0% found this document useful (0 votes)
23 views

Projecttimetable

This Gantt chart outlines the schedule for a project from June 2023 to March 2024. It includes tasks such as forming a project group, identifying requirements, developing and testing software, and revising documentation. Major milestones include title approval, proposal submission, chapter defenses, system evaluation, pilot testing, and final submission. The project consists of 24 total tasks scheduled over 204 days.

Uploaded by

Markjohn Valdez
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views

Projecttimetable

This Gantt chart outlines the schedule for a project from June 2023 to March 2024. It includes tasks such as forming a project group, identifying requirements, developing and testing software, and revising documentation. Major milestones include title approval, proposal submission, chapter defenses, system evaluation, pilot testing, and final submission. The project consists of 24 total tasks scheduled over 204 days.

Uploaded by

Markjohn Valdez
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task Name Duration Start Finish

Half 1, 2023 Half 2, 2023 Half 1, 2024


M J J A S O N D J F M A M
0 Projecttimetable 204 days Mon 6/19/23 Thu 3/28/24
1 Group Creation; 1 day Mon 6/19/23 Mon 6/19/23
2 Identify and Select Project Title; 3 days Wed 6/21/23 Fri 6/23/23
3 Stakeholders and End-users; 3 days Mon 6/26/23 Wed 6/28/23
4 Initial Project Requirements; 4 days Thu 6/29/23 Tue 7/4/23
5 Title Presentation and Approval; 1 day Thu 7/6/23 Thu 7/6/23
6 Analysis and Data Gathering; 2 days Fri 7/7/23 Sun 7/9/23
7 Current system of target locale; 3 days Tue 7/18/23 Thu 7/20/23
8 Project Proposal Documentation; 1 day Thu 7/20/23 Thu 7/20/23
9 Project Development; 2 days Thu 7/27/23 Fri 7/28/23
10 Sub. of Project Proposal Doc; 1 day Mon 7/31/23 Mon 7/31/23
11 Chapter 1-3 Defense 1 day Tue 8/1/23 Tue 8/1/23
12 Project Proposal Revisions; 4 days Wed 8/2/23 Mon 8/7/23
13 Software Development 15 days Mon 10/9/23 Fri 10/27/23
14 System Evaluation 1 day Thu 11/23/23 Thu 11/23/23
15 Sysyem Revision 3 days Mon 11/27/23 Wed 11/29/23
16 Pilot testing 51 days Wed 11/29/23 Wed 2/7/24
17 Creation of Chapter IV and system Evaluation 4 days Mon 2/12/24 Thu 2/15/24

18 Revision of Chapter IV and System Revision 3 days Fri 2/16/24 Tue 2/20/24
19 Creation of Chapter V ans System Evaluation 4 days Thu 3/21/24 Tue 3/26/24
20 Revision of Chapter V and System Revision 2 days Wed 3/27/24 Thu 3/28/24
21 Submision oof complete Documents 1 day Mon 3/4/24 Mon 3/4/24
22 Final Defense

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Projecttimetable
Summary Manual Summary Rollup Progress
Date: Tue 3/5/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slippage

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start Finish
Half 1, 2023 Half 2, 2023 Half 1, 2024
M J J A S O N D J F M A M
23 Revision of Complete Documens
24 Submision of Final Software Product and Complete
Documentation

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Projecttimetable
Summary Manual Summary Rollup Progress
Date: Tue 3/5/24
Project Summary Manual Summary Manual Progress

Inactive Task Start-only Slippage

Inactive Milestone Finish-only

Page 2

You might also like