Analisis Biaya Siklus Hidup Gedung Komite Olahraga
Analisis Biaya Siklus Hidup Gedung Komite Olahraga
ABSTRACT: The Indonesian National Sports Committee Building or the abbreviation KONI Tapin Regency has been established
since 2012 and has been operating for almost 10 years. So that the function of the building does not decrease during the design life,
routine maintenance is needed. However, the maintenance carried out on the building so far has only been carried out if there is
damage or as needed. Therefore, it is necessary to study life cycle costs at KONI Tapin Regency to analyze operating costs throughout
the life of the plan. The purpose of this study was to determine the life cycle costs of the Tapin Regency Indonesian National Sports
Committee (KONI) Building for 2021-2035 and to determine the largest maintenance costs during the life cycle of the Tapin Regency
Indonesian National Sports Committee (KONI) Building for 2021-2035. The research method used is the life cycle cost analysis
method which is equipped with interviews with building managers and field identification. The research results obtained are, the total
maintenance costs for the years 2021 to 2035 with an inflation rate of 4.50% is IDR. 1,939,225,599. For maintenance costs per year
of IDR. 129,281,707 for 15 years. The biggest maintenance cost during the life cycle of the Tapin Regency Indonesian National
Sports Committee (KONI) Building for 2021-2035 is the electrical component of IDR. 51,329,237 per year or 39.703%. While the
smallest maintenance costs are mechanical components of IDR. 3,257,850 per year or 2.520% of the total maintenance cost.
KEYWORDS: building maintenance; life cycle cost; maintenance components.
ABSTRAK: Gedung Komite Olahraga Nasional Indonesia atau disingkat KONI Kabupaten Tapin telah berdiri sejak tahun 2012
dan beroperasi hampir 10 tahun lamanya. Supaya fungsi gedung tidak menurun selama umur rencana, maka perlu dilakukan
pemeliharaan berkala. Namun selama ini, pemeliharaan pada gedung tersebut hanya dikerjakan jika terjadi kerusakan atau
menyesuaikan kebutuhan. Berdasarkan hal tersebut, perlu dilakukan penelitian tentang biaya siklus hidup pada Gedung KONI
Kabupaten Tapin untuk menentukan biaya operasional sepanjang umur rencana. Tujuan penelitian ini adalah untuk menghitung biaya
siklus hidup Gedung KONI Kabupaten Tapin untuk tahun 2021-2035 dan untuk mengetahui biaya pemeliharaan terbesar selama
siklus hidup Gedung KONI Kabupaten Tapin untuk tahun 2021-2035. Metode penelitian adalah dengan analisis biaya siklus hidup
yang dilengkapi wawancara dengan pengelola gedung dan identifikasi lapangan. Hasil penelitian yang didapatkan adalah, total biaya
pemeliharaan untuk tahun 2021 sampai 2035 dengan tingkat inflasi 4.50% adalah sebesar Rp. 1,939,225,599. Untuk biaya
pemeliharaan per tahun sebesar Rp. 129,281,707 selama 15 tahun. Biaya pemeliharaan terbesar selama siklus hidup Gedung KONI
Kabupaten Tapin untuk tahun 2021-2035 adalah komponen elektrikal sebesar Rp. 51,329,237 per tahun atau mencapai 39.703%.
Sedangkan biaya pemeliharaan terkecil adalah komponen mekanikal sebesar Rp. 3,257,850 per tahun atau mencapai 2.520% dari
total biaya pemeliharaan.
KATA KUNCI: pemeliharaan gedung; biaya siklus hidup; komponen pemeliharaan.
© The Author(s) 2020. This article is distributed under a Creative Commons Attribution-ShareAlike 4.0 International license.
   DOI 10.22225/pd.11.1.3974.24-32
   ISSN Print: 2303-2693                                                                                                                                   24
   ISSN Online: 2581-2939
Vol. 11 No. 1 (Juni 2022)                                    PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa
sebagai biaya siklus hidup. Biaya siklus hidup          4.     Analisi data dan pembahasan. Tahapan ini
adalah konsep pemodelan perhitungan biaya dari tahap           meliputi analisis data dan pembahasan. Data yang
permulaan sampai pembongkaran suatu aset dari                  diperoleh akan diolah dengan menggunakan
sebuah proyek sebagai alat untuk mengambil                     analisis Life Cycle Cost (LCC) atau biaya siklus
keputusan atas sebuah studi analisis dan perhitungan           hidup. Hasil penelitian dibahas dalam bentuk
dari total biaya yang ada selama siklus hidupnya               tabel dan pembahasan.
(Kamagi et al., 2013). Tujuan dari biaya siklus
hidup adalah untuk mengelola proses dari perencanaan    2.2 Teknik Pengolahan Data
hingga pemusnahan atau penggantian suatu aset, untuk         Cara yang dipakai adalah melakukan studi
mengelola biaya daur hidup, untuk memastikan            pustaka dan lapangan. Kedua cara ini saling
pelayanan sesuai tujuan dirancangnya suatu bangunan,    mendukung untuk mencapai tujuan penelitian
untuk menjaga keberlanjutan dan meminimalisir resiko    (Mahardhika et al., 2014). Selain itu juga dilakukan
kegagalan serta memaksimalkan kelebihan penyediaan      penggunaan internet untuk mendapatkan informasi–
layanan (Buyung et al., 2019).                          informasi yang terkait dengan penelitian
     Berdasarkan latar belakang di atas, perlu
dilakukan suatu penelitian untuk mengidentifikasi       2.3 Metode Analisis Data
biaya siklus hidup pada bagian-bagian komponen               Analisis data meliputi identifikasi lokasi
bangunan Gedung KONI Kabupaten Tapin dengan             penelitian dengan melakukan survei lapangan.
membuat financial schedule biaya pemeliharaan           Kemudian        melakukan     identifikasi   komponen
sepanjang umur rencana. Hasil penelitian ini            bangunan yang ditinjau untuk melakukan analisis
diharapkan dapat memberikan gambaran dan masukan        semua biaya pemeliharaan yang diperlukan sepanjang
tentang biaya siklus hidup Gedung KONI Kabupaten        umur rencana Gedung KONI Kabupaten Tapin. Dalam
Tapin dan dapat menghitung biaya pemeliharaan           penelitian ini, peneliti menggunakan analisis Life Cycle
terbesar sepanjang umur rencana bangunan. Sebagai       Cost aktual (Firsani & Utomo, 2012), yaitu perhitungan
perbandingan, Hudaya (2018) melakukan penelitian        Life Cycle Cost berdasarkan pada biaya pemeliharaan
dengan judul “Identifikasi Life Cycle Cost Pada         Gedung KONI Kabupaten Tapin selama dua tahun
Pemeliharan Gedung (Studi Kasus: Gedung Kantor          terakhir.
Badan Pengelola Keuangan Daerah Pematangsiantar)”.
Hasil penelitian didapatkan bahwa komponen biaya        2.4 Komponen Bangunan Yang Ditinjau
pemeliharaan terbesar adalah dari komponen elektrikal
                                                              Identifikasi dilakukan untuk menentukan
dengan persentase mencapai 29.860% dari keseluruhan
                                                        komponen bangunan yang ditinjau. Komponen yang
biaya pemeliharaan. Sedangkan biaya pemeliharaan
                                                        ditinjau merupakan komponen–komponen yang
terkecil adalah dari komponen mekanikal sebesar
                                                        mendukung berjalannya fungsi dari bangunan
14.770% dari keseluruhan biaya pemeliharaan.
                                                        (Wongkar et al., 2016) dalam hal ini Gedung KONI
                                                        Kabupaten Tapin. Komponen-komponen yang diamati
2    METODOLOGI                                         adalah komponen arsitektural, komponen struktur,
                                                        komponen         mekanikal, komponen     elektrikal,
2.1 Tahap-Tahap Penelitian                              komponen tata ruang luar bangunan gedung dan
     Tahap-tahap yang dilakukan dalam penelitian ini    komponen kebersihan.
antara (Krisnanda, 2020):
1. Studi pustaka. Tahapan ini meliputi pencarian        2.5 Perhitungan
     bahan-bahan pustaka dari internet maupun                Nilai inflasi dipakai untuk menghitung biaya
     perpustakaan. Studi pustaka dilakukan untuk        pemeliharaan Gedung KONI Kabupaten Tapin selama
     mendapatkan teori-teori pendukung yang sesuai      10 tahun ke depan. Nilai inflasi didapat berdasarkan
     dengan penelitian                                  laman Badan Pusat Statistik (BPS) Provinsi Kalimantan
2. Persiapan. Tahapan ini meliputi persiapan untuk      Selatan selama 10 (sepuluh) tahun terakhir. Langkah
     menentukan data-data yang akan dibutuhkan          berikutnya adalah menentukan rata-ratanya. Data
     dalam penelitian.                                  inflasi Provinsi Kalimantan Selatan dalam 10 tahun
3. Pengambilan data. Data yang dibutuhkan adalah        terakhir terlihat pada Tabel 1.
     data primer dan data sekunder. Data sekunder            Kemudian kita akan menggunakan tabel bunga
     berupa Rencana Anggaran Biaya (RAB)                untuk memperoleh nilai faktor inflasi. Tabel bunga
     Pembangunan Gedung KONI Kabupaten Tapin            yang dipakai merupakan tabel bunga yang didapatkan
     dan pustaka yang diperoleh di perpustakaan dan     dari buku tabel bunga majemuk. Setelah memperoleh
     internet. Data primer adalah data yang diperoleh   nilai faktor inflasi, langkah berikutnya adalah
     langsung di lapangan berupa wawancara dengan       menghitung biaya pemeliharaan selama sepuluh tahun
     pengelola Gedung KONI Kabupaten Tapin dan          dengan memakai rumus suku bunga pembayaran
     gambar-gambar komponen gedung yang                 tunggal. Setelah memperoleh jumlah biaya
     dijadikan studi.                                   pemeliharaan selama sepuluh tahun ke depan. Langkah
                                                                                      DOI 10.22225/pd.11.1.3974.24-32
25                                                                                              ISSN Print: 2303-2693
                                                                                              ISSN Online: 2581-2939
PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa                                                                                    Cahyadi et al.
terakhir adalah menentukan biaya pemeliharaan                                       Penurunan rumus pembayaran tunggal (mencari F
terbesar melalui cara menghitung persentase biaya                             bila diketahui P) (Utari & Samad, 2021):
pemeliharaan komponen setiap tahunnya.                                        F = P (1 + i)n......................................................... (2)
                                                                                    Persamaan tersebut juga dapat dinyatakan sebagai
  Tabel 1. Inflasi Provinsi Kalimantan Selatan Sepuluh                        berikut (Rahman & Apriadi, 2021):
                     Tahun Terakhir
                                                                              F/P = (F/P, i%, N) ............................................... (3)
     No                   Tahun                      Inflasi (%)                    Dimana artinya adalah kita ingin mendapatkan
       1                   2011                          3.98                 nilai F dengan mengetahui nilai P, i%, dan N. Dengan
                                                                              demikian, persamaan tersebut juga bisa dituliskan
       2                   2012                          5.96                 dengan (Wongkar et al., 2016):
       3                   2013                          6.98                 F = P (F/P, i%, N) ............................................... (4)
       4                   2014                          7.28                       Dengan menggunakan rumus ini kita dapat
                                                                              dengan mudah mendapatkan nilai-nilai F pada berbagai
       5                   2015                          5.14
                                                                              nilai P, i%, dan N yang berbeda karena faktor (F/P, i%,
       6                   2016                          3.57                 N) telah tersedia dalam bentuk tabel.
       7                   2017                          3.82
                                                                              2.8 Diagram Alir Penelitian
       8                   2018                          2.63                      Diagram alir yang merupakan proses pada studi
       9                   2019                          4.01                 ini dapat dilihat pada Gambar 1.
      10                   2020                          1.68
                                                                              3     HASIL DAN PEMBAHASAN
                        Rata-Rata                        4.50
Sumber: Anonim, 2021                                                          3.1 Identifikasi Komponen Bangunan Yang
                                                                                   Ditinjau
2.6 Bunga Sederhana                                                                Komponen penelitian yang menjadi bahan studi
     Bunga sederhana dihitung hanya dari induk tanpa                          adalah komponen-komponen di dalam Gedung KONI
memperhitungkan bunga yang telah diakumulasikan                               Kabupaten Tapin yang mendukung jalannya fungsi
pada periode sebelumnya. Secara sistematis                                    dari bangunan tersebut. Pada penelitian ini penulis
dirumuskan (Kaming et al., 2019):                                             meneliti 6 (enam) komponen pemeliharaan yaitu:
I=P x i x N ........................................................... (1)   komponen arsitektural, struktur, mekanikal,
                                                                              elektrikal, tata ruang luar bangunan gedung dan
dimana, I = bunga yang terjadi (rupiah), P = induk yang
                                                                              komponen kebersihan.
dipinjam, i = tingkat bunga per periode, N = jumlah
periode pemajemukan.
                                                                              3.2 Estimasi Biaya Pemeliharaan
2.7 Bunga Majemuk                                                                  Berdasarkan hasil wawancara dan survei
                                                                              lapangan, maka didapatkanlah estimasi biaya
     Bunga majemuk adalah besarnya bunga pada
                                                                              pemeliharaan Gedung KONI Kabupaten Tapin untuk
suatu periode dihitung bedasarkan besarnya induk
                                                                              dua tahun terakhir. Datanya adalah sebagai berikut
ditambah dengan besarnya bunga yang telah
terakumulasi pada periode sebelumnya. Ada beberapa                            3.2.1 Komponen struktur
notasi yang diterapkan oleh standar nasional Amerika                                Yang termasuk dalam pemeliharaan komponen
untuk Ekonomi Teknik (Mulyandari & Saputra, 2010).                            struktur adalah pemeliharaan dinding. Berdasarkan
Notasi tersebut adalah sebagai berikut:                                       hasil wawancara dan analisis lapngan, maka komponen
1. r = tingkat bunga nominal per periode                                      kerusakan struktur pada Gedung KONI Kabupaten
2. i = tingkat bunga efektif per periode                                      Tapin dapat dilihat pada Tabel 2. Diasumsikan
3. N = jumlah periode pemajemukan                                             kerusakan dinding akibat retak mencapai 6% volume
4. P = nilai sekarang (present worth).                                        awal dan biaya perbaikan adalah Rp. 250,000/m2.
5. F = nilai mendatang (future worth)                                               Tabel 2 merupakan hasil wawancara terkait biaya
6. A = aliran kas pada akhir periode yang besarnya                            pemeliharaan komponen struktur. Berdasarkan tabel
     sama untuk beberapa periode yang berurutan                               diatas, rata-rata biaya pemeliharaan komponen struktur
7. G = aliran kas dari satu periode ke periode                                untuk dinding selama kurun waktu 2 tahun (2019-
     berikutnya terjadi penambahan atau pengurangan                           2020) adalah sebesar 6% atau Rp. 6,927,690.00.
     kas
DOI 10.22225/pd.11.1.3974.24-32
ISSN Print: 2303-2693                                                                                                                                26
ISSN Online: 2581-2939
     Vol. 11 No. 1 (Juni 2022)                                                        PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa
 4
 5                                                                     Pengumpulan Data
 6
 7
 8
 9                                   Data Primer :                            Data Sekunder:
                                     Wawancara                                Pemeliharaan Gedung Tahun 2020
10                                   Observasi Lapangan                       Data Inflasi Berdasarkan BPS Kalsel
11                                                                            RAB
12
13
14
                                                                          Data Cukup
15
                                                                                                                    Tidak
16
                                                                                        Ya
17
18
19                                          Analisis biaya LCC                                Analisis Komponen
20                                        Komponen pemeliharaan                            pemeliharaan biaya terbesar
21
22
23                                        Hasil analisis biaya LCC                    Hasil analisis biaya LCC komponen
                                                                                                     terbesar
24
25
26                                 Pembahasan analisis biaya LCC                      Pembahasan analisis LCC komponen
27                                                                                                terbesar
28
29
30                                 Kesimpulan analisis biaya LCC                           Kesimpulan analisis biaya LCC
                                                                                                     terbesar
31
32
33
34
                                                                          Saran
35
                                                       Gambar 1. Diagram Alir Penelitian
                      Tabel 2. Biaya Pemeliharaan Komponen Struktur Gedung KONI Tapin Tahun 2019-2020
                                                                                                                     Vol
       Tahun       Komponen          Bidang         Rusak ringan              Satuan            Vol. awal                            % kerusakan
                                                                                                                  kerusakan
                                                  Retak kecil
                   Struktur        Dinding                                m2                   329.89            19.7934           6,00%
      2019                                        0.075 -0.6 cm
                   Biaya                                                                                         350,000.00        6,927,690.00
                                                  Retak kecil
                   Struktur        Dinding                                m2                   329.89            19.7934           6,00%
      2020                                        0.075 -0.6 cm
                   Biaya                                                                                         350,000.00        6,927,690.00
                     Tabel 3. Biaya Pemeliharaan Komponen Arsitektur Gedung KONI Tapin Tahun 2019-2020
       Komponen                  Bidang               Satuan         Vol. awal        Vol. kerusakan          % kerusakan               Biaya
                       Cat pelapis                   m2              909.75           260                    28.58%              10,000,000.00
      Arsitektur       Plafond Silika Board          m2              166.07           10                     6.02%               1,500,000.00
                                                       2
                       Pasangan keramik              m               144.71           30                     20.73%              7,500,000.00
      Biaya                                                                                                                      19,000,000.00
                                                                                                                         DOI 10.22225/pd.11.1.3974.24-32
     27                                                                                                                            ISSN Print: 2303-2693
                                                                                                                                 ISSN Online: 2581-2939
PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa                                                              Cahyadi et al.
               Tabel 4. Biaya Pemeliharaan Komponen Mekanikal Gedung KONI Tapin Tahun 2019-2020
    Komponen                              Bidang                    Harga Per Bulan (Rp)          Harga Per Tahun (Rp)
 Mekanikal             Biaya Air PDAM                             125,000.00                    1,500,000.00
                       Perawatan Jaringan Air Bersih                                            750,000.00
 Biaya                                                                                          2,250,000.00
               Tabel 5. Biaya Pemeliharaan Komponen Elektrikal Gedung KONI Tapin Tahun 2019-2020
     Komponen                     Tahun               Bidang             Harga Per Bulan (Rp)       Harga Per Tahun (Rp)
                                               Biaya Listrik            1,100,000.00               13,200,000.00
                                               Jaringan Listrik                                    4,500,000.00
                        2019                   Jaringan
                                                                        1,000,000.00               12,000,000.00
                                               Internet/Komputer
                                               Generator Set                                       5,000,000.00
 Elektrikal
                        2020                   Biaya Listrik            1,100,000.00               13,200,000.00
                                               Jaringan Listrik                                    5,000,000.00
                                               Jaringan
                                                                        1,000,000.00               12,000,000.00
                                               Internet/Komputer
                                               Generator Set                                       6,000,000.00
DOI 10.22225/pd.11.1.3974.24-32
ISSN Print: 2303-2693                                                                                                        28
ISSN Online: 2581-2939
Vol. 11 No. 1 (Juni 2022)                                              PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa
           Tabel 6. Biaya Pemeliharaan Komponen Tata Ruang Luar Gedung KONI Tapin Tahun 2019-2020
            Tahun                                                         Komponen
                                 Atap                              Pengecatan Luar                Listplank Silika Board
 2019                            2,500,000.00                      5,000,000.00                   1,500,000.00
 2020                                                                                             1,500,000.00
                                                                                                   DOI 10.22225/pd.11.1.3974.24-32
29                                                                                                           ISSN Print: 2303-2693
                                                                                                           ISSN Online: 2581-2939
PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa                                                 Cahyadi et al.
                Tabel 9. Rekapitulasi Biaya Pemeliharaan Gedung KONI Tapin 2021-2035 per Komponen
                 No.                      Komponen                    Biaya Pemeliharaan (Rp)
                  1        Struktur                                                150,462,499.00
                  2        Arsitektur                                              412,661,000.00
                  3        Mekanikal                                                48,867,750.00
                  4        Biaya Listrik                                           286,690,800.00
                  5        Jaringan Listrik                                        103,165,250.00
                  6        Jaringan Internet/Komputer                              260,628,000.00
                  7        Genset                                                  119,454,500.00
                  8        Atap                                                     15,615,000.00
                  9        Pengecatan Luar                                          37,800,000.00
                 10        Listplank                                                32,578,500.00
                 11        Kebersihan                                              471,302,300.00
                           Total                                                 1,939,225,599.00
DOI 10.22225/pd.11.1.3974.24-32
ISSN Print: 2303-2693                                                                                           30
ISSN Online: 2581-2939
Vol. 11 No. 1 (Juni 2022)                                     PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa
     Untuk biaya pemeliharaan per tahun dari 2021           129,281,707.00. Untuk perhitungan persentase per
sampai 2035 dapat dilihat pada Tabel 10 dan Gambar          komponen dapat dilihat pada Gambar 3. Dari Gambar
3. Dari Tabel 10 di atas terlihat peningkatan biaya         3 terlihat bahwa biaya elektrikal menjadi komponen
pemeliharaan Gedung KONI Tapin dari tahun ke                terbesar untuk pemeliharaan Gedung KONI Tapin.
tahun. Hal ini disebabkan adanya inflasi tahunan yang       Nilainya mencapai 39.703% dari total biaya
diperkirakan sebesar 450% per tahun (Berdasarkan            pemeliharaan. Sedangkan komponen mekanikal
data BPS). Biaya terbesar dicapai pada tahun 2035           menjadi komponen terkecil dengan nilai mencapai
yaitu sebesar Rp. 172,849,080.00. Sedangkan rata-rata       2.520% dari total biaya pemeliharaan.
biaya pemeliharaan tahunan adalah sebesar Rp
                       Tabel 10. Rekapitulasi Biaya Pemeliharaan Per Tahun Gedung KONI Tapin
                     No.               Tahun                  Biaya Pemeliharaan Total (Rp)
                       1               2021                                       90,734,936.00
                       2               2022                                      100,520,837.00
                       3               2023                                      102,052,894.00
                       4               2024                                      103,585,434.00
                       5               2025                                      114,697,302.00
                       6               2026                                      113,049,652.00
                       7               2027                                      121,727,486.00
                       8               2028                                      130,898,975.00
                       9               2029                                      129,025,947.00
                      10               2030                                      134,843,403.00
                      11               2031                                      153,641,341.00
                      12               2032                                      147,259,762.00
                      13               2033                                      153,858,667.00
                      14               2034                                      170,479,882.00
                      15               2035                                      172,849,080,00
                                       Total                                   1,939,225,599.00
                                     Rata-Rata                                   129,281,707.00
Gambar 3. Persentase Biaya Pemeliharaan Per Komponen Per Tahun Gedung KONI Tapin 2021-2035
                                                                                       DOI 10.22225/pd.11.1.3974.24-32
31                                                                                               ISSN Print: 2303-2693
                                                                                               ISSN Online: 2581-2939
PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa                                                      Cahyadi et al.