 Item                             Descrip on                            Unit    Qty          Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        WORK BELOW LOWEST FLOOR FINISH
        Excava on Works
          Excavate to reduce level commencing from forma on level
          not exceeding 0.25m deep get out, deposit, spread and
          levelled where directed within the site in making up levels
          and remainder load and cart away
  A         Excavate for ground floor slab                               M2      442                 3.00     1,326.00
  B         Excavate for apron slab                                     M2      159                 3.00       477.00
          Excavate commencing from reduce level get out, part
          return, fill in and well ram, part load, cart deposit and
          spread in making up levels where directed within the site
          and remainder removed from site including all necessary
          planking and stru ng, trimming sides and levelling and
          compac ng bo om of excava on.
               Excavate pit for Pad Founda on
  C         depth not exceeding 2.0 m                                   M3      28              18.00          504.00
               Excavate Trench to receive ground beam
  D         depth not exceeding 1.00 m                                  M3      21              12.60          264.60
        Hardcore as described:-
  E         Hardcore, well spread, levelled and compacted to
            receive concrete floor slab.                                 M3      44              85.00        3,740.00
  F         Di o, for apron slab, di o.                                 M3      16              85.00        1,360.00
        Concretor
          50 mm lean concrete (G15) as described:-
  G         under Pile cap                                              M2      37                  4.80       177.60
  H         Underside of ground beam                                    M2      71                  4.80       340.80
                                                                         TOTAL CARRIED TO COLLECTION         8,190.00
                                                                                      BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                      WORK BELOW LOWEST FLOOR FINISH
 Item                            Descrip on                             Unit    Qty          Rate          Amount
        WORK BELOW LOWEST FLOOR FINISH (Cont'd)
        Concretor (Cont'd)
          Reinforced concrete (G35) as described in :-
  A         Pad Founda on                                               M3      11             378.55        4,164.05
  B         Column stump                                                M3       2             378.55          757.10
  C         Ground beam.                                                M3      32             378.55       12,113.60
  D         Ground floor slab, 150-300 mm thick                          M3      74             378.55       28,012.70
  E         Apron slab, 100-125 mm thick.                               M3      19             378.55        7,192.45
        High tensile / mild steel rod reinforcement as described in:-
          Pad Foo ng
  F         various diameters including links and s rrups               KG      550                 3.47     1,908.50
          Column Stump
  G         various diameter including links and s rrups                KG      500                 3.47     1,735.00
          Ground Beam
  H         various diameter including links and s rrups                KG     4,160                3.47    14,435.20
        Steel fabric reinforcement BRC A7 mass of 3.02 kg/m2 to B.S.
        4483 with 150mm side and end laps including cu ng,
        bending and bedding in concrete (measured ne -no
        allowance made for laps) as described in :-
  J         in ground slab                                              M2      442             11.07        4,892.94
  K         In Apron Slab                                               M2      159             11.07        1,760.13
        Sawn Formwork as described to :-
  L         To sides of pad foo ng                                      M2      59              25.70        1,516.30
  M         To sides of column stump                                    M2      37              30.30        1,121.10
  N         To sides of ground beam, exceeding 250 mm not
            exceeding 500 mm high                                        m      756             30.30       22,906.80
                                                                         TOTAL CARRIED TO COLLECTION       102,515.87
                                                                                   BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                   WORK BELOW LOWEST FLOOR FINISH
 Item                           Descrip on                           Unit    Qty          Rate          Amount
        WORK BELOW LOWEST FLOOR FINISH (Cont'd)
        Sawn Formwork as described to :- (Cont'd)
  A         To sides of apron slab, not exceeding 250 mm high         M      102                 7.50       765.00
        Damp Proof Membrane
  B         A layer of 0.10mm heavy duty polythene sheet as
            described laid below concrete bed (measured ne -no
            allowance made for laps)                                 M2      442                 3.00     1,326.00
        An termite
  C         An -termite chemical soil treatment as described to be
            carried out by an approved specialist to soil surfaces
            below pile cap, ground beams, ground floor and apron
            slab, all in accordance to the specialist and
            manufacturer's specifica on including obtaining wri en
            cer ficate of guarantee for two (2) years.                M2      442                 3.00     1,326.00
        Perimeter Drain
  D         Excavate trench not exceeding 1.0 m deep commencing
            from pla orm level and disposal of excess materials      M3       3                  7.60        22.80
  E         150 mm half round pre cast drain channel laid on mass
            concrete (1:3:6)                                          M      103             20.00        2,060.00
          Drain Cover
  F         237 mm wide Heavy duty MS gra ng drain cover with
            welded connec on, 6mm thick angle all round infilled
            with 40 mm x 6 mm thick flats at 30 mm centres, painted
            with one coat red oxide primer, set in 100 mm thick
            mass concrete on brick edge                               M      18              55.00          990.00
                                                                      TOTAL CARRIED TO COLLECTION         6,489.80
                                                                          BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                          WORK BELOW LOWEST FLOOR FINISH
 Item                                    Descrip on                                        Amount
        WORK BELOW LOWEST FLOOR FINISH
        COLLECTION
        Page NO.1/1/1                     …………………………………………………………                                8,190.00
        Page NO.1/1/2                     …………………………………………………………                              102,515.87
        Page NO.1/1/3                     …………………………………………………………                                6,489.80
                                                 TOTAL CARRIED TO COLLECTION SUMMARY          117,195.67
                                                                                BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                        FRAME
 Item                            Descrip on                      Unit    Qty           Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        FRAME
        Steel Reinforcement, straight and bent bar
          in column
  A         various sizes                                        KG     4,750                 3.31    15,722.50
          In Beams
  B         various sizes                                        KG     1,950                 3.42     6,669.00
          Roof Beams
  C         various sizes                                        KG      600                  3.51     2,106.00
        Reinforced Concrete Grade 35
  D         Column                                               M3      19              378.55        7,192.45
  E         Beams                                                M3      15              378.55        5,678.25
  F         Roof Beams                                           M3       4              378.55        1,514.20
  G         100 mm thick flat roof                                m2      10               38.00          380.00
        Fabric reinforcement, including laps and bent to sides
  H         BRC A8 in flat roof slab                              m2      10               20.00          200.00
        Sawn Formwork as described to:
  J         Sides of column                                      M2      291              30.30        8,817.30
  K         Sides and soffit of beam, height above 3.50 m above
            ground                                               M2      284              30.30        8,605.20
  L         Sides and soffit of roof beam, di o                    M2       8               30.30          242.40
  M         soffit of flat roof                                     m2      10               30.30          303.00
                                                                  TOTAL CARRIED TO COLLECTION         57,430.30
                                                                              BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                      FRAME
 Item                        Descrip on                         Unit    Qty          Rate        Amount
        FRAME (Cont'd)
        Water proofing
  A         Supply and apply approved cementa ous water proof
            membrane to flat room                                m2      10              40.00         400.00
                                                                 TOTAL CARRIED TO COLLECTION          400.00
                                                         BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                 FRAME
 Item                   Descrip on                                       Amount
        FRAME
        COLLECTION
        Page NO.1/2/1    …………………………………………………………                               57,430.30
        Page NO.1/2/2    …………………………………………………………                                   400.00
                                TOTAL CARRIED TO COLLECTION SUMMARY           57,830.30
                                                                                           BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                                    ROOF
 Item                             Descrip on                                 Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        ROOF
        Lightweight Steel Roof Truss System
        Any deficiency in design and costs of upgrading and
        replacement of defec ve members shall be en rely borne by the
        Contractor
        The Contractor shall provide 10 years structural warranty to the
        metal roof structure system proposed and accepted
        The Tenderer must submit all his detailed design calcula ons,
        drawings of the proposed system complete with specifica ons
        and priced Bill of Quan es and Schedule of Rates for the
        system proposed
        Supply, fabricate and deliver to site including all shop
        drawings, fixing and hois ng in posi on all steel roof truss,
        ra ers, chord, bearers, e, strut, packing piece, wall plate, truss
        connector, pain ng, and other associated works, materials and
        labour straps required for the concrete installa on of the steel
        roof trusses
          Design, supply and fix in posi on including hois ng of metal
          roof truss system comprising of main trusses, ra er, wall
          plates, ba ens, plates, fixing bolts and brackets, all
          inaccordance with manuracturer's instruc ons:
  A          hoist 10 m above ground level                                   M2      34              70.00       2,380.00
  B          3 m above ground level                                          m2      693             60.00      41,580.00
        Roof Construc on and Finishes
        NOTES:
        The Contractor must submit a complete proposal design, details
        calcula on, shop drawings all to be cer fied by Professional
        Engineer and method statements and to S.O approval before
        execu on of the works.
                                                                              TOTAL CARRIED TO COLLECTION       43,960.00
                                                                                       BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                                ROOF
 Item                            Descrip on                              Unit    Qty          Rate        Amount
        ROOF (Cont'd)
        Roof Construc on and Finishes (Cont'd)
        A er acceptance of the tender and prior to start works the
        Contractor shall submit two (2) copies of the detailed working
        drawings including calcula ons for review and approval the
        S.O. Upon approval he shall resubmit three(3) copies of the
        working/construc on drawings including calcula ons for
        endorsement by the S.O. All drawings and calcula on shall be
        endorsed by a Professional Engineer (P.E) prior submission to
        the S.O
        The contractor shall submit on comple on of works three (3)
        copies as-built drawings including calcula ons properly binded
        for acceptance and reference of the S.O.
        Measurement of roof trusses shall be taken from/to edges of
        trusses. A combina on of various pitch and height of
        connected trusses shall be measured together. Isolated trusses
        shall be measured separately.
          Roof Fihishes
               Roofing Covering
  A         Approved 0.42mm thick superior Rib PU Form metal
            deck roofing or other equivalent form to profile as
            shown in the architect's drawing complete with ridge,
            capping, flashing and all necessary accessories as in
            accordance to manufacturer's specifica on as a roof
            covering.                                                    M2      727             70.00      50,890.00
               Fascia Board
  B         230mm plank or other equal and approved fascia board
            to manufacturer's detail and to S.O approval                  m      590             30.00      17,700.00
               Galvanised Iron Flashing
  C         Approved profile 20 gauge galvanised iron flashing, 300
            mm wide forming V-profile laid under metal roof finish          m      11              10.00         110.00
                                                                          TOTAL CARRIED TO COLLECTION       68,700.00
                                                         BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                  ROOF
 Item                   Descrip on                                       Amount
        ROOF
        COLLECTION
        Page NO.1/3/1    …………………………………………………………                               43,960.00
        Page NO.1/3/2    …………………………………………………………                               68,700.00
                                TOTAL CARRIED TO COLLECTION SUMMARY          112,660.00
                                                                                  BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                 STEPS AND RAMPS
 Item                             Descrip on                        Unit    Qty          Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        STEPS AND RAMPS
        STEPS
          Concretor
                Reinforced concrete (G35) as described in :-
  A         Steps                                                   M3       1             378.55          378.55
                High tensile / mild steel rod reinforcement as
                described in :-
                Steps
  B         various sizes                                           KG      200                 3.51       702.00
                Sawn formwork as described to :-
  C         Sides of steps                                          M2       2              30.30           60.60
  D         Riser exceeding 100mm high not exceeding 200mm high      M      14                  6.06        84.84
          Steps Finishes
                Ceramic les
        Ceramic les or other equivalent, 200mm x 200mm, with
        cemen ous water proofing as specified; bedded and jointed
        in cement and sand (1:3) mortar; poin ng with grout in
        white cement; on and including 20mm thick cement and sand
        (1:6) screed.
  E         250mm wide treads                                       M2       4              90.00          360.00
  F         155mm high risers                                       M2       4              90.00          360.00
                                                                     TOTAL CARRIED TO COLLECTION         1,945.99
                                                                                      BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                     STEPS AND RAMPS
 Item                           Descrip on                              Unit    Qty          Rate        Amount
        STEPS AND RAMPS (Cont'd)
        RAMP
          Reinforced Concrete Ramp
               100 mm thick overall laid to slopes including 150 mm
               thick hardcore including excava on to reduce level not
               exceeding 0.25 m, reinforcement, formwork to sides
               of ramp, surface finishes as specified and forming
               striated lines on the surface
  A         1180x1780 wide                                              NO       2             500.00       1,000.00
  B         1870 x 2120 wide                                            NO       1             800.00         800.00
                                                                         TOTAL CARRIED TO COLLECTION        1,800.00
                                                           BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                          STEPS AND RAMPS
 Item                     Descrip on                                       Amount
        STEPS AND RAMPS
        COLLECTION
        Page NO.1/4/1      …………………………………………………………                                1,945.99
        Page NO.1/4/2      …………………………………………………………                                1,800.00
                                  TOTAL CARRIED TO COLLECTION SUMMARY            3,745.99
                                                                                     BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                     EXTERNAL WALLS
 Item                          Descrip on                             Unit    Qty           Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        EXTERNAL WALLS
        EXTERNAL WALLS
          Brickwork
  A         Half brickwall (112mm thick) in clay brick laid on and
            cement and sand (1:3) mortar including brick
            reinforcement 'Exmet' at every fourth course.             M2      230              38.40        8,832.00
  B         Horizontal damp proof course [DPC] as described laid
            on half brickwall (measured ne -no allowance made for
            laps).                                                     M      89                   2.30       204.70
  C         6mm Diameter mild steel wall bonding es, 450mm
            long, one end cast into concrete and the other end cast
            into concrete and the other end built into joints of
            brickwall as work proceeds.                               NO     1,383                 0.50       691.50
          Mild steel railing
  D         1100mm high M.S railing comprising of 75mm x 75 mmx
            1.2 mm thick mild steel Handrail to be welded with
            intermediate RHS railing and baluster and MS plate
            fixed to concrete surface with concrete screw anchor
            including cu ng, fixing and pain ng                         m      74              155.00       11,470.00
                                                                       TOTAL CARRIED TO COLLECTION         21,198.20
                                                          BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                          EXTERNAL WALLS
 Item                    Descrip on                                       Amount
        EXTERNAL WALLS
        COLLECTION
        Page NO.1/5/1     …………………………………………………………                               21,198.20
                                 TOTAL CARRIED TO COLLECTION SUMMARY           21,198.20
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                              WINDOWS AND DOORS
 Item                          Descrip on                             Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        WINDOWS AND DOORS
        DOORS
          Lintols
  A         Reinforced concrete (G30) lintol,size 125mm x 200mm
            as described reinforced with and including 4 nos. 10mm
            diameter high tensile steel bar reinforcement and 6mm
            diameter mild steel s rrups at 150mm centers including
            formwork and all other necessary works.                    M      42              26.00       1,092.00
          Door Frames and Leaves
               Supply and install the following doors; glazing,
               ironmongeries, pain ng and all other necessary
               fi ngs and fixing in accordance to manufacturer's
               details
  B         overall size 3000 x 4500 fixed glass panels according to
            the design, including 6 mm thick nted glazing (Type
            GP1)                                                       nr      1           4,700.00       4,700.00
  C         overall size sliding aluminium door 2775 x 2700 mm
            high sliding door, fixed on heavy duty aluminium track
            including nted glazing (Type SD1)                          nr      2           2,700.00       5,400.00
  D         overall size sliding aluminium door 3000 x 2700 mm
            high sliding door, fixed on heavy duty aluminium track
            including nted glazing (Type SD2)                          nr      2           3,000.00       6,000.00
  E         overall size 1500 x 2100 high mber panel door with
            steel frame (Type D1)                                     Nr       1           1,500.00       1,500.00
  F         overall size 900 x 2100 high    mber panel door with
            steel frame (Type D2)                                     Nr       5             750.00       3,750.00
  G         Overall size 750mm x 2100mm high uPVC door with
            metal framing, (Type D3)                                  Nr       3             180.00         540.00
                                                                       TOTAL CARRIED TO COLLECTION       22,982.00
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                              WINDOWS AND DOORS
 Item                          Descrip on                             Unit    Qty          Rate        Amount
        WINDOWS AND DOORS (Cont'd)
        WINDOWS
          Lintols
  A         Reinforced concrete (G30) lintol, size 125mm x 200mm
            as described lintol reinforcement with and including 4
            nos. 10mm diameter high tensile steel bar reinforcement
            hooked at both ends with 6mm diameter mild steel bar
            reinforcement as described s rrups at 150mm center
            including formwork and all other necessary works.          M      14              26.00         364.00
          Window Frames and Glazing
          Supply and install the following windows; complete with
          35 x 150 mm x 3.5 mm thick powder coated aluminium
          frames, ironmongeries, 8 mm thick nted glazing all other
          necessary fi ngs and fixing in accordance to
          manufacturer's details
  B         Overall size 1800 wide x 1800 mm high fixed casement
            window (Type W1)                                          Nr       2           1,135.00       2,270.00
  C         Overall size 1200mm x 1800 mm high foxed casement
            window (Type W2)                                          Nr       2             760.00       1,520.00
  D         Overall size 600mm x 600 mm high top hung casement
            window(Type W3)                                           Nr       2             130.00         260.00
                                                                       TOTAL CARRIED TO COLLECTION        4,414.00
                                                             BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                       WINDOWS AND DOORS
 Item                       Descrip on                                       Amount
        WINDOWS AND DOORS
        COLLECTION
        Page NO.1/6/1        …………………………………………………………                               22,982.00
        Page NO.1/6/2        …………………………………………………………                                4,414.00
                                    TOTAL CARRIED TO COLLECTION SUMMARY           27,396.00
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                        INTERNAL WALL AND PARTITION
 Item                          Descrip on                             Unit    Qty          Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        INTERNAL WALL AND PARTITION
        INTERNAL WALL AND PARTITION
        INTERNAL WALL
          Brickwork
  A         Brickwall (113mm thick) in clay brick in strecher bond
            with cement and sand (1:3) mortar including brick
            reinforcement 'Exmet' at every fourth course.             M2      65              44.50        2,892.50
  B         Horizontal damp proof course [DPC] as described laid
            on half brickwall (measured ne -no allowance made for
            laps).                                                     M      20                  2.30        46.00
  C         6mm Diameter mild steel wall bonding es, 450mm
            long, one end cast into concrete and the other end cast
            into concrete and the other end built into joints of
            brickwall as work proceeds.                               Nr      392                 0.30       117.60
                                                                       TOTAL CARRIED TO COLLECTION         3,056.10
                                                                       BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                           INTERNAL WALL AND PARTITION
 Item                                 Descrip on                                       Amount
        INTERNAL WALL AND PARTITION
        COLLECTION
        Page NO.1/7/1                  …………………………………………………………                                3,056.10
                                              TOTAL CARRIED TO COLLECTION SUMMARY            3,056.10
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                            INTERNAL FLOOR FINISHES
 Item                           Descrip on                            Unit    Qty          Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        INTERNAL FLOOR FINISHES
        INTERNAL FLOOR FINISHES
          Cement and sand (1:3) rendering with cemen ous water
          proofing as specified, trowelled smooth to falls.
  A         20 mm thick On concrete floor slab                         M2       -              15.00
  B         20 mm thick on apron floor slab                            m2      159             15.00        2,385.00
          "White Horse" or approved equivalent Floor Tiles bedded
          and jointed in cement and sand (1:3) mortar; poin ng with
          grout in white cement; on and including 20mm thick
          cement and sand (1:6) screed.
  C         600x600 ceramic les                                       M2      392             94.30       36,965.60
  D         300 mm x 300 mm non slipped ceramic les                   M2      47              88.40        4,154.80
          300 mm x 150 mm skir ng
  E         ceramic les                                                M      59                  9.80       578.20
          Extra over ceramic les for Drop:
  F         150 mm                                                     m      17
  G         50 mm                                                      M       2                  5.00        10.00
          Water proofing to toilet
  H         Approved cementa ous water proofing                        m2      26              40.00        1,040.00
                                                                       TOTAL CARRIED TO COLLECTION        45,133.60
                                                                   BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                           INTERNAL FLOOR FINISHES
 Item                             Descrip on                                       Amount
        INTERNAL FLOOR FINISHES
        COLLECTION
        Page NO.1/8/1              …………………………………………………………                               45,133.60
                                          TOTAL CARRIED TO COLLECTION SUMMARY           45,133.60
                                                                                 BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                          INTERNAL WALL FINISHES
 Item                           Descrip on                         Unit    Qty          Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        INTERNAL WALL FINISHES
        INTERNAL WALL FINISHES
          Plaster and Pain ng
  A         20 mm thick cement and sand (1:3) plastering in two
            coats as specified on walls                             M2      364             15.50        5,642.00
  B         Prepare and apply one undercoat and two coats of
            approved emulsion paint as described to wall and
            column, all as per Architect's approval.               M2      364                 5.40     1,965.60
          Ceramic Tiles
  C         "White Horse" Ceramic        le or other approved
            equivalent, 300mm x 600mm, bedded and jointed in
            cement and sand (1:3) mortar, poin ng with grout in
            white cement, on and including 20mm thick cement and
            sand (1:6) screed.                                     M2      63              70.00        4,410.00
                                                                    TOTAL CARRIED TO COLLECTION        12,017.60
                                                                  BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                           INTERNAL WALL FINISHES
 Item                            Descrip on                                       Amount
        INTERNAL WALL FINISHES
        COLLECTION
        Page NO.1/9/1             …………………………………………………………                               12,017.60
                                         TOTAL CARRIED TO COLLECTION SUMMARY           12,017.60
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                           INTERNAL CEILING FINISHES
 Item                           Descrip on                            Unit    Qty          Rate          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        INTERNAL CEILING FINISHES
        INTERNAL CEILING FINISHES
          Skim Coat and Pain ng
  A         3 mm thick approved skimcoat to underside of concrete
            surface                                                   M2      10                  9.80        98.00
  B         Prepare and apply one undercoat and two coats of
            approved emulsion paint as described to ceiling, all as
            per Architect's approval.                                 M2      740             12.00        8,880.00
          Suspended plain fibrous plasterglass ceiling, pressure
          treated mber suspension system, fixing all in accordance
          to manufacturer's specifica on
              13mm thick fix plaster ceiling panel to be skim to fine
              finish and all join ng to be finish with fiber join ng
              stripe including all necessary works and to be
              approved by Architect's
  C         less than 3.50 m high from ground level                   m2      109             35.00        3,815.00
  D         5.0 m to 6.5m high from ground level                      m2      631             40.00       25,240.00
  E         Prepare and apply one undercoat and two coats of
            approved emulsion paint as described to ceiling, all as
            per Architect's approval.                                 M2      740             15.00       11,100.00
  F         Decora ve cornite: 100 mm x 100 mm                         M      495             25.00       12,375.00
                                                                       TOTAL CARRIED TO COLLECTION        61,508.00
                                                                     BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                            INTERNAL CEILING FINISHES
 Item                               Descrip on                                        Amount
        INTERNAL CEILING FINISHES
        COLLECTION
        Page NO.1/10/1               …………………………………………………………                                61,508.00
                                            TOTAL CARRIED TO COLLECTION SUMMARY            61,508.00
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                  EXTERNAL FINISHES
 Item                            Descrip on                           Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        EXTERNAL FINISHES
        EXTERNAL FLOOR FINISHES
          Cement and sand (1:3) rendering with cemen ous water
          proofing as specified, trowelled smooth to falls.
  A         on Apron floor slab                                        M2      159             15.00       2,385.00
        EXTERNAL WALL FINISHES
          Plaster and Pain ng
  B         19mm thick cement and sand (1:3) with an approved
            plas ciser as specified; steel trowelled to walls.         M2      68              14.00         952.00
  C         Prepare and apply one undercoat and two coats of
            approved An fungal external paint as described to wall
            and column, all as per Architect's approval.              M2      68              15.00       1,020.00
        EXTERNAL CEILING FINISHES
          Suspended plain fibrous plasterglass ceiling, pressure
          treated mber suspension system, fixing all in accordance
          to manufacturer's specifica on
  D         13mm thick fix plaster ceiling panel to be skim to fine
            finish and all join ng to be finish with fiber join ng
            stripe including all necessary works and to be approved
            by Architect's.                                           M2      268             35.00       9,380.00
  E         Prepare and apply one undercoat and two coats of
            approved emulsion paint as described to ceiling, all as
            per Architect's approval.                                 M2      268             12.00       3,216.00
  F         Decora ve cornite: 100 mm x 100 mm                         M      79              25.00       1,975.00
          Skim Coat and Pain ng
  G         Prepare and apply one undercoat and two coats of
            approved emulsion paint as described to ceiling, all as
            per Architect's approval.                                 M2      268             12.00       3,216.00
                                                                       TOTAL CARRIED TO COLLECTION       22,144.00
                                                             BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                           EXTERNAL FINISHES
 Item                       Descrip on                                       Amount
        EXTERNAL FINISHES
        COLLECTION
        Page NO.1/11/1       …………………………………………………………                               22,144.00
                                    TOTAL CARRIED TO COLLECTION SUMMARY           22,144.00
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                            FITTINGS AND FURNITURE
 Item                          Descrip on                             Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        FITTINGS AND FURNITURE
        Mimbar
  A         Allow a Provisional Sum for The Design, Construct and
            supply "Mimbar" , to be expended in accordance with
            the instruc ons given by the S.O. and the amount to be
            finalized a er the appointment of the carpenter             nr      1          10,000.00      10,000.00
        Curtain and Railing
  B         Supply and install stainless steel railing and suitable
            fabric for the curtain and its accessories                 m       8             100.00         800.00
                                                                       TOTAL CARRIED TO COLLECTION       10,800.00
                                                                  BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                          FITTINGS AND FURNITURE
 Item                            Descrip on                                       Amount
        FITTINGS AND FURNITURE
        COLLECTION
        Page NO.1/12/1            …………………………………………………………                               10,800.00
                                         TOTAL CARRIED TO COLLECTION SUMMARY           10,800.00
                                                                                         BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                       SANITARY FITTINGS
 Item                             Descrip on                               Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        SANITARY FITTINGS
        SANITARY FITTINGS
        Notes:-
        The whole works under this sec on shall be executed by a
        Licensed plumber registered with the relevant Authority and
        shall be carried out to comple on and to the sa sfac on of the
        Authority concerned.
        Materials and fi ngs used shall be as per requirement or as
        stated in the drawings and shall be approved by the Architect
        before installa on.
        Fixing of all fi ngs to be in accordance to Manufacturer's
        details and to include for all brackets, etc.
        On comple on of the works, the tenderer is responsible for
        arranging to test of the plumbing and sanitary installa ons to
        the sa sfac on of the Authority and the S.O.
        All piping, bends, tees, junc on, reducer etc, shall be of
        approved type and shall include for all fixing accessories.
        Supply and fix the following sanitary wares and fi ngs in
        standard white colour including all accessories unless otherwise
        stated including storing, assembling, bedding, plugging and
        screwing with matching screws, cu ng and pining or building
        in brackets join ng and connec ng to services and to soil and
        waste pipe and making good all works described:-
        The tenderer is to allow for any other items deemed required for
        the due comple on of the works. (Tenderer to list the items and
        indicate costs)
          Supply and fix the following sanitary wares and fi ngs in
          standard white colour including all accessories unless
          otherwise stated including storing, assembling, bedding,
          plugging and screwing with matching screws, cu ng and
          pining or building in brackets join ng and connec ng to
          (Cont'd)
                  WC pedestal and squat type
  A         Approved pedestal type (tandas duduk)                          Nr       3             450.00       1,350.00
                                                                            TOTAL CARRIED TO COLLECTION        1,350.00
                                                                                   BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                 SANITARY FITTINGS
 Item                           Descrip on                           Unit    Qty          Rate        Amount
        SANITARY FITTINGS (Cont'd)
        SANITARY FITTINGS (Cont'd)
          Supply and fix the following sanitary wares and fi ngs in
          standard white colour including all accessories unless
          otherwise stated including storing, assembling, bedding,
          plugging and screwing with matching screws, cu ng and
          pining or building in brackets join ng and connec ng to
          (Cont'd) (Cont'd)
              Wash hand basin
  A         Approved white glazed ceramic wash hand basin come
            with stopper, bo le traps and connec on to waste pipes   Nr       4             180.00         720.00
              Hand Spray Flexible Hose
  B         chrome hand spray bidet with 1.2m flexible hose and
            wall bracket                                             Nr       3             250.00         750.00
          Mirror
  C         DOE silver plated quality mirror size 300mm x 450mm x
            6mm thick with 20mm bevelled edge fixed on 6mm thick
            water proofed plywood backing and 3/8" (9.5mm)
            aluminium framing around including 2 nos fixing
            bracket                                                  Nr       3             150.00         450.00
          Abuli on facili es
  D         Construct and complete 1050mm x 150mm high
            reinforced concrete ablu on kerb including all
            necessary concrete work, 675 mm x 1000 mm high half
            brickwall, reinforcement, formwork, brickwork and
            300mm x 300mm x 10mm Thick non slip ceramic floor
             le, 300 mm x 300 mm x 10 mm ceramic wall le to
            brickwall including all other item to complete
            construc on of ablu on kerb                              Nr       -
          Bib Tap
  E         1/2" "DOE" or approved equivalent chrome plated brass
            bib tap                                                  Nr      18              90.00       1,620.00
          Shower Rose
  F         Approved Chrome plated shower rose                       Nr       3              30.00          90.00
                                                                      TOTAL CARRIED TO COLLECTION        3,630.00
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                                  SANITARY FITTINGS
 Item                          Descrip on                             Unit    Qty          Rate        Amount
        SANITARY FITTINGS (Cont'd)
        SANITARY FITTINGS (Cont'd)
          Floor Trap
  A         Resistant stainless steel floor trap, 150 MM Chess
            square and plas c collar with Stainless steel lining
            including 100 mm trap body with inlet and                 Nr      10              38.00         380.00
          Tes ng
  B         On Comple on of Sanitary Installa on and fi ngs, test
            all apparatus, fi ngs and pipings, make good all defects
            and leave the whole works in perfect working order and
            to the sa sfac on of the S.O and Local Authori es.        Item     -                  -         300.00
                                                                       TOTAL CARRIED TO COLLECTION          680.00
                                                             BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                           SANITARY FITTINGS
 Item                       Descrip on                                       Amount
        SANITARY FITTINGS
        COLLECTION
        Page NO.1/13/1       …………………………………………………………                                1,350.00
        Page NO.1/13/2       …………………………………………………………                                3,630.00
        Page NO.1/13/3       …………………………………………………………                                   680.00
                                    TOTAL CARRIED TO COLLECTION SUMMARY            5,660.00
                                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                          SOIL, WASTE AND VENT PIPES
 Item                          Descrip on                             Unit    Qty          Rate         Amount
        BANGUNAN MASJID & DEWAN UTILITI
        SOIL, WASTE AND VENT PIPES
        SOIL AND WASTE AND VENT PIPES INSTALLATIONS
        (ALL QUANTITIES ARE PROVISIONAL)
          Excavate trench
  A         to receive soil and waste pipes commencing from
            reduced level, average depth 0.75 m including grading
            bo oms, filling in, compac on and disposal of surplus
            soil                                                       M      39              12.00          468.00
          Supply and install UPVC waste, soil and vent pipe to
          BS4515, BS5255 and BS4660 including all joints, bends,
          tees, branches, expansion joints, and fi ngs in accorcance
          to the manufacturer's specifica on:
  B         110 mm Laid in trench under concrete bed                   M       8              25.00          200.00
  C         75 mm diameter laid in trench                              m      28
          Gully Trap
  D         300mm x 300 mm Gully trap at Ground Floor of deep
            sealed coated cast iron type with outlet to suit come
            with all necessary extension piece and 300 mm x 300
            mild steel cover to be bedded and surrounded with plain
            concrete Grade 30 and 115 mm brickwall on all sides
            plastered internally with high alumina cement and sand
            rendering                                                  nr      2             150.00          300.00
          Manholes
  E         Half brickwall manholes overall dimension 600mm x
            450 mm x 600 mm deep, including all excava on works,
            common bricks, 100 mm thick concrete base, plastering
            internally and on any exposed concrete surfaces,
            formworks and reinfocements and to provide pre cast
            iron manhole cover                                        Nr       3             500.00        1,500.00
                                                                       TOTAL CARRIED TO COLLECTION         2,468.00
                                                                      BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                            SOIL, WASTE AND VENT PIPES
 Item                                Descrip on                                        Amount
        SOIL, WASTE AND VENT PIPES
        COLLECTION
        Page NO.1/14/1                …………………………………………………………                                 2,468.00
                                             TOTAL CARRIED TO COLLECTION SUMMARY             2,468.00
                                                                                   BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                                         COLD WATER INSTALLATIONS
 Item                          Descrip on                            Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        COLD WATER INSTALLATIONS
        Supply and install cold water system pipes including all
        necessary elbows, bend, reducers and connec ons with
        requisite connectors to water tank storage and sanitary
        appliances with requisite pipe fi ngs and stopcock complete
          HDPE Pipes for Cold Water
  A         25 mm diameter , chased in brickwall                      m      60              15.00         900.00
          Cold Water Storage Tank and associated fi ngs and
          accessories
  B         400 gallon HDPE tanks with proper mber support and
            12 mm thick waterproof plywood based                      nr      1           1,300.00       1,300.00
                                                                      TOTAL CARRIED TO COLLECTION        2,200.00
                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                          COLD WATER INSTALLATIONS
 Item                              Descrip on                                       Amount
        COLD WATER INSTALLATIONS
        COLLECTION
        Page NO.1/15/1              …………………………………………………………                                2,200.00
                                           TOTAL CARRIED TO COLLECTION SUMMARY            2,200.00
                                                                                   BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                        BUILDER'S WORK IN CONNECTION WITH SERVICES
 Item                           Descrip on                            Unit    Qty         Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        BUILDER'S WORK IN CONNECTION WITH SERVICES
        Construct and complete reinforced concrete ablu on kerb
        including all necessary concrete work, 675 mm x 1000 mm
        high half brickwall, reinforcement, formwork, brickwork and
        300mm x 300mm x 10mm Thick non slip ceramic floor le,
        300 mm x 300 mm x 10 mm ceramic wall le to brickwall,
        provide floor traps and including all other item to complete
        construc on of ablu on kerb
  A         overall length 5.10 m x 0.60 m in the Muslimah Wudhuk
            Area                                                       nr      1          1,000.00       1,000.00
  B         overall length 7.00 m x 0.60 m in the Muslimin wudhuk
            area                                                       nr      1          1,500.00       1,500.00
                                                                       TOTAL CARRIED TO COLLECTION       2,500.00
                                                                           BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                BUILDER'S WORK IN CONNECTION WITH SERVICES
 Item                                    Descrip on                                        Amount
        BUILDER'S WORK IN CONNECTION WITH SERVICES
        COLLECTION
        Page NO.1/16/1                     …………………………………………………………                                2,500.00
                                                 TOTAL CARRIED TO COLLECTION SUMMARY             2,500.00
                                                         BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                ELECTRICAL INSTALLATIONS
 Item                         Descrip on   Unit    Qty          Rate        Amount
        BANGUNAN MASJID & DEWAN UTILITI
        ELECTRICAL INSTALLATIONS
                                            TOTAL CARRIED TO COLLECTION
                                                                    BANGUNAN MASJID & DEWAN UTILITI
Masjid RPS DALA
                                                                           ELECTRICAL INSTALLATIONS
 Item                              Descrip on                                       Amount
        ELECTRICAL INSTALLATIONS
        COLLECTION
        Page NO.1/17/1              …………………………………………………………
                                           TOTAL CARRIED TO COLLECTION SUMMARY
Masjid RPS DALA                                                         BANGUNAN MASJID & DEWAN UTILITI
 Item                                Descrip on                        Page No.          Amount
        BANGUNAN MASJID & DEWAN UTILITI
        COLLECTION SUMMARY
        WORK BELOW LOWEST FLOOR FINISH                                   1/1/4              117,195.67
        FRAME                                                            1/2/3                57,830.30
        ROOF                                                             1/3/3              112,660.00
        STEPS AND RAMPS                                                  1/4/3                 3,745.99
        EXTERNAL WALLS                                                   1/5/2                21,198.20
        WINDOWS AND DOORS                                                1/6/3                27,396.00
        INTERNAL WALL AND PARTITION                                      1/7/2                 3,056.10
        INTERNAL FLOOR FINISHES                                          1/8/2                45,133.60
        INTERNAL WALL FINISHES                                           1/9/2                12,017.60
        INTERNAL CEILING FINISHES                                       1/10/2                61,508.00
        EXTERNAL FINISHES                                               1/11/2                22,144.00
        FITTINGS AND FURNITURE                                          1/12/2                10,800.00
        SANITARY FITTINGS                                               1/13/4                 5,660.00
        SOIL, WASTE AND VENT PIPES                                      1/14/2                 2,468.00
        COLD WATER INSTALLATIONS                                        1/15/2                 2,200.00
        BUILDER'S WORK IN CONNECTION WITH SERVICES                      1/16/2                 2,500.00
        ELECTRICAL INSTALLATIONS                                        1/17/2
                                                     TOTAL CARRIED TO FINAL SUMMARY         507,513.46
Item                            Descrip on                      Page No.       Amount
       MASJID RPS DALA
       FINAL SUMMARY
       BANGUNAN MASJID & DEWAN UTILITI                            1.S/1           507,513.46
                                             TOTAL CARRIED TO FORM OF TENDER      507,513.46