer’s electrician:
o may decide to use the PME terminal to earth the house / offices/ shop etc.
or,
o may decide to segregate the earth conductor / wire armouring of the pool
building circuit, install a separate earth electrode for the pool building and
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 25
• Where the pool is within the same building the consumer’s electrician:
o may decide to use a TT system to earth the entire installation
or,
o may decide to use a TT system to earth the pool installation, and segregate
the metalwork and pipes from the rest of the building and connect them to a
separate earth electrode
or,
o may decide to use the PME earth if a metallic grid is installed under the
poolside areas and connected to the equipotential bonding.
6.2.6 Caravans, boats, marinas, camp sites and amenity/shower blocks (including
sports pavilions)
6.2.6.1 Caravans
The Electricity Safety, Quality and Continuity Regulations 2002, as amended, preclude the
provision of a PME earthing terminal to a caravan. Supplies to caravans should be from a TT
system utilising a separate earth electrode segregated from the PME earth and protected by
an RCD which must be provided by the consumer or site owner.
NOTE: This does not preclude the provision of PME to mobile homes which are not of caravan construction (See
6.2.7)
Where outside showers have been provided, provision of PME earthing is not recommended
as providing a reliable equipotential cage may prove impractical.
Where no shower area exists nor is likely to exist in a sports pavilion, PME may be offered
provided the appropriate metalwork is bonded and due consideration is given to the
construction of the building, ie wooden or brick construction.
NOTE: This does not preclude a PME earthing terminal being provided for use in permanent buildings on a caravan
site such as the site owner's living premises and any bars or shops.
NOTE: This does not preclude a PME earthing terminal being provided for use in permanent buildings on a marina
site such as the site owner's living premises and any bars or shops.
• any metalwork connected to the earth terminal is within reach of a person in contact
with the general mass of earth, or
• it is not permanently sited, or
• it is not permanently connected to water or sewerage services.
This definition does not include mobile or transportable units (e.g. outside broadcast vehicles)
which are covered in paragraph 6.2.3.2.
If the site has a dedicated secondary substation that only supplies the consumer it will usually
be possible to provide a TN-S earth terminal directly from the transformer neutral.
NOTE: The requirements for supplies to the working areas are covered by specific statutory legislation (see
BS 7671, section 110.1).
Where the filling station is part of a larger site, PME facilities may be provided for permanent
buildings such as restaurants and shops, provided the filling station area has an earth system
segregated from the PME earth system.
An insulating insert may be incorporated in the pipe to an outside water tap. However, care
should be taken to ensure that simultaneous contact with metal pipework on each side of the
insert is not possible if there is likely to be a potential across the insert under this condition.
NOTE: For photovoltaic installations in buildings, see DTI Publication “Photovoltaics in Buildings – Guide to the
installation of PV Systems”
6.2.14 Street lighting and road signs with electrical load of 500W or less
Part II of the The Electricity Safety, Quality and Continuity Regulations 2002, as amended,
which covers protection and earthing, applies to supplies to street lighting installations and
other street electrical fixtures.
An earth electrode shall be provided at the end of every service supplying more than one street
lamp or road sign.
An earth electrode shall be provided at the source pillar or supply point servicing more than
one street lamp or road sign. Where the load on the pillar is greater than 500W the earth
electrode shall be in accordance with section 6.2.15 of this this Engineering Recommendation.
Where a street lamp or road sign is installed within an insulated foundation such as a plastic
or non-conductive collar an earth electrode shall be installed connected to the earth terminal
at each such installation.
In accordance with BS 7671, bonding conductors shall have a minimum size of 6mm2 copper
equivalent for supply neutral conductors with copper equivalent cross-sectional areas up to
10mm2. For larger sized supply neutral conductors the main bonding shall comply with Table
4.9a.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 28
These requirements apply to street lighting and road signs supplied by a DNO and by a street
lighting authority when using CNE cables. In this latter case supply from the DNO is usually to
a pillar. See Figure 6.2.14a.
Private installations and local authority installations using SNE cables which are supplied from
PME services must comply with Figure 6.2.14b.
Figure 6.2.14a: Lighting Authority C.N.E. distributor fed from PME service
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 30
Figure 6.2.14b: Lighting Authority S.N.E. distributor fed from PME service
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 31
Table 6.2.15
If the conditions for a Class I installation cannot be met, a PME terminal should not be offered.
The earthing system of the installation should form part of a TT system by installing a separate
earth electrode and fitting appropriate protection in accordance with BS 7671 (eg an RCD).
The risk of a neutral fault on EVCP installations which form part of a Class 1 construction street
electrical fixture supplied at single phase or unbalanced 3 phase is sufficient to classify the
structure as special situations where the consumer must utilise an additional or alternative form
of protection to PME.
For an EVCP installation the contact by a member of the public to the charging point, to connect
and disconnect the vehicle and to the vehicle (which will become an extension of the charging
point installation) will be frequent and less fleeting in nature than for a typical street electrical
fixture installation. As EVCPs will be used in all weather conditions, the contact scenario should
be assumed to be in wet conditions. For these reasons, the value of impedance to earth of a
supplementary electrode used as the sole means of additional protection for an electric vehicle
charging point is required to be less than as described in Section 6.2.15. Consequently, this
approach has been discounted for EVCPs.
Currently BS 7671 section 722 permits the protection against a neutral fault condition to be
provided by the use of a protective device which responds to an open neutral condition.
Where an open neutral detection and earth disconnection device is used as the additional form
of fault protection the designer, installer and owner of the device must ensure that the device
is designed, installed, maintained and operated to protect members of the public from the risks
associated with the rise of voltage on the street electrical fixture in the event of an open neutral
condition.
As a minimum requirement, any open neutral detection and earth disconnection device must
be designed to comply with the guidance in the current version of BS 7671 and to comply with
all relevant national and international technical construction and design standards.
At the time of writing no definitive product standards were in existence for the design and
construction of an open neutral detection and earth disconnection device. Until such standards
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 33
are developed, in addition to the requirements above, it shall be demonstrated that the device
is fit for purpose by type testing and certification at an independent test centre to:
• Verify that it responds to all likely fault scenarios, under typical system and
environmental conditions.
• Verify it locks out on detection of a fault scenario.
• Demonstrate that it does not falsely operate under expected network operating
conditions.
• Demonstrate that it is fail-safe to prevent the operation of the charger if any major or
significant component fails.
Consideration should be given to the size of bonding conductor, because in the event of an
open circuit neutral the consumer’s earth electrode may carry most of the diverted neutral
current. The size of the consumer earthing and bonding connections may be insufficient for
this current, particularly where the service size is small. Where necessary, DNOs should
provide guidance on the bonding requirements.
When periodic testing of the lightning protection system is undertaken, precautions are
necessary when breaking the link between the lightning protection electrode and the
consumer's earth since the consumer's earth may be at a potential above true earth.
Substation earth electrodes, end of main electrodes and stay wires should be situated as far
as possible from the cathodic protection ground bed.
In order to prevent the possible neutral current diversion detailed above, the consumer should
be advised to create a TT earthing system that meets BS 7671 for either:
b) the part of the installation feeding the radio/communication equipment and any associated
metalwork
In the case of b), the TT installation earthing must be segregated from the earthing/bonding in
the rest of the consumer installation and DNO earthing. With the TT installation, a RCD shall
be provided to comply with the earth fault disconnection time requirements in BS 7671.
Where disruption due to possible RCD nuisance tripping would be unacceptable, an alternative
to the above TT earthing system is to use TN-C-S earthing for the whole installation and
increase the size the consumer earthing and bonding conductors; these shall not be less than
the cross-sectional area of the service neutral.
Communication sites can be sensitive to the effects of diverted neutral current passing through
earthing/bonding paths. This can arise with PME at multi-user sites sharing a common
communication tower/mast. The neutral current due to load of one user/consumer can cause
noise problems with certain consumer earthing practices by passing through equipment,
chassis, signal wires, screening braids etc of other consumers. The noise problems may be
overcome if consumers employ earthing practices that eliminate parallel paths for neutral
current in earthing/bonding connections. With PME, the practice of providing only a single
service connection per communication tower/mast will reduce the above effect. If more than
one service is provided then see requirements in 6.2.19.5.
In the following, the term ‘Main Building’ refers to the building which has the communication
station located on/in it.
In general, where the ‘Main Building’ has a PME earth terminal at its Connection Point then
provision of an additional Connection Point to the communication station is not recommended;
alternative options to provide an electrical supply to the communication station are as follows:
Roof-top
Communication
Station
SNE Sub-
Bonding to extraneous
service from
conductive part (e.g.
consumer
steel frame,
communication mast)
Electricity
Meter Bonding to
Main Earth extraneous
M
Terminal conductive
part (e.g. steel
TN-C-S frame)
Intake to Bonding to
Building 1 N/E
BS 7671
M
PME Earth
Terminal Insulated
Insert (If
fitted)
3 Phase CNE
Mains Cable
PME Gas
Earth, if
applicable Water
Other
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 37
(6) Paragraphs (1) to (4) shall not apply to a generator’s network which is situated
within a generating station if, and only if, adequate alternative arrangements
are in place to prevent danger.
Protective multiple earthing
9.— (1) This regulation applies to distributors’ low voltage networks in which the neutral
and protective functions are combined.
(2) In addition to the neutral with earth connection required under regulation
8(4)(b), a distributor shall ensure that the supply neutral conductor is connected
with earth at---
(a) a point no closer to the source of voltage (as measured along the
distributing main) than the junction between the distributing main and
the service line (the supply neutral conductor of the latter being
connected to the protective conductor of a consumer’s installation)
which is most remote from the source; and
(b) such other points as may be necessary to prevent, so far as is
reasonably practicable, the risk of danger arising from an accidental
disconnection of any such connection with earth.
(3) The distributor shall not connect his combined neutral and protective conductor
to any metalwork in a caravan or boat.
Equipment on a consumer’s premises
24.— (4) Unless he can reasonably conclude that it is inappropriate for reasons of safety, a
distributor shall, when providing a new connection at low voltage, make available his supply
neutral conductor or, if appropriate, the protective conductor of his network for connection to
the protective conductor of the consumer’s installation.
(5) In this regulation the expression “new connection” means the first electric line, or the
replacement of an existing electric line, to one or more consumer’s installations.
ENA Engineering Recommendation G12
Issue 4 + Amendment 2 2022
Page 39