NAM MO 2 HYDROPOWER PROJECT
NEAR PLAN QC INSPECTION ON 02-03-2024
Phase type(**)
No. Descriptions Request No Location Expecting time Action by(*) Remark
I W H
Witnessing comprssive strength of CVC Trial Mix in Laboratory @3days
mix code:
C30-19-(14-18)-107 02/03/2024
1 NM2-SCI-GP-0-CON-IR-0238 Laboratory RL F
C30-37.5-(12-16)-108 7:30
C35-19-(14-18)-109
C35-37.5-(12-16)-110
Witnessing compresssive strength of cement for LVV P52.5 Type I 02/03/2024
2 NM2-SCI-GP-0-CON-IR-0239 Laboratory RL F
cement . Delivery on site:23/2/24. Lot No : BPI 524010 @7days 8:00
Witnessing compresssive strength of concrete for Headrace Tunnel 02/03/2024
3 NM2-SCI-HT-4-CON-IR-0216 Laboratory RL F
Block: BT-12,5-14,5 Section 1 @7days 8:00
Witnessing compresssive strength of Grout for Rock Bolts installation on 02/03/2024
4 NM2-SCI-SP-5-CON-IR-0087 Laboratory RL F
right abutment of Scour Hole Type 2 @7days 8:00
Rebar checking and concrete pouring for Block: TP-19-20,5 Headrace tunnel 02/03/2024
5 NM2-SCI-HT-4-CON-IR-0215 AP F
Section 1 Section 1 15:00
Inspection before pouring concrete of Main Dam Right bank grout cap 22/01/2024
6 NM2-SCI-DA-3-CON-IR-0017 Main Dam AP F Postponed
concrete- Block BR-06 8:30
02/03/2024
7 Inspection before upstream and downstream cofferdam embankment NM2-SCI-RD-2-FIL-IR-0138 Cofferdams AP F
8:00
Legend:
(*) RL-Laboratory Responsible, SM-Site Manager ,SQM- Site Quality Manager, QCE-Field QC Engineer,
RT-Surveyor, AP-Production Supervisor, GEO-Geologist Engineer
(**) I-Information, W- witness, H-Hold point(need to approval before start)
Page 1 of 1
MR-NM2- 01-01
REQUEST FOR INSPECTION
Req. No: NM2-SCI-RD-2-FIL-IR-0138
m
To: NM2 Employer’s Engineer (LJ Hydro Consultancy) Date: 01/03/2024
□ Civil □Geologist □ HM □ E&M □ HSE □ QC □ Survey
□ River Diversion □ Power Intake □ Access Road
□ Diversion Tunnel □ Intake Slope □ Temporary Access Road
□ Upstream Cofferdam □ Intake Foundation □ Operation Road
□ Downstream Cofferdam □ Headrace Channel □ Operator Camps
□ Main Dam □ Power Tunnel □ Camp at Powerhouse
□ Dam Body □ Headrace Tunnel □ Camp at Headwork
□ Left Dam Abutment □ Vertical Shaft
□ Temporary Facilities
□ Right Dam Abutment □ Penstock
□ Crushing Plant at.........
□ Auxiliary Dam □ Powerhouse platform
□ Batching Plant at.........
□ Left Dam Abutment □ Powerhouse Platform
□ Other...........................
□ Right Dam Abutment □ Powerhouse Building
□ Laboratory
□ Spillway □ Powerhouse Slope
□ Quarry works
□ Spillway □ Tailrace Channel
□ Chute □ Switchyard □ H&M at the ………………....
□ Plunge Pool / Stilling Basin □ Auxiliary Tunnel □ E&M at the ………………....
□ Spillway Slope □ Adit 1 □ Adit 2 □ Other: ……………………….
□ Adit □ Other…..
The NM2_EPC Contractor is hereby informing/requesting inspection □ I □ W □ H as follows:
Purpose of
Location (Elevation, Station) Item for Inspection Inspection1
Proposed Date and Time Remarks
02/03/2024
Inspection before upstream and downstream 8:00
F
cofferdam embankment
Location: Headworks Site
1) Inspection purpose:
A-Punch List D-Re-evaluation of NCR G-Material’s manufacturing at site
B-QC completion inspection E-Notification of NCR deficiency of correction H-Field testing and inspection
C-Definition of construction detail F-General inspection during work I-Others…..
Requested by SCI AP/QCE/QCM: Received by EE:
Name: Nguyen Van, Kien Name:
Employer / Engineer QC Remarks
By Employer/ Engineers QC:
Name:________________________________Signature:________________________Date:______________