SCC Flooding and Stormwater Management Guidelines Final v1 Signed
SCC Flooding and Stormwater Management Guidelines Final v1 Signed
Guidelines
Version 1 – September 2020
FOREWORD
THE FLOODING AND STORMWATER MANAGEMENT GUIDELINES AIM TO
SUPPORT THE CODES AND POLICIES THE SUNSHINE COAST PLANNING SCHEME
2014 BY PROVIDING ADDITIONAL DETAIL AROUND HOW STORMWATER
QUALITY, QUANTITY AND DRAINAGE AND FLOODING ISSUES ARE TO BE
MANAGED.
Document Information
Revision Author Reviewer Approval Date
Draft 0 LPR CJS CJS 20 July 2017
Draft 1 LPR CJS CJS 27 July 2017
Draft 2 CJS 8 November
2017
Draft 3 LPR CJS CJS 12 January 2018
Draft 4 CJS NJC NJC 11 April 2018
Draft 5 CJS RB/NG NJC 6 July 2018
Draft 6 CJS CJS NJC 15 April 2019
Draft 7 CJS CJS NJC 4 July 2019
Final 1 CJS Digitally signed by Crispin Smythe
DN: cn=Crispin Smythe,
o=Sunshine Coast Council, ou,
NJC 1 September
email=crispin.smythe@sunshineco
ast.qld.gov.au, c=AU
Date: 2020.10.20 12:03:00 +10'00' 2020
Disclaimer
Information contained in this document is based on
available information at the time of writing. All figures
and diagrams are indicative only and should be referred Acknowledgements
to as such. While the Sunshine Coast Regional Council Council wishes to thank all stakeholders involved in the
has exercised reasonable care in preparing this development of this document, with specific thanks to
document it does not warrant or represent that it is Tony Howard (Cardno Pty Ltd), Chris Walker (Covey
accurate or complete. Council or its officers accept no and Associates) and Andrew McPhail (Calibre
responsibility for any loss occasioned to any person Consulting)
acting or refraining from acting in reliance upon any
material contained in this document.
1 Increased rainfall intensity allowance is based on the emissions. SCC considers it prudent to adopt this
Intergovernmental Panel on Climate Change 5th Report scenario until such time as international efforts to reduce
(scenario RCP 8.5) based on current tends of CO2 CO2 emissions are effective
Issue Environment Sunshine Coast Planning Scheme 2014 Requirements Flooding and Stormwater Management
and Guidelines Content
Liveability
Strategy
Stormwater Quality and Environmental Flows – Primary Code: Stormwater Management Code (SMC) and Planning Scheme Policy for Development Works (PSPDW)
Open space Policy Position PSPDW SC6.14.3.6 specify performance standards for stormwater in parks, including: Contains design advice on achieving good integration of
integration 6.2(e), 6.3(e) stormwater into open space
• Only areas above the 5%AEP inundation level from regional and local flooding
(including stormwater treatment and detention facilities) may be considered for
credit towards LGIP trunk open space network or minimum land required for
non-trunk open space (i.e. local recreation park)
• Infrastructure (BBQ, playground) above 1 in 100 AEP
Land Dedication – Policy Position PSPDW SC6.14.3.4 (6)-(15) define requirements for reserves and easements Nil
reserves, 6.2(e)
easements, freehold Default position is reserve. Easement accepted where:
• Rural land
• Rural Residential and drains <5Ha
• Urban and drains <1Ha of non-Council land
Inter-allotment drainage in easement vested in favour of upstream property owner
Performance of Policy Position PSPDW SC6.14.3.8 Documents the certification required for products which remain in Restates PSPDW position
proprietary products 6.3(d) private ownership and the testing required to verify the performance of proprietary
and emerging products (GPTs) and emerging technologies proposed as donated infrastructure
technologies
Tailwater levels (gw, Policy Position Stormwater Management Code (SMC) PO2 requires a drainage system to be provided Provides background to adopted climate change
tidal, drainage 6.2(a) for development which considers climate change parameters and links for IFD estimation
impacts, climate
change) PSPDW SC6.14.3.3 requires drainage design to include 20% increased rainfall intensity
and 0.8m increase in sea level
Environmental Flows Policy Position SMC PO6 requires channel erosion be controlled by limiting post-development changes Provides detailed guidance on how to demonstrate
and Waterway 6.3(d)(g)(e) in flows compliance with waterway stability objective
stability
PSPDW SC6.14.3.7 provides objectives and application for waterway stability,
consistent with the SPP.
SMC PO7 and PO8 require that low-flow/frequent flow hydrology be maintained to
protect in-stream ecology
PSPDW SC6.14.3.7 notes assessment of frequent-flow hydrology will not normally be
required except in specific circumstances where derivation of site-specific objectives will
be required
Stormwater Quality Policy Position SMC PO9 and AO9.1, AO9.2 requires development achieve pollutant load reduction A number of compliance approaches are documented on
Objectives and 6.3(d)(g)(e) targets and such targets are met prior to entering a waterway/wetland buffer or a how to demonstrate compliance with the stormwater
Compliance constructed waterbody quality design objective.
PSPDW SC6.14.3.8 Quantifies the stormwater quality design objectives and provides
criteria for when such objectives apply
Stormwater Quality Policy Position No specific design details on stormwater quality treatment devices are provided Detailed design guidance is provided for a range of
Treatment Devices 6.3(d)(g)(e) technologies, including standard drawings for streetscape
bioretention devices (biopods)
Stormwater SMC PO13-PO15 provide requirement for developments which choose to incorporate Nil
Harvesting stormwater harvesting. For systems donated to Council, AO15.1 requires an over-riding
community benefit to establish the scheme and AO15.2 requires a secure on-going
funding source.
PSPDW SC6.14.3.9 reflects and restates the above requirements
Construction and Policy Position SMC PO16 AO6.1 and AO6.2 requires construction methods in accordance with Nil
establishment 6.3(d)(g) PSPDW and timing of construction to minimise risks
SMC PO17 requires vegetated systems be established during the maintenance period
PSPDW SC6.14.11 contains specifications for construction tolerances, testing,
inspections and certifications which covers WSUD infrastructure
Constructed Policy Position SMC PO18-PO22 have specific requirements for constructed waterbodies, which Nil
waterbodies 6.2(b) include:
• That new waterbodies are avoided
• That waterbodies achieve EVs and WQOs
• That waterbodies have secure on-going funding sources
• That they are not used as stormwater treatment devices
• That they provide multiple benefits and do not pose healthy, safety or
aesthetic risks
PSPDW SC6.14.9 comprehensively addresses the requirements for constructed
waterbodies
Reporting Policy Position Nil Reporting template for stormwater management plans
requirements for 6.2(c) provided as Appendix 1
Stormwater
Management Plans
Off-site Solutions Policy Position Nil Off-site solutions are identified as a possible compliance
6.3(d) approach through infrastructure agreements, however
Council does not currently support Council delivered off-
site solutions.
Stormwater Quantity and Drainage – Primary Code: Stormwater Management Code (SMC) and Planning Scheme Policy for Development Works (PSPDW)
Vegetated channel Policy Position SMC PO3 and AO3.1-3.3 mandate use of natural channel design which supports Further discussion on the common problems of vegetated
design details 6.2(a)(b), landscape, passive rec and ecological functions channels plus design approaches and planting palettes
6.3(e)(f)(g) are provided
SMC PO4 requires stormwater infrastructure to be designed to minimise maintenance
costs
PSPDW SC6.14.3.3 contain requirements for open channels, which include:
• Must comply with BCC Natural Channel Design Guidelines
• Channel works/rehabilitation not to be included in stormwater quality load
reduction calculations
• Designed with min ‘n’ of 0.15 with sensitivity +/- 50% to check for freeboard
and scour effects
• Requirements for safety and maintenance berms
Lawful Point of Policy Position Stormwater Management Code (SMC) PO2 and AO2.1 require LPoD to be met. Contains a comprehensive discussion on the background
Discharge (LPoD) 6.1(b) of the 2-point test relating to Lawful Point of Discharge as
PSPDW SC6.14.3.4 defines requirements for LPoD. well as checklists and requirements for addressing each
point
Detention – when Policy Position PSPDW SC6.14.3.5 Table SC6.14.3B contains criteria for when peak flow management
required 6.1(b) objectives are triggered.
Detention – Policy Position PSPDW SC6.14.3.5 contains design requirements for detention basins Provides further advice on detention for in-fill situations
implementation 6.2(a)(b)(e) and preferred arrangements when open detention basins
(ownership, form, not feasible
integration with
WSUD)
Drainage Design Policy Position Stormwater Management Code (SMC) PO2 requires a drainage system to be provided Includes advice on determining design rainfall intensities
6.1(a)(b), for development which considers climate change and achieves LPOD and additional advice on design of vegetated channels
6.2(a)(b)(e)
PSPDW SC6.14.3.3 covers drainage design requirements in detail.
Flooding – Primary Code: Flood Hazard Overlay Code (FHOC) and Planning Scheme Policy for Flood Hazard Overlay Code (PSP FHOC)
Loss of Flood Policy Position FHOC Table 8.2.7.3.1 PO4 and AO4.1 requires that any filling for accepted development Additional discussion is provided on the circumstances
Storage – 6.3(a)(b)(c) within the flood and inundation area does not result in net filling on the site when preservation of floodplain storage is or is not
specifically infill required. Requirements for how to calculate flood storage
FHOC Table 8.2.7.3.2 PO2 requires that physical alteration of land within the flood and are also provided.
inundation area does not occur except in specific circumstances.
PO9 and AO9.1 requires that any filling for assessable development within the flood and
inundation area is offset by providing compensatory flood storage within the site.
Acceptable or Policy Position SPP2017 Assessment benchmark (3) of the State Interest for Natural Hazards, Risk and Includes detailed guidance for determining whether risk to
Tolerable risk to 6.1(b) Resilience requires that development mitigates risk to people and property to an people and p[property should be deemed acceptable or
people or property acceptable or tolerable level. This State Interest is not currently fully reflected in the tolerable for a range of AEPs.
Planning Scheme so the SPP2017 becomes the assessment benchmark.
Acceptable or Policy Position FHOC PO9 and AO9 – require no offsite changes based on current climate and future Includes detailed guidance for determining whether
Tolerable levels of 6.1(b) climate at 2100 changes caused off-site are either acceptable or
impacts tolerable. Requirements include analysing impacts for a
range of AEP based on current climate and only the
1%AEP for future climate
Addressing Residual Policy Position SPP2017 Assessment benchmark (3) of the State Interest for Natural Hazards, Risk and Includes discussion on the practical implementation of
Flood Risk 6.1(a), 6.3(c) Resilience requires that development mitigates risk to people and property to an these requirements and the implications for development
acceptable or tolerable level. This State Interest is not currently fully reflected in the design.
Planning Scheme so the SPP2017 becomes the assessment benchmark.
In addition to the above, FHOC Table 8.2.7.3.2 PO4 requires residual flood risk (up to
the PMF or PMST) to be addressed. A range of requirements are provided through the
acceptable measures including provision of either feasible evacuation or refuge
strategies.
Flood Immunity Policy Position FHOC Table 8.2.7.3.1 PO1 and PO2 set flood immunity levels for floor levels and car Nil
Requirements 6.1(a) parking respectively for dual occupancy and dwelling house
FHOC Table 8.2.7.3.2 PO3, PO6, PO7 and PO8 specify flood immunity requirements for
assessable development for development, essential network infrastructure, essential
community infrastructure, and hazardous materials respectively
Levees Policy Position PSP FHOC prohibits use of levees for achievement of flood immunity standards Nil
6.1(a)
Climate Change Policy Position PSP FHOC – requires 0.8m sea level rise. Design rainfall intensities required to be These requirements are restated in the guidelines
6.2(a) increased by 20%
Technical modelling Policy Position Nil The guidelines contain requirements for:
requirements 6.2(c)
• Hydrology model: software, sub-catchment
delineation, assumptions
• Hydraulics model: software, steady/unsteady,
1D/2D, roughness
• Calibration/validation
• Temporal patterns
• Design loss rates
• Design rainfall
• Climate change parameters
• Boundary Conditions – joint probabilities
• Sensitivity analysis
Flood Impact Policy Position Nil The guideline contains a template for flood hazard
Reporting 6.2(c) assessment report and flood hazard mitigation report
Requirements
The land development industry is also a key 3.1.3 Construction, Establishment and
part of the Sunshine Coast economy and it is Handover
vital that land development occurs in ways
which are sustainable and which preserve the The construction, establishment and handover
quality of our waterways. of water sensitive urban design treatment
measures is to be undertaken in accordance
The following sections support the codes and with the latest version of the following:-
policies specified in the Sunshine Coast
Planning Scheme 2014, by providing • Construction and Establishment
additional guidance on key issues relating to Guidelines: Swales, Bioretention Systems
stormwater quality management. In addition, and Wetlands (Water by Design, 2010)
Appendix 1 contains a reporting template for • Maintaining Vegetated Stormwater Assets
the preparation of Stormwater Management (Water by Design, 2012)
plans (SWMP) to support development
• Transferring Ownership of Vegetated
applications.
Assets (Water by Design, 2012)
• Provided with concrete base and concrete • the GPT is located in an accessible
maintenance access location (not in swampy areas, at the
bottom of embankments or other
3.4.6 Infiltration systems inaccessible locations);
Generally, infiltration systems are used where • the GPT is not located near electrical
stormwater discharge is to a natural system equipment or where a voltaic cell can
and groundwater recharge and maintaining occur;
pre-development runoff volume is required. • the GPT can be fitted with a suitably
Stormwater quality design objectives shall be designed lockable access cover approved
achieved prior to stormwater entering an by Council that prevent entry of
infiltration device. An exception to this are unauthorised persons;
source controls which replace impervious
areas (such as porous pavements). • re-suspension of captured pollutants
during flows in excess of the SQID design
event is prevented;
2
Tidal waters under this exemption are to have minimum
dimensions of more that 1m depth and cross sectional area
2.5m2
1) Determine pre and post-development peak 1 in 100 AEP inflows for model validation as per A Review of
Simple Peak Flow Estimation Methods for use on the Sunshine Coast following the release of ARR 2016
(SCC, 2018a)
2) Develop a hydrologic model with appropriate sensitivities to urbanisation, as informed by estimates from
Step 1.
3) Determine pre-development inflows from the hydrologic model, using ensemble temporal patterns with
pre-burst rainfall and ARR Datahub Initial Loss and Continuing Losses. This is to be done for the range of
a. Durations: 0.167, 0.25, 0.5, 0.75,1,1.5.2,3,4.5,6,9,12,18,24
b. AEPs: 63%, 39%, 18%, 10%, 5%, 2, 1%.
For each AEP and duration combination calculate the average (or rank 6) peak flow across all 10
ensembles. Prepare a critical duration analysis table of AEP vs duration.
4) Create a Post Development version of the hydrologic model and repeat the ensemble analysis returning
peak discharges but limiting the maximum duration to twice the critical duration of pre-development
inflows, or 3hrs (whichever is the greater). Prepare a critical duration analysis table, similar to Step 3, from
the average of the ensemble peak discharge results for each AEP/duration combination.
In the example shown in Table 3 the critical duration of pre-development inflows is 4.5hrs, thus the post
development situation is limited to 9hrs (as shown in Table 4).
Table 4 Example of Post-Development Peak Inflows Critical Duration Analysis Results
Duration
ARI 0.167 0.25 0.5 0.8 1 1.5 2 3 4.5 6 9
1 0 0 1.22 1.45 1.72 2.25 1.71 2.12 2.04 1.61 1.53
2 0 1.19 2.46 2.13 2.38 2.86 2.26 2.8 2.94 2.12 2.06
5 2.59 3.53 4.31 3.66 3.82 3.85 3.22 3.71 3.98 2.97 2.92
10 4.73 4.67 4.96 4.53 4.2 3.82 4.32 4.42 5.03 3.92 3.72
20 6.06 5.75 6.16 5.34 5.03 4.7 5.11 5.25 5.95 4.69 4.48
50 6.98 7.02 7.14 6.63 5.6 5.56 5.21 8.28 5.77 5.83 4.93
100 7.7 7.71 7.95 7.45 6.3 6.32 5.94 9.5 6.64 6.73 5.69
6) Set up outlets.
It is suggested that outlets be sized to convey all flows up to and including the 1 in 100 AEP, and that the
spillway is designed for larger events.
The hydrologic model must adopt hydraulic formulas that appropriately consider whether small or large
orifice equations apply. In addition the modeller must consider the likelihood of the orifice being outlet
controlled by an elevated downstream water level.
It is suggested that the level between the invert of the lowest outlet and the spillway be divided equally
into three and that stage outlets are initially sized for the first stage to take the 63% (1yr ARI) pre
development peak flow, the second stage to take the 10% AEP pre development peak flow and the third
stage to take the 1 in 100 AEP pre development peak flow.
This should serve to create a Storage vs Discharge rating that approximates a linear relationship, as seen
in the example of Figure 11.
7) Rerun the hydrologic model ensemble analysis for the post-development scenario, returning peak
discharges from the detention basin, for the same durations and AEPs as Step 3.
Prepare a critical duration analysis table, similar to Step 3 from the average of the ensemble peak
8) Subtract the table of results from step 6 from the table of results from step 3.
9) Check to ensure that differences are acceptable.
Acceptable differences are:
a. <= than 2% of the pre-development flow for the same duration-AEP event, OR
b. <= or 0.5% of the 1 in 100 AEP pre-development peak inflow, OR
c. <= 0.01 m3/s.
10) Repeat steps 8 and 9 to optimise the orifice settings and storage size.
Failure Impact Assessment 2100) drainage flood level. In addition the floor
level must be above flood levels from the
As detention basins are effectively dams. The following sensitivity analyses:
Statutory requirements of the Water Supply
(Safety and Reliability Act) 2008 apply. Where • A Severe Storm that is the defined flood
it is considered that the failure of a detention event with 100% structure blockages.
basin may have a population at risk of 2 or • A Severe Storm that is the 1 in 2000 AEP
more persons, a failure impact assessment of event.
the detention basin is required to determine
the downstream impact of a failure of the • The defined flood event with roughness
asset that releases the full volume over a values reflective of unmaintained
period of 30 minutes. The requirement for the channels/site areas.
failure impact assessment is purely based on
population at risk and not height or volume of
4.4 Waterway Stability
the detention basin. The waterway stability objective is defined in
the Planning Scheme Policy for Development
Where a failure impact assessment confirms a
Works as limiting the post-development peak
PAR of 2 or more persons the design will not
63% AEP event discharge within the receiving
be accepted by Council. The applicant will be
waterway to the pre-development peak 63%
able to resubmit once they have consulted
AEP discharge, and is only applicable when
with the regulator of the Water Supply (Safety
runoff from the site passes through or drains
and Reliability Act) 2008 and the construction
to natural channels, non-tidal waterways or
standard for failure immunity has been
wetlands
determined.
As it is the flow within the receiving waterway
Advice from the regulator indicates that the
that is the critical consideration, this objective
minimum design standard required for failure
should not be applied when the development
immunity is a 1 in 2000 AEP, but the specifics
site is only a small portion (<5%) of the
of a given situation may require a higher
catchment and there is limited potential for
standard.
further development within the catchment.
For basins with a population at risk of less
Compliance with the objective is
than 2 the design failure immunity shall be
demonstrated through hydrologic calculations,
based upon the severe storm.
with the level of complexity appropriate to the
4.3.3 Freeboard Requirements catchment context and scale of development.
The following compliance methodology has
The floor levels of buildings or lots adjacent to been adapted from the Gold Coast City
detention storages should be set at least Council Planning Scheme (2016) and Healthy
300mm above the calculated 1 in 100 AEP (at Waterways (2006).
A B1 B2
Method A – A simple method which can be used when runoff-routing modelling is not
required for the development for any other purpose
Deemed to Comply
Calculation of 1) Calculate the desired peak outflow (Qo) for the 1 year ARI (63%AEP)
detention storage to storm event at the boundary of the site using the Sunshine Coast
manage peak 1yr ARI Rational Method calculated as per A Review of Simple Peak Flow
flow at boundary of Estimation Methods for use on the Sunshine Coast following the
site release of ARR 2016 (SCC, 2018a). For this calculation the
predevelopment form of the equation is to be use a sheet flow method
with a surface type of Densely Grassed (unless otherwise agreed).
This ensures the storage is sized to restore 1 year flows to rural or
forested conditions.
2) Determine required detention storage volume from the following
equation (derived from Healthy Waterways, 2006)
Storage Volume (m3/ha) = 152 + 0.83 x fi
Where fi = fraction impervious (%)
3) Size detention storage outlet to restrict discharge from the detention
basin to the desired peak outflow (Qo) using the small orifice equation.
Otherwise other standard calculations for outlet may be used.
Qo = C.A (2.g.h)0.5
C = 0.6 (orifice discharge coefficient)
A = orifice area (m2)
g = 9.81m2/s (gravity)
h = hydraulic head above centroid of orifice (m), or the downstream tail
water level, whichever is greater.
Note: For the small orifice equation to be accurate the ratio of h (m) to orifice
diameter (m) should be greater than 2 otherwise hydraulic equations relevant to
flow through a large orifice should be used.
Figure 12 Poor Open Channel –Ponding, odour, weed incursion, unable to be maintained (source: Switchback
Consulting)
The primary technical resources for the 5.2.2 Safe Refuge from Flooding
hydrologic and hydraulic aspects of flood
A safe refuge from flooding is to have a floor
investigations and flood hazard assessments
level immunity from the Probable Maximum
are noted below and are to be followed unless
Flood or the Probable Maximum Precipitation
superseding requirements are noted in this
Design Flood. It must also be designed to
guideline or the Planning Scheme:
withstand the hydrostatic forces of the flood
• Australian Rainfall and Runoff: A Guide to adopted for the specification of floor level
Flood Estimation (Commonwealth of immunity.
Australia, 2019)
In addition, a building that is to be designed
• Application of Design Temporal Patterns for the purposes of a safe refuge in a flood
on the Sunshine Coast (SCC, 2018b). event, where the duration of refuge is 18
Where the assessment involves an urban hours or greater is to satisfy Council’s
drainage system the above resource may be requirements for a tier 1 evacuation centre.
supplemented by the following: Preferred Sheltering Practises for Emergency
Sheltering in Australia (Red Cross, 2015)
• Queensland Urban Drainage Manual V4 provides details of the standards for such a
(IPWEAQ, 2019) facility.
Flood Depth-
Hazard Velocity Depth Velocity
Category Description Limit Limit Limit
H1 Generally safe for vehicles, people and buildings ≤ 0.3 m2/s ≤ 0.3 m ≤ 2.0 m/s
H2 Unsafe for small vehicles. ≤ 0.6 m /s2
≤ 0.5 m ≤ 2.0 m/s
H3 Unsafe for vehicles, children and the elderly ≤ 0.6 m2/s ≤ 1.2 m ≤ 2.0 m/s
H4 Unsafe for vehicles and people. ≤ 1.0 m /s2
≤ 2.0 m ≤ 2.0 m/s
Unsafe for vehicles and people. All building types
H5 vulnerable to structural damage ≤ 4.0 m2/s ≤ 4.0 m ≤ 4.0 m/s
Unsafe for vehicles and people. All building types
H6 considered vulnerable to failure > 4.0 m2/s > 4.0 m > 4.0 m/s
1 in 2000 AEP
1 in 100 AEP
10% AEP
Acceptable Risk
Unacceptable Risk
In addition to the above quantitative risk residual flood risk) through either refuge
assessment approach, the Flood Hazard or evacuation strategies.
Overlay Code provides a number of These requirements can often be achieved
prescriptive outcomes to manage risk by: through filling and/or built-form design, with
• Specifying minimum lot, floor and the Council publication titled Guidelines for
infrastructure levels for different Improving Flood Resilience for New
development categories based on a Development (SCC, 2016) providing
nominated DFE; and examples of how flood risk can be addressed
for common categories of development.
• Requiring that safety is addressed for
events which exceed the DFE (the
Red Cross Australia. (2015) Preferred Sheltering Water by Design. (2014b). Water Sensitive
Practises for Emergency Sheltering in Australia Designs
Stormwater Australia (2018) Stormwater Quality Water by Design. (2017) Wetland Technical
Improvement Device Evaluation Protocol, Field Design Guidelines
Monitoring (v1.3)
1 Introduction
Include the sites address, real property description, type of application and a description of the
proposed development including a figure. Any previous reports, approvals or strategies and their
relevance should be noted and discussed.
2 Existing Conditions
A description and accompanying figure is to be provided illustrating the existing site topography,
drainage patterns and discharge points from the site, external catchments, and vegetation.
The broader context of the catchment including downstream receiving environments and extent of
current and future development should also be discussed, as should whether lawful point of
discharge currently exists.
3 Design Objectives
A review of the Planning Scheme Design Objectives as well as a review of any State or National
requirements is to be undertaken. A summary of the objectives and the point at which they are to
be achieved is to be provided. Objectives to be discussed include:
• Stormwater quality design objectives
• Waterway stability design objectives
• Stormwater quantity objectives for lawful point of discharge (eg. Peak flow management)
• Whether frequent flow objectives are required and their derivation
4 Stormwater Strategy
Describe the opportunities and constraints and the selected strategies for achieving compliance
with each of the design objectives. This is to include a plan or series of plans which shows that the
spatial and level constraints/requirements associated with each strategy element has been catered
for in the development layout and clearly identifying proposed site catchments and release points.
5. Stormwater Quality
The compliance methodology selected (i.e. on-site (MUSIC modelling or Complying Solutions),
reduced imperviousness) is to be noted and supporting assumptions and calculations
demonstrating compliance provided.
The concept design parameters adopted are to be summarised and additional plans may be
necessary to show how the devices fit spatially within the development layout. This is particularly
relevant for streetscape solutions where a level of detail commensurate with preliminary
engineering/OPW design will be required.
6. Stormwater Quantity
This section includes both flow mitigation required to meet the waterway stability objective and any
mitigation required to achieve no actionable nuisance downstream of the site.
8. Conclusion
Summarise strategy and any key issues for detailed design
References
Include all references used in the report
Appendices
Include supporting calculations or figures include preliminary engineering plans or earthworks
designs
RPEQ Certification
The certifying RPEQ must sign a statement of certification, which is to be included inside the front
cover of the report.
The statement of certification must take the following form, with details for any statements
answered ‘No’ to be provided on a separate sheet at the end of the certification:
Mechanisms of Flooding Y N
This flood assessment has considered whether the following mechanisms of flooding
are relevant to the site.
• Flooding from a regional catchment
• Flooding from a local area catchment
• Flooding from a storm tide event
Flood mapping and impact mapping has been included in this report for all relevant
flood mechanisms.
The flood assessment has specifically included boundary conditions that represent
backflow flooding of the local stormwater network from a regional event.
Methodology
Flood Analyses
Flood modelling has been completed for a base case and developed case, for the
63%AEP (Q1), 39% AEP (Q2), 10% AEP, 1 in 100 AEP, 1 in 2000 AEP and the PMF
current climate and 1 in 100 AEP future climate (at 2100) flood events.
Flood mapping has been produced and included in this report for the following
parameters, water surface level, depth, velocity and hazard.
Flood level hydrographs are produced at relevant locations to demonstrate that
nuisance changes to inundation times are not created and that maximum inundation
times for roads are not exceeded.
This information has been used to demonstrate that this development design
produces acceptable flood impacts in accordance with default tolerances prescribed
in the SCC Flooding and Stormwater Management Guidelines (2020)
Afflux mapping has been produced for the 63%AEP (Q1), 39% AEP (Q2), 10% AEP
and 1 in 100 AEP current climate flood events and the 1%AEP future climate (2100)
event. This information has been used to demonstrate that this development design
produces acceptable flood impacts in accordance with default tolerances prescribed
in the SCC Flooding and Stormwater Management Guidelines (2020)
Pad levels for essential network infrastructure within a site (e.g. electricity, water
supply, sewerage and telecommunications) have been specified in this report, in
accordance with the flood immunity requirements of Table 8.2.7.3.3 of the Sunshine
Coast Planning Scheme Flood Overlay Code.
Where the development design has a need for materials with high water resistance to
improve the flood resilience of infrastructure, details of the specific requirements
have been provided in this report.
The development design provides flood immunity to the DFE for the protection of
property. Pad levels and Floor levels have been specified for each lot as part of the
lot table information, with consideration of the freeboard requirements that vary
depending on the mechanism of flooding.
Where the development design has a need for unenclosed car parks, the level of the
carpark has been specified such that it provides:
• flood immunity for the 10% AEP,
• a flood depth no greater than 250mm in the 1 in 100 AEP to 250mm, and
• a velocity no greater than 2.0m/s, and
• a depth x velocity ratio no greater than 0.4m2/s;
Where basements form part of the development design, the report has specified the
provision of waterproofed perimeter walls, air vents and has specified the level of
entry/exit ramps on the basis that are at least above the 1%AEP flood level plus
freeboard (at 2100);
Where the development design incorporates lots requiring driveways with a downhill
slope; For each relevant lot, the need for a raised entry ramp from the roadway (to
satisfy the requirements of QUDM (IPWEA, 2016) for containment of flood flows) has
been noted in the comments field (Column 14) of the lot table information.
It has been demonstrated, using the methodology prescribed in the Sunshine Coast
Council Flooding and Stormwater Management Guidelines, that the development
design provides acceptable flood risk.
The development design has provided for residual flood risk beyond the DFE, for the
protection of life.
For events other than storm tide, the development design does not rely on
evacuation routes to offsite locations that are shown to be flood affected in DFE
mapping. This requirement is for the purpose of managing the residual flood risk
beyond the DFE for the protection of life.
The development design ensures that public safety and the environment are not
adversely affected by the detrimental impacts of floodwater on hazardous materials
manufactured or stored in bulk during the DFE or DSTE;
Where the development design included a detention basin, the population at risk
downstream has been determined and documented. A failure impact assessment
has been completed when the population at risk is 2 persons or more.
1 Introduction
The introduction should give an overview of the proposed development application and any
relevant background information. The scope of studies presented in the report should also be
outlined. It may be appropriate to include a locality plan showing the location of the proposed
development site.
2 Available data
Provide a summary of the sources of data used for the investigation. An appropriate way to
present this information may be in tabular form, an example of which is shown below.
At the commencement of any hydrologic investigation, applicants are encouraged to contact
Council’s Customer Service Centre to determine whether Council holds existing information that
may be of relevance. Applicants should be aware of Council’s “Hydrologic Data Policy” which
applies to any hydrologic information provided by Council. This includes extractions from regional
flood models. Please note that fees apply.
The applicant should also contact Council’s Customer Service Centre to determine whether
historical flood levels are available in the area of interest. Council records such levels along
waterways after major flood events and has a regional network of maximum height gauges. This
data may be useful in the calibration of hydraulic models.
Example:
Table 1 Source data
Historical flood levels SCRC Advanced Flood Peak flood levels for 1989
Search Certificate No:12345 flood event
4 Previous studies
A number of flood investigations have been undertaken of waterways draining the Region. The
applicant should contact Council’s Customer Service Centre to determine if previous flood
investigations have been undertaken in the vicinity of the proposed development. Applicants
should be aware of Council’s “Hydrologic Data Policy” which applies to any hydrologic information
provided by Council. This policy requires applicants to make their own assessment of the
applicability of existing studies.
5 Model setup
Hydrology
Applicants should undertake hydrologic modelling using industry-accepted software. Council is
unable to recommend any particular software, however, checking of results will be expedited if
applicants use software currently employed by Council. Details of Council’s current hydrologic
modelling software may be obtained through the Customer Service Centre.
The following should be documented:
• Model software - Details of the adopted model software should be documented in this section,
including software version number.
• Model setup - Describes detail of the model setup undertaken for the existing and post-
development catchment conditions
• Subcatchment delineation - Provide a plan showing the configuration of the model, in particular
the extent of sub-catchments and the location of the proposed development. Discharges at
locations of interest should not be obtained from the output at a single sub-catchment. Where
distinct areas of different land use occur within a catchment, the catchment sub-division should
reflect land use boundaries wherever possible.
• Summary details of the model, such as sub-catchment areas, fraction imperviousness,
catchment lag and routing parameters, should be presented in tabular form, in sufficient detail
that a model could be developed from the supplied data.
6 Calibration
This section is to detail the calibration of the hydrologic and hydraulic models. The method of
calibration is to be stated and justified based on the availability of existing Council model results,
recorded historic flows and/or levels or use of flood frequency analysis.
Commentary should be provided on the quality of the calibration and the confidence in the
calibrated model for design flood estimation. The quality of the calibration should be informed by
some form of goodness of fit qualification, between modelled and observed flood data.
Existing catchment
Provide mapping for the pre-development catchment condition of WSL, depth, velocity and hazard
(using the methodology of the Floodplain Management Guidelines of Australia). This mapping
should be provided for the following events: 63%AEP (Q1), 39% AEP (Q2), 10% AEP, 1 in 100
AEP, 1 in 2000 AEP and the PMF for current climate and 1%AEP future climate (2100).
Developed catchment
Provide mapping for the developed catchment condition of WSL, depth, velocity and hazard (using
the methodology of the Floodplain Management Guidelines of Australia). This mapping should be
provided for the following events: 63%AEP (Q1), 39% AEP (Q2), 10% AEP, 1 in 100 AEP, 1in
2000 AEP and the PMF for current climate and 1 in 100 AEP future climate (2100).
9 Sensitivity Testing
Document the results of all sensitivity testing relating to both design WSL and impact assessments
At a minimum, sensitivity analyses that inform floor levels shall consider
Regional Catchment Flooding
• 1 in 500 AEP Design Flood Event (Severe Storm)
12 References
Provide a list of documents referred to in the study. Where a reference document is not widely
available a copy of the document or the relevant section should be included as an Appendix.
Flow B
Side entry pit
Kerb & Channel Kerb & Channel
Hand formed inlet chute
0
20
0
0
Planted Batter
10
500
R
Planted Batter
Non-slotted uPVC drain
500x500 Forebay with
50mm slots (one per side)
Turf
ALL DRAWINGS TO BE PRINTED IN COLOUR!
200
Concrete
mowing edge
C C
Slotted UPVC subsoil drain B
Planted batter 1 in 3
slope (sized to suit
location)
RP Boundary / Footpath
A
PLAN
N.T.S.
N.T.S.
0
R1
0
precluded.
10
000
R
Planted Batter
Side drains under kerb and
channel to connect to inlet
pit separately to bioretention
1000x500 underdrainage
Forebay with Turf
50mm slots
Slotted UPVC subsoil drain
200 Concrete
mowing edge
ALL DRAWINGS TO BE PRINTED IN COLOUR!
C C
Slotted UPVC subsoil drain
RP Boundary/Footpath
PLAN
N.T.S.
Clean out point. Clean outs at head of subsoil Inlet Chute Filter media surface Pit crest set 50mm
drain, max. spacing 30m. C.I. Cap extended set 200mm below kerb below kerb invert at
Energy Dissipator invert at turn-out turn-out
50mm above basin surface with locking provision
1 in 3
3 1 in
200
Standard
Non-slotted 900x900
Ø100 PVC Field Inlet.
Non-woven geotextile glued to
Provide End Cap at Refer perimeter of pit. Extends 100mm
head of subsoil drain IPWEA Std above filter media, 100mm below
Dwg media and laterally 300mm min
DS-050
SECTION C-C
N.T.S.
1000mm min
(usually larger to
2000mm min (larger at inlet but may
achieve max 1 in 2
reduce to 2000mm min at upstream
batter)
Batter stabilised with dense planting 1000mm extent of device) RP/Footpath
using species suitable for planting next Coarse sediment
to road pavement forebay, base min
Batter stabilised with 50mm proud of filter
dense planting media
Kerb alignment
50mm x 50mm lip with Kerb and channel
2 50mm drainage gap
Gra 1 in (1 per side)
de v
arie
s Non-woven Geotextile filter Pavement
cloth keyed into batter and
Compacted pinned 300mm min
fill
Filter media 700mm depth to allow tree 150 thick concrete, SL62 reinforcing, 50 top
planting unless depth constrained cover. 1:4 max. Geotechnical engineer to
150mm mass
concrete base confirm compaction requirements
100mm Transition layer
course sand size 0.5-2.0mm
Lay filter cloth and/or impermeable
200mm Drainage layer. liner over insitu soil 300 min. Pin
Fine aggregate 2-5mm filter cloth to insitu soil and lay
concrete onto cloth
Slotted uPVC subsoil drains
Ø100mm (min) 50mm cover of
drainage layer
W
Legend
Stormwater
S
E
W
Pavement fall
S
E
W
Major flow direction
Gully pit
S
E
W
Water W W
S
E
Sewer S S
W
Electrical E E
S
E
W
Landscape Batter
Type 1 biopod 4m 6m 5m
3m width desirable
2m min
S
E
Biopod
W
ALL DRAWINGS TO BE PRINTED IN COLOUR!
S
E
W
Note:
Additional verge widening
S
E
W
may be required to
maintain maximum 1 in 2 Biopod ~60m² -
max catchment
S
E
W
batter to RP boundary.
~0.6Ha
0 to 0.9m
1m min.
S
E
W
E E E E E E E E E E E E E E E E E E E E E E E E E E E E E
S
E
W
S
E
5m typ
S
E
W
S
E
1m maintenance strip
as per standard detail
6m
S
E
W
S
E
S S S S S S S S S S S S S S S S S S S S S S S
4m
W W W W W W W W W W W W W W W W W W W W W W W
S
E
W
S
E
long-axis to biopod to
avoid need for electrical
S
E
conduit crossing of
biopod to service lots
S
E
W
S
E
W
S
E
W
Legend
S
E
W
Stormwater
Pavement fall
S
E
W
Major flow direction
S
E
W
Gully pit
Water W W
S
E
W
Sewer S S
Electrical E E
S
E
W
4.30m 6.00m 5.00m
Landscape Batter
S
E
W
Biopod
S
E
W
ALL DRAWINGS TO BE PRINTED IN COLOUR!
Type 1 biopod
3m width desirable
S
E
W
Note:
2m min
Additional verge widening may be
required to maintain maximum 1 in 2
S
E
W
batter to RP boundary.
Biopod ~60m² -
S
E
W
max catchment
~0.6Ha
1mmin.
1m
S
E
3m
0 to 900mm
S
E
E E E E E E E E E E E E E E E E W E E E E E E
E E E E E E
S
E
4.25m
S
E
W
S
E
1m maintenance strip
W
15.3m
(1m from top of kerb)
S
E
5.50m
S
E
S S S S S S S S S S S S S S S S S S S S S S S
S
E
W W W W W W W W W W W W W W W W W W W W W W W
4.25m
S
E
W
S
E
W
S
E
W
S
E
W
E
Legend
Stormwater
W
E
Pavement fall
W
E
Major flow direction
W
Gully pit
E
Water W W
W
E
Sewer S S 4.00m 6.00m 5.30m
Electrical E E
W
E
Landscape Batter
Type 1 biopod S E
W
Biopod 3m width desirable
S E
2m min
W
Local widening of road
ALL DRAWINGS TO BE PRINTED IN COLOUR!
reserve to accommodate
W
min biopod width of 1.5m
1m maintenance strip
Additional widening may
E
W
treatment requirements
E
or to maintain max.
W
batter 1:2 to RP
0.50m
E
boundary
W
W W W W W W W W W W W W W W W
E
W W W W W W W W
5400
E
4.00m
W
E
W
Type 2 biopod
E
6.00m
E
18.60m
W
2m
E
W
E
5.30m
S S S S S S S S
E
7.20m
S
E E E E E E E E Field inlet dome grate
W
E E E E E E E E E E E E E E E E E E E E E E
W
1.00m
E
1.80m
back of kerb
E
1.00m
W
S E
W
S
required if shared
W
S
path
W
E
Stormwater
W
Pavement fall
E
Major flow direction
W
E
Gully pit
W
Water W W
E
4.00m 6.00m 5.30m
Sewer S S
W
Electrical E E E
Landscape Batter S E
W
Local widening of
road reserve to S E
Biopod
accommodate min
W
biopod width of 1.5m
E
S
ALL DRAWINGS TO BE PRINTED IN COLOUR!
Additional widening
W
may be necessary 1m maintenance strip
E
W
requirements or to
maintain max. batter
E
1:2 to RP boundary
0.50m
E
W
W W W W W W W W W W W W W W W
E
W W W W W W
5.40m
E
4.25m
W
E
W Type 2 biopod
E
5.50m
E
17.50m
S
2m
E
W
E
S S S S S S
4.25m
S
W
E E E E E E
6.35m
S
E
E
S S S S S S S S S S S S S S S S S S S S S
E
Field inlet dome grate
W
W
E
1.20m
1m maintenance strip
W
1.00m
E
S
W
W
S
E
W
S
E
W
S
Concrete
Road Surface
Landscape Batter
Stormwater System
ALL DRAWINGS TO BE PRINTED IN COLOUR!
Property Boundary
With M5 Kerb and
Channel Profile. Inverts
of the Kerb Adapter and
Channel are to Match
Sand or Screenings
Surround
270
270
1. Site Location
A plan should be provided showing the location of the asset, including the nearest street
intersection and the name of any park or reserve in which the asset is located
2. Functional Description
This section should include a brief description of the purpose and key design features of the asset
and may include a schematic drawing showing the functional components. The full design
drawings should be referenced and provided as an appendix to the report.
3. Maintenance Access
A plan is to be provided of the asset showing access to the asset from the nearest road and
around/within the device. The Planning Scheme Policy for Development Works identifies minimum
maintenance access requirements for different types of vegetated stormwater assets.
The plan is to identify the width and surface type (e.g. concrete, gravel, turf, etc.) of each access
as well as the location of any access restrictions such as gates or removable bollards.
This reporting template should be considered in conjunction with this guideline as well as the
Flood hazard overlay code and associated planning scheme policy.
Provision of a Flood Emergency Management Plan may be an alternative solution for
demonstrating that an acceptable level of flood risk is achieved to ensure the safety of people in
all flood events as required by the Flood Hazard Overlay Code. It will not be acceptable to Council
as an alternative to achieving the minimum levels for property and infrastructure specified by the
Code and will only be considered as an alternative solution for safety where:
• The use does not involve permanent residential aspects; and
• The flooding characteristics are not flash flooding (defined as having a time to peak of less
than 6 hours)
The completed Flood Emergency Management Plan is required to be registered with Council’s
Disaster Management Team.
Further guidance on developing evacuation plans can be obtained from Evacuation Planning
(AIDR, 2017a).
Document details and certification
Details of the authorship of the Flood Emergency Management Plan should be provided and must
be prepared by someone having not less than 5 years’ experience in disaster management.
All flood modelling used to inform the plan must be undertaken and certified by an RPEQ with
experience in Flood Modelling and Management.
Note: It is a requirement of the Act that professional engineering services in Queensland are
carried out by a RPEQ, or alternatively by a person who carries out the services under the direct
supervision of a RPEQ who is ultimately responsible.
Example:
Report Title: Flood Emergency Management Plan for Proposed
Maroochy Woods Development, Maroochy Road,
Maroochydore
Street Address 15-35 Maroochy Rd, Maroochydore
RP Description Lots 1,2 & 7 on RP 123456
Prepared For: Maroochy Development Company Pty Ltd
Date: 7 Sept 2016
Revision No. 3
Report Status: Draft/Final
Prepared By:
Name Bob Jones
Qualifications BE
Company Water Consultants Pty Ltd
Phone No. 5555 1234
Executive summary
The summary provides a brief (1-2 page) overview of the development proposal, the findings and
the associated recommendations and conclusions.
1 Introduction
The introduction should give an overview of the development and any relevant background
information. It may be appropriate to include a locality plan showing the location of the proposed
development site.
Any technical terms used in the document such as “DFE”, “AEP” or “PMF” should be defined and
explained for non-technical readers. As the document must be able to be read and followed by
non-technical readers it may be appropriate to define terms such as “Minor”, “Major” and “Extreme”
flood events and then use these terms throughout the document.
• Identify relevant water level and rainfall alert gauges operated by BoM
• Sunshine Coast Council Disaster Hub for consolidated listing of local and State roads
closed plus BoM and Council current weather warnings
http://disaster.sunshinecoast.qld.gov.au/
In developing the plan there are a range of technical industry guidelines which can be used
including the Sunshine Coast Council (2016) publication titled Guidelines for Improving Flood
Resilience for New Development
f. Emergency Contacts
Emergency contacts during a flood emergency are to be listed and should include as a minimum
the following public organisations:
g. Recovery
Flood recovery may be a significant undertaking depending on the use and nature of the flood risk.
While the Plan primarily focuses on safety during an event, planning for Flood Recovery can
significantly reduce the overall economic and social consequences of a flood event by allowing
normal operations to recommence as soon as possible.
Specific strategies, procedures and responsibilities for dealing with the immediate aftermath of an
event should be documented here with the aim on return the use to normal operation as soon as
possible.
Advice for improving the resilience of development to flooding can be found in the Sunshine Coast
Council (2016) publication titled Guidelines for Improving Flood Resilience for New Development.
b. Resource Requirements
The resources required will vary greatly with the strategy adopted. For strategies relying on shelter-
in-place for able-bodied people and for brief periods of isolation then resources may be limited to
simple first-aid kits and supplies for making isolation more comfortable such as water, torches and
radios.
For uses with more sensitive populations and/or that involve evacuation procedures then resource
requirements (both in terms of equipment and personnel) are likely to be far more intensive.