Mahadi Report
Mahadi Report
AT
REAL LIFE REPORT SUBMITTED TO THE UGANDA BUSINESS AND TECHNICAL EXAMINATIONS
BOARD IN PARTIAL FULFILLMENT OF THE REQUIREMENT FOR THE AWARD OF A NATIONAL
DIPLOMA IN BUILIDING AND CIVIL ENGINEERING
BY
NTAGA MAHADI
SUPERVISOR'S SIGNATURE…………….………………
SUPERVISOR'S NAME................................................................
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
ACKNOWLEDGEMENT
Assistance during report writing.
I would like to appreciate all the staffs of the college most especially
real life project teacher Mr. kiberu and my fellow students at large
for the coordination and team work they showed during the period
of real life project.
ABSTRACT
1.0 Most practical work carried out
This Field report exposes you to the practical works carried out at St. benedict
technical college kisubi which include; Construction of columns and beams
Technical Challenges
Delay in the preparation of materials due to the scarcity of tools and
equipment
1.2Conclusions
In conclusions, the project was successfully done for the estimated time give and
it was so beneficial to me.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
LIST OF ACRONYMS
DPC……… Damp Proof Course
Pg.…………………...page
mm………………... millimeters
m…………………. meters
Kgs………………. kilograms
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
DECLARATION
I NTAGA MAHADI hereby declare that this project report is an authentic record of
my own work carried at the construction of beams and columns at St benedict
technical college kisubi under the guidance of our supervisor and has never been
submitted to any institution for academic purpose.
Signature
.........................................................................................................
NTAGA MAHADI
Date
……………………………………………………………………
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
INTRODUCTION
PROJECT
This report exposes you to the construction activities carried out on the two
beams and two columns constructed at the college premise.
The dimension of the beams was 400x300mm and the column size was
300x200mm
Its objective is to construct and complete the structure and to equip the students
with practical skills.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
CHAPTER ONE:
SETTING OUT OF COLUMNS.
Tools used
String line
pegs
Claw Hammer
Builders square
Tape measure
METHODS OF SETTING OUT USED.
Under this method of setting out all measurements are based on the
centerline of the structure or walls, since we never had the architectural
drawings on site, we established the location and the position of the
columns by obtaining the center line from the already existing columns on
the project.e.g.
We determined the Centre of columns by tying the string line onto the
Centre of the existing columns apart and diagonally.
After obtaining the Centre of the columns we used a measuring tape to
offset the dimensions of the columns from those centers. Which helped us
to obtain the position of the two columns (dimensions of columns was
300x200mm)
After making the dimensions of the columns, we also demarcated the width
of the footing, depending on the nature of the soil on site we decided to
use the
1200x1200mm square pad footing
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
CHAPTER TWO:
FOUNDATION EXCAVATION FOR COLUMNS.
Tools used
Hoes
Spade
Pickaxe
wheelbarrow
We used pad foundation, after setting out the dimensions of the
foundation we stated excavation process. the depth of the foundation was
1500mm below the existing ground
1200x1200mm
1200mm
Footing area
1200mm
V=LXWXH
V=1200X1200X1500=216M3 per
foundation
The volume of soil excavated was collected in pits which was later spread as
backfill for the project.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
CHAPATER THREE:
BLINDING LAYER.
After excavation of the foundation a blinding layer was casted which
was of the mix ratio of 1:2:4 (one part of cement, two parts of fine
aggregate and four parts of coarse aggregate)
Procedure;
Purpose of blinding
To make the strata firm to receive the base of the column.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
Materials used
Cement.
Fine aggregate.
Coarse aggregate.
Water.
Transportation of concrete.
Wheelbarrows and mortar pans were used to carry the concrete
from the place of mixture to the place of casting.
Compaction of concrete.
Curing of concrete.
CHAPTER FOUR;
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
FOOTING REBAR
For the base we used y12 steel bars which were cut 1.1m and tied using
binding wires to make the base of the column as 1.1m2
To make the base of the column we arranged the cut 1.1m steel bars into a
square form each at a distance of 150mm with each steel bars bent or hook
at their both ends.
Then we also measured y12 steel bars 2m each and made one end cracked
and another end hooked then tied them in a rectangular form as per the
dimensions of the column by using y8 steel bars for links. (250mmx150mm)
and 25mm space was left on both side to cater for the concrete cover of
the column.
After the preparation of the reinforcement we again tied the string line
from the Centre of the existing columns to obtain the center of our new
columns. After obtaining the Centre then we bring our reinforcement base
place it in the trench and place the column bottom reinforcement hooked
onto the base reinforcement as per the Centre of the column obtained to
be aligned with the existing columns. We made the reinforcement firm at a
position as we tied it using steel benders to the column base reinforcement
ready to receive the formwork. Then after we casted the base allowed it
to harden to receive the bottom column formwork.
Laying of steel Rebar for the footing and main wall
Steps 1 measuring and marking the position of bottom bars for the footing
Laying of bottom 1 and bottom 2 Rebar, putting spacers, chair and laying of
top bars
Making form work.
The overlap is determined from : Overlap =50D were D is the diameter of the
bars
TOOLS USED.
Hack saw.
Steel bender.
Hammer.
Plier.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
CHAPTER FIVE;
FORMWORK FOR THE COLUMN.
This is a temporary mold prepared to receive newly casted concrete
for the column.
PROCEDURES USED.
We selected the required materials like timbers i.e.; 12 IX1I 4
I
X2I, 3I X2I and poles.
Then we marked and cut them to the required sizes.
After that we applied the releasing agent to the inner surface
of the board using burnt engine oil.
We arranged the boards by nailing them together in a
rectangular form as per the dimensions of the column
(300mmx200mm).
We assembled the boards together around the steel
reinforcement Skelton and firmly fastened it using the 100x50
and 125x50mm.
By using plumb bob and string line we achieved the vertical
and horizontal straightness of the column.
With the aid of poles, we supported the aligned formwork to
stand in place ready to receive the concrete.
TOOLS USED.
Hammer.
Tape measure.
String and pins.
Plumb bob.
Bow saw.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
CHAPTER SIX;
CASTING OF THE COLUMN CONCRETE.
PROCEDURES USED.
Method of batching.
Batching by volume
Material mixing
As for the placement the concrete was scoped in a mortar pan and
allowed to drop from the top opening of the formwork to the base
and by use of long iron bar to strike through the dropped concrete
for compaction and the same procedure is repeated until the
formwork is filled with concrete up to the required height.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
Table 2.0
Area Thickness Volume
Blinding layer 1.2x1.2m 0.05m 0.075m3
Footing 1.1x1.1m 0.15m 0.1815m3
Column 1 0.3x0.2m 3.2m 0.192m3
Column 2 0.3x0.2m 3.2m 0.192m3
Total volume 0.6405m3
Hoes.
Spades.
Wheelbarrows.
Mortar pans.
Claw hammer.
Striking rod.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
CHAPTER SEVEN:
CONSTRUCTION OF BEAMS.
PROCEDURES FOR CONSTRUCTION OF BEAMS.
Construction of a scaffold.
Claw hammer.
Hoes.
Tape measure.
Bow saw.
Materials used.
Wooden poles.
Timbers.
Nails.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
1 Claw hammer. 2. Tape measure. 3. Bow saw. 4. Hack saw. 5 Steel bender. 6.
Spirit level. 7. String line.
Procedures.
Method of batching.
Batching by volume
Material mixing
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
We used wheelbarrows and mortar pans to carry the concrete from the place of
mixture to the place of casting.
For placement, concrete was scooped into the mortar pans and given to the
person who poured it into the formwork of the beam.
This system consists of special portable units which are handed once in use easily
moved in formwork and embedded in the fresh concrete to produce a uniform
compaction.
It vibrates the concrete directly as the head of the vibrator is drawn into the
concrete and out as required for compaction.
Hoes.
Spades.
Wheelbarrows.
Mortar pans.
Pork vibrator.
Jerri cans.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
RECOMENDATIONS.
I recommend that students should take part in each of the
construction works and they should give in 100% of their time,
efforts and potentials as we mold our Engineering careers
We students should endeavor to put into practice training
instructions as given by the instructor
Students should endeavor to relate theoretical knowledge with
practical application.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
REFERENCE
• BUILDING CONSTRUCTION HAND BOOK BY ROYCHUDLEY AND
ROGER
CONCLUSION
This project was successfully done and it enabled me to gain more
skills and practical knowledge and aspects of engineering
As per the experience gained, I now know what it takes and what one
goes through during the construction work.
I thank the Almighty Allah for this great achievement as part of the
journey of molding me into an up to date civil engineer
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
APPENDICES.
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
Fixing form work for the beam fixing the soffit boards for the beam
Props and support for the beam casting of concrete for the beam
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
Center to center method footing and starter bars for the column
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
Contents
ACKNOWLEDGEMENT.................................................................................................................................2
ABSTRACT............................................................................................................................................2
Technical Challenges...............................................................................................................................2
1.2Conclusions....................................................................................................................................2
LIST OF ACRONYMS.....................................................................................................................................3
DECLARATION..............................................................................................................................................4
INTRODUCTION...........................................................................................................................................5
LOCATION OF THE PROJET...................................................................................................................5
CHAPTER ONE:.............................................................................................................................................6
SETTING OUT OF COLUMNS................................................................................................................6
CHAPTER TWO:............................................................................................................................................7
FOUNDATION EXCAVATION FOR COLUMNS............................................................................................7
CHAPATER THREE:.......................................................................................................................................8
BLINDING LAYER......................................................................................................................................8
CHAPTER FOUR..........................................................................................................................................10
COLUMN REINFORCEMENT PREPARATION...........................................................................................10
FOOTING REBAR................................................................................................................................10
CHAPTER FIVE;...........................................................................................................................................11
FORMWORK FOR THE COLUMN............................................................................................................11
PROCEDURES USED............................................................................................................................11
CHAPTER SIX;.............................................................................................................................................12
CASTING OF THE COLUMN CONCRETE..................................................................................................12
PROCEDURES USED............................................................................................................................12
CHAPTER SEVEN:.......................................................................................................................................14
CONSTRUCTION OF BEAMS...................................................................................................................14
PROCEDURES FOR CONSTRUCTION OF BEAMS.................................................................................14
FORMWORK PREPARATION FOR BEAMS...................................................................................................15
Procedures for making formwork for the beams...............................................................................15
PREPARATION OF REBAR FOR THE BEAMS................................................................................................16
Procedures for the steel reinforcement skeleton preparation..........................................................16
CASTING OF THE BEAM CONCRETE...........................................................................................................17
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
Procedures................................................................................................................................................17
TECHNICAL CHALLENGES FACED DURING THE REAL LIFE PROJECT...........................................................19
RECOMENDATIONS...................................................................................................................................19
REFERENCE................................................................................................................................................20
CONCLUSION.............................................................................................................................................20
NTAGA MAHADI—UBT194-2019-T-D-A-174
PROJECT REPORT
NTAGA MAHADI—UBT194-2019-T-D-A-174