Method of Statement For LV Panel Maintenance
Method of Statement For LV Panel Maintenance
Approved By:
METHOD STATEMENT FOR LV PANEL MAINTENANCE
REVISION RECORD
This cover page is a record of all revisions of the document identified above by number and title. All previous
cover pages are hereby superseded and are to be destroyed.
Approvals
Rev. No. Date By Chkd. Description and Page Numbers of Revisions
HMR
00 14/08/2023 AR VK AM 1st Submission
Approved By:
METHOD STATEMENT FOR LV PANEL MAINTENANCE
CONTENTS
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
8. HSE REQUIREMENTS
9. WORK PERMIT
1. PURPOSE
The purpose of generating this method statement is to define the procedure step by step to
implement the correct practices for LV Panel Maintenance through the guidelines contained here in so
as to ensure that the job execution complies with specification and serves the intended function to
satisfactory level where applicable in the building.
2. SCOPE OF WORK
This method statement covers all processes related to following:
METHOD STATEMENT FOR LV PANEL MAINTENANCE
SR
MAINTENANCE WORK IN LV PANEL
NO
1 Visual Test
2 Check for temperature rise
3 Check for damage
4 Check for ingress / leakage
5 Torque test of Bus bar
6 Check bus bar for signs of heating
7 Cleaning of LV Panels
8 Insulation resistance test for ACB
9 Thermography test (Infra-Red Gun)
10 MCCB Operation check
11 ACB Electrical operation check
12 ACB Mechanical operation check
13 ATS change over check ( If Applicable)
14 Ensure all back feeding sources are isolated
Clean the breaker rear and front compartment with an air blower , vacuum cleaner and a
15
dry cloth
16 Clean all insulators with a soft dry cloth and contact cleaner
17 Check insulators for damage and cracks
18 Functional test for all LV panels ACBs, ATS, Control Panels
19 Observe ON/OFF operation and indication as well
20 Noting the Readings of Voltage, Ampere, kwh etc.
21 Record the date of test
22 Preparation of test reports
METHOD STATEMENT FOR LV PANEL MAINTENANCE
3. REFERENCE
The works will all be undertaken in accordance with the following documents:
a) ISO 9001:2008.
b) Electrical Standards.
c) M/s TDGISERV HSE Standards and requirements.
d) Project Quality Plan
e) Project HSE Plan
f) Manufacturer’s Data sheets.
g) Manufacturer’s recommendations.
h) Regulation of the local Electrical Authority, KAHRAMAA
i) Electrical standards for LV Panels
4. DEFINITIONS
COMPANY : TDGISERV
Contractor : Arrowhead Switchgear
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method of Statement
5. RESPONSIBILITIES
Responsibilities for ensuring that the steps in this procedure shall be carried out are specified at
relevant steps in the procedure:
- Testing Engineer
- Site Engineer
- Site Supervisor/Technician
8. HSE REQUIREMENTS
a. Ensure only trained / certified persons only shall operate the power tools.
b. Ensure that Temporary live cable management plan shall develop and implemented.
c. Necessary PPE to be worn while working in energized circuits.
d. Ensure adequate lighting is provided in the working area at night time and if inside the
building area to be well illuminated.
e. Ensure service area/work area openings are provided with barricade, tape, safety nets
and warning signage to be provided.
f. Ensure that the Fire alarm and Fire fighiting devices are de – activated.
g. Ensure LOTO procedure to be followed and implement comprehensive locked out & tag
out during execution of work.
h. Emergency response plan & procedure shall be developed and established as per the site
condition during the execution of activity.
i. Ensure that training cards issues as to identify the power tools operatives.
j. Calibrated Instruments only to be used.
9. WORK PERMIT
a. Ensure LOA work permit is valid and approved by M/s. TDGISERV
b. Ensure LOTO permit is valid and approved by M/s. TDGISERV
c. Ensure the Fire Alarm and Fire Fighting (FM – 200) De Activated.
17. Check for any loose connection at auxiliary and main contacts.
18. Check the busbar connection for sign of overheating and weak insulation.
19. Check the proper operation of indicating device and interlock.
20. Verify the asset identification tag marking is available and readable.
21. Ensure that all moving parts of the asset are separately, and individual connected to the
ground system terminal.
22. Check all cables and wires identification tags
23. Inspect the panel for any damage, corrosion, broken lock, cover and lost screw rectify
as necessary.
24. Check the metering devices for proper operation.
25. Check the ON/OFF and Trip mechanism of moulded case circuit breaker.
26. Rack out each main Air Circuit Breaker (ACB) in the panel compartment and clean the
contact point, springs and knives blade with CRC/WD40 and cleaning with wet cloth.
27. Apply a thin layer of contact grease in the contact point and spring to protect against
dust etc.
28. Verify all the busbar joints. Torque should be checked by using calibrated torque wrench
and value to be set in manufacturer recommendation.
THERMOGRAPHY
a. Open the door from Cable and Bus bar compartment and remove the protective covers
and taken the thermal images.
b. Thermal images will be taken from the LV compartment Cable sides.
c. Barricading of working area & respective safety aspects shall be followed by M/s.
Arrowhead
d. Carrying out LV Panel maintenance work as per SOW.
Receiving all safety measures from safety dept. of M/s TDGISERV which are to be followed by M/s.
Arrowhead while working.
b. Pick up all tools and equipment used, scraps and debris of materials used for S/S PPM
activity and dispose accordingly into allocated waste bins.
c. Remove barricade.
d. Notify end user.
e. Close the permit.
More FURTHER CONTROLS (Elimination, Substitution, Engineering Controls, PPE REQUIRED (other than
HAZARD/RISK Who May Be Harmed EXISTING CONTROLS
L S R Required? Signage) site mandatory) L S R
Manual handling, Operatives involved in Work area to be fully controlled by M Use mechanical aids instead of manual lifting.Specific job training shall be given
actvity
Rigger Hand Gloves
Other Contractors
e to the workers before starting the task.Correct manual handling tecniques to be
specialist and competent gang.All L
working close by d
3 3 9 YES followed by all operatives, Firm grip, Good communication. Noise level must be 1 1 1 O
Visitors personnel associated with the task must i
assessed and precuations to be taken.Hearing protection to be provided if W
u
Dust, Noise wear the site mandatory PPE m necessary Dust Mask
Emergency rescue Operatives involved in Alarm / Siron Report to immediate responsible supervisoror safety officer.All emergency
actvity M
Other Contractors e contact number will be provided.Emergency response procedure , safety training
working close by Escape route L
d
Visitors 2 4 8 YES and induction will be given to all prior to commence the work.All activities will 1 1 1 O
i
Assembly point Tool Box W
Emergency Response u be preceded by a safety induction conducted by client. All activities will be
m
procedure Team Talk excuted in accordance with the Client's HSE guidelines and instruction.
Risk Assessment Prepared By: Signature: Date: 14-08-2023 Supervisor Responsible for Implementation: Signature:
Arunagiri R
Risk Assessment Approved By: Signature: Date: 14-08-2023 Periodical Review to Take Place On:
Abid