The document provides a work breakdown structure and schedule for the construction of a proposed 3 bedroom residential building with an area of 84.25 sqm. It lists 34 activities from site clearing to cleaning, along with the duration, resources and dependencies of each task. The critical path passes through activities like site clearing, rebar installation, concrete pouring and laying of hollow blocks. The total project duration is estimated at 180 days from September 30, 2019 to March 9, 2020.

Uploaded by

enm.235drive
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views8 pages

Ronnel CMPM

The document provides a work breakdown structure and schedule for the construction of a proposed 3 bedroom residential building with an area of 84.25 sqm. It lists 34 activities from site clearing to cleaning, along with the duration, resources and dependencies of each task. The critical path passes through activities like site clearing, rebar installation, concrete pouring and laying of hollow blocks. The total project duration is estimated at 180 days from September 30, 2019 to March 9, 2020.

Uploaded by

enm.235drive
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

RONNEL CESISTA FABIA

BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 30, 2019
Area: 84.25 sq. m Date Finish: March 9, 2020
NO. TOTAL ACTIVITY NUMBER OF DURATION DESCRIPTION
FLOAT WORKERS (DAYS)
1 0 A 3 5 Site Setting and Clearing

2 0 B 3 3 Layout and Fabrication of Steel Rebar

3 0 C 2 3 Excavation ,Demolition and Earthworks


4 0 D 3 4 Installation of Footing Rebar and Framework

5 0 E 3 7 Concrete Pouring for Footing

6 5 F 3 5 Installation of Tie Beam Rebar and Framework

7 5 G 3 5 Installation of Formwork for Tie Beam

8 5 H 3 7 Concrete Pouring for Tie Beam

9 0 I 3 4 Installation of Column Rebar and Framework

10 0 J 4 8 Installation of Formwork for Column

11 0 K 5 7 Concrete Pouring for Column

12 0 L 3 5 Installation of Roof Beam Rebar and Framework

13 0 M 4 7 Installation of Formwork for Roof Beam

14 8 N 3 7 Concrete Pouring for Roof Beam

15 0 O 4 15 Removing for Formworks for Column and Tie


Beam
16 0 P 3 5 Backfill and Compaction

17 1 Q 4 12 Laying of CHB
18 1 R 3 4 Finishing of CHB Joints

19 12 S 5 9 Plumbing Works and Installation of Septic Tank

20 12 T 4 7 Removing of Formworks form for Roof Beam

21 0 U 3 6 Fabrication of Trusses

22 0 V 3 6 Installation of Scaffolding

23 0 W 3 5 Installation of Trusses

24 0 X 3 8 Installation of Gutter and Roofing and Ceiling Joist

25 7 Y 2 5 Electrical Works

26 28 Z 2 6 Installation of Doors and Windows


27 7 A’ 5 9 Plastering

28 0 B’ 5 10 Installation of Floor Slab Rebar and Framework

29 0 C’ 3 7 Concrete Pouring for Floor Slab

30 7 D’ 2 4 Installation of Ceiling

31 0 E’ 3 8 Installation of Water Closet, Lavatory, Faucet, and


Waterline
32 7 F’ 5 9 Painting

33 0 G’ 6 30 Tiles Work

34 0 H’ 5 10 Cleaning

Total Cost: Php. 2,445,518.97


RONNEL CESISTA FABIA
BSCE – 5B
Project Name: Proposed 3 Bedroom Residential Date Starts: September 30, 2019
Area: 84.25 sq. m Date Finish: March 9, 2020
NO. ACTIVITY EARLY EARLY LATEST LATEST TOTAL FREE CRITICAL
START FINISH START FINISH FLOAT FLOAT PATH
1 A 0 5 0 5 0 0 CP

2 B 5 8 5 8 0 0 CP

3 C 5 8 5 8 0 0 CP
4 D 8 12 8 12 0 0 CP

5 E 16 23 16 23 0 0 CP

6 F 16 21 21 26 5 0 -

7 G 21 26 26 31 5 0 -

8 H 38 45 43 50 5 0 -

9 I 12 16 12 16 0 0 CP

10 J 23 31 23 31 0 0 CP

11 K 31 38 31 38 0 0 CP

12 L 38 43 38 43 0 0 CP

13 M 43 50 43 50 0 0 CP

14 N 50 57 58 65 8 0 -

15 O 50 65 50 65 0 0 CP

16 P 65 70 65 70 0 0 CP

17 Q 70 82 71 83 1 0 -
18 R 82 86 83 87 1 0 -

19 S 65 74 77 86 12 0 -

20 T 74 81 86 93 12 0 -

21 U 70 76 70 76 0 0 CP

22 V 76 82 76 82 0 0 CP

23 W 82 87 82 87 0 0 CP

24 X 87 95 87 95 0 0 CP

25 Y 86 91 93 98 7 0 -

26 Z 86 92 114 120 28 0 -
27 A’ 91 100 98 107 7 0 -

28 B’ 95 105 95 105 0 0 CP

29 C’ 105 112 105 112 0 0 CP

30 D’ 100 104 107 111 7 0 -

31 E’ 112 120 112 120 0 0 CP

32 F’ 104 113 111 120 7 0 -

33 G’ 120 150 120 150 0 0 CP

34 H’ 150 160 150 160 0 0 CP

COMPUTATION
SITE SETTING AND CLEARING
Duration = 5 days for 3 men
FABRICATION OF STEEL BAR
Duration = 5 days for 3 men
EXCAVATION
Volume = 1(1)(1)(15)+0.4(0.5)(51) = 25.20 cu.m
Duration = 25.20cu.m / (0.61cu.m./hrs) (8hrs/day)
Duration = 5.164 days for 1 man
Duration = 3 days for 2 men
CONCRETING OF FOOTING
Volume = 0.2(1)(1)(15)+0.2(0.4)(69.50) = 8.56 cu.m
Duration = 8.56cu.m / (0.42cu.m/day)
Duration = 20.381 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF TIE BEAM
Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF REINFORCE FLOORING
Volume = 86.25sq.m (0.1m) = 8.625 cu.m
Duration = 8.625cu.m / (0.42cu.m/day)
Duration = 20.536 days for 1 man
Duration = 7 days for 3 men
CONCRETING OF COLUMN
Volume = 0.3(0.4)(4.8)(15) = 8.64 cu.m
Duration = 8.64 cu.m / (0.25cu.m/day)
Duration = 34.56 days for 1 man
Duration = 7 days for 5 men

CONCRETING OF ROOF BEAM


Volume = 0.2(0.4)(63.25) = 5.06 cu.m
Duration = 5.06cu.m / (0.25cu.m/day)
Duration = 20.24 days for 1 man
Duration = 7 days for 3 men
INSTALLATION OF REBAR FOR FOOTING
Mass of Rebar = 980 kg
Duration = 980kg (9hrs/100kg) / (8hrs/day)
Duration = 11.025 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF REBAR FOR TIE BEAM
Mass of Rebar = 1210 kg
Duration = 1210kg (9hrs/100kg) / (8hrs/day)
Duration = 13.6125 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF REBAR FOR FLOORING
Mass of Rebar = 4390 kg
Duration = 4390kg (9hrs/100kg) / (8hrs/day)
Duration = 49.3875 days for 1 man
Duration = 10 days for 5 men
INSTALLATION OF REBAR FOR COLUMN
Mass of Rebar = 910 kg
Duration = 910kg (9hrs/100kg) / (8hrs/day)
Duration = 10.2375 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF REBAR FOR ROOF BEAM
Mass of Rebar = 1210 kg
Duration = 1210kg (9hrs/100kg) / (8hrs/day)
Duration = 13.6125 days for 1 man
Duration = 5 days for 3 men

INSTALLATION OF FORMWORKS FOR TIE BEAM


Surface Area = (0.2+0.4)(63.25) = 37.95 sq.m
Duration = 37.95sq.m (2.8manhours/sq.m) / (8hrs/day)
Duration = 13.2825 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF FORMWORKS FOR COLUMN
Surface Area = 2(0.3+0.4)(4.8)(15) = 100.80 sq.m
Duration = 100.80sq.m (2.5manhours/sq.m) / (8hrs/day)
Duration = 31.50 days for 1 man
Duration = 8 days for 4 men
INSTALLATION OF FORMWORKS FOR ROOF BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (3.01manhours/sq.m) / (8hrs/day)
Duration = 28.557 days for 1 man
Duration = 7 days for 4 men
REMOVING OF FORMWORKS FOR TIE BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (2.8manhours/sq.m) / (8hrs/day)
Duration = 26.565 days for 1 man
Duration = 7 days for 4 men
REMOVING OF FORMWORKS FOR COLUMN
Surface Area = 2(0.3+0.4)(4.8)(15) = 100.80 sq.m
Duration = 100.80sq.m (2.5manhours/sq.m) / (8hrs/day)
Duration = 31.50 days for 1 man
Duration = 8 days for 4 men
REMOVING OF FORMWORKS FOR ROOF BEAM
Surface Area = 2(0.2+0.4)(63.25) = 75.90 sq.m
Duration = 75.90sq.m (3.01manhours/sq.m) / (8hrs/day)
Duration = 28.557 days for 1 man
Duration = 7 days for 4 men

BACKFILL AND COMPACTION


Volume = 0.9(86.25)+25.20-13.164 = 89.661 cu.m
Duration = 89.661cu.m (1.34manhours) / (8hrs/day)
Duration = 15.018 days for 1 man
Duration = 5 days for 3 men
LAYING OF CHB
No. of Pieces = 184.75sq.m (12.5pcs/sq.m) = 2309.375 pcs. Say 2310 pcs.
Duration = 2310pcs. / (50pcs./day)
Duration = 46.2 days for 1 man
Duration = 12 days for 4 men
FINISHING OF CHB JOINTS
No. of Pieces = 184.75sq.m (12.5pcs/sq.m) = 2309.375 pcs. Say 2310 pcs.
Duration = 2310pcs. / (210pcs./day)
Duration = 11 days for 1 man
Duration = 4 days for 3 men
INSTALLATION OF SCAFFOLDING
Duration = 6 days for 3 men
FABRICATION OF TRUSS
Mass of Truss = 2,160 kg
Duration = 2,160kg / (120kg/day)
Duration = 18 days for 1 man
Duration = 6 days for 3 men
INSTALLATION OF CEILING
Surface Area = 84.25 sq.m
Duration = 84.25sq.m / (22.5sq.m/day)
Duration = 3.744 days for 1 man
Duration = 2 days for 2 men
INSTALLATION OF CEILING JOIST
No. of Board Feet = 84.25sq.m (4Brd.Ft./sq.m) = 337 Brd.Ft.
Duration = 337Brd.Ft. / (80Brd.Ft./day)
Duration = 4.2125 days for 1 man
Duration = 2 days for 2 men

INSTALLATION OF TRUSS
No. of Sets = 20 sets
Duration = 20sets / (1.333sets/day)
Duration = 15 days for 1 men
Duration = 5 days 3 men
INSTALLATION OF G.I. SHEETS
No. of Sheets = 122.045sq.m. / (1.71sq.m effective size/Sheets) = 71.37 say 72 sheets
Duration = 72sheets / (5.5sheets/day)
Duration = 13.091 days for 1 man
Duration = 5 days for 3 men
INSTALLATION OF GUTTER AND DOWNSPOUT
Duration = 3 days for 3 men
PLUMBING WORKS
Duration = 3 days for 5 men
INSTALLATION OF WATERLINE
Duration = 2 days for 3 men
INSTALLATION OF WATER CLOSET
No. of Sets = 2 sets
Duration = 2sets / (0.5set W.C./2days)
Duration = 8 days for 1 man
Duration = 3 days for 3 man
INSTALLATION OF LAVATORY
No. of Sets = 3 sets
Duration = 3sets / (0.5set/1.5days)
Duration = 9 days for 1 man
Duration = 3 days for 3 men
INSTALLATION OF SEPTIC TANK
Duration = 6 days for 5 men
INSTALLATION OF DOOR AND WINDOW JAMB
No. of Board Feet = 54 Brd.Ft.
Duration = 54Brd.Ft. / (40Brd.Ft./day)
Duration = 1.35 days for 1 man
Duration = 1 days for 2 man

INSTALLATION OF DOORS
No. of Sets = 7 pcs
Duration = 7pcs / (2pcs/day)
Duration = 3.5 days for 1 man
Duration = 2 days for 2 men
INSTALLATION OF WINDOWS
No. of Sets = 9 pcs
Duration = 9pcs / (2pcs/day)
Duration = 4.5 days for 1 man
Duration = 3 days for 2 men
ELECTRICAL WORKS
Duration = 5 days for 2 men
PLASTERING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180sq.m / (4sq.m/day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
PAINTING BOTH SIDES
Surface Area = 180 sq.m
Duration = 180 sq.m / (4sq.m./day)
Duration = 45 days for 1 man
Duration = 9 days for 5 men
INSTALLATION OF TILES
No. of Tiles = (84.25sq.m+66sq.m) / (0.023226sq.m/pc) = 6,469 pcs
Duration = 6,469pcs. / (36pcs./day)
Duration = 179.69s days for 1 man
Duration = 30 days for 6 men
FINAL CLEANING
Duration = 10 days for 5 men