Getting Started With M&E Vertical Risers - 8 Things To Consider
Getting Started With M&E Vertical Risers - 8 Things To Consider
8 min read
March 24, 2022
Getting
started with
M&E vertical
risers: 8
things to
consider
Mouj Hijazi
Got any questions? I'm happy to
help.
Back to blog
A vertical riser is anything that rises vertically in a building – most
commonlyCallreferring to pipes,
Email cables, ducts, and conduits.
0 ITEMS
Vertical risers are typically designed to distribute building services, such as water and electricity,
throughout all the floors in the building. Due to the nature of a project of this scale, as an M&E
contractor, there are certain factors you should take into account that are fundamental for
efficient delivery. The key things to consider when you want to design a core riser are:
Number of floors
Riser duct/Space constraints
Loads and load paths
Services
Material options and profiles
Timeframes/deadlines
Stakeholders
Transport and lifting
Call Email 0 ITEMS
Number of floors
This point is self-explanatory – you need to know how many floors the riser is intended for to
determine how the riser will be built. If it’s only two or three floors, you might be able to fabricate
it as one complete unit as opposed to breaking it down into modules. Usually, though, risers will
be built in sections and then stacked on top of each other – this is mainly due to the difficulty of
transporting such a large structure. The number of floors will then obviously also determine the
size of the riser, as well as affect the weight of it with all the components. Based on the number
of floors and how it’s being built, that would also impact things like load calculations – the more
floors there are, the higher the load is at the bottom of the column.
Call Email 0 ITEMS
Load/load paths
When it comes to loads, there are a couple of points to keep in mind. You need to think about the
load of the frame itself, how it can support itself under its own weight, and whether it needs
redistributing, as well as the loads of the services on the frame. If needed, the load path can be
redirected laterally to the existing floor slabs, by introducing something like cantilever arms to
connect to the structure at each floor level. The frame needs to be designed to be able to handle
the load of all of the services combined, while taking into account that the load will vary at
different floor levels based on which floor it is, and what services need to be distributed to that
floor. For example, the bottom of the structure will be carrying the most weight, and it will
decrease as you go up - each floor needs to take the correct load. If the bottom needs to be
much stronger, you can create extra support/reinforcement on the sides; it can be designed in a
way that the Call
load-bearing capacity Emailof the module on 0oneITEMS
floor is much greater than another. It all
comes down to the design. All the frame is doing is creating something you can anchor the
services to – you’ve still got to fix a pipe to the frame and what’s used to do so can be a weak
point if you don’t select the right item (e.g. pipe clamps, anchors, etc.) – this can make all the
difference. Moreover, keep in mind that modular steel is much lighter than traditional steel, which
would impact the overall weight of the frame and the load that it puts on the building, as well as
reduce the pressure at the bottom. On top of all of this, if you’re dealing with pipework, there are
some more specific concerns you should watch out for – bear with me! This leads to our next
point.
Services
Whether the services being distributed by the pipework are water, electricity, or something else,
it’ll have its knock-on effects. The services are being supported vertically, and the distance is
usually between four floors up to eight. Considering all of that pipework – let’s say, around 30
metres’ worth - and the weight coming down on itself and bending at the bottom, that
unsurprisingly causes a lot of pressure (column load), especially when the pipes are filled with
water. If the water in the pipes doesn’t change temperatures, there’s no need to worry about the
riser weight being unevenly distributed (if you’ve selected the correct hardware). However, when
the water is heated, the pipe will expand against the riser clamps (pipe supports on every other
floor) – enter thermal expansion. This is a very elaborate topic, in which I am not an expert - but
Call will give you aEmail
the linked podcast 0 ITEMS of it. I highly recommend checking
much deeper understanding
it out because it is most definitely a significant element to consider. It's best to engage an expert
in this topic in real life as well, to help you decide what anchors you'll need and where, and guide
the brackets' positioning on the frame. Something else to think about is how often the services
need to be supported; or 'support centres', because they will also have an influence on the design
of the riser. For example, with cable tray, that might only need to be supported between every
1.2-1.5 metres, whereas ladder may need to be supported every 3 metres. Also, give some
thought to the service position and density. If they're nicely arranged around the perimeter, that
makes it much easier for supporting compared to if they were densely packed next to each other.
Timeframes/deadlines
The reason why this is a consideration is, if planned correctly and engaged early, the modular
solution can be delivered much faster done offsite. A recent study on a riser project here at
MIDFIX demonstrated that using a modular type box section, even if in an offsite environment, will
still take approximately 10x less time than it would to fabricate a riser using traditional steel. If it
was something like pipe supports, the time difference wouldn’t be so noticeable simply because
the construction industry works more in days rather than hours. So although it would only take a
few hours to fabricate pipe supports using Framo, with traditional steel, for example, it would take
longer but still be done within the day. Whereas with a riser, something that could take a day
could take up to two weeks, considering all the welding, drilling, cutting, galvanising, and bolting
that has to take place with traditional steel. The other argument against modular steelwork is that
it needs to be planned ahead to be done effectively, in the planning stage as opposed to the
fabrication stage.
If you’ve got to have a riser installed in three weeks, it might be quite difficult to plan it in that time
and to get all the needed stakeholders involved. In contrast, a lot of people will default to
traditional steel because the planning hasn’t been done, and it’s selected at the ‘last-minute’ so
modular is no longer an option. To me, this doesn’t make sense though – because at the end of
the day, the fabricating will take ten-fold longer – you might as well spend that time planning and
save yourself the labour! Whether you end up going with modular or traditional steel, you’ll have
to fit the time into your schedule either way.
Call Email 0 ITEMS
Stakeholders
The importance of crystal clear and open communication throughout the supply chain with the
client, subcontractor, and even internally with the design department and sales team, will be
recognised from early on in the projects. Otherwise, there will be hiccups. During a lot of
installations, the responsibility and management of it fall mostly on the M&E contractor because
there isn’t much impact on the rest of the site. Whereas a riser is very significant – when
arranging things like crane lifts, you’d have to include the Tier 1 contractor because they’re
primarily responsible for the project as a whole. There are a lot of moving parts that you have to
coordinate, so it’s to take a collaborative approach right from the concept phase. Given all the
variables and dynamics and scale of the structure, it’s also very important that it’s designed and
engineered in a reliable 3D environment that has the ability to output the correct information
clearly and relevantly (e.g. CAD Autodesk inventor); this would be the responsibility of the
supplier.
Transport
Call
and lifting
Email 0 ITEMS
Referring back to the point about lifting, there’s more to reflect on when it comes to the physical
transportation of the structures. It needs to be well-planned because it could involve multiple
vehicles and multiple flat-bed lorries. Often given the size of the risers, which could be
overhanging the edge of the vehicle, certain specialist transport requirements may need to be
considered, such as wide loads with escorts and movement orders. This is when the driver can
only drive down certain routes because of the width of the vehicle, and that width has to be
approved by council and police, etc. All of the above factors will in some way influence the
transport of the riser or riser modules to the site. Also, give some thought to what access there is
on-site for the transport – because of the size of risers, sometimes access is limited and the
vehicle can’t actually get close enough to the site. A site might have a standard-width entrance
that is normally used for goods-in and offloading, but this isn’t always accessible for the wider
vehicles used to transport riser/riser modules. Often, for high-rises, for example, the vehicle
needs to be parked as close to the entrance as possible and then the goods are craned off the
lorry onto the site. This in itself takes quite a bit of coordination - it first needs to be tipped and
lifted upright by the crane. Additionally, the location of the riser duct within the building can quite
drastically impact what type of crane and equipment you’ll need. If it’s right in the middle of the
building, the arm of the crane at the end of it has to get right above that hole, meaning it has a
good distance to go over to reach it. Just to make sure it doesn’t topple over, weights are often
placed on the crane (by other smaller cranes!). Yes, you might need a crane to set up another
crane. Hopefully, you’re not too overwhelmed reading this. Whichever stakeholder is coordinating
with the crane lifting company needs to include them in the conversation as early as possible, so
that they can adequately plan for it. Furthermore, you need to ensure the correct lifting eyes are
used to lift the riser modules, and that the manufacturer can provide a certificate to prove its
testing and lifting capabilities.
Call Email 0 ITEMS
Conclusion
Although it may seem overly meticulous to review everything mentioned, especially considering
this level of diligence hasn’t been common throughout the history of the construction industry,
trust us when we say it’s for the better. You will save much more time, effort, and money in the
long run if you think about everything that can go wrong before it actually does, particularly with
projects of this scale. We hope that this article has helped you feel a bit more educated (if a little
swamped!), ready for your upcoming vertical riser projects and that you will mull it all over in
preparation. Good luck!
protected by reCAPTCHA
Privacy - Terms
SUBMIT
Products
Call
About us0 ITEMS What we do
Email
Supports & Latest News Technical Solutions
Suspensions Careers Engineered Design
Cable Containment About Us Concept Design
Cutting & Drilling Meet The Team Prefabrication and
Threaded Fasteners Blog Offsite Manufacture
Fixings & Anchors Delivery Commitment Case Studies
Pipework Products
Cable Accessories
© 2021 MIDFIX | Privacy Policy