2023-24 SSR Rates Simplified
2023-24 SSR Rates Simplified
WORKS
(Worked out as per SSR 2023-24)
.
Lead Statement 2023-24 (conveaynce of lead for Example 1 Km)
BUILDING WORKS (Pl Prepare the estimates seniorage charges separately )
S. Material Machine
Blasting Conveyance
No per Item No Initial cost Crushing Lead charges
Loading Unloading Total Cost
Charges
Charges
1 Sand for Mortor for Plastering 1Cum 721.00 1 37.30 0 0 758.30
MAT-00029
2 Sand for Concrete 1Cum 605.00 1 37.30 0 0 642.30
MAT-00027
3 Sand for fillling 1Cum 460.00 1 37.30 0 0 497.30
MAT-00028
4 6mm size HBG Metal SS 5 1Cum 661.00 70.00 165.25 1 35.90 0 0 932.15
MAT-00215
5 10mm size HBG Metal SS 5 1Cum 831.00 70.00 207.75 1 35.90 0 0 1144.65
MAT-00216
6 12mm size HBG Metal SS 5 1Cum 989.00 70.00 247.25 1 35.90 0 0 1342.15
MAT-00217
7 20mm size HBG Metal SS 5 1Cum 1242.00 70.00 310.50 1 35.90 0 0 1658.40
MAT-00218
8 40mm size HBG Metal SS5 1Cum 744.00 70.00 186.00 1 35.90 0 0 1035.90
MAT-00220
9 40mm size HBG Metal SS5 ( Hand
1Cum 744.00 70.00 1 35.90 0 0 849.90
broken) MAT-00220
10 2nd Class Bricks 1000Nos BMT-A.01 8164.00 1 59.80 73.00 73.00 8369.80
11 Fly ash solid Bricks 290
x 225 x 140 mm 1000Nos BMT-A.10 33000.00 1 299.00 73.00 73.00 33445.00
Unit = 10 sqm
Taking output = 1 hectare
By Machanical Means
In area of non-thorny jungle (light jungle)
Taking out put = 1 Hectare
a) Labour
Mazdoor (un-skilled) day 4.16 560.00 2329.60
Add Agency Allowance 0.000% 0.00
b) Machinery
Dozer D-50 with attachment or suitable machinery for hour 10.00 1907.00 19070.00
removal of trees & stumps
Tractor with trolley 3t hour 1.00 543.00 543.00
21942.60
c) Add Overhead charges and contractors profit 13.615% 2987.48
Rate per Hectare 24930.08
Rate per 1 Sqm (a+b+c+d)/10000 2.49
RBR- Cutting of trees, including cutting of trunks, branches and removal of stumps &
STCL- roots, refilling, compaction of backfilling and stacking of serviceable material by
2
3(A) manual means with all lifts as per Technical Specification Clause 201MORD /
(iii) MORTH including overhead & Contractor profit.
Lead upto 100 m
Unit = each
Girth above 900 mm to 1800 mm
a) Labour
Mate day -
Mazdoor (Unskilled) day 2.08 560.00 1,164.80
Add Agency Allowance 0.000% 0.00
b) Machinery
Tractor with trolley 3t hour 0.28 543.00 152.04
Total 1,316.84
c) Add Overhead charges and contractors profit 13.615% 179.29
Rate per 1 No 1496.13
Uprooting and Removing Stumps & roots, compaction of backfilling and stacking
RBR- of servicable material by manual means as per Technical Specification Clause
3
STCL-4 201. as per Technical Specification Clause 201MORD / MORTH including
overhead & Contractor profit.
Lead upto 100 m
Unit = each
Girth above 900 mm to 1800 mm
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.416 560.00 232.96
Add Agency Allowance 0.000% 0.00
b) Machinery
Sl.
Description of Item Unit Qty Rate Amount
No.
Tractor with trolley 3t hour 0.018 543.00 9.77
Total 242.73
c) Add Overhead charges and contractors profit 13.615% 33.05
Rate per 1 No 275.78
4 RBR- Construction of embankment with material obtained from road way
EECD- cutting by using Machinery
3 Construction of embankment with approved materials deposited at site from
roadway cutting and excavation from drain (not exceeding 0.6 m depth) and
foundation of other structures graded and compacted with 8 to 10 T capacity
vibratory roller to meet requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5 MORD/ 305 MORTH using machinery including
overhead & Contract profit but excluding GST & Seignorage Charges.
Unit = cum
Taking output = 120 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 46.80 560.00 26208.00
Add Agency Allowance 0.000% 0.00
Rate per 120 Cum 26208.00
Rate per 1 Cum 218.40
e) Add Overhead charges and contractors profit 13.615% 29.74
248.14
Add S&C Charges Cum 1.00 0.00 0.00
Rate per cum 248.14
8 RBR- Scarifying existing granular surface to a depth of 50 mm and disposal of
EECD- scarified material with a lift upto 3 m and leads upto 1000 m as per Technical
1 (i) Specification Clause 301.4. MORD including over head charges&contractors
profit but excluding GST and Seignorage Charges.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day - - -
Mazdoor (Unskilled) day 4.16 560.00 2329.60
Add Agency Allowance 0.000% 0.00
b) Machinery
Sl.
Description of Item Unit Qty Rate Amount
No.
Tractor with trolley hour 1.50 543.00 814.50
3144.10
f) Add Overhead charges and contractors profit 13.615% 428.07
Rate per 100 Sqm 3572.17
Rate per 1 Sqm 35.72
9 RBR- Scarifying the existing bituminous road surface to a depth of 50 mm and
EECD- disposal of scarified material with all lifts and lead upto 1000 m as per Technical
2 (ii) Specification Clause 305.4.3 MORTH including over head charges&contractors
profit but excluding GST and Seignorage Charges.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day - - -
Mazdoor (Unskilled) day 0.26 560.00 145.60
Add Agency Allowance 0.000% 0.00
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.08 543.00 43.44
Front end loader 1 cum bucket capacity @ 50 cum per hour 0.20 2023.00 404.60
hour
Tipper 5.5 cum capacity, 4 trips per hour hour 0.23 1242.70 285.82
879.46
f) Add Overhead charges and contractors profit 13.615% 119.74
Rate per 100 Sqm 999.20
Rate per 1 Sqm 9.99
10 Picking old metalled surface to a depth of 40 to 100 mm and spreading metal
including watering with an initial lead of 2 Hectometers and rolling with power
rollers watering and power roller rolling including hire charges of power roller( 8
to 10 T ) barricading and diversion of traffic and wetting the new consolidation
for a fortnight(for compacted thickness of ) Including All Over Heads , And
Contractors Profit But Excluding GST And Seigniorage Charges
Rate as per SSR for 75mm thick 10 Sqm 1.00 231.00 231.00
Rate per 1 Sqm 23.10
e) Add Overhead charges and contractors profit 13.615% 3.15
Rate per 1 Sqm 26.25
11 Cement Stabilisation for improving subgrade
Cement stabilisation for improviding subgrade: Laying and spreading available
soil in the subgrade on a prepared surface, pulverising, mixing the spread soil in
place with rotavatorwith 4% of cement, grading with tractor grader and
compacting with the smooth wheel road roller at 80-100 kN OMC to the desired
density to form a layer of improved sub grade as per technical specificaiton
clause 403 MoRD includng contractors profit and overhead charges but
excluding GST and Seignorage Charges etc complete
By manual Means
Taking out put = 360 cum
Sl.
Description of Item Unit Qty Rate Amount
No.
a) Labour
Mazdoor (Skilled) day 12.08 560.00 6764.80
Mazdoor (unskilled) day 250.00 560.00 140000.00
Add Agency Allowance 0.000% 0.00
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour hour 6.00 3499.60 20997.60
Water tanker 6kl capacity hour 24.00 822.00 19728.00
c) Material
Cost of materials
60-63 mm IRC HBT Metal (25% of 50% of 435.60 cum) Cum 54.45 597.90 32555.66
40-45 mm IRC HBT Metal (25% of 46% of 435.60 cum) Cum 50.10 1005.90 50395.59
19-22 mm IRC HBG M/C Metal (25%x4% of 435.60 cum) Cum 4.36 1518.40 6620.22
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm cum 86.40 793.40 68549.76
(Average rate of 5-7mm & 2.36-5mm)
Binding Material @ 0.06 cum per 10 sqm for Grading 2 cum 28.80 192.30 5538.24
material
Basic rate of WBM-Gr-II for 360 cum 351149.87
d) Basic rate of WBM -Gr-II cum 975.42
e) Add Overhead charges and contractors profit 13.615% 132.80
1108.22
Add S&C Charges
Gr II Metal cum 0.623 0.00 0.00
Rate per Cum including conveyance 1108.22
16 RBR- WBM Grading 2 (using Graded Metal)
SBBS- Providing, laying, spreading and compacting stone aggregates of specific sizes
9 to water bound macadam specification including spreading in uniform thickness,
hand packing, rolling with Vibratory Roller 80-100 KN in stages to proper grade
and camber, applying and brooming, stone screening/binding materials to fill-up
the interstices of coarse aggregate, watering and compacting to the required
density grading 2 as per Technical Specification Clause 405 MORD by manual
means using HBT metal 60-63 mm (50%),40-45 mm metal (46%) and HBG
machine crushed metal 19-22 mm(4%) for compacted thickness of 75 mm
including overhead charges & Contractor profit, but excluding GST &
Seignorage charges.
By manual Means
Taking out put = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 560.00 6764.80
Mazdoor (unskilled) day 250.00 560.00 140000.00
Add Agency Allowance 0.000% 0.00
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour hour 6.00 3499.60 20997.60
Water tanker 6kl capacity hour 24.00 822.00 19728.00
c) Material
Cost of materials
60-63 mm IRC HBT Metal (50% of 435.60 cum) Cum 217.80 597.90 130222.62
40-45 mm IRC HBT Metal (46% of 435.60 cum) Cum 200.38 1005.90 201562.24
19-22 mm IRC HBG M/C Metal (4% of 435.60 cum) Cum 17.42 1518.40 26450.53
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm cum 86.40 793.40 68549.76
(Average rate of 5-7mm & 2.36-5mm)
Binding Material @ 0.06 cum per 10 sqm for Grading 2 cum 28.80 192.30 5538.24
material
Basic rate of WBM-Gr-II for 360 cum 619813.79
d) Basic rate of WBM -Gr-II cum 1721.70
Sl.
Description of Item Unit Qty Rate Amount
No.
e) Add Overhead charges and contractors profit 13.615% 234.41
1956.11
Add S&C Charges
Gr II Metal cum 1.530 0.00 0.00
Rate per Cum including conveyance 1956.11
17 RBR- WBM Grading 3 (using Graded Metal)
SBBS- Providing, laying, spreading and compacting stone aggregates of specific sizes
9 to water bound macadam specification including spreading in uniform thickness,
hand packing, rolling with Vibratory Roller 80-100 KN in stages to proper grade
and camber, applying and brooming, stone screening to fill-up the interstices of
coarse aggregate, watering and compacting to the required density Grading 3
as per Technical Specification Clause 405 MORD/ MORTH 404 by manual means
using HBG machine crushed metal of 40-45 mm (82%) and 19-22 mm (18%)
for compacted thickness of 75 mm, including overhead charges & Contractor
profit, But excluding GST & Seignorage charges.
By manual Means
Taking Output = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 560.00 6764.80
Mazdoor (unskilled) day 250.00 560.00 140000.00
Add Agency Allowance 0.000% 0.00
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour hour 6.00 3499.60 20997.60
Water tanker 6kl capacity hour 24.00 822.00 19728.00
c) Material
Cost of materials
40-45 mm IRC HBG M/c Metal ( 82% of 435.60 Cum) Cum 357.19 597.90 213563.90
19-22.40 mm IRC HBG M/c Metal ( 18% of 435.60 cum) Cum 78.41 1518.40 119057.74
Stone Screening
Type -B 11.2mm @ 0.18 cum per 10 sqm cum 86.40 485.90 41981.76
(rate of 2.36 mm & below)
Binding Material
Basic rate of WBM-Gr-III for 360 cum 562093.80
d) Basic rate of WBM -Gr-III cum 1561.37
e) Add Overhead charges and contractors profit 13.615% 212.58
1773.95
Add S&C Charges
Gr II Metal cum 1.450 0.00 0.00
Rate per Cum including conveyance 1773.95
18 RBR- Wet Mix Macadam
SBBS- Providing, laying, spreading and compacting graded stone aggregate to wet mix
11 macadam specification including premixing the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying
in uniform layers in sub-base/base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100kN / Vibratory Roller 80-100
kN weight to achieve the desired density including lighting, barricading and
maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical
Specification Clause 406 MORD/ MORTH,including overhead charges &
Contractor profit, But excluding GST
Aggregates 22.4 mm to 2.36 mm using M/C metal @ 40% cum 53.20 1096.15 58315.18
(Average of 19-22mm,12-14mm,9.5-11.20 mm,5-7mm &
2.36-5 mm metal)
Fine aggregate/crushed sand 2.36 mm to 75 mm micron cum 39.90 497.30 19842.27
@ 30%
Basic rate of WMM for 100Cum 175300.70
d) Basic rate of WMM per Cum 1753.01
e) Add Overhead charges and contractors profit 13.615% 238.67
1991.68
Add S&C Charges
Metal cum 1.330 0.00 0.00
Rate per 1 cum 1991.68
19 Modified Penetration Macadam
Construction of penetration macadam over prepared base by providing a layer
of compacted crushed coarse aggregate using chips spreader with alternate
applications of bituminous binder and key aggregates and rolling with a three
wheel 80-100 kN static roller as per Tech. Specification No 506 MORD.
B 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum)
(I) Bitumen (S-90)
a) Labour
Mate day -
Mazdoor (Unskilled) day 8.000 560.00 4480.00
Mazdoor (Skilled) day 2.400 560.00 1344.00
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic self propelled chip spreader both for aggregates hour 6.000 3264.00 19584.00
and key aggregates @ 1500 sqm per hour for 4500 x 2
sqm = 9000 sqm
Bitumen pressure distributor for @ 1750 sqm per hour hour 2.570 1907.00 4900.99
Tipper 5.5 cum capacity for carriage of aggregates from hour 10.000 1242.70 12427.00
stockpile to chip spreader
Three wheel 80-100 kN Static Roller hour 33.750 1743.60 58846.50
Front end loader 1 cum bucked capacity hour 6.000 2023.00 12138.00
c) Material
Bitumen @ 2 kg per sqm t 9.000 33210.00 298890.00
40 mm size hand broken metal @ 0.09 cum per sqm cum 405.000 849.90 344209.50
12 mm size stone chips @ 0.018 cum per sqm cum 81.000 1342.15 108714.15
865534.14
Add Overhead charges and contractors profit 13.615% 117842.47
Cost of 4500 sqm = a+b+c+d+e 983376.61
218.53
Add S&C Charges
Metal cum 0.108 0.00 0.00
Sl.
Description of Item Unit Qty Rate Amount
No.
Rate per 1 Sqm 218.53
Rate per Cum 2913.73
20 RBR- Bituminous Macadam
BASC- Providing and laying bituminous macadam with 40-60 TPH hot mix plant using
3 crushed aggregates of grading as per Table 500.4 premixed with bituminous
binder, transported to site upto a lead of 1000 m laid over a previously
prepared surface with paver finisher to the required grade, level and alignment
and rolled to achieved the desired compaction as per Technical Specification
Clause 504 MORD (using vibratory Roller 80-100 KN for intermediate rolling and
3 wheel roller 80-100 KN for initial and final rolling)., including overhead
charges & Contractor profit, But excluding GST
Unit = cum
Taking output = 102.5 cum (225 t)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.00 560.00 5600.00
Mazdoor (Skilled) day 3.52 560.00 1971.20
Add Agency Allowance 0.000% 0.00
b) Machinery
Batch mix HMP 40-60 THP @ 40 t per hour actual output hour 6.00 23965.00 143790.00
Hydraulic broom @ 1250 sqm per hour hour 1.10 455.00 500.50
Air compressor 210 cfm hour 1.10 633.00 696.30
Paver finisher hour 6.00 3891.00 23346.00
Generator 125 KVA hour 6.00 1836.00 11016.00
Front end loader 1 cum bucket capacity hour 6.00 2023.00 12138.00
Tipper 5.5 cum, 10 t / 5-6 t capacity hour 6.21 1242.70 7717.17
Three wheel 80-100 kN static roller for initial break down hour 12.00 1743.60 20923.20
rolling, final and finishing rolling
Vibratory roller 80-100 kN for intermediate rolling hour 6.00 3499.60 20997.60
c) Material
(i) Bitumen @ 3.3 per cent of mix t 7.43 33210.00 246584.25
(Weight of mix = 102.5 x 2.2 = 225 t)
(ii) Aggregate
Total weight of mix = 225 t
Weight of bitumen = 7.425 t
Weight of aggregate = 225 – 7.425 = 217.575 t
Taking density of aggregate = 1.5 t/cum
Volume of aggregate = 145.05 cum
Grading (19 mm nominal size) :
25 -10 mm - 40 per cent cum 58.02 1386.53 80446.18
10– 5 mm - 40 per cent cum 58.02 1006.53 58398.58
5 mm and below - 20 per cent cum 29.01 694.65 20151.80
Rate per 102.50 Cum 654276.78
Rate per 1 Cum 6383.19
e) Add Overhead charges and contractors profit 13.615% 869.07
7252.26
Add S&C Charges
Metal cum 1.415 0.00 0.00
Rate per 1 cum 7252.26
21 RBR- Prime Coat (Low Porosity)
BASC- Providing and applying primer coat with bitumen emulsion (SS-1) on prepared
1 surface of granular base including cleaning of road surface and spraying primer
at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical
Specification Clause 502 MORD (for use on Wet mix macadam &
WBM) ,including overhead charges & Contractors profit but excluding GST.
Unit = 1 sqm
Taking output = 1750 Sqm
Sl.
Description of Item Unit Qty Rate Amount
No.
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.04 560.00 582.40
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 455.00 637.00
Air compressor 210 cfm hour 1.40 633.00 886.20
Bitumen emulsion pressure distributor @ 1750 sqm/hour hour 1.00 1073.00 1073.00
Water tanker 6 kl capacity 1 trip per hour hour 0.50 822.00 411.00
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm MT 1.48 26230.00 38820.40
Water Kl 3.00 0.00 0.00
Cost for 1750 sqm (a+b+c) 42410.00
Basic rate per cum 24.23
d) Add Overhead charges and contractors profit 13.615% 3.30
Rate per Sqm including conveyance 27.53
22 RBR- Prime Coat (Low Porosity)
BASC- Providing and applying Primer Coat with Bitchem Emulsion (SS-1) on prepared
1 surface of granular base including cleaning of road surface and spraying primer
at the rate of 0.70-1.0 kg/sqm using mechanical means as per Technical
Specification Clause 502
Unit = 1 sqm
Taking output = 1750 Sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.04 560.00 582.40
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 455.00 637.00
Air compressor 210 cfm hour 1.40 633.00 886.20
Bitumen emulsion pressure distributor @ 1750 sqm/hour hour 1.00 1073.00 1073.00
Water tanker 6 kl capacity 1 trip per hour hour 0.50 822.00 411.00
c) Material
Bitchem Bitumen Emulsion (SS-1) @ 0.85kg per sqm MT 1.48 26230.00 38820.40
Water Kl 3.00 0.00 0.00
Cost for 1750 sqm (a+b+c) 42410.00
Basic rate per cum 24.23
d) Add Overhead charges and contractors profit 13.615% 3.30
Rate per Sqm including conveyance 27.53
23 RBR- Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
BASC- distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular
2 surfaces treated with primer / (or dry and hungry bituminous surface) &
cleaned with Hydraulic broom as per Technical Specification Clause 503
MORD,including overhead charges & Contractors profit but excluding GST.
Unit = 1 sqm
Taking output = 1750 Sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.04 560.00 582.40
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 455.00 637.00
Air compressor 210 cfm hour 1.40 633.00 886.20
Emulsion pressure distributor @1750 sqm per hour hour 1.00 1073.00 1073.00
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm MT 0.48 33800.00 16224.00
Cost of 1750 sqm = (a+b+c) 19402.60
Sl.
Description of Item Unit Qty Rate Amount
No.
Rate per sqm = (a+b+c)/1750 11.09
d) Add Overhead charges and contractors profit 13.615% 1.51
Rate per Sqm Including conveyance 12.60
24 RBR- Providing and applying Tack Coat with BitChem Emulsion (RS-1) using emulsion
BASC- distributor at the rate of 0.20 to 0.25 kg per sqm on the prepared bituminous
2 surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
Unit = 1 sqm
Taking output = 1750 Sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.04 560.00 582.40
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 455.00 637.00
Air compressor 210 cfm hour 1.40 633.00 886.20
Emulsion pressure distributor @1750 sqm per hour hour 1.00 1073.00 1073.00
c) Material
BitchemEBitumen Emulsion (RS-1) @ 0.225 kg per sqm MT 0.48 33800.00 16224.00
Cost of 1750 sqm = (a+b+c) 19402.60
Rate per sqm = (a+b+c)/1750 11.09
d) Add Overhead charges and contractors profit 13.615% 1.51
Rate per Sqm Including conveyance 12.60
25 RBR- 20mm thick Open-Graded Premix Carpet using Bituminous
BASC- (penetration grade/modified bitumen) Binder
14 Providing, laying and rolling of open-graded premix carpet of 20 mm thickness
composed of 13.2 mm to 5.6 mm aggregates either using penetration grade
bitumen 60/70 grade at the rate of 14.6 kg/10 sqm to required line, grade and
level to serve as wearing course on a previously prepared base, including
mixing in a Hot Mix plant of 40TPH, laying and rolling with a three wheel 0-100
kN static roller capacity, finished to required level and grades to be followed by
seal coat of either Type A or Type B or Type C including cost and conveyance of
all materials from approved sources, labour charges and hire and operational
charges of power road roller and all other machinery, tools and plants, providing
barricading for diversion of traffic, erecting red flags other incidental and
operational charges etc., complete for finished item of work as per clause 508
MORD.including overhead charges & Contractors profit but excluding GST &
Seignorage charges.
By Mechanical Means
Bitumen (S-65)
Unit = sqm
Taking output = 4000 sqm (80 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 10.00 560.00 5600.00
Mazdoor (Skilled) day 3.52 560.00 1971.20
Add Agency Allowance 0.000% 0.00
b) Machinery
HMP 30/40 t per hour hour 6.00 23965.00 143790.00
Electric generator set 125 KVA hour 6.00 1836.00 11016.00
Front end loader 1 cum bucket capacity hour 6.00 2023.00 12138.00
Tipper 5.5 cum - 10 t capacity hour 3.64 1242.70 4523.43
Paver finisher hour 6.00 3891.00 23346.00
Three wheel 80-100 kN static roller hour 16.00 1743.60 27897.60
c) Material
Bitumen (S-65) @ 14.60 kg per 10 sqm MT 5.84 33210.00 193946.40
Sl.
Description of Item Unit Qty Rate Amount
No.
Crushed stone chipping, 13.2 mm to 5.6 mm @ 0.27 cum cum 108.00 1089.23 117637.20
per 10 sqm (average of 12-14 mm,9.5-11.2mm & 5-7 mm
metal)
B By Mechanical Means
(II) Bitumen (S-65)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 6.24 560.00 3494.40
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic self propelled chips spreader hour 6.00 3264.00 19584.00
Tipper 5.5 cum capacity hour 6.00 1242.70 7456.20
Front end loader 1 cum bucket capacity hour 6.00 2023.00 12138.00
Bitumen pressure distributor hour 6.00 1907.00 11442.00
Three wheel 80-100 kN static roller hour 15.00 1743.60 26154.00
c) Material
Bitumen (S-65) @ 9.80 kg per 10 sqm MT 7.35 33210.00 244093.50
Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 892.15 60220.13
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm
Basic rate of OGPC for 7500 Sqm 384582.23
d) Basic rate of OGPC per Sqm 51.28
e) Add Overhead charges and contractors profit 13.615% 6.98
58.26
Add S&C Charges
Metal cum 0.009 0.00 0.00
Rate per Sqm including conveyance 58.26
27 RBR- Seal Coat - Case II: Type B (510-MoRD) - By mechanical means
BASC- Providing and laying seal coat sealing the voids in a bituminous surface laid to
17 the specified levels, grade and cross fall using Type B, as per technical
specification clause 510 MoRD (using three wheel 80-100 kN static roller)
including overhead charges but excluding GST & seignorage charges
B By Mechanical Means
(II) Bitumen (S-65)
Sl.
Description of Item Unit Qty Rate Amount
No.
Unit = sqm
Taking output = 5000 sqm (30.00 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 4.16 560.00 2329.60
Add Agency Allowance 0.000% 0.00
b) Machinery
HMP of 30/40 t per hour hour 2.00 23965.00 47930.00
Electric generator set 125 KVA hour 2.00 1836.00 3672.00
Front end loader 1 cum bucket capacity hour 2.00 2023.00 4046.00
Tipper 5.5 cum - 10 t capacity hour 1.36 1242.70 1690.07
Paver finisher hour 2.00 3891.00 7782.00
Three wheel 80-100 kN static roller hour 10.00 1743.60 17436.00
c) Material
Bitumen (S-65) @ 6.80 kg per 10 sqm MT 3.40 33210.00 112914.00
Crushed sand defined as passing 2.36 mm sieve and cum 30.00 497.30 14919.00
retained on 180 micron sieve applied @ 0.06 cum /10 sqm
B By Mechanical Means
(III) Bitumen (S-65)
Unit = sqm
Taking output = 7500 sqm (67.5 cum)
a) Labour
Mate day -
Mazdoor (Unskilled) day 5.20 560.00 2912.00
Add Agency Allowance 0.000% 0.00
b) Machinery
Hydraulic self propelled chips spreader hour 6.00 3264.00 19584.00
Tipper 5.5 cum capacity hour 6.00 1242.70 7456.20
Front end loader 1 cum bucket capacity hour 6.00 2023.00 12138.00
Bitumen pressure distributor hour 6.00 1907.00 11442.00
Three wheel 80-100 kN static roller hour 15.00 1743.60 26154.00
c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm MT 4.88 33210.00 162064.80
Crushed stone chipping of 6.7 mm size 100 per cent cum 67.50 892.15 60220.13
passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.09 cum per 10 sqm
Basic rate of OGPC for 7500 Sqm 301971.13
d) Basic rate of OGPC per Sqm 40.26
Sl.
Description of Item Unit Qty Rate Amount
No.
e) Add Overhead charges and contractors profit 13.615% 5.48
45.74
Add S&C Charges
Metal cum 0.009 0.00 0.00
Rate per Sqm including conveyance 45.74
29 RBR- Semi-Dense Bituminous Concrete
BASC- Providing and laying semi dense bituminous concrete with 40-60 TPH batch
8 type HMP producing an average output of 37.5 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 4.5 to 5
per cent of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve
the desired compaction as per MoRTH specification clause No. 508 complete in
all respects
Unit = cum
Taking output = 195 cum (450 tonnes)
a) a) Labour
Mate day
Mazdoor (Unskilled) working with HMP, mechanical broom, day 12.00 560.00 6720.00
paver, roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.84 560.00 3270.40
Add Agency Allowance 0.000% 0.00
b) Machinery
HMP 40-60 TPH hour 11.00 23965.00 263615.00
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.00 3891.00 23346.00
per hour
Generator 250 KVA hour 6.00 2572.00 15432.00
Front end loader 1 cum bucket capacity hour 6.00 2023.00 12138.00
Smooth wheeled roller 8-10 tonnes for initial break rolling. hour 3.90 1743.60 6800.04
(6 x 0.65)
Vibratory roller 8 tonnes for intermediate rolling. hour 3.90 3499.60 13648.44
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 3.90 2208.00 8611.20
roller
c) Material
Grading II: 10 mm (Nominal Size)
Bitumen 60/70 Grade @ 4.5 per cent of weight of mix t 22.50 33210.00 747225.00
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.50 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285.00 cum
9.50-11.20mm HBG M/c Chips cum 81.23 1120.90 91045.10
5-7mm HBG M/c Chips cum 81.23 892.15 72464.88
2.36-5mm HBG M/c Chips cum 58.43 694.65 40584.93
2.36mm and below cum 58.43 485.90 28388.71
Filler @ 2 per cent of weight of aggregates (Stone Dust) cum 5.70 485.90 2769.63
By Mechanical Means
Taking out put = 8200 Sqm (205Cum) (450 tonnes)
a) Labour
Mate day 0 0.00
Mazdoor working withHMP, Mechanical brrom, paver, day 14.84 560.00 8310.40
roller, asphalt cutter and assistance for setting oulines,
levels and layout of construction.
Skilled Mazddor for checking line and levesl day 5.00 560.00 2800.00
Add Agency Allowance 0.000% 0.00
b) Machinery
HMP 40 -60 TPH hour 12.00 23965.00 287580.00
Electric generator set 250 KVA hour 6.00 2572.00 15432.00
Front end loader 1cum bucket capacity hour 6.00 2023.00 12138.00
Paver finisher @ 100 TPH hour 4.80 3891.00 18676.80
Three wheel 80-100 kN static roller hour 6.00 1743.60 10461.60
c) Materials
Cost of materials
Crushed stone chips of 13.2mm to 5.6mm size @ 0.34 cum 276.75 889.65 246210.64
cum per 10 sqm. ( 66% of 11.20 mm HBG chips and 34 %
of 5 to 7 mm HBG chips
Bitumen 60/70 grade @ 23.75 Kg per 10 sqm MT 19.48 33210.00 646930.80
Basic rate of OGPC for 8200 Sqm 1248540.24
Basic rate of OGPC per Sqm 152.26
e) Add Overhead charges and contractors profit 13.615% 20.73
172.99
Add S&C Charges
Metal cum 0.034 0.00 0.00
Rate per sqm 172.99
31 Providing, laying and rolling of close graded premix surfacing (Mixed seal
surfacing) material of 25 mm thickness composed of 11.20mm to 0.09mm
(Type B) aggregatres asp er Table 500.15 of MoRD using CRRI-BitChem tailor
made cold max binder to required line, grade and lavel to serve as wearing
course on a previously prepared base, incluidng mixing in a suitable plant by
manual means, laying and rolling with a three wheel 8-10kN static roller and
finishing to required level and grades as per technical specification clause 509
MoRD, infor finished item of work in all respects as directed by Enginer-in-
charge including contractors profit & overhead charges, GST and seignorage
charges etc complete but excluding seinorage charges and GST
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 670.00 3350.00
Mason (2nd class) day 5.00 605.00 3025.00
Mazdoor (unskilled) day 150.00 560.00 84000.00
Mazdoor(skilled) day 6.00 607.00 3642.00
Surveyor day 2.00 1040.00 2080.00
Mazdoor (semi-skilled) day 6.00 560.00 3360.00
Add Agency Allowance 0.000% 0.00
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 mixers) with Hour 36.00 692.70 24937.20
weight batcher and suitable capacity calibrated water tank
Cost of materials
Selected Earth cum 360.00 172.30 62028.00
Water Kl 18.00 99.00 1782.00
Basic rate of Selected earth shoulders for 300 cum 107773.60
d) Basic rate of Selected earth shoulders cum 359.25
e) Add Overhead charges and contractors profit 13.615% 48.91
408.16
Add S&C Charges
S Earth cum 1.200 0.00 0.00
Rate per cum 408.16
34 RBR- Filling in foundation trenches and approchs with Stone Dust as per drawing and
FNDN technical specification Clause 305.3.9 MORD & 304 MORTH ,including overhead
-2 charges & Contractors profit but excluding GST.
1) Stone dust filling
Taking output - 1 Cum
unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 560.00 173.60
Add Agency Allowance 0.000% 0.00
Sl.
Description of Item Unit Qty Rate Amount
No.
b) Material
Stone Dust Cum 1.00 485.90 485.90
Basic rate per 1 cum 659.50
Basic rate per cum 659.50
c) Add Overhead charges and contractors profit 13.615% 89.79
749.29
Add S&C Charges cum 1.00 0.00 0.00
Rate per cum including conveyance 749.29
35 RBR- Filling in foundation trenches and approchs with Selected earth as per drawing
FNDN and technical specification Clause 305.3.9 MORD & 304 MORTH ,including
-2 overhead charges & Contractors profit but excluding GST.
1) Selected earth filling
Taking output - 1 Cum
unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 560.00 173.60
Add Agency Allowance 0.000% 0.00
b) Material
Selected earth Cum 1.00 172.30 172.30
Basic rate per 1 cum 345.90
Basic rate per cum 57.65
c) Add Overhead charges and contractors profit 13.615% 7.85
65.50
Add S&C Charges cum 1.00 0.00 0.00
Rate per cum including conveyance 65.50
36 RBR- ExcaGSTion for Structures
FNDN Earthwork in excacation for structures as per drawing and technical
-1 specifications Clause 305.1 including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and backfilling in trenches with
excaGSTed suitable material as per Technical Specification 305 MORD / 304
MORTH ,including overhead charges & Contractors profit but excluding GST.
1) Sand filling
Taking output - 1 Cum
unit = cum
a) Labour
Sl.
Description of Item Unit Qty Rate Amount
No.
Mate day -
Mazdoor (Unskilled) day 0.31 560.00 173.60
Add Agency Allowance 0.000% 0.00
b) Material
Sand Cum 1.00 497.30 497.30
Basic rate per 1 cum 670.90
Basic rate per cum 670.90
c) Add Overhead charges and contractors profit 13.615% 91.34
762.24
Add S&C Charges cum 1.00 0.00 0.00
Rate per cum including conveyance 762.24
38 RBR- Providing concrete for plain concrete M 10 grade in open foundations using 40
FNDN mm nominal size Graded hard stone aggregate, mechanically mixed, placed in
-4 foundation and compacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD
and 1500, 1700 & 2100 MORTH ,including overhead charges & Contractors
profit but excluding GST.
I. P.C.C grade M 10
(i) Nominal mix 1:3:6
unit = cum
a) Material
Cement t 0.220 4220.00 928.40
Coarse sand cum 0.450 642.30 289.04
40 mm aggregate cum 0.900 1035.90 932.31
Water kl 0.000 99.00 0.00
b) Labour
Mate day -
Mason (1st Class) day 0.10 670.00 67.00
Mazdoor (Unskilled) day 1.39 560.00 778.40
Add Agency Allowance 0.000% 0.00
c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted hour 0.40 692.70 277.08
with water measuring device and preferably also with load
cell.
Water tanker 6 kl capacity hour 0.13 822.00 106.86
Basic Rate 3379.09
d) Formwork @ 4 % on cost of material, labour and machinery (a+b+c) 135.16
3514.25
e) Add Overhead charges and contractors profit 13.615% 478.47
3992.72
Add S&C Charges
Metal cum 0.90 0.00 0.00
Sand cum 0.45 0.00 0.00
Rate per cum incluidng conveyance 3992.72
39 RBR- Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically
SBST- mixed in substructure complete as per drawings and technical specification
5 Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200
MORTH ,including overhead charges & Contractors profit but excluding GST.
Unit = cum
a) Material
Cement t 0.407 4220.00 1717.54
Coarse sand cum 0.450 642.30 289.04
20 mm aggregate cum 0.540 1658.40 895.54
10 mm aggregate cum 0.360 1144.65 412.07
HYSD bar reinforcement including binding wire (Rate as t 0.075 0.00 0.00
per item 13.2) except OH & CP
b) Labour
Mate day -
Mason (1st Class) day 0.10 670.00 67.00
Mazdoor (Unskilled) day 1.39 560.00 778.40
Mazdoor (Unskilled) for cleaning deck slab concrete day 0.15 560.00 84.00
surface
Add Add Agency Allowance 0.000% 0.00
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hr / cum 0.40 692.70 277.08
Generator 33 KVA hour 0.40 1356.90 542.76
5063.43
d) Formwork @ 3% on cost of material, labour and machinery (a+b+c) 151.90
5215.33
c) Add Overhead charges and contractors profit 13.615% 710.07
5925.40
Add S&C Charges
Metal Cum 0.90 0.00 0.00
Sand Cum 0.45 0.00 0.00
Rate per cum 5925.40
44 Providing and laying reinforced cement concrete R.C.C M 25 Grade (Design
Mix) using 20 & 10 mm HBG Metal in superstructure including cost, and
conveyance of all materials to site and all labour charge mechanically mixed as
per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 MORD
including contractors profit & Over head charges but excluding Steel , GST
for Approach slab
II R.C.C M 25 Grade (Design Mix)
Unit =cum
A Case I : Using Concrete Mixer.
a) Material
Cement t 0.400 4220.00 1688.00
Coarse sand cum 0.450 642.30 289.04
20 mm aggregate cum 0.540 1658.40 895.54
10 mm aggregate cum 0.360 1144.65 412.07
Sl.
Description of Item Unit Qty Rate Amount
No.
b) Labour
Mate day -
Mason (1st Class) day 0.10 670.00 67.00
Mazdoor (Unskilled) day 1.39 560.00 778.40
Add Add Agency Allowance 0.000% 0.00
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour/cum 0.40 692.70 277.08
Unit= Tonne
a) Labour
Mate day - - -
Blackmith day 3.00 630.00 1890.00
Mazdoor (Un-skilled) day 8.44 560.00 4726.40
Add Add Agency Allowance 0.000% 0.00
b) Materials
HYSD bars including 5% over laps and wastage MT 1.05 61000.00 64050.00
Binding wire Kgs 8.00 70.00 560.00
Final Rate per 1 MT 71226.40
c) Add Overhead charges and contractors profit 13.615% 9697.47
Rate per 1 MT 80923.87
47 RBR- Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure
SBST- complete as per drawings and technical specification Clauses 1002, 1005, 1010
6 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia
including over laps and wastage, where they are not welded.
Unit= Tonne
a) Labour
Mate day - - -
Blackmith day 2.00 630.00 1260.00
Mazdoor (Un-skilled) day 6.84 560.00 3830.40
Add Add Agency Allowance 0.000% 0.00
b) Materials
HYSD bars including 5% over laps and wastage MT 1.05 61000.00 64050.00
Binding wire Kgs 6.00 70.00 420.00
Final Rate per 1 MT 69560.40
c) Add Overhead charges and contractors profit 13.615% 9470.65
Rate per 1 MT 79031.05
48 RBR- Supplying, fitting and placing HYSD bar reinforcement in foundation complete
FNDN- as per drawings and technical specifications Clauses 1000 and 1202 MORD &
7 1100, 1600 MORTH for Bars below 36 mm dia including over laps and wastage,
where they are not welded.
Unit= Tonne
a) Labour
Mate day - - -
Blackmith day 2.00 630.00 1260.00
Mazdoor (Un-skilled) day 6.40 560.00 3584.00
Add Add Agency Allowance 0.000% 0.00
b) Materials
HYSD bars including 5% over laps and wastage MT 1.05 61000.00 64050.00
Binding wire Kgs 6.00 70.00 420.00
Final Rate per 1 MT 69314.00
c) Add Overhead charges and contractors profit 13.615% 9437.10
Rate per 1 MT 78751.10
49 RBR- Providing concrete for plain/reinforced concrete in open foundations using 40
FNDN- mm nominal size Graded hard stone aggregate, mechanically mixed, placed in
4 foundation and compacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD
and 1500, 1700 & 2100 MORTH.
Sl.
Description of Item Unit Qty Rate Amount
No.
Nominal mix 1:2.5:5 (Hand mixing) (MORD)
Taking output = cum
a) Labour
Mate day - - -
Mason (1st class) day 0.10 630.00 63.00
Mazdoor (Un-skilled) day 2.36 560.00 1321.60
Add Agency Allowance 0.000% 0.00
b) Materials
Cement MT 0.275 4220.00 1160.50
Coarse Sand cum 0.48 642.30 308.30
40 mm aggregate cum 0.54 1035.90 559.39
20 mm aggregate cum 0.27 1658.40 447.77
10 mm aggregate sqm 0.09 1144.65 103.02
Total 3963.58
Formwork @ 4% on cost of (a + b) 0.00
3963.58
Add S&C Charges
Metal Cum 0.800 0.00 0.00
Sand Cum 0.480 0.00 0.00
0.00
Total 3963.58
50 RBR- Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure
SBST- complete as per drawings and technical specification Clauses 1002, 1005, 1010
6 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia
including over laps and wastage, where they are not welded.
Unit= Tonne
a) Labour
Mate day - - -
Blackmith day 2.00 630.00 1260.00
Mazdoor (Un-skilled) day 6.84 560.00 3830.40
Add Agency Allowance 0.000% 0.00
b) Materials
HYSD bars including 5% over laps and wastage MT 1.05 61000.00 64050.00
Binding wire Kgs 6.00 70.00 420.00
Final Rate per 1 MT 69560.40
51 Painting on Concrete/Steel Surfaces with Epoxy
RBR- Painting two coats including prime coat with epoxy paint of approved brand on
TSRA- concrete/steel surfaces after through cleaning of surface to give an even shade
9 as per drawing and Technical Specification Clause 1701 MORD
Unit=sqm
Taking output = 10 sqm
a) Labour
Mate day - - -
Painter (1st class) day 0.60 750.00 450.00
Mazdoor (Un-skilled) day 0.65 560.00 364.00
Add Agency Allowance 0.000% 0.00
b) Materials
Epoxy primer / Red Oxide ltr 0.60 160.00 96.00
Epoxy paint ltr 1.25 362.00 452.50
add @ 1% on cost of material for scaffolding whevever cum 5.49
required
Total (a+b) 1367.99
Rate per 1 Sqm 136.80
52 Painting two coats on New Concrete Surfaces
RBR- Painting two coats including primer coat after filling the surface with synthetic
TSRA- enamel paint in all shades on new, plastered / concrete surfaces as per drawing
6 and Technical Specification Clause 1701MORD.
Unit=sqm
Sl.
Description of Item Unit Qty Rate Amount
No.
Taking output = 40 sqm
a) Labour
Mate day - - -
Painter (1st class) day 3.00 750.00 2250.00
Mazdoor (Un-skilled) day 2.20 560.00 1232.00
Add Agency Allowance 0.000% 0.00
b) Materials
Cement primer as per specification ltr 3.00 173.00 519.00
Paint conforming to requirement ltr 6.00 191.00 1146.00
add 1% on cost of material for scaffolding whenever requir cum 16.65
Total (a+b) 5163.65
Rate per 1 Sqm 129.09
53 RBR- Printing new letter and figures of any shade with synthetic enamel paint black
TSRA- or any other approved colour to give an even shade as per drawings and
1 Technical Specification Clause 1701 MORD / 801 MORTH
Unit = Each
Taking out put = one typical board
i ExcaGSTion for foundation cum 0.252 203.84 51.37
ii Cement Concrete M15 grade cum 0.252 3963.58 998.82
iii Painting on MS Steel tubes with primer and two coats of
epoxy paint
2x2.05x0.30=1.23
1x1.10x188= 0.21
As per item no. sqm 1.80 136.80 246.24
iv Printing new letters and figures of any shade with
synthetic enamel paint black or any other approved colour
to give an even shade.
Middle plate words 28x5 = 140 per cm height per letter
Bottom plate border 150x2x5 = 1500 per cm height per
letter
Bottom plate border 60x2x5 = 600 per cm height per
letter
Words 101x2.5 = 252.5
Words 80x3 = 240.00
Total (2732.5 per cm height per letter)
As per item no. 24 per cm ht 2732.50 0.85 2322.63
per letter
a) Labour
Mate day - - -
Mazdoor (Un-skilled) day 0.78 560.00 436.80
Add Agency Allowance 0.000% 0.00
b) Material
2nos. MS tubes 75mmx75mm of 12 SWG sheet 2650 mm kg 63.15 61.00 3852.15
long
1no. MS tubes 47mmx47mm of 12 SWG sheet 1100 mm kg 4.47 61.00 272.67
long
Angle iron 50mmx50mmx5mm for lugs kg 2.12 61.00 129.32
1.6mm thick MS sheet strengthened by 25mmx5mm MS sqm 1.25
flat iron logo and middle plate angle iron
25mmx25mmx5mm on bottom plate painting with stove
enameled paint on both sides as per MORD specification.
RBR-FNDN-1 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other deleterious
material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches
with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH
15 Unit = 1cum
A. MATERIALS:
Cement kg 129.60 4220.00 546.91
Coarse aggregate 40 mm cum 0.90 1035.90 932.31
Fine aggregate (Sand) cum 0.45 642.30 289.03
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 hour 1.00 692.70 692.70
cum) capacity
C. LABOUR:
Mason 1st class day 0.10 670.00 67.00
Mazdoor (unskilled) day 1.39 560.00 778.40
Water (including for curing) kl 1.20 99.00 118.80
Grand Total 3425.16
CP0% 0.00
Grand Total 3425.16
Page 34 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Footings
BASIC COST per 1 cum Cum 1.00 6252.34 6252.34
Material Hire Charges 1.00 301.00 301.00
Labour charges 1.00 672.00 672.00
7225.34
CP0% 0.00
Grand Total 7225.34
Pedastals
BASIC COST per 1 cum 1.00 6252.34 6252.34
Material Hire Charges 1.00 343.00 343.00
Page 35 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Lintels
BASIC COST per 1 cum 1.00 7105.02 7105.02
Material Hire Charges 1.00 826.00 826.00
Labour charges 1.00 1332.00 1332.00
9263.02
CP0% 0.00
Grand Total 9263.02
Columns
BASIC COST per 1 cum 1.00 7105.02 7105.02
Material Hire Charges 1.00 249.00 249.00
Labour charges 1.00 1871.00 1871.00
9225.02
CP0% 0.00
Grand Total 9225.02
RCC SLABS, BEAMS
Beams
BASIC COST per 1 cum 1.00 5076.57 5076.57
Material Hire Charges 1.00 1458.00 1458.00
Page 36 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Unit = 1 MT
A) MATERIAL
HYSD/TMT/ MS bars including 5
per cent for overlaps and wastage MT 1.05 61000.00 64050.00
Binding wire Kg 6.00 70.00 420.00
B) LABOUR for cutting, bending,
shifting to site, tying, lap splicing
and placing in position
BLD-CSTN-3-2 Brick Masonry in CM (1:8) with Bricks traditional size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement kg 36.00 4.22 151.92
Page 37 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Reinforced Brick Masonary walls of 11.5cm in CM(1:6) using FlyAsh/2nd cl bricks having a
crushing strength of not less than 35.00kg/cm2 and using two mild steel bars of 6m dia in every
third layer of brick masory, with free joints of the main block work including cost and seignorage
charges and conveyance of all materials and water from approved sources to work site and all
BLD-CSTN-3-4 operational, incidental, labour charges such as scaffolding mixing mortor constructing masonary lift
charges, curing etc. complete but excluding the cost of steel and its fabrication charges for finished
item of work as per SS 509
32 Ground Floor :
A. MATERIALS:
II Class Bricks cum 512 8369.80 4285.34
C.M.(1:6) cum 0.200 1921.01 384.20
B. LABOUR:
Mason 1st class day 0.600 670.00 402.00
Mason 2nd class day 0.600 605.00 363.00
Mazdoor (unskilled) day 2.750 560.00 1540.00
ADD Scafolding charges Sqm 8.70 95.40 829.57
MA 0% 0.00
Grand Total 7804.11
R.C.C. M-20 Design Mix
Supply and placing of the M 20 Grade Design Mix Concrete corresponding to IS 456 using WEIGH
BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse
aggregate) from approved quarry including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales &
other taxes on all materials including all operational, incidental and labour charges such as weigh
batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its
BLD-CSTN-2-14 fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per
IS code from standard suppliers approved by the department including pumping, centering,
shuttering, laying concrete, vibrating, curing etc. complete but excluding cost of steel and its
fabrication charges for finished item of work.
FOUNDATIONS, PLINTH,
PEDESTALS (Below Plinth)
A. MATERIALS:
20mm HBG graded metal cum 0.48 1658.40 796.03
12mm HBG graded metal cum 0.12 1342.15 161.06
10mm HBG graded metal cum 0.12 1144.65 137.36
6mm HBG graded metal cum 0.08 932.15 74.57
Sand for Concrete cum 0.40 642.30 256.92
Cement Kgs 350.00 4.22 1477.00
1st Class Mason day 0.133 670.00 89.11
Page 38 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Footings
BASIC COST per 1 cum Cum 1.00 6771.75 6771.75
Material Hire Charges 1.00 301.00 301.00
Labour charges 1.00 672.00 672.00
7744.75
Pedastals
BASIC COST per 1 cum 1.00 6771.75 6771.75
Material Hire Charges 1.00 343.00 343.00
Labour charges 1.00 1069.00 1069.00
Vibrating Charges 1.00 274.40 274.40
8458.15
Plinth beams
BASIC COST per 1 cum 1.00 6771.75 6771.75
Material Hire Charges 1.00 1453.00 1453.00
Labour charges 1.00 1620.00 1620.00
Vibrating Charges 1.00 274.40 274.40
10119.15
COLUMNS, LINTELS, WATER TANKS, RCC WALLS IN BUILDINGS
Lintels
BASIC COST per 1 cum 1.00 7294.03 7294.03
Material Hire Charges 1.00 826.00 826.00
Labour charges 1.00 1332.00 1332.00
9452.03
Columns
BASIC COST per 1 cum 1.00 7294.03 7294.03
Material Hire Charges 1.00 249.00 249.00
Labour charges 1.00 1871.00 1871.00
Vibrating Charges 1Hour 1.00 274.40 274.40
9688.43
RCC SLABS, BEAMS
ANY GRADE OF MIX
20mm HBG graded metal cum 0.48 1658.40 796.03
12mm HBG graded metal cum 0.12 1342.15 161.06
10mm HBG graded metal cum 0.12 1144.65 137.36
Page 39 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Ground Floor
Unit = 1 cum
A. MATERIALS:
Flyash Cement solid blocks of size day
290 x 225 x 140 mm 110.000 33445.00 3678.95
Cost of Cement Mortar (1:8) cum 0.100 1667.82 166.78
B. LABOUR
Mason 1st class day 0.420 670.00 281.40
Mason 2nd class day 0.920 605.00 556.60
Man Mazdoor day 0.700 560.00 392.00
Woman Mazdoor day 2.100 560.00 1176.00
Page 40 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 2933.82 440.07
B. LABOUR:
Mason 1st class day 0.45 670.00 301.50
Mason 2nd class day 1.050 605.00 635.25
Mazdoor (unskilled) day 2.80 560.00 1568.00
2944.82
Add Scafolding charges Sqm 10.00 19.51 195.10
MA 0% 0.00
Grand Total 3139.92
CP0% 0.00
Grand Total 3139.92
Providing impervious coat to exposed RCC roof slab surface with CM(1:3), 12mm thick with 1kg of
water proof compound per bag of cement laid over roof when it is green including cost of all
materials, seigniorage charges, excluding conveyance charges of materials and including all
operational, incidental and labour charges for mixing mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall and slab etc,, complete for finished item of work
Unit = 10 sqm
A. MATERIALS:
Page 41 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Page 42 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1 as per
India Gypsum) using 12.5 mm thick Gyp Board conforming to IS 2095 - 1982 fixing to Gyp steel GI
perimeter channels of size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick along the perimeter of
ceiling screw fixed to brick work/ partition at 610 mm c/c and suspending the frame work using
Intermediate channels (45 mm x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c with ceiling
angle (25 mm x 10 mm x 0.55 mm) fixed with GI Cleat and steel expansion fasteners & connecting
clip to the ceiling channels (with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm) fixed in
direction perpendicular to the intermediate channel at 457 mm c/c and fixing the 12.5 mm tapered
edge Gypboard with 25 mm drywall screws at 230 mm c/c & jointing and finishing using joint
compound and paper tape to have a flush look including filling the tapered & square edges with
jointing compound, two coats of drywall topcoat complete for finished item of work as per Idia
Gypsum Ltd specification.
UNIT -1 sqm
A) Material requirement as per
India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards 1.03 285.00 292.30
BMT-M.01 sqm
Ceiling Angle
BMT-M.04 25 mm x 10 mm x 0.55 mm RM 0.64 80.00 51.20
BMT-M.17 Connecting Clips Nos 1.84 11.00 20.24
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 2.30 110.00 253.00
BMT-M.05 RM
0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm 0.84 81.00 68.04
BMT-M.06 RM
Perimeter Channel
BMT-M.07 20 mm x 27 mm x 30 mm(web) of RM 0.40 72.00 28.80
BMT-M.18 0.55
Rawlmm
Plugthick Nos 0.64 4.00 2.56
BMT-M.20 Soffit Cleats Nos 0.64 4.00 2.56
BMT-M.21 Drywall Screws - 25 mm Nos 18.00 5.00 90.00
BMT-M.22 Jointing Compound Kgs 0.55 33.00 18.15
BMT-M.23 Jointing Paper Tape RM 1.46 6.24 9.11
BMT-M.24 Drywall Top Coat Lits 0.15 156.00 23.40
B) LABOUR CHARGES
1st Class Carpenter day 0.40 750.00 300.00
2nd Class Carpenter day 0.40 605.00 242.00
1st Class Painter day 0.08 750.00 60.00
2nd Class Painter day 0.08 605.00 48.40
Unskilled Mazdoor day 0.24 560.00 134.40
Power Drill - Hand Operated - 0.08 735.00 58.80
day
LAB-00025 Operator
Unskilled Mazdoor day 0.24 560.00 134.40
C) Machinery
Power Saw Cutter - Hand Operated 0.32 132.00 42.24
Hrs
BMC-X.02 - Hire charges
Power Drill - Hand Operated - Hire 0.64 121.00 77.44
Hrs
BMC-X.03 Charges
Scaffolding charges 1% 1957.04
BASIC COST per 1 sqm 1957.04
Page 43 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Anti corrosion CRPPC (Corrosion Resistant) inhibitive admixture Treatement of soil Beneath the
building and around the foundations conduct and chemical use as per BIS - IS 6313 (Part -2) 2013
code specification & CIB RC registered termiticide which creates a continuouschemical barrier
beneath the building which kills or repels terminates & impervious to tremite entry Imidacloprid
30.5% SC (IS 63131) dissolve 2.1 Ml/1 liter of water and apply emulsion/solution @ 7.5
Litres/Square meter (Sqm) of internal, external vertical surface of the colums , plinth beams (Back
filling) walls and floor junction, external perimeters, along reatining wall @ 5.0 Liters/Sqm of the
horizontalsurface of basement top surface of the basement filling below flooring bed (Plinth) & @
2.0 Litres/ Line meter at expansion joints. The substructure of a depth of 500mm around coulmns
& 300mm deep around plinth beams, basements & floor filling area including excavation channel
along the wall & rodding etc. cost & Conveyance of all materials to the site, cost of labour for
sparying, rodding etc. completefor furnished item of work as per the approval of the Engineer-in-
charge BMT-H. 66
Supply and installation of Double grooved and precoated extruded mineral (cement)
roof tiles of size 420 mmx330 mm of corrugated profile tiles with variable overlapping for coverage
of 1-1.2 per tile with European standards BEEN 490:2004 Monotone colour ; Orange, red BMT-
C.53(a)
Sqm 1 1234.20 1234.2
Page 44 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Flooring with Non-skid red or white full body Ceramic floor tiles of Size 600 mm x 600mm and
thickness between 8-10 mm and 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to 15)
of any colour and finish in all shades and designs, set over base coat of cement mortar (1:8), 12 mm
thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency
BLD-CSTN-7-6 spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with pigment of
matching shade, including cost of all materials like cement, sand water and tiles etc., complete, including
seigniorage charges, etc., complete for finished item of work, but excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles BMT-C.03 sqm 10.10 520.00 5252.00
Cement for CM (1:8) for base coat kg. 21.60 4220.00 91.15
Cement for slurry kg. 33.00 4220.00 139.26
White cement BMS-W.68 kg. 2.00 31.00 62.00
Sand for CM (1:8) cum 0.12 758.30 91.00
B. LABOUR
Mason 1st class day 0.96 670.00 643.20
Mason 2nd class day 2.24 605.00 1355.20
Mazdoor (unskiled) day 3.30 560.00 1848.00
Add Water Charges 1% 94.82
Grand Total 9576.63
CP0% 0.00
Grand Total 9576.63
S No Descitpion of item of Work per Quantiy Rate Amont
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick sqm 10.00 520.00 5200.00
Sand for cm 1:3 base coat cum 0.12 758.30 91.00
Cement for cm 1:3 base coat kgs 57.60 4.22 243.07
Cement for slurry kgs 33.00 4.22 139.26
White cement for jointing & pointing kgs 6.00 31.00 186.00
B. LABOUR
Mason 1st class day 0.77 670.00 515.90
Mazdoor (unskiled) day 0.80 560.00 448.00
Add Water Charges 1% 68.23
Grand Total 6891.46
CP0% 0.00
Grand Total 6891.46
Flooring with Double charged / multi charged stain free full body porcelain vitrified tiles with
double layer pigment of Size 600 x 600 mm of 1st quality, set over base coat of cement mortar (1:8),
12 mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with
BLD-CSTN-7-5 pigment of matching shade, including cost of all materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost
of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size 600x600 BMT-C.09 sqm 10.10 612.00 6181.20
Cement for CM (1:8) for base coat kg. 21.60 4.22 91.15
Cement for slurry kg. 33.00 4.22 139.26
Cement for Pointing with CM (1:3) kg. 6.000 4.22 25.32
Sand for CM (1:8) cum 0.12 758.30 91.00
Sand for pointing cum 0.020 758.30 15.17
B. LABOUR
Mason 1st class day 0.96 670.00 643.20
Mason 2nd class day 2.24 605.00 1355.20
Mazdoor (unskiled) day 3.30 560.00 1848.00
Add Water Charges 1% 42.08
10431.58
CP0% 0.00
Grand Total 10431.58
Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal to
flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like tiles, cement, sand and water etc.,
complete including seigniorage charges, etc., complete for finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality sqm 10.10 612.00 6181.20
Sand for cm 1:5 base coat cum 0.12 758.30 91.00
Cement for cm 1:5 base coat kgs 34.56 4.22 145.84
Cement for slurry kgs 33.00 4.22 139.26
S No Descitpion of item of Work per Quantiy Rate Amont
Dadooring to walls with digital / polished glazed full body porcelain highlighter wall tiles of size 300
x 600 mm with any type of design texture such as marble finish, wooden, bamboo, stone finishes etc.,
scratch less, stain free and thickness between 6-8 mm, set over base coat of cement mortar (1:6), 12
mm thick over CC bed already laid or RCC roof slab, including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm & jointed neatly with white cement paste mixed with pigment of
matching shade to full depth, including cost of all materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc., complete for finished item of work, but excluding the cost
of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
polished glazed full body porcelain sqm 10.10 605.00 6110.50
highlighter wall tiles of size 300 x 600 mm BMT-C.26
Cement for CM (1:6) for base coat kg. 28.80 4.22 121.54
Cement for slurry kg. 33.00 4.22 139.26
White cement for jointing & pointing kg. 6.00 31.00 186.00
Sand for CM (1:6) cum 0.12 758.30 91.00
B. LABOUR
Mason 1st class day 0.96 670.00 643.20
Mason 2nd class day 2.24 605.00 1355.20
Mazdoor (unskiled) day 3.30 560.00 1848.00
Add MA 0% on labour 0.00
Add water charges 1% 0.00% 104.95
Grand Total 10599.65
Add 0% Over head Charges 0.00
10599.65
S No Descitpion of item of Work per Quantiy Rate Amont
PAINTINGS
White washing two coats with whiting of approved quality to give an even shade after thoroughly
brushing the surface to remove all dirt and remains of loose powdered materials including cost of
BLD- all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for
CSTN-9-5 finished item of work, but excluding conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement cum / kg 2.00 31.00 62.00
B. LABOUR
Brick Layers / Painter Page 65 of SSR day 0.210 670.00 140.70
Mazdoor (unskilled) day 0.320 560.00 179.20
MA 0% 0.00
Sundries including brushes, ladders, etc., 1.00% 3.82
385.72
CP0% 0.00
Grand Total 385.72
Painting to new walls with 2 coats of snocem paint Over a primary coat of whtie cement (making
3 Coats) in all to give an even shade after thourughly brushing the surface to remove all dirt and
BLD- remains of loose powdered materials, including cost and conveyance of all materials to work site
CSTN-10-5 and all operational, incidental, labour charges etc. complete for finished item of work as per SS
912 for internal walls
PAINTINGS
2nd class painter day 0.35 605.00 211.75
Mazdoor (unskilled) day 1.50 560.00 840.00
MA 0% 0.00
Total cost 1980.20
BLD- Painting with Synthatic Enamil Paint Two coats over a Primary coat of white lead including cost
CSTN-10- and conveyance of all mateirals etc complete
12
a PRIME COAT WITH WHITE LEAD
white lead kg 1.600 121.00 193.60
B. LABOUR
Painter day 0.700 750.00 525.00
Add MA 20/0% on labour 0.00
b Painting with Synthetic Enamel paints - Two Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint L 1.200 191.00 229.20
B. LABOUR
Painter day 1.200 750.00 900.00
Add MA 20/0% on labour 0.00
Total cost for 10 sqm 1847.80
CP0% 0.00
Grand Total 1847.80
PAINTINGS
Brick Layers / Painter Page 65 of SSR day 0.11 500.00 55.00
Mazdoor (unskilled) day 0.22 560.00 123.20
Add MA 20/0% on labour 0.00
Sundries including brushes, ladders, etc., 0.50% 1.08
Plastic Emulsion paint Lr 0.8 201.00 160.80
Painter 1st class Nos 0.21 750.00 157.50
Painter 2nd class Nos 0.49 605.00 296.45
Mazdoor Nos 1.5 560.00 840.00
Add MA 20/0% on labour 0.00
Sundries for Spraying Machine etc., LS 4.36
Unit -10Sqm 1675.59
CP0% 0.00
Grand Total 1675.59
Providing and applying synthetic plaster putty or plaster of paris putty or lime punning
of average 1 to 2 mm thickness over plastered surface to prepare the surface even and
smooth after thoroughly brushing the surface to remove all dirt and remains of loose
powdered materials, applying emery paper, Sand the surface, clean & wipe off loose
dust, applying knifing paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand
with 180 and 320 No., emery paper for the surface preparation including cost and
conveyance of all materials to work site and all operational, incidental, labour charges
etc. complete for finished item of work for Internal walls
PAINTINGS
13.615% 502.34
4191.97
S No Descitpion of item of Work per Quantiy Rate Amont
Frames :
Cost of Salwood for frames cum 0.0266 53275.00 1417.12
Shtters :
Cost of Salwood for shutters cum 0.0288 66549.00 1916.61
Total wood Qty. cum 0.0554
Labor charges :
S No Descitpion of item of Work per Quantiy Rate Amont
S.N
Description of item Unit Qty Rate Amount
o.
Clearing the Light Jungle on either side of Road margins inlcuidng removing burning ashes etc compelte as
1 per standards specifications
Clearing the heavy Jungle on either side of Road margins inlcuidng removing burning ashes etc compelte as
2 per standards specifications
Scarifying existing granular surface to a depth of 50 mm and disposal of scarified material with all lifts and
3 leads upto 1000 m as per Technical Specification Clause 305.4.3 MORTH
Unit = sqm
Taking output = 100 sqm
Labour
Mazdoor (Unskilled) day 4.160 560.00 2329.60
Machinery
Tractor with trolley hour 1.000 543.00 345.00
2674.6
Cost for 100 sqm = a+b+c+d 26.75
Rate per sqm = (a+b+c+d)/100
Unit = cum
Taking output = 120 cum
a) Labour
Mazdoor (Unskilled) day 46.800 560.00 26208.00
Cost of 120 cum = a+b+c 218.40
Rate per cum = (a+b+c)/120
Unit = cum
Taking output = 120 cum
a) Labour
Mazdoor (Unskilled) day 46.800 560.00 26208.00
b) Machinery
Truck 5.5 cum capacity hour 10.000 1242.70 12427.00
Cost of 120 cum = a+b+c+d 38635.00
Rate per cum = (a+b+c+d)/120 321.96
By Manual means
Taking out put = 360 cum
Labour
Mazdoor (Skilled) day 12.08 560.00 6764.80
Mazdoor (unskilled) day 250.00 560.00 140000.00
Machinery
Vibratory Roller 80-100 KN @60cum per hour OR hour 6.00 3499.60 20997.60
Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00 1743.60 52308.00
Water tanker 6kl capacity hour 24.00 822.00 19728.00
Material (Total Qty 435.60 Cum)
60-63 mm IRC HBG Metal (50% of 435.60 cum) Cum 217.80 597.90 130222.62
40-45 mm IRC HBG Metal (46% of 435.60 cum) Cum 200.38 1005.90 201562.24
19-22 mm IRC HBG M/C Metal (4% of 435.60 cum) Cum 17.42 1518.40 26450.53
Stone Screening
Type B 11.2 mm for Grading 2 @ 0.18 / 0.20 cum/10sqm cum 86.40 902.57 77981.76
Binding Material @ 0.06 cum per 10 sqm for Grading 2 material cum 28.80 485.90 13993.92
By Manual means
Taking out put = 360 cum
Labour
Mazdoor (Skilled) day 12.08 560.00 6764.80
Mazdoor (unskilled) day 250.00 560.00 140000.00
Machinery
Vibratory Roller 80-100 KN @60cum per hour OR hour 6.00 3499.60 20997.60
Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00 1743.60 52308.00
Water tanker 6kl capacity hour 24.00 822.00 19728.00
Material (total Qty of Metal 435.60 Cum)
40-45 mm IRC HBG M/c Metal ( 82% of 435.60 Cum) Cum 357.19 1005.90 359297.42
19-22.40 mm IRC HBG M/c Metal ( 18% of 435.60 cum) Cum 78.41 1518.40 119057.74
Stone Screening
Type -B 11.2mm @ 0.18 cum per 10 sqm cum 86.40 694.65 60017.76
(rate of 2.36 mm & below)
Binding Material
Basic rate for 360 Cum 778171.32
Rate per Cum 2161.59
Add for conveyance for Metal cum 1.45 0.00 0.00
Page 55 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Rate per cum 2161.59
Construction of granular sub-base/shoulders using Gravel & Sand by providing well graded material, spreading in
uniform layers with motor grader on prepared surface and compacting with Vibratory Roller 80-100 KN @10cum per
hour capacity to achieve the desired density, complete as per Technical Specification Clause 402 MORD, , But
excluding VAT
Unit = cum
Taking output = 300 cum
a) Labour
Mazdoor (Skilled) day 2.48 560.00 1388.80
Mazdoor (Unskilled) day 8.00 560.00 4480.00
b) Machinery
Three wheel 80-100 kN static roller @10 cum per hour hour 30.00 1743.60 52308.00
Water tanker 6 kl capacity hour 5.00 822.00 4110.00
c) Material
Gravel cum 384.00 192.30 73843.20
Cost for 300 cum = a+b+c+d+e 136130.00
Rate per cum = a+b+c+d+e/300 453.77
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
Labour
Mason (1st class) day 5.00 670.00 3,350.00
Mason (2nd class) day 5.00 605.00 3,025.00
Mazdoor (unskilled) day 150.00 560.00 84,000.00
Mazdoor(skilled) day 6.00 560.00 3,360.00
Mazdoor (semi-skilled) day 6.00 560.00 3,360.00
97095.00
Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 mixers) with weight Hour 36.00 692.70 24,937.20
batcher and suitable capacity calibrated water tank
Plate vibrator Hour 9.00 70.00 630.00
Water tanker 6 Kl. Capacity Hour 5.00 822.00 4,110.00
29,677.20
Material
Crushed stone coarse aggregates, grading will be as per clause
1501.2.4.1 (Table 1500.1) of specifications @ 0.90 Cum/cum of
concrete
20mm Cum 44.55 1658.40 73,881.72
12mm Cum 22.95 1342.15 30,802.34
Sand as per IS:383 and conforming to clause 1500.2.4.2. @ 0.45 cum 33.75 642.30 21,677.63
cum of concrete
Cement @ 330 Kg/cum of concrete t 24.75 4220.00 104,445.00
Page 57 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Polythene sheet 125 micron sqm 412.5 15.25 6,290.63
Joint filler board 12.70 mm thick as per IS:1838 sqm 3.00 #REF! #REF!
(4x3.75x0.200 = 3 sqm) #REF!
#REF!
Form work @ 3% on (a+b+c) #REF!
Cost for 75 cum = a+b+c+d #REF!
Rate per Cum = (a+b+c+d+e)/75 #REF!
Rate per cum #REF!
144 Cutting of Grooves 75mm deep with petrol saw as per the direction of Engineer-in-charge, inclusive of all machinary
and labour charges for finished item of work complete
Unit 100 Rm
A) Machenary:
Generator 35 KVA (3Phase) Hr 4.00 882.90 3531.60
Floor Saw cutting hire charges Rm 1.00 15.00 15.00
Water Tanker Hr 4.00 630.00 2520.00
B) Labour:
Floor saw cutter Skilled No. 0.50 420.00 210.00
Floor saw cutter unskilled No. 1.00 370.00 370.00
Man Mazdoor No. 1.00 370.00 370.00
Provision towards fillilng the joints bitumen Rate as per SSR 2017-18 Rm 1.00 15.00 15.00
Add MA on labour 0% 0.00
Cost per 100 Rm 7031.60
Cost per 1 Rm 70.316
12 B T Prime Coat
Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including
cleaning of road surface and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical means as per
Technical Specification Clause 502 MORD (for use on Wet mix macadam & WBM) ,including overhead charges &
Contractors profit but excluding VAT.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.040 560.00 582.40
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400 455.00 637.00
Air compressor 210 cfm hour 1.400 633.00 886.20
Bitumen emulsion pressure distributor @ 1750 sqm/hour hour 1.000 1073.00 1073.00
Water tanker 6 kl capacity 1 trip per hour hour 0.500 822.00 411.00
c) Material
Bitumen emulsion (SS-1) @ 0.85 kg per sqm t 1.480
Rate per sqm
B T Teak coat
13 Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30
kg per sqm on the prepared granular surfaces treated with primer & cleaned with Hydraulic broom as per Technical
Specification Clause 503 MORD,including overhead charges & Contractors profit but excluding VAT.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mazdoor (Unskilled) day 1.040 560.00 582.40
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.400 455.00 637.00
Air compressor 210 cfm hour 1.400 633.00 886.20
Page 58 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Emulsion pressure distributor @1750 sqm per hour hour 1.000 1073.00 1073.00
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.480 0.00
Cost of 1750 sqm = (a+b+c+d+e)
Rate per sqm = a+b+c+d+e/1750
Rate per sqm
BT OGPC Layer
Providing and laying Open Graded Premix Carpet (OGPC) surfacing material of 20 mm thick composed of 13.20 mm
to 5.60 mm size machine crushed hard blasted granite chips using bitumen of 60/70 grade at the rate of 14.60 kgs
per 10 sqm area of road surface over tack coat to required line, level, grade to serve as wearing course on
previously prepared base including mixing in a Mixer of 6 to 10 T capacity,trasporting the mixer to point of use and
rolloing with three wheeled 8-10 Tonnes capacity static roller and finishing to required level and grades including
14 cost and conveyance of all materials from approved sources, seigniorage, labour charges and hire and operational
charges of power road roller and all other machinery, tools and plants, providing barricading for diversion of traffic,
erecting red flags other incidental and operational charges etc., complete for finished item of work by manual means
as per technical specification clause 508(ii) of MORD including overheads & Contractors profit but excluding VAT.
By Manual Means
Taking out put = 1100 Sqm
Labour
Bitumen Sprayer day 1.00 560.00 560.00
Mazdoor (un-skilled) day 22.00 560.00 12320.00
Mazdoor (semi-skilled) day 7.15 560.00 4004.00
Machinery
Bitumen boiler oil fired, capacity1000 lts fitted with spray set hour 2.20 261.00 574.20
Three wheel 80-100 kN static roller hour 2.20 1743.60 3835.92
Page 59 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Materials
Bitumen (S-65) 60/70 grade @ 9.80 kgs per 10 sqm. t 1.078
Crushed stone chipping of 6.7 mm size 100% passing 11.2mm cum 9.90 892.15 8832.29
seive and retained on 2.36 mm sieve applied @ 0.09 cum per 10
sqm.
Basic rate of Seal coat Type-A for 1100 Sqm
foundation and compacted by vibration including curing for 14 days complete for Side drain Portion as per drawings
and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50
16 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical
Specification 305 MORD / 304 MORTH
Manual Means
Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mazdoor (Unskilled) day 3.64 560.00 2038.40
Cost for 10 cum = a+b+c 203.84
Rate per cum = (a+b+c)/10
17 Filling in foundation trenches as per drawing and technical specification Clause 305.3.9 MORD & 304
MORTH
Sand filling
Unit = 6cum
a) Labour
Mate day -
Page 60 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Mazdoor (Unskilled) day 0.31 560.00 173.60
b) Material
Sand cum 6.00 497.30 2983.80
3157.40
Rate per cum 526.23
Providing concrete for plain concrete M 10 grade in open foundations using 40 mm nominal size Graded hard
stone aggregate, mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days
16 complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100
MORTH ,including overhead charges & Contractors profit but excluding VAT.
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 4220.00 928.40
Coarse sand cum 0.45 642.30 289.04
40 mm aggregate cum 0.9 1035.90 932.31
(b) Labour
Mate day -
Mason (1st Class) day 0.10 670.00 67.00
Mazdoor (Unskilled) day 1.39 560.00 778.4
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water hour 0.40 692.70 277.08
measuring device and preferably also with load cell.
Water tanker 6 kl capacity hour 0.13 822.00 106.86
3379.09
(d) Formwork @ 4% on cost of material, labour and machinery 4.00% 135.16
(a+b+c)
3514.25
Add for conveyance for Metal cum 0.90 35.90 32.31
Add for conveyance for Sand cum 0.45 37.30 16.79
Rate per cum = a+b+c+d+e+f 3563.35
Page 61 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Reinforced cement concrete M25 grade (Design Mix) using 20 & 10mm metal mechanically mixed in
substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and
1204 MORD and 1500, 1700 & 2200 MORTH ,including overhead charges & Contractors profit but excluding VAT
upto 5m height.
R.C.C. grade M 25 (Design Mix)
Unit = cum
Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement t 0.403 4220.00 1700.66
Coarse sand cum 0.450 642.30 289.04
20 mm aggregate cum 0.540 1658.40 895.54
10 mm aggregate cum 0.360 1144.65 412.07
(b) Labour
Mason (1st Class) day 0.10 670.00 67.00
Mazdoor (Unskilled) day 1.39 560.00 778.40
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 692.70 277.08
4419.79
(d) Formwork @ 10% on (a+b+c) 10.00% 441.98
4861.77
Rate per cum = a+b+c+d+e+f 4861.77
Providing and laying cement concrete wearing course M 30 (Design Mix) grade using 20 & 10mm metal
mechanically mixed excluding reinforcement complete as per drawing and technical specifications Clauses 800 and
1206.3 MORD and 2702 MORTH ,including overhead charges and contractors profit but excluding cost of steel and
VAT.
Unit = cum
(a) Material
Cement t 0.407 4220.00 1717.54
Sand cum 0.45 642.30 289.04
20 mm aggregate cum 0.54 1658.40 895.54
10 mm aggregate cum 0.36 1144.65 412.07
(b) Labour
Mason (1st Class) day 0.10 670.00 67.00
Mazdoor (Unskilled) day 1.39 560.00 778.40
Mazdoor (Unskilled) for cleaning deck slab concrete surface day 0.15 560.00 84.00
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 692.70 277.08
4520.67
(d) Formwork @ 3% of cost of concrete 3.00% 135.62
4656.29
Rate per cum = a+b+c+d+e+f 4656.29
Page 62 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Cement at site t 0.07 4220.00 295.40
RCC pipe NP3 pipe at site m 7.50
RCC pipe NP3 collar at site Nos 2.00
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
1000 mm dia
a) Labour
Mate day -
Mason (1st Class) day 0.25 670.00 167.50
Mazdoor (Unskilled) day 2.09 560.00 1170.40
Laying & fixing of Pipes with colors in position including lifting, rm
aligning etc.,
b) Material
Sand at site cum 0.04 642.30 25.69
Cement at site t 0.03 4220.00 126.60
RCC pipe NP3 pipe at site m 7.50
RCC pipe NP3 collar at site Nos 2.00
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
750 mm dia
a) Labour
Mate day -
Mason (1st Class) day 0.15 670.00 100.50
Mazdoor (Unskilled) day 1.25 560.00 700.00
Laying & fixing of Pipes with colors in position including lifting, rm
aligning etc.,
b) Material
Sand at site cum 0.024 642.30 15.42
Cement at site t 0.018 4220.00 75.96
RCC pipe NP3 pipe at site m 7.50
RCC pipe NP3 collar at site Nos 2.00
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 600 mm dia Hume pipe may be derived from the
rates for 750 dia by decreasing 20 per cent
Laying Cement Concrete Pipe NP3 on first class bedding of granular material including fixing collar with cement sand
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry work in head wall and
parapet as per Tech Specification No. 1100 MORTH
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
750 mm dia
a) Labour
Mate day -
Mason (1st Class) day 0.30 670.00 201.00
Mazdoor (Unskilled) day 2.51 560.00 1405.60
b) Material
Sand at site cum 0.04 642.30 25.69
Cement at site t 0.036 4220.00 151.92
RCC pipe NP3 pipe at site m 7.50
RCC pipe NP3 collar at site Nos 2.00
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 300 mm dia shall be decreased by 20%
Page 63 of 93
S.N
Description of item Unit Qty Rate Amount
o.
Laying Cement Concrete Pipe NP3 on first class bedding of granular material including fixing collar with cement sand
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry work in head wall and
parapet as per Tech Specification No. 1100 MORTH
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
500 mm dia
a) Labour
Mate day -
Mason (1st Class) day 0.11 670.00 73.70
Mazdoor (Unskilled) day 0.94 560.00 526.40
b) Material 120.02
Sand at site cum 0.02 642.30 720.12
Cement at site t 0.01 4220.00 144.02
RCC pipe NP3 pipe at site m 7.50 576.10
RCC pipe NP3 collar at site Nos 2.00 76.81
c&d) Overheads & Contractors Profit
Cost for 7.5 m = a+b+c+d
Rate per m = (a+b+c+d)/7.5
Note : The labour rate for 300 mm dia shall be decreased by 20%
Page 64 of 93
Data Sheet Water supply and sanitary items & Electrification for Buildings (2023-24)
Page 65 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Providing & Placing on Terrace(at all floor levels) polyethylene water storage tank with Double layer approved brand &
9 manufacture with cover and suitable locking arrangement & making necessary holes for inlet & outlets and over flow pipes
but without fittings & base support for tanks
Unit Each - 1Ltr
water storage tank (BMW-G.01) 1 Ltr 1.00 8.50 8.50
Rate per Each Rate per 1 Ltr 8.50
10 Supply of Plastic storage tank lid with hinges including cost and conveyance of all materails and labour charges etc
complete.
Unit Each.
tank lid (BMW-G.03) Each 1.00 70.00 70.00
Rate per Each 70.00
11 Supply and Fixing of 12.7mm N.P bib tap Indian make including cost and conveyance of all materails and labour charges
etc complete.
Unit Each.
bib tap (BMW-E.07) Each 1.00 387.00 387.00
Rate per Each 387.00
Supply and Fixing of 12.7 mm brass stop cock Indian make heavy duty Ist quality including cost and conveyance of all
12
materials and labour charges etc complete
Unit 1 No.
stop cock (BMW-E.13) Nos 1.00 222.00 222.00
Rate per 1.00 No 222.00
13
Supplying & Fixing 12.7 mm PVC connection with brass union nut C.P coated including cost and conveyance of all
materials and labour charges etc complete
Unit 1 No.
PVC connection (BMW-I.48) Nos 1.00 95.00 95.00
Rate per 1.00 No 95.00
Supply and fixing of 25mm Gunmetal (GM) Ball valve with SS Ball and SS Spindle Indian make heavy type including cost
14
and conveyance of all materials and labour charges etc complete
Unit Each.
ball valve (BMW-F.59) Each 1.00 864.00 864.00
Rate per Each 864.00
15
Supplying & fixing Gunmetal (GM) Vertical Check (Non return) Valve as per IS-778 I-class heavy duty - 40 mm NB Size
including cost and conveyance of all materials and labour charges etc complete
Unit Each.
check valve (BMW-F.51) Each 1.00 1370.00 1370.00
Rate per Each 1370.00
Electrical Data
1.4.2
Supply and Fixing of 25mm dia 1.80/2.00mm thick PVC pipe (ISI MARK) concealed in wall with all required accessories including
masonary work and labour charges etc., complete.
Page 66 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Sundries
C) Cost for 100 RM 10002.00
Rate per Metre = C/100 100.02
(b) Supply and Fixing of 20mm dia 1.5mm thick P.V.C. pipe (ISI MARK) concealed in wall with all required accessories
including masonary work for light, fan and separate plug point with well seasoned wooden deep box including all labour
charges etc., complete.
Taking Output = 100 M
a) Material
MAT 02675
20mm dia 1.5mm thick PVC pipe 100 M 100 26.00 2600.00
MAT 04226 U' Links 100 Nos 2 36.00 72.00
ELEC-1.4.1 e 10" x 8" Wooden deep box Each 3 61.00 183.00
MAT 02699 20mm dia 1,2,3 & 4 way deep Junction Box Each 12 32.00 384.00
MAT 02704 20mm PVC bends Each 12 9.00 108.00
MAT 04287 Cement kg 50 10.00 500.00
b) Labour charges :
Skilled Electrician day 2 745.00 1490.00
Semi skilled Electrician day 2 607.00 1214.00
Helpers day 2 605.00 1210.00
Mason Ist class day 2 670.00 1340.00
C) Cost for 100 RM 9101.00
Rate per Metre = C/100 91.01
Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant (FR) P.V.C. insulated flexible copper cable (ISI MARK) in
2.1.1 existing pipe with 6A switch, Ceiling rose and 3mm thick hylam sheet covering to switch control box including all labour
charges etc., complete for light, bell, fan and exhaust fan points in Non-Residential Buildings
Taking Output = 6 Points
a) Material
MAT 02748 14/0.3mm PVC FR flexible copper wire 100 M 1 1238.00 1238.00
MAT 02833 6A Switch each 6
80.00 480.00
MAT 02818 6A 2 way Ceiling Rose@17/each S. No 214 each 6 22.00 132.00
MAT 02836 Modular covering plate 6 Modular each 1 122.00 122.00
b) Labour charges :
Skilled Electrician day 0.6 745.00 447.00
Semi skilled Electrician day 1.2 607.00 728.40
Helpers day 0.6 605.00 363.00
C) Cost for 6 Points 3510.40
Rate per Point = C/6 585.07
585.07
Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant (FR) P.V.C. insulated flexible copper cable (ISI MARK) in
2.1.1 existing pipe with 20A 1 Way 1 Module Modular Switch with Indicator, Ceiling rose and 3mm thick hylam sheet covering to
switch control box including all labour charges etc., complete for light, bell, fan and exhaust fan points in Non-Residential
Buildings
Taking Output = 6 Points
a) Material
MAT 02748 14/0.3mm PVC FR flexible copper wire 100 M 1 1238.00 1238.00
MAT 02842 20A Switch each 6
117.00 702.00
MAT 02818 Ceiling Rose each 6 22.00 132.00
MAT 02836 Modular covering plate 6 Modular each 1 122.00 122.00
b) Labour charges :
Skilled Electrician day 0.6 745.00 447.00
Semi skilled Electrician day 1.2 607.00 728.40
Helpers day 0.6 605.00 363.00
C) Cost for 6 Points 3732.40
Rate per Point = C/6 622.07
622.07
Supply and fixing of 6A 3 pin wall plug socket with 6A switch control on a common switch board with earth continuity
2.1.4
including wire leads, earth connections along with all labour charges etc., complete.
Page 67 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Taking Output = each
a) Material
MAT 02853 6A 3 pin / 2 pin Socket
each 1 94.00 94.00
MAT 02853 6A switch
each 1 61.00 61.00
b) Labour charges :
Skilled Electrician day 0.067 745.00 49.92
Helpers day 0.067 605.00 40.54
Rate per each 245.46
245.46
Supply and Fixing of 16A/20A 3pin and 6A 3pin plug socket and 16A switch control duly recessed in wall with metal deep
2.1.6
box of covered with modular covering plate including earth connections and all labour charges etc., complete.
Taking Output = each
a) Material
MAT 02713 supply of 6 modular box each 1.00 155.00 155.00
MAT 02853 6A Moduar plate each 1.00 132.00 132.00
MAT 02861 16A/6A 1 way Combi Socket each 1.00 138.00 138.00
b) Labour charges :
Skilled Electrician day 0.10 745.00 74.50
Semi Skilled Electrician day 0.10 607.00 60.70
Helpers day 0.10 605.00 60.50
Rate per each 620.70
620.70
3.1.2 Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. insulated flexible copper cable in existing pipe for earth
continuity including all labour charges etc., complete.
Taking Output = 100 M
a) Material
MAT 02748 14/0.3mm FR PVC copper wire 100 M 1 1238.00 1238.00
b) Labour charges :
Skilled Electrician day 0.34 745.00 253.30
Semi Skilled Electrician day 1 607.00 607.00
Helpers day 0.34 605.00 205.70
Sundries
C) Cost for 100 RM 2304.00
Rate per Metre = C/100 23.04
23.04
3.1.1 Supply and run of 2 of 14 /0.3mm (1.0 Sq.mm) FR P.V.C. insulated flexible copper cable in existing pipe for earth
continuity including all labour charges etc., complete.
Taking Output = 100 M
a) Material
MAT 02748 14/0.3mm FR PVC copper wire 100 M 2 1238.00 2476.00
b) Labour charges :
Skilled Electrician day 0.67 745.00 499.15
Semi Skilled Electrician day 2 607.00 1214.00
Helpers day 0.67 605.00 405.35
Sundries
C) Cost for 100 RM 4594.50
Rate per Metre = C/100 45.95
45.95
Note : Labour Charges considered for 150 M / day
3.1.4 Supply and run of 2 of 36/0.3mm (2.5 Sq.mm) F.R P.V.C. insulated flexible copper cable in existing pipe for mains
inlcuding all labour charges etc., complete.
Taking Output = 100 M
a) Material
Page 68 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
MAT 02750 36/0.3mm (2.5 sqmm) FR PVC copper wire 100 M 2 2874.00 5748.00
b) Labour charges :
Skilled Electrician day 0.67 745.00 499.15
Semi Skilled Electrician day 2 607.00 1214.00
Helpers day 0.67 605.00 405.35
Sundries
C) Cost for 100 RM 7866.50
Rate per Metre = C/100 78.67
78.67
3.1.5 Supply and run of 2 of 56/0.3mm (4 Sq.mm) F.R P.V.C. insulated flexible copper cable in existing pipe for mains inlcuding
all labour charges etc., complete.
Taking Output = 100 M
a) Material
a) Material
MAT 03600
Ceiling Fan of 48" (1200mm) No 1 2766.00 2766.00
MAT 02787 23/0060 Twin Core wire M 1 11.20 11.20
Transportation charges on unit cost 1% 2766.00 27.66
9.7.35 b) Labour charges.
Skilled Electrician day 0.125 745.00 93.13
Helper day 0.125 605.00 75.63
Rate per Each 2973.62
2973.62
9.7.26 Supply and erecting step type Modular regulator for ceiling fans 1200mm sweep complete erected on existing board.
Page 69 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
MAT 03319 28/0060 twin core flexible copper cable M 1.00 11.20 11.20
Aluminium flat (as per requirment) LS
b) Labour charges for cutting P.O.P / false ceiling and Fixing
MOT
Skilled Electrician day 0.125 745.00 93.13
Carpenter day 0.125 750.00 93.75
Semi skilled Electrician / Helper day 0.125 605.00 75.63
273.71
Rate per each 1150.71
Supply and fixing TPN Distribution board with IP-20 protection (Metal Door) suitable for single phase ELCB / RCCB / FP
Isolator as incomer and 10kA SP MCBs as outing going including internal connection and labour charges for surface /
flush mounting etc., complete.
40A FP Isolator - 1 No for incomer, 10kA-6-32A SP MCBs - 4 Nos for outgoing.
Taking Output = each
a) Material
MAT 03073 40-63A DP MCB each 1.00 1100.00 1100.00
MAT 03095 40A D.P.Isolator / ECCB / RCCB each 1.00 432.00 432.00
MAT 03070 10kA - 6-32A range SP MCBs each 4.00 228.00 912.00
b) Labour charges :
Skilled Electrician day 0.50 745.00 372.50
Semi Skilled Electrician day 0.50 607.00 303.50
Helpers day 1.00 605.00 605.00
Sundries such as TW Plugs, Screws Cement etc, LS
Rate per each 3725.00
Supply and fixing of batten holder / slanting holder in lieu of ceiling rose of light point complete with all connections and all
2.1.7
labour charges with 18W pin type CFL Lamp (for new installation).
MAT 02830 PVC batten holder 1.7.25 each 1 23.00 23.00
MAT 03282 18W pin type CFL lamp each 1 105.00 105.00
Skilled Electrician day 0.05 745.00 37.25
Helpers day 0.05 605.00 30.25
Rate per each 195.50
Total Rate 1 No 195.50
Providing independent earthling by excavating a trench to a depth of 2.1 M in all soils, as per size specified in
the Data, using 40mm dia 'B' class GI pipe of 2.5 Mtrs length with necessary accessories with hume pipe ring
5.1.1
duly providing staggered holes including filling with equal proportion of Salt and Charcoal in layers and all
labour charges etc., complete for small quarters.
a) Material
MAT 04294 Earth Work Excavation of Hard gravel Soil with small
boulder for trench 1st step of size 1.5 x 0.6 x 0.9 m cum 0.85 303.00 257.55
(5'x2'x3')
Excavation of Hard disteggrated rocks and boulders for
cum 0.90 303.00 272.70
MAT04294 trench 2nd Step of size 1.2 x 0.6 x 1.2 m (4'x2'x4')
25% extra for narrow trench & pit and back filling with Sand, Coke, Salt etc., and leveling 132.56
MAT 04292 40mm dia 'B' Class G.I pipe. Mtr 2.5 425.00 1062.50
25 x 6 mm (1"X 1/4") G.I Flat duly drilled 12mm holes (4
MAT 04151 Each 1 97.00 97.00
Nos) of 200 mm (8") length
MAT 04295 Drilling of 16 Nos through holes of 12mm dia to G.I pipe Each 16 8.00 128.00
MAT 04295 G.I Nuts, Bolts an Washers Set 4 14.00 56.00
MAT 04295 18"(450mm) dia hume pipe ring., Each 1 303.00 303.00
MAT 04232
Hard Coke., Kg 20 24.00 480.00
MAT 04233 Salt. Kg 10 19.00 190.00
b) labour charges for fixing pipe ring and connections
Semi skilled Electrician Nos 0.50 607.00 303.50
Helpers Nos 0.50 605.00 302.50
Rate per each 3585.31
Page 70 of 93
S No Descitpion of item of Work per Quantiy Rate Amont
Supply and Run of 4 of 16 Sq.mm WPSC Aluminium cable along with No.10 SWG G.I bearer wire through PVC cleats with
6.1.6 all accessories including labour charges etc., complete for service mains.
a) Material
MAT 02791 16 Sq.mm WPSC Aluminium cable 100 M 4.00 3300.00 13200.00
MAT 04271 No.10 SWG GI Wire (6.7kg x 2) Length 200 RM
kg 13.40 85.00 1139.00
MAT 04236 Binding wire kg 0.25 73.00 18.25
MAT 04235 PVC Cleats / Separters 4 Way 100 Nos 1.00 520.00 520.00
b) labour charges
Skilled Electrician day 2.00 745.00 1490.00
Semi skilled day 2.00 607.00 1214.00
Helper day 2.00 605.00 1210.00
Sundries such as insulation tapes and rounding off
C) Cost for 100 M 18791.25
Rate per mtr c/100 187.91
187.91
Supply and Transportation of 1 HP Single phase ISI Mono block CI body motor pumpset (25x25mm). Makes:
11.1.1
Kirloskar / Crompton / Texmo / CRI / KSB/Lubi / Havells Hi-flow V2 as per SSR
MAT 03700 1 HP single phase mortor Each 1.00 8652.00 8652.00
b) labour charges
Skilled Electrician day 0.50 745.00 372.50
Helper day 1.00 607.00 607.00
plumber day 0.50 605.00 302.50
Rate per Each 9934.00
Supply and fixing of three phase energy meter, 240 V AC, 50 HZ as per IS13010 with 2.5-5 / 5-10/10-20 Amps range wth
14.2.9
200% over load capacity complete with connection etc., complete on the existing board.
MAT 03992 meter each 1 3,080.00 3,080.00
Skilled Electrician day 0.33 745.00 245.85
Total Rate 1 No 3325.85
Page 71 of 93
RCC HUME PLAIN ENDED PIPES RATES 2019-20
144 Supply and fixing of MS name board of size 4feet X No. 1 Rate to be
3feet size including painting and required lettering as fed by the
per standard specifications EE
Concerned
Unit 1 No
A) Matereial Requirement
Iron section
Outer Frame MS Pipe of 32mm dia total 14+14' = 8.53m Rm 8.53 185.00 1578.86
Painting with enmail paint over primary coat 1Sqm 1.00 124.00 124.00
Painting letters of 5CM size 59+ 23Nos 1Cm 410.00 1.60 656.00
144 Supply and fixing of MS name board of size 4feet X No. 1 Rate to be
3feet size including painting and required lettering as fed by the
per standard specifications EE
Concerned
Unit 1 No
A) Matereial Requirement
Iron section
Outer Frame MS Pipe of 32mm dia total 14+14' = 8.53m Rm 8.53 185.00 1578.86
4 RCC M20 for Columns, Plinth, Lintel, Roof 11.08 11.08 9.97 4.99 0.00
beams
5 RCC M20 Sunshade 0.75/0.50m th 0.60m 15.13 0.95 0.85 0.43 0.00
wide
6 RCC M20 Roof Slab 110mm thick 76.42 8.41 7.57 3.78 0.00
1 Concrete Mixer 0.28 Cum. HIR-00018 692.70 1 Hour 1 Mason 1st Class LAB-00011 670.00 day 1 White Cement BMS-W.68 31.00
2 Needle Vibrator 40mm 274.40 1 Hour 2 Carpenter 1st Class 750.00 day 2 Water proof cement BMT-J.23 54.00
HIR00040 LAB-00004 paint
3 Vibratory roller 8 tonne HIR--00062 3499.60 1 Hour 3 Painter 1st Class 750.00 day 3 Cement Primer BMT-J.01 173.00
LAB-00035
4 Smooth wheeled roller 8tonne HIR-00050 1743.60 1 Hour 4 Mason 2nd Class LAB-00091 605.00 day 4 Wood Primer BMT-J.05 176.00
5 Water tanker 6 Kilolitre HIR-00076 822.00 1 Hour 5 Carpenter 2nd Class LAB-00060 605.00 day 5 Red Oxide BMT-J.03 160.00
6 Tractor with Grader HIR-00077 531.00 1 Hour 6 Painter 2nd Class LAB-00093 605.00 day 6 White Lead BMT-J.08 121.00
7 Tractor with rotavator HIR-00078 543.00 1 Hour 7 Black smith 630.00 day 7 Synthetic Enamel Paint BMT-J.30 191.00
LAB-00002
8 Tipper 5.5Cum capacity 1242.70 1Hour 8 Electrician Skilled 745.00 day 8 Plastic Emulsion paint - BMT-J.24 201.00
Ext
HIR-00054 LAB-00005
9 Bitumen boiler HIR-00094 261.00 1Hour 9 Mazdoor (Unskilled) 560.00 day 9 Oil Bound Distember BMT-J.21 85.00
LAB-00120
10 Dozer( D 80 ) HIR-00008 3050.60 1 Hour 10 Semi skilled Electrician 607.00 day 10 Dry Powder Distemper BMT-J.20 46.00
LAB-00079
11 Dozer( D 50 ) HIR-00072 1907.00 1 Hour 11 Helper Electrical 605.00 day 11 Synthatic Plaster Putty
LAB-00079 BMT-J.31 30.30
12 Tractor with ripper HIR-00079 543.00 1 Hour 12 1040.00 day JUNGLE
attachment Diploma Engineer / Surveyor LAB-00127
13 Hydralic Broom HIR-00081 455.00 1Hour 13 Brick layer 670.00 day 1 Cleraing heavy Jungle MAT-00479 3.20
LAB-00011
14 Air Compressor HIR-00002 633.00 1Hour 14 Operator Lathe/Drilling/Shearing 735.00 day 2 Clering Light jungle MAT-00480 2.80
machine LAB-00025
15 Bitumen pressure distributer HIR-00082 1907.00 1Hour 15 Power Saw Cutter - Hand Operated - 132.00 day Water
Hire charges BMC-X.02
16 Emulsion pressure distributer HIR-00083 1073.00 1Hour 16 Power Drill - Hand Operated - Hire 121.00 day 1 Rural water rate 99.00
Charges BMC-X.03 MAT-00540
17 Front end loader HIR-00074 2023.00 1Hour Materials
18 Motor grader HIR-00073 3796.00 1Hour GYP BOARD CEILING MATERIALS
19 Hydrallic exacavator HIR-00052 3561.50 1Hour S.no Item 1219 mm x 1829 mm size 285.00
BMT-M.01
Boards
20 Wet Mix Plant 60TPH HIR-00080 1984.00 1Hour WOOD WORK Ceiling Angle 25 mm x 10 mm
x 0.55 mm
21 Generator 30 KVA HIR-00023 1356.90 1Hour 1 Medium Teakwood Scantlings (2-3m) BMT-E.02 96183.50 1 Cum BMT-M.04 80.00
22 Plate compacter HIR-00115 70.00 1 Hour 2 Medium Teakwood Planks BMT-E.04 168193.00 1 Cum Connecting Clips BMT-M.17 11.00
23 125 micron Polythene sheet MAT-00539 15.25 1Sqm 3 Country wood Scantlings BMT-E.15 53275.00 1 Cum Ceiling Section 51.5 mm x
26 mm x 10.5 mm x 0.55
24 M-120 70.00 1 Kg 4 Country wood Planks BMT-E.16 66549.00 1 Cum mm thick BMT-M.05 110.00
Joint Sealant Compound
25 Water tanker 8 Kilolitre HIR-00064 1207.60 1 Hour OTHER RATES Intermediate Channel 45 mmx
15 mm x 15 mm x 0.9 mm
26 3264.00 1 Hour 1 Supply and fixing of false ceiling POP BMT-M.51 441.00 1 Sqm 81.00
Hydraulic Chip Spreader HIR-00090 BMT-M.06
board 12 mm TH
27 Hot mix Plant – 40 to 60 TPH 23965.00 1 Hour 2 Supply and fixing of false ceiling POP BMT-M.52 368.00 1 Sqm Perimeter Channel 20 mm x
27 mm x 30 mm(web) of 0.55
capacity HIR-00087 board 10 mm TH mm thick
28 Paver Finisher Hydrostatic with 3891.00 1 Hour 3 A.C.Sheets Corrugated 6mm BMT-E.17 237.50 1 Sqm 72.00
sensor control 100 TPH HIR-00088 BMT-M.07
29 Generator 125 KVA HIR-00111 1836.00 1 Hour 4 G.I.Sheets Plain / Corrugated BMT-E.20 73.50 1 Kg Rawl Plug BMT-M.18 4.00
30 Generator 250 KVA HIR-00110 2572.00 1 Hour 5 Water Proof Compound BMT-H.93 111.00 1 Kg Soffit Cleats BMT-M.20 4.00
31 Tandem Road roller HIR-00091 2208.00 1 Hour 6 Cement Jali- 25 mm Thick BMS-W.15 218.00 1 Sqm Drywall Screws - 25 mm BMT-M.21 5.00
S.no Item SSR Code No Rate Rs. Unit S.no Item Rate Rs. Unit S.no Item Rate Rs.
32 261.00 1 Hour 7 Cement Jali- 40 mm Thick BMS-W.16 283.00 1 Sqm Jointing Compound
BMT-M.22 33.00
Bitumen boiler oil fired HIR-00094
33 Plasticizer MAT-05375 83.00 1 Kg 8 Cement Jali- 50 mm Thick BMS-W.17 388.00 1 Sqm Jointing Paper Tape BMT-M.23 6.24
34 Epoxy compound with accessories for 362.00 1 Kg 9 Binding wire MAT-00003 70.00 1 Kg. Drywall Top Coat BMT-M.24 156.00
preparing epoxy mortar MAT00254
35 Bitumenous sealant MAT-00275 70.00 1 Kg 10 Rabbit wire(Chicken mesh) BMT-F.28 22.00 1Sqm
11 GALVANISED PROFILE SHEET BMS-W.45 836.00 1Sqm
12 ROOFING
Labour for Fabricating Grills BMM-V.14 33.00 1 Kg
13 Labour for Fixing Grills BMM-V.15 6.00 1 Kg
1 Kg
1 Kg
1 Kg
1 Ltr.
1 Ltr.
1 Kg
1 Ltr.
1 Ltr.
1Kg
1Kg
1Kg
1Sqm
1Sqm
Unit
Centering Charges
GROUND FLOOR FIRST FLOOR SECOND FLOOR
S.no Item Hire Labour Total Unit Hire Labour Total Unit Hire Labour Total Unit
1 Footings 301.00 672.00 973.00 1 Cum
2 Bed blocks 67.00 363.00 430.00 1 Cum
3 Pedastels 343.00 1069.00 1412.00 1 Cum
4 Plinth Beams 1453.00 1620.00 3073.00 1 Cum
HIRE CHARGES FOR CENTERING & SCAFFOLDING - Unsupported
Height upto 3.66 M Steel scaffolding pipes, jack Props, wallers, Foot
plates, brackets, steel Centering Plates,etc.
5 Lintels 1233.00 1720.00 2953.00 1 Cum 1233.00 1892.00 3125.00 1 Cum 1233.00 2064.00 3297.00 1 Cum
6 Sunshades & Chajjas 243.00 264.00 507.00 1 Sqm. 243.00 290.00 533.00 1 Sqm. 243.00 317.00 560.00 1 Sqm.
7 Columns 371.00 2415.00 2786.00 1 Cum 371.00 2657.00 3028.00 1 Cum 371.00 2898.00 3269.00 1 Cum
8 Beams 2179.00 2027.00 4206.00 1 Cum 2179.00 2230.00 4409.00 1 Cum 2179.00 2432.00 4611.00 1 Cum
9 Slabs-upto 150mm thick 247.00 241.00 488.00 1 Sqm. 247.00 265.00 512.00 1 Sqm. 247.00 289.00 536.00 1 Sqm.
10 Slabs150-300mm thick 254.00 248.00 502.00 1 Sqm. 254.00 273.00 527.00 1 Sqm. 254.00 298.00 552.00 1 Sqm.
11 Slabs 300mm above 265.00 260.00 525.00 1 Sqm. 265.00 286.00 551.00 1 Sqm. 265.00 312.00 577.00 1 Sqm.
HIRE CHARGES FOR CENTERING & SCAFFOLDING - Unsupported
Height upto 3.66 M Casurina Ballies, Bamboos, Wooden Reapers,
Runners, Wood Posts, Wall Plates etc.
12 Lintels 826.00 1332.00 2158.00 1 Cum 826.00 1465.00 2291.00 1 Cum 826.00 1598.00 2424.00 1 Cum
13 Sunshades & Chajjas 163.00 204.00 367.00 1 Sqm. 163.00 224.00 387.00 1 Sqm. 163.00 245.00 408.00 1 Sqm.
14 Columns 249.00 1871.00 2120.00 1 Cum 249.00 2058.00 2307.00 1 Cum 249.00 2245.00 2494.00 1 Cum
15 Beams 1458.00 1569.00 3027.00 1 Cum 1458.00 1726.00 3184.00 1 Cum 1458.00 1883.00 3341.00 1 Cum
16 Slabs-upto 150mm thick 165.00 186.00 351.00 1 Sqm. 165.00 205.00 370.00 1 Sqm. 165.00 223.00 388.00 1 Sqm.
17 Slabs150-300mm thick 170.00 193.00 363.00 1 Sqm. 170.00 212.00 382.00 1 Sqm. 170.00 193.00 363.00 1 Sqm.
18 Slabs 300mm above 178.00 201.00 379.00 1 Sqm. 178.00 212.00 390.00 1 Sqm. 178.00 232.00 410.00 1 Sqm.
19 Scaffolding for Brick work for 10.78 84.62 95.4 1 Sqm. 10.78 121.18 131.96 1 Sqm. 10.78 157.72 168.5 1 Sqm.
20 Scaffolding for Plastering 1.08 8.47 9.55 1 Sqm. 1.08 12.12 13.2 1 Sqm. 1.08 15.77 16.85 1 Sqm.
21 Scaffolding for Ceiling Plastering 2.57 16.94 19.51 1 Sqm. 2.57 24.04 26.61 1 Sqm. 2.57 31.13 33.7 1 Sqm.
VITRIFIED TILES
1 soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm BMT-C.06 425.00 1 Sqm
2 Nano polished /stain free soluble salt porcelain vitrified tiles screen printed of size 600 x 1 Sqm
600 mm BMT-C.07 462.00
3 Double charged / multi charged stain free full body porcelain vitrified tiles with double
layer pigment of Size 600 x 600 mm BMT-C.09 625.00 1 Sqm
4 Double charged / multicharged stain free full body porcelain vitrified tiles with double layer
pigment BMT-C.10 770.00 1 Sqm
5 digital / polished glazed full body porcelain vitrified tiles with any type of design texture
such as marble finish, wooden, bamboo, stone finishes etc., scratch less, stain free and
Size 800 x 800 mm BMT-C.12 770.00 1 Sqm
6 glazed vitrified tiles with matt finish of size 600 x600mm BMT C.13(a) 825.00 1 Sqm
CERMIC TILES
1 Non-skid red or white full body Ceramic floor tiles of Size 300 mm x 300 BMT-C.01 396.40 1 Sqm
2 Non-skid red or white full body Ceramic floor tiles of Size 450 mm x 450 BMT-C.02 390.00 1 Sqm
3 Non-skid red or white full body Ceramic floor tiles of Size 600 mm x 600 BMT-C.03 520.00 1 Sqm
4 Non-skid red or white full body Ceramic floor tiles of Scratch free-stain free and scratch
free-nano finish of Size 600 mm x 600 mm BMT-C.04 530.00 1 Sqm
5 GLAZED TILES
6 scratch less, stain free and thickness between 6-8 mm BMT-C.26 605.00 1 Sqm
7 Polished Marble Tiles
8 Polished Marble Tiles of 8 - 10 mm thickness of all sizes and varieties BMT-B.15 510.00 1 Sqm
Conveyance 2023-24
Sand Metal Bricks
Lead excluding excluding excluding
OH OH OH
Page 82 of 93
Sand Metal Bricks
Lead excluding excluding excluding
OH OH OH
Page 83 of 93
Sand Metal Bricks
Lead excluding excluding excluding
OH OH OH
Page 84 of 93
Labour Days =
S. No. Description Depth Qty Labour Hours
hrs/8
1 DUR Piles 375 mm dia 3.50 0.760 51.04 6.380
DUR Piles 375 mm dia 3.75 0.787 53.00 6.625
DUR Piles 375 mm dia 3.80 0.793 53.40 6.675
DUR Piles 375 mm dia 4.65 0.886 59.00 7.375
Supply and fixing of Bath room / Toilet door shutter with 16mm
laminated (IS 14276) door shutter with all-round „U‟ lipping of PPS
section of size 12mm X 18mmX 12mmX0.6mm thickness with a
hardware of 12mm dia X200mm long aluminum aldrop – 2 nos( ISI
BMT-N.69 make)2 No of 125mm long handles(ISI make) and also 3 no Of IS304 1 2660.00 1 Sqm 2660.00
grade Patee Hinges 3mmX12mmX180mm long with pole receiver of
10mm dia pole X40mm long welded on 2mm X40mm(ss304) plates
works as receiver for RT patte hinges. The price inclusive of all material
at site
Fe - 415 Grade Steel Fe - 500 Grade Steel
HYSD bars Binding Blacksmith / Mazdoor HYSD bars Binding Blacksmith Mazdoor
Month & Basic Basic including 5 wire Bar bender (Unskilled)
Rate for Rate for Month & Basic Basic including 5 per wire / Bar (Unskilled
Rate
Year Steel Rate per cent for
overlaps and
Ground First Year Steel Rate cent for
overlaps and
bender ) for
Rate includin wastage Floor Floor Rate including wastage Ground
g GST GST Floor
August-2019 36500 43070 45224 330 4950 4200 54703.50 55618.50 August-2019 37000 43660 45843.00 330 4950 4200 55323
September-2019 36500 43070 45224 330 4950 4200 54703.50 55618.50 September-2019 37000 43660 45843.00 330 4950 4200 55323
October-2019 36500 43070 45224 330 4950 4200 54703.50 55618.50 October-2019 37000 43660 45843.00 330 4950 4200 55323
November-2019 36500 43070 45224 330 4950 4200 54703.50 55618.50 November-2019 37000 43660 45843.00 330 4950 4200 55323
December-2019 36500 43070 45224 330 4950 4200 54703.50 55618.50 December-2019 37000 43660 45843.00 330 4950 4200 55323
January-2020 38500 45430 47702 330 4950 4200 57181.50 58096.50 January-2020 39000 46020 48321.00 330 4950 4200 57801
Feburuary-2020 38500 45430 47702 330 4950 4200 57181.50 58096.50 Feburuary-2020 39000 46020 48321.00 330 4950 4200 57801
March-2020 39000 46020 48321 330 4950 4200 57801.00 58716.00 March-2020 40000 47200 49560.00 330 4950 4200 59040
April-2020 39000 46020 48321 330 4950 4200 57801.00 58716.00 April-2020 40000 47200 49560.00 330 4950 4200 59040
May -2020 39000 46020 48321 330 4950 4200 57801.00 58716.00 May -2020 40000 47200 49560.00 330 4950 4200 59040
June -2020 40500 47790 50180 330 4950 4200 59659.50 60574.50 June -2020 41500 48970 51418.50 330 4950 4200 60898.5
July-2020 40500 47790 50180 330 4950 4200 59659.50 60574.50 July-2020 41000 48380 50799.00 330 4950 4200 60279
August-2020 40500 47790 50180 336 5250 4600 60365.50 61350.50 August-2020 41000 48380 50799.00 336 5250 4600 60985
September-2020 41000 48380 50799 336 5250 4600 60985.00 61970.00 September-2020 41000 48380 50799.00 336 5250 4600 60985
October-2020 41000 48380 50799 336 5250 4600 60985.00 61970.00 October-2020 41500 48970 51418.50 336 5250 4600 61604.5
November-2020 41000 48380 50799 336 5250 4600 60985.00 61970.00 November-2020 43000 50740 53277.00 336 5250 4600 63463
December-2020 46000 54280 56994 336 5250 4600 67180.00 68165.00 December-2020 48000 56640 59472.00 336 5250 4600 69658
January-2021 53000 62540 65667 336 5250 4600 75853.00 76838.00 January-2021 55000 64900 68145.00 336 5250 4600 78331
Feburuary-2021 50000 59000 61950 336 5250 4600 72136.00 73121.00 Feburuary-2021 53000 62540 65667.00 336 5250 4600 75853
March-2021 50500 59590 62570 336 5250 4600 72755.50 73740.50 March-2021 53000 62540 65667.00 336 5250 4600 75853
April-2021 51000 60180 63189 336 5250 4600 73375.00 74360.00 April-2021 54000 63720 66906.00 336 5250 4600 77092
May -2021 52500 61950 65048 336 5250 4600 75233.50 76218.50 May -2021 55000 64900 68145.00 336 5250 4600 78331
June -2021 53000 62540 65667 336 5250 4600 75853.00 76838.00 June -2021 55000 64900 68145.00 336 5250 4600 78331
July-2021 52000 61360 64428 336 5250 4600 74614.00 75599.00 July-2021 55000 64900 68145.00 336 5250 4600 78331
August-2021 51500 60770 63809 384 5500 4900 74592.50 75632.50 August-2021 53500 63130 66286.50 384 5500 4900 77070.5
September-2021 51500 60770 63809 384 5500 4900 74592.50 75632.50 September-2021 54500 64310 67525.50 384 5500 4900 78309.5
October-2021 54500 64310 67526 384 5500 4900 78309.50 79349.50 October-2021 56500 66670 70003.50 384 5500 4900 80787.5
November-2021 55000 64900 68145 384 5500 4900 78929.00 79969.00 November-2021 60000 70800 74340.00 384 5500 4900 85124
December-2021 55000 64900 68145 384 5500 4900 78929.00 79969.00 December-2021 60000 70800 74340.00 384 5500 4900 85124
January-2022 56000 66080 69384 384 5500 4900 80168.00 81208.00 January-2022 58000 68440 71862.00 384 5500 4900 82646
Feburuary-2022 56000 66080 69384 384 5500 4900 80168.00 81208.00 Feburuary-2022 60000 70800 74340.00 384 5500 4900 85124
March-2022 60500 71390 74960 384 5500 4900 85743.50 86783.50 March-2022 68000 80240 84252.00 384 5500 4900 95036
HYSD bars Binding Blacksmith / Mazdoor HYSD bars Binding Blacksmith Mazdoor
Month & Basic Basic including 5 wire Bar bender (Unskilled)
Rate for Rate for Month & Basic Basic including 5 per wire / Bar (Unskilled
Rate
Year Steel Rate per cent for
overlaps and
Ground First Year Steel Rate cent for
overlaps and
bender ) for
Rate includin wastage Floor Floor Rate including wastage Ground
g GST GST Floor
April-2022 65000 76700 80535 384 5500 4900 91319.00 92359.00 April-2022 73000 86140 90447.00 384 5500 4900 101231
May -2022 62000 73160 76818 384 5500 4900 87602.00 88642.00 May -2022 72000 84960 89208.00 384 5500 4900 99992
June -2022 62000 73160 76818 384 5500 4900 87602.00 88642.00 June -2022 69000 81420 85491.00 384 5500 4900 96275
July-2022 62000 73160 76818 384 5500 4900 87602.00 88642.00 July-2022 64000 75520 79296.00 384 5500 4900 90080.00
August-2022 62000 73160 76818 420 5900 5250 88388.00 89503.00 August-2022 65000 76700 80535.00 420 5900 5250 92105
September-2022 62000 73160 76818 420 5900 5250 88388.00 89503.00 September-2022 64000 75520 79296.00 420 5900 5250 90866
October-2022 61000 71980 75579 420 5900 5250 87149.00 88264.00 October-2022 64000 75520 79296.00 420 5900 5250 90866
November-2022 61000 71980 75579 420 5900 5250 87149.00 88264.00 November-2022 64000 75520 79296.00 420 5900 5250 90866
December-2022 58000 68440 71862 420 5900 5250 83432.00 84547.00 December-2022 62000 73160 76818.00 420 5900 5250 88388
January-2023 60000 70800 74340 420 5900 5250 85910.00 87025.00 January-2023 62000 73160 65100 420 5900 5250 76670
February-2023 60000 70800 74340 420 5900 5250 85910.00 87025.00 February-2023 63000 74340 66150 420 5900 5250 77720
March-2023 61000 71980 75579 420 5900 5250 87149.00 88264.00 March-2023 64500 76110 67725 420 5900 5250 79295
April-2023 61000 71980 75579 420 5900 5250 87149.00 88264.00 April-2023 64500 76110 67725 420 5900 5250 79295
Rate for
First
Floor
56238.00
56238.00
56238.00
56238.00
56238.00
58716.00
58716.00
59955.00
59955.00
59955.00
61813.50
61194.00
61970.00
61970.00
62589.50
64448.00
70643.00
79316.00
76838.00
76838.00
78077.00
79316.00
79316.00
79316.00
78110.50
79349.50
81827.50
86164.00
86164.00
83686.00
86164.00
96076.00
Rate for
First
Floor
102271.00
101032.00
97315.00
91120.00
93220.00
91981.00
91981.00
91981.00
89503.00
77785.00
78835.00
80410.00
80410.00