3 3 6 9 12 15
4 4 8 12 16 20 5 Certain 5 Fatality, major damage, industry disruption
5 5 10 15 20 25 Risk Rating (RR) = Likelihood (L) x Severity (S)
Risk Rating
E - Extreme risk: Activity not to commence. Review of task and controls by relevant Manager / Coordinator, with workgroup to identify control measures to
lower the level of risk. If the risk remains Extreme then authorization from the General Manager is required before the activity can
commence.
H - High risks: Authorized by relevant Manager / Coordinator. Should only be an acceptable level of risk for ‘Major’ or ‘Catastrophic’ consequences.
M - Moderate risk: Authorized by Supervisor / Team Leader. An acceptable level of risk.
L - Low risk: Manage by routine procedures. An acceptable level of risk
Hazard Controls
Selecting control measures (WHS Regulations 2012, Regulation 36 – Hierarchy of control measures)
1. Eliminate the risks so far as is reasonable practicable
2. If this is not reasonably practicable, minimize them so far as reasonably practicable by applying the following hierarchy of control measures: Minimize the
risk by doing one or more of the following:
o substituting the hazard
o isolating the hazard
o implementing engineering controls
If the risk still remains, minimize the remaining risk by implementing administrative controls
If the risk still remains, minimize the remaining risk by ensuring the provision and use of suitable personal protective equipment (PPE).
Job Step Hazards Risk Controls and actions to eliminate or minimize each hazard Residual
Rating Risk
Preparing for work: 1. Injury or property damage as a 1.M 1a. Indoctrination training reviews activity hazards, controls, and safety policies as AHA 1. L
general. result of lack of knowledge/poorly posted at job site.
Equipment. 1b. Employees are provided adequate orientation, equipment and training as per their
duties and responsibilities.
2. Injury or property damage as a 2.M 2a. Crew leaders and supervisors are responsible for providing crewmembers with 2. L
Result of lack of PPE. adequate PPE and related training.
2b. Remove any contaminated clothing; do not smoke in the work area, and wash. Hands
at the end of each shift and before eating/smoking.
2c. Any tool or piece of equipment deemed unsatisfactory will be tagged and removed
.
3. Fire and Emergency response 3.M 3a. Training would include: fire extinguisher use, Phone communication, first aid. 3.L
Transporting material 1. Tripping / Falling while carrying 1.M 1a. Inform and Training all workers about hazards in site area. 1. L
to site materials 1b. PPE: Helmet, Reflective Vest, Safety Shoes, gloves, safety googles.
1c. When Hauling material DO NOT over carry to obstruct vision.
1d. trenches should be properly blocked either by guard system or caution tape
Located 1.8 meters from trench.
2. Ergonomic injury 2.M 2a. When lifting all materials make sure employees are lifting with their legs and not 2. L
their backs.
2b. Use a device to lift and reposition heavy objects to limit force exertion.
2c.Require that heavy loads are only lifted by two people to limit force exertion
3.M 3a. Drink enough water depends on activity ,weather conditions and every
3. Weather Case of thirstiness- each person individually. 3. L
Job Step Hazards Risk Rating Controls and actions to eliminate or minimize each hazard Residual
Risk
operating 1. Technical malfunction 1. M 1a. possess, at all times while operating any vehicle/equipment, a license/permit (proof of 1.L
motor vehicle/ qualification) valid for the equipment being operated.
1b. Inspections, tests, maintenance and repairs shall be conducted by a qualified person
machinery/ In accordance with the manufacturer's recommendations.
mechanized 1c. Vehicles/equipment not meeting safe operating conditions shall be immediately
equipment removed from service, its use prohibited until unsafe conditions have been corrected, and
Re-inspected before being placed in service again. 2.L
2. lack of skill 2.M 2a. an Operator Equipment Qualification Record documentation may be maintained on file at
The SSHO project office for all site vehicle/equipment operators. 3.L
3. bad visibility conditions 3. M 3a. all vehicles or combinations of vehicles, in use shall be equipped with: Two headlights, one
On each side in the front; Reverse signal (back-up) alarm, Guarding and Safety Devices.
4. Injury/wounds 4. M 4a. No guard, safety appliance, or device shall be removed from machinery or 4.L
Equipment, or made ineffective, except for making immediate repairs, lubrications,
Or adjustments, by component person.
5.Distraction 5.M
5a. Prior to using a hand-held cellular phone, drivers shall find a safe place to bring 5.L
Their vehicle to a stop.
5b. Text messaging by the operator is strictly prohibited while operating motor vehicles.
Job Step Hazards Risk Controls and actions to eliminate or minimize each hazard Residual
Rating Risk
1.Dust Allergy 1. M 1a. During offloading of filling material persons shall wear dust mask.
Filling soil/beds 1b. Water will be sprayed to suppress the dust. 1. L
2. M 2a.All area must be barricaded with warning boards to prevent any unauthorized entry.
2. Slipping
3.Buried materials/person 3. M 3a.Sand filling will be carried out in coordination and supervised by the foreman. 2. L
2. Electrocution.
2. M 2a.Disconnection of active power lines Insulation and removal of electrical equipment
2. L
From the water-tightening area.
3.L
3. Movement of Machine. 3. M 3a.Operation of the bomag roller shall be carried out by qualified employees and
License."Bomag roller" must be equipped with swing/reverse alarms.
Job Step Hazards Risk Controls and actions to eliminate or minimize each hazard Residual
Rating Risk
Backfilling work 1. Damage to 1. M 1a. Prior to start of backfilling works, it must be ensured no underground services exist 1. L
Underground services. in the immediate vicinity.
1b.Waste generated from the activity must be disposed to designated area.
4. Accident. All material must be stored in designated area and if stored in open area must
Be properly barricaded with warning tape and signage.
Safe access must be maintained all time
5. Equipment or vehicle Personal protective equipment including high visibility apparel for vehicular traffic and
hit/ trap with make sure every worker wears them.
Job Step Hazards Risk Rating Controls and actions to eliminate or minimize each hazard Residual
Risk
Excavations & 1. Collapse of 1. M Prior to any excavation, all underground utilities in the work area must be positively identified by 1.L
trenching excavation. the contractor
Locate all buried services. Contact the owners of any underground utilities/services that may
Be in that location and ask them to identify and mark the location.
2. fall of equipment/ Identify and locate overhead power lines.
personnel Make sure these services are de-energized as necessary.
Determine if nearby buildings or structures and their foundations may put pressure on the 2.L
Soil and affect the walls of the trench.
2.M Good housekeeping practices including moving debris and excavated soil far enough
Away from the excavation site. 3.L
Have a worker above ground when a worker is working in the trench to warn those in the trench
3. M of danger and to provide emergency help.
Do not enter an unprotected trench deeper than 1.2 meters (4 feet).
Excavation been marked to make the workers and others aware of the excavation.
Proper barriers or guardrails in place to protect anyone or equipment falling into the excavation
4. M or trench. 4.L
Digging permits (Excavation permits). All underground lines/utilities
2. cave-ins (communication lines, water, fuel, electric lines) shall be located and protected from
Damage or displacement.
Slopping, benching and shoring must be done as applicable considering the nature of soil. 5.L
5.M Excavated area shall be barricaded by Crash Barrier and Deep Excavation Board will be
displayed.
Do not place the sections of pipes, piles of spoil, unused tools, and timber, and other materials
within 1 meter from the trench’s edge 6.L
6.M Use Temporary protective structures such as (shoring, trench boxes, pre-fabricated systems)
.
Job Step Hazards Risk Controls and actions to eliminate or minimize each hazard Residual
Rating Risk
Install 1. M 1a.Wear safety glasses or goggles, or a face shield (with safety glasses or goggles). 1. L
Interlocking 1. Injury from wet saw 1b.If work is dusty, use respirator or dust mask.
1c.Wear appropriate hearing protection.
Concrete Pavers 1d.Make sure any adjustments are secure before making a cut. Only make adjustments
2. M 1e.when the power is off and the machine is not moving.
1f.Keep one hand on the trigger switch and handle and use the other hand to hold 2. L
the stock against the fence
1g.Keep guards in place and in working order.
3. M 1h.Do not leave the saw until it has stopped completely. Turn the power off and unplug 3.L
1i.The saw.
1j.Do not use electric tools in damp or wet locations
Training Requirements/Competent or
Inspection Requirements
Equipment to be Used Qualified Personnel name(s)
1. Welding equipment. Competent/Qualified Personnel: 1. A competent person should regularly inspect ladders.
2. MEWP Mr. Eyal babu - QP/Safety Man(SSHO) 2. Daily Housekeeping of work areas and scaffolding
3. Manual lifting winch. Mr. Eyal babu- QP/First Aid and CPR 3. Inspect PPE to include fall protection harnesses and
4. Portable/Extension Ladders. Mr. Mohamed tartor – CP/Scaffolding lanyards prior to use.
5. angle grinder -MEWP -Operator 4. Inspect power cord sets prior to use.
6. hammer power tool Mr. "Abo gama gaber" -Fall Safety 5. Inspect temporary power panel box, circuit breakers,
7. Scaffold components Mr "Mohamed abo sabila"- Welding electric/ grounding, etc. at least monthly.
8. Full body harness autogenic- Qualified 6. Inspect first aid kit at least monthly.
9. Lanyard Training Requirements: 7. Daily site safety inspections by SSHO and CQC
10. First Aid Kit. Manual lifting winch -EMPLOYIE 8. All electrical leads, portable power tools, devices will
Scaffold Assembly 9. Inspected by a competent person.
Fall Protection 10. Safe work practices should exist for all welding
Inspection of Work Platforms activities.
Daily/Monthly safety toolbox meetings 11. Gas cylinders are to be handled and stored safely-
read the label and the Material Safety Data Sheet
(MSDS) before use.
12. Daily Housekeeping of work areas include.
CONTRACTOR'S ACKNOWLEDGEMENT