The document provides a list of items and units of measurement for estimating the cost of a given structure based on drawings provided. It includes 17 sub-heads covering earthwork, concrete, brickwork, stonework, woodwork, steelwork, flooring, roofing, plastering/finishing, and miscellaneous items. For each item, it specifies the particulars, units of measurement, and units of payment. The list appears to be for preparing a detailed cost estimate and bill of quantities for a construction project.

Uploaded by

uvraj1234567891
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views3 pages

Experiment No.-1 ECV

The document provides a list of items and units of measurement for estimating the cost of a given structure based on drawings provided. It includes 17 sub-heads covering earthwork, concrete, brickwork, stonework, woodwork, steelwork, flooring, roofing, plastering/finishing, and miscellaneous items. For each item, it specifies the particulars, units of measurement, and units of payment. The list appears to be for preparing a detailed cost estimate and bill of quantities for a construction project.

Uploaded by

uvraj1234567891
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

EXPERIMENT NO.

-01
Prepare the list of items to be executed with units for detailed estimete of a given structure from the giving drawing.
giving drawing
Unts of
measurem Units of
Sub-head S.No. Particulars ent payments
Earthwork 1 Earthwork in excavation CUM Per CUM
2 Earthwork in filling in foundation trenches CUM Per CUM
3 Earthwork in filling in plinth CUM Per CUM
Concrete 1 Lime concrete in foundation
2 cement foundation in lintels
3 RCC in slab
4 Cement concrete or RCC in chujja,sunshade
5 Lean concrete in roof terracing (thickness specified) SQM Per SQM
6 Cement concrete bed CUM Per CUM

7 Reinforced concrete sunshade (specified width and height) CUM Per CUM
DPC 1 Damp proof course (DPC)-Thickness mentioned SQM Per SQM
Brickwork 1 Brickwork in foundation CUM Per CUM
2 Brickwork in plinth
3 Brickwork in super structure
4 Thin partition walls SQM Per SQM
5 Brickwork in arches CUM Per CUM
6 Reinforced Brickwork CUM Per CUM
Random Rubble masonry, Coursed Rubble masonry, Ashlar
Stone work 1 masonry walling and arches. CUM Per CUM
2 Stone work in wall facing etc. SQM Per SQM
Cut or Dressed stone work as in sills, steps, cornices, lintels,
3 copings etc. CUM Per CUM
4 Boulderwork CUM Per CUM

Wood work 1 Doors and windows frames or chaukhats, rafters, beams. CUM Per CUM
2 Shuters of doors and windows (thickness specified) SQM Per SQM
Doors and window fittings (like hinges, tower bolts, sliding
3 bolts, handles) Each Per Each
Per
Steel work 1 Steel reinforcement bars etc in RCC and reinforced brick work Quintal Quintal
Per
2 Bending, bending of steel reinforcement Quintal Quintal
Rivets,bolts and nuts,anchor bolts,lewis bolts, holding down Per
3 bolts Quintal Quintal
Per
4 Iron hold fasts Quintal Quintal
5 iron railing (height and types specified)
6 Iron grills SQM Per SQM
25mm cement concrete over 75mm lime concrete floor
Flooring 1 (including lean concrete) SQM Per SQM
2 25mm or 40mm cement concrete floor SQM Per SQM
3 Doors and window sills (CC or cement mortar plain SQM Per SQM
Roofing 1 RCC and RB slab roof (excluding steel ) CUM Per CUM
Lean concrete roof over and inclusive of tiles or brick or stone
2 slab etc (thickness specified) SQM Per SQM
3 Centering and shutering formwork SQM Per SQM
4 AC sheet roofing SQM Per SQM
Plastering,P
oints and plastering-cement or lime mortar (thickness and proportion
finishing 1 specified SQM Per SQM
2 Pointing SQM Per SQM
White washing,colour washing, cement washing, (number of
3 coats specified) SQM Per SQM
4 Distempering (number of coast specified) SQM Per SQM
5 Painting, varnishing (mumber of coats specified) SQM Per SQM
Miscellane-
ous item 1 Rain water pipe/plain pipe RM Per RM
2 steel wooden truss Each Per Each
3 Glass panels (supply) SQM Per SQM
4 Fixing of glass panels or cleaning Each Per Each
e giving drawing.