K88 P5 020G 06 SDW ELE 450 0301 00 Reply
K88 P5 020G 06 SDW ELE 450 0301 00 Reply
D
20G LPG1
- - D
15 3-The contractor should respect one “D”
spacing for the main feeders during
1CTG4 1CTG5 1CTG5
installations
CT 436mm HCU LAUNDRY CT 508mm HCU CT 508mm HCU 4-The utilization of the existing incoming PROJECT MANAGEMENT & COST CONSULTANCY :
IL: +320mm MANAGER 1CTG1 IL: +300mm IL: +300mm cables shall be subject to passing the
HOT DIP GALVANIZED 00-001 HOT DIP GALVANIZED HOT DIP GALVANIZED
PERFORATED CABLE CT 123mm
PERFORATED CABLE PERFORATED CABLE
required testing in addition to its
TRAY IL: +3200mm sufficiency to handle the new loads,
TRAY TRAY
HOT DIP GALVANIZED
A 1CTG5 which shall be submitted for Engineer’s A
3
PERFORATED CABLE
CT 508mm HCU
IL: +3200mm
TRAY review and approval in shop drawing
1CTG2
HOT DIP GALVANIZED stage, otherwise existing cables shall
- PERFORATED CABLE be replaced.
TRAY
GF
5-. Spare capacity on cable trays to be indicated as 20%.
SOILED LINEN GF GF
00-002
FHC
2 -
020G-MW01 CONSULTANT DESIGN REVIEWER :
Laundry Facility
052
BOILERS 1CTG4
1CTG2 CT 436mm
007 00-006 CT 220mm HCU IL: +3200
IL: +2500mm HOT DIP GALVANIZED
HOT DIP GALVANIZED PERFORATED CABLE
RECEIVING PERFORATED CABLE TRAY
section 2 TOILET TRAY LAUNDRY
00-004 & SORTING FACILITY
SANITATION SYSTEM 00-003 00-007
MZ 1CTG1
CT 123mm HCU ROOM
00-005
FHC
IL: +2500mm ##
HOT DIP GALVANIZED
PERFORATED CABLE
- S DESIGNER :
- - B
B
TRAY
020G-MW08 020G-MW09
2CTG5
1CTG1 CT 508mm
CT 123mm HCU IL: +3000 & IL: +3200mm DETERGENT
IL: +320mm 1CTG5
HOT DIP GALVANIZED
HOT DIP GALVANIZED DISPENSING CT 508mm
BOILER ROOM
PERFORATED CABLE
PERFORATED CABLE TRAY ROOM IL: +3000mm 00-010
TRAY 00-008 DRYER MAINTENANCE HOT DIP GALVANIZED
2CTG6 ROOM PERFORATED CABLE
TRAY
CT 600mm HCU 1CTG2 00-009
IL: +2300 & IL:+2200mm CT 220mm HCU
HOT DIP GALVANIZED IL: +2500mm
PERFORATED CABLE HOT DIP GALVANIZED
TRAY PERFORATED CABLE CONTRACTOR :
TRAY
GF
B 1 X CTGYC
B
1 A
GROUND FLOOR PLAN_LAYOUT B C D D1
Receiving & sorting F G H SUBCONTRACTOR :
201 Scale 1:50
003
4 Boilers room
section 5
1CTG1 006
E SETRAA ADVANCED TECHNOLOGY CO.
MZ CT 123mm
IL: +2600mm
HCU-Electrical room P.O. BOX 53008 RIYADH 11583 KINGDOM OF SAUDI ARABIA
HOT DIP GALVANIZED TEL : +966 (1) 4736292 - FAX : +966 (1) 4736291
PERFORATED CABLE M-002 Email : [email protected]
TRAY
section 7
MZ LEGEND :
Section 8
1CTG2
3 FHC
RF
1CTG6
1CTG1 CT 600mm HCU
CT 220mm HCU
CT 123mm HCU IL: +2600mm
IL: +2500mm
IL: +2500mm HOT DIP GALVANIZED
HOT DIP GALVANIZED
HOT DIP GALVANIZED PERFORATED CABLE
PERFORATED CABLE
1CTG6 PERFORATED CABLE TRAY
TRAY
CT 600mm HCU TRAY
HCU TERRACE
IL: +2600mm
ELECTRICAL 1CTG2
2 ROOM
HOT DIP GALVANIZED
PERFORATED CABLE
CT 220mm
IL: +2600mm
HCU
TRAY
GF M-002 HOT DIP GALVANIZED
B20G-TL-PP3 GF
PERFORATED CABLE
TRAY
B20G-TL-PP1 B20G-TL-AC11CTG6
CT 600mm HCU
MZ
TRAY
GF
1 TYPICAL WALL MOUNTED CABLE TRAY INSTILLATION DETAIL.
TYPICAL CEILING CABLE TRAY INSTILLATION DETAIL.
DETAIL -02
DETAIL -01
A B C D D1 E F G H
951.750
405.000
2 MEZZANINE PLAN_LAYOUT TYPICAL SURFACE MOUNTED PANEL BOARD DETAIL.
DETAIL -03 TYPICAL SURFACE MOUNTED SWITCHBOARD DETAIL.
DETAIL -04 SHOP DRAWING
Roof Floor
201 Scale 1:50
Section 9 4
D A ROOF CABLE TRAY INSTALLATION DETAIL
D
- SCALE: NTS
3
PERFORATED COVERED
RF CABLE TRAY ELECTRICAL MECHANICAL ICT
- - -
Roof Floor
Section 10 2
IJ dar al-handasah
lhair il1lf partnm
C
-
DISCONNECT SWITCH INSTALLATION DETAIL
SCALE: NTS
DRAWN BY
S.M
CHECKED BY
S.M
APPROVED BY
S.M
0 CON l: APPROVED
1CTG2C 0 C®£ I: APPIOVED AS NOTED K88_PROJECT
CT 220mm
1CTG2C
-Approved panel boards shop drawings to be provided IW MY IIICIIIIIIlKTlO
IL: +300mm
HOT DIP GALVANIZED
HCU
Roof Floor CT 220mm HCU -Approved shop drawing layouts to be provided [LTG, PWR, MECH.] IIICOIINMtll Of EIIOIIID N
IL: +300mm
PERFORATED COVERED
CABLE TRAY Section 12 HOT DIP GALVANIZED -Approved material submittal for each load/equipment on the layout to be provided matching the approved panel co.um. BUILDING NUMBER & NAME :
PERFORATED COVERED
RF
CABLE TRAY SDW D conE c: RlYISIAaiiSUBIIT 020G
-Reference approved material submittal for the mentioned items on the layout to be provided e.g. trays, supports, IOIIIIAY lOTPIOCUD
cables, BMS cables…etc. D COD! DI RE-JECTED BUILDING 020G
MAIN LAUNDRY FACILITY
1CTG1C -Provide table of cable tray size calculation showing number of cables, cross section area, VD, overall diameter
CT 123mm HCU 1CTG1C for each cable [approved material to be provided], weight, spacing and the spare percentage as specified By:WGhasoup D•te: 22/1/23 BUILDING KEY PLAN : DRAWING TITLE :
IL: +300mm
Roof Floor CT 123mm HCU
HOT DIP GALVANIZED 1CTG2C
CT 220mm HCU IL: +300mm associated. ~ ......... Centrlctor
--............
PERFORATED COVERED
HOT DIP GALVANIZED
Section 11 CABLE TRAY IL: +300mm
-Cross sections showing cables on trays and spacing for each section/run to be provided of., of 1111 IJIIItils- the N
E
RF
HOT DIP GALVANIZED
PERFORATED COVERED
PERFORATED COVERED
CABLE TRAY
-Sectional details for tray connection to panels, equipment, change levels ...to be provided Colltract. Clllllfllllllllltallall BUILDING 020G E
CABLE TRAY
-Stick to specification for supports/fastenings to the structure, to carry the greater of the calculated load multiplied of..., . . . " Cenlract Deaalls. GROUND FLOOR
by a safety factor of 4. Contrlctoris,...... .. MEZZANINE FLOOR&ROOF
1CTG2C -Install expansion connectors where cable trays runs that exceed 27m as specified.
CT 220mm HCU
-Deflection between supports is not to exceed 1/350 under full loading capacity as specified
CABLE TRAYS
IL: +300mm
HOT DIP GALVANIZED
withotJ.trMn.
PERFORATED COVERED
CABLE TRAY
RF 1 I
SCALE - SHEET SIZE DATE CAD FILE
3 I
ROOF PLAN_LAYOUT
1/50 10-01-2023 K88-P5-020G-06-SDW-ELE-450-0301-00
DOCUMENT NUMBER :
201 I Scale 1:50
A B C D D1 E F G H K88 P5 020G 06 SDW ELE 450 0301 00
I PROJECT PROGRAM BUILDING PHASE DOC. TYPE DISCIPLINE TRADE DOC. NUMBER REVISION
1 2 3
I 4 5 6