Japan Club - Fall Preventer Devices 2015 07

Fall Preventer Devices (FPDs) are required by regulations to minimize risks during lifeboat drills and maintenance. Defects have been found in FPDs during inspections. The document provides guidelines for FPD use, including that procedures for installation, training, inspection and maintenance be documented in the vessel's safety management system and training manuals. It is important to follow regulations and ensure effective procedures and training for lifeboat equipment like FPDs.

Uploaded by

Raj Andhankat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views4 pages

Japan Club - Fall Preventer Devices 2015 07

Fall Preventer Devices (FPDs) are required by regulations to minimize risks during lifeboat drills and maintenance. Defects have been found in FPDs during inspections. The document provides guidelines for FPD use, including that procedures for installation, training, inspection and maintenance be documented in the vessel's safety management system and training manuals. It is important to follow regulations and ensure effective procedures and training for lifeboat equipment like FPDs.

Uploaded by

Raj Andhankat
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Focus on Fall Preventer Devices (FPD)

1.Preface 1)
There are regular accidents during routine lifeboat drills and maintenance. Personnel in the
lifeboats at the time often suffer injury and even death. There were many causes for these
accidents, not just the failure of the release function of on-load release hooks. In the early
2000's, the international shipping industry associations and UK government thus analyzed
lifeboat accidents and reported its results. The report dealt with new design criteria for
on-load release hooks and training, testing and maintenance procedures on vessels. One of the
objects of the report was to prevent a lifeboat inadvertently falling from a ship.
As a result, amendments to SOLAS III/1.5 (Resolution MSC.317(89)) were adopted at the 89th
session of the Maritime Safety Committee (MSC 89) of the International Maritime Organisation
(IMO) in May 2011. Therefore, the lifeboat release and the retrieval systems (LRRS) must comply
with LSA Code IV amended by Res.MSC.320(89) not later than the next scheduled dry-docking after
1 July 2014, and not later than 1 July 2019. Additionally, Fall Preventer Devices (FPDs) may
be required until such time as the said devices have undergone the necessary design review
and performance test, and have been either confirmed compliant with the relevant requirements
of the revised LSA Code or replaced with compliant devices. In case that a Flag State
Administration requires FPDs to be employed, the FPDs (Picture 2) shall be approved by an
Administration or a Recognised Organization in accordance with IMO circular MSC.1/Circ.1327.

Strap Type
FPD

Picture1 Lifeboat Picture2 FPD


(Quoted 2012 ClassNK Technical Seminar (fall))

However, defects are still being found in FPDs during PSC vessel inspections and condition
surveys. We would like to discuss the defects and how to prevent similar accidents in the future.

2.Detailed studies on life boat accidents 2)3)


In the early 2000's, international shipping industry associations and the UK government analysed
lifeboat accidents and reported the results.
At first, international shipping industry associations such OCIMF(Oil Companies International
Marine Forum, INTERTANKO (International Association of Independent Tanker Owners), and SIGTTO
(Society of International Gas Tanker and Terminal Operators) made statistical comprehensive
studies to find the causes of lifeboat accidents in which personnel were killed and injured

1
in the boat during routine drills and maintenance work. Then, they found that equipment failure
was the most common cause and that release mechanism was the piece of equipment to fail most
frequently. The following matters were all considered to be contributory factors in such
casualties.
(1)Design failure
(2)Lack of maintenance
(3)Failure of correct procedures
(4)Lack of proper training

In addition, in 2006 the UK Marine Accident Investigation Branch (MAIB) identified that the
design requirements of the on-load release hooks were unstable & unsafe, and so proposed that
an additional safer design had to be developed in DE50 of IMO.

3.Recent studies 4)
In April 2015, the “Safety Digest”, issued by the UK’s Marine Accident Investigation Branch
(MAIB), in order to promote within the marine community the learning of lessons arising from
a variety of accidents, drew attention to the serious failure of a lifeboat release mechanism
during a drill that caused injury to a seafarer.
(1) To be effective, risk assessments must cover all aspects of an operation and, where
appropriate, should be supported by a ‘standard operating procedure’. These must be
utilised for each operation to which they pertain.
(2) Launching routines should form part of the maintenance schedule and include a thorough
inspection of all associated equipment.
(3) Launching instructions should be reviewed to ensure that communications between the OIC
and release and retrieval system operators are effective.

4.Defects found at Inspection / Survey


At a PSC(Port State Control)Inspection or our condition survey, the following items are
found defective.
(1) Case 1
・Both life boats have Fall preventer devices (FPD) installed in accordance with IMO regulations.
However, no training or maintenance was going on at time of the inspection.
(2) Case 2
・Both life boats have FPD installed in accordance with IMO regulations.
However, no procedure for abandon ship situation had been followed.

5. Guidelines for the fitting and use of Fall Preventer Devices under IMO 1)
A“Fall Preventer Device” (FPD) can be used to minimize the risk of injury or death by
providing a secondary alternate load path in the event of failure of the on-load hook or its
release mechanism or of the accidental release of the on-load hook.
The guidelines for the fitting and use of Fall Preventer Devices (IMO MSC.1/Circ.1327)
prescribe the following matters
(1) various design requirements relating to both function and performance
(2) Lifeboat FPDs are properly in place before commencing any drill, testing, inspection
or maintenance where persons are in the lifeboat.

2
(3)The ship’s operating crew should be familiar with the operation of the FPD fitted to
the lifeboat on their ship. The procedure to be followed should be contained in the ISM
Code documentation and the ship’s training manual.

6.Application requirements. Examples of the employment of FPDs, as provided by flag states 1)


On the home page of their website, Class NK shows the application requirements on the employment
of FPDs employment from some flag states under the heading “News of Lifeboat Release and
Retrieval Systems”.
Here are some examples :
(1) Panama: issued “Merchant Marine Circular MMC-250”
・FPDs should be employed as an interim risk mitigation measure for each existing lifeboat
release and retrieval system until the system meets the requirements stated in the
MSC.1/Circ.1392, Paragraph 6.1 to 6.5; and at the master’s discretion.
・FPDs shall be approved by a Recognized Organization in accordance with IMO
MSC.1/Circ.1327.

(2)Liberia: issued “Marine Notice SAF-005 Rev.06/12”


・FPDs shall be employed for each existing lifeboat release and retrieval
system until the system meets the requirements stated in the MSC.1/Circ.1392, Paragraph
6.1 to 6.5; and at the master’s discretion.
・FPDs shall be designed, installed, inspected, and utilised in accordance
with IMO MSC.1/Circ.1327.

Circulars with IMO, UK, Liberia, and Panama

(3)UK: issued “Marine Guidance Note MGN445(M+F)”


・The MCA strongly urges that all UK vessels fitted with lifeboat on-load release systems
should be equipped with FPDs pending the evaluation of the systems for compliance with
the requirements of the revised LSA Code.
・FPDs should be fitted in accordance with IMO MSC.1/Circ.1327.
・In addition, following matters are stipulated
・Procedures for use, inspection and maintenance are to be available and
documented in the ship's Safety Management System (SMS) and training
documents.
・Decisions relating to the fitting and use of FPDs should be documented in the vessel’s
SMS and training manual.
・The professional judgement of the Master is necessary in deciding the
occasions and circumstances when FPDs are used.
The FPD manufacturer’s limitations for use should be taken into account when making
this decision.

3
・Where a different procedure is followed during routine drills compared
with an abandon ship situation, this should be clearly described.

7.Operating examples of shipping companies


The following are examples of how shipping companies manage the use, training, and maintenance
of FPDs in terms of their vessel’s SMS and training manual.
(1) Case 1
Whether the lifeboat release and the retrieval systems (LRRS) comply with LSA Code IV amended
by Res.MSC.320(89),or not, as a measure of precaution there are cases where FPD is employed
as part of the company’s safety policy.
In such case, along with the employment of the FPD, the use, training, and maintenance of
FPDs are described in their vessel’s SMS and training manual as follows.
Example① FPDs must be disconnected immediately after the drill
and stored safely.
Example② FPDs must not be used in a real emergency situation.
Example③ The disconnection procedure of FPDs must also include simple method in case
of an emergency situation arising.
(2)Case 2
Depending on Flag state’s requirements or the specification of FPDs, there are some FPDs
which stay connected all the time. With such FPDs, the procedure of disconnection and training
for this procedure must be described clearly in the ship’s SMS and training manuals.

8. Conclusion
Maintenance, operation and training & drills are very important as regards lifesaving appliances.
We would recommend that you review your standards of the lifeboat release and the retrieval
systems. If it is necessary for you to use a FDP, please ensure that it complies with the
instructions and guidelines of IMO and your Flag State. Finally, ensure that procedures for
use, training, emergency operation, and maintenance of FPDs are all established under the
vessel’s SMS and training manuals and implemented effectively.
--END

Bibliography
1)“News of Lifeboat Release and Retrieval Systems”, Class NK Homepage
https://www.classnk.or.jp/hp/en/activities/statutory/solas/solas_treaty/voyage/lifeboat_news.html
2)“Lifeboat safety solutions”, Harry Gale BSc (Hons), Seaways, March 2008
http://www.nautinst.org/download.cfm?docid=BB3ED9D3-A3EF-4CF6-A2ACF00089D5EBB3
3)“lifeboat incident”, 2002 ClassNK technical seminar paper
http://www.classnk.or.jp/hp/pdf/reseach/seminar/old/kyumeitei_txt_2002.pdf
4) “CASE 4 Badly Timed Tackle Results in Another Lifeboat Accident”,
MAIB safety digest volume 1, 2015
https://www.gov.uk/government/publications/maib-safety-digest-volume-1-2015