CHECK LIST FOR:
TESTING & COMMISSIONING OF EXTERNAL FIRE HYDRANT Ref. No:
SUBCONTRACTOR X CONTRACTOR Rev. No: 00
Page : 1 of 1
SECTION OF WORK: FIRE FIGHTING SYSTEM LOCATION:
LEVEL: WIR No.:
ITEM Checked by Checked Date
by
STAGE
S/C CONT CONS.
1. Ensure all shop drawings has been approved by the cons..
SETTING OUT
2. Check Levels, elevations, distances & supports & equipment are as per
approved shop drawings & material approvals.
3. Ensure all material approvals & material verification records have been
approved by the cons..
4. Only trained & experienced personnel shall perform the work.
5. Ensure civil clearance has been issued prior to start of any Testing &
CIVIL
commissioning.
1. Verify that the hydrant can be easily accessible.
2. Verify that the hydrant has been fitted with maintenance record tag.
Testing & Commissioning
3. Verify that signage has been provided that clearly indicates the location of
the fire hydrant.
4. Verify that all water flow alarm & valve monitoring system switches operate
correctly.
5. Verify water pressure & flow rate at the fire Hydrant.
6. Connect fire hose to the fire hydrant. Open the fire hydrant & ensure that the
water should at least 20 meters.
7. Ensure all safety precautions have been complied before & after
Safety
commissioning.
For S/C Date: FOR CONTRACTOR Date: For CONS. Date:
QA/QC: QA/QC: Rep.:
Name: Sign: Name: Sign: Name: Sign:
Page 1 of 1