0 ratings0% found this document useful (0 votes) 72 views85 pagesChapter 3 8
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
TABLE OF CONTENTS
(CHAPTER- 1 CONCRETE
Plain and Reinforced Concrete
The Principles of Concrete Mixing
The Unit of Measure
Concrete Proportions
Concrete Slab
Estimating by the Area Method
Concrete Column
Estimating Concrete Column by ihe Linear
Meter Method
Post and Footing
1-10 Rectangular Column
1-11 Rectangular Beam and Girder
41-12 Circular Column
1-13 Concrete Pipes
CHAPTER- 2 MASONRY
24
22
2-3
24
Concrete Hollow Blocks
Special Types of Concrete Hollow Blocks
Decorative Concrete Blocks
Adobe Stone
CHAPTER- 3 METAL REINFORCEMENT
3-1
3-2
3-3
34
3-5
Steel Bars
Identification of Steel Bars
Bar Splice, Hook and Bend
Reinforcement for Concrete Hollow Blocks
Tie Wire for Steel Reinforcement3-6 independent Footing Reinforcement
3-7 Post and Column Reinforcement
3-8 Beams and Girders Reinforcement
3-9 Lateral Ties
3-10 Stirrups for Beam and Girder
3-11 Spiral and Coiumn Ties
3-12 One Way Reinforced Concrete Slab
3-13 Two Way Reinforced Concrete Slab
3-14 Concrete Pipe Reinforcement
CHAPTER- 4 LUMBER
4-1 Wood
4-2. Definitions of Terms
4-3 Classification of Wood
4-4 Methods of Log Sawing
4-5 Defects in Wood
4-6 Seasoning of Lumber
4-7. The Unit Measure of Lumber
4-8 Wood Post
4-8 Girder
4-10 Floor Joist and T&G Flooring
4-11 Siding Wood Board
4-12 Girts, Rafters, Truss, Purlins and Fascia Board
4-13 Studs
4-14 Ceiling Joist
4-15 Ceiling Board
4-16 Door Frame
4-17 Window Frame
CHAPTER - S FORMS, SCAFFOLDING AND STAGING
5-1 Forms
5-2 Greasing of Forms
5-3 Scaffolding and Staging
177
179
1795-4 Comparative Analysis Between the T&G and
Plywood as Forms 181
5-5 Forms Using Plywood 190
5-6 Forms of Circular Column 193
5-7 Estimating the Scaffolding and Staging 200
CHAPTER - 6 ROOFING MATERIALS
6-1 Galvanized Iron Sheet 206
6-2 Gutter, Flashing, Ridge, Hipped and
Valley Roll 222
6-3 Asbestos Roofing 228
6-4 Colorbond Klip-Lok 235
6-5 Banawe Horizontal Metal Tile 237
6-6 Marcelo Roofing System 238
6-7 Colorbond Custom Orb 239
6-8 Milano Long span Steel Bricks 240
6-9 Colorbond Trimdex Hi-Ten 241
6-10 Brick Tiles Roofing 242
CHAPTER -7 TILEWORK
7-1 Ceramic Tiles 243
7-2 Marble Tiles 252
7-3. Vinyl and Rubber Tiles 254
7-4 Terrazzo and Granolothic 256
7-5 Cement Tiles 260
74 Wood Tiles 263
7-7 Pebbles and Washout Finishes 265
CHAPTER - 8 HARDWARE
8-1 Bolts 2678-2 Screw
8-3 Nails
CHAPTER - 9 STAIRCASE
9-1 Introduction
9-2 Stairs Layout
9-3 Stringer
CHAPTER - 10 PAINTING
10-1 Paint
410-2 Ingredients of Paint
40-3 Essential and Specific Properties of a
Good Quality Paint
10-4 The Elements of a Good Painting Job
10-5 Specifications for Surface Preparation
10-6 Kinds of Paint, Uses and Area Coverage
10-7 Estimating Your Paint
10-8 Paint Failure and Remedy
10-9 Wall Papering
CHAPTER - 11 AUXILIARY TOPICS
14-1 Accordion Door Cover
11-2 Glass Jalousie
14-3 Water Tank
11-4 Wood Piles
11-5 Bituminous Surface Treatment
11-6 Filling Materials
11-7. Nipa Shingle Roofing
11-8 Anahaw Roofing
Construction Terminologies
274
279
291
295
301
339
341
342
346
348
350
352
366
359CHAPTER 3
METAL REINFORCEMENT
3-1 STEEL BARS
Steet is the most widely used reinforcing material for almost
all types of concrete construction. it is an excellent partner of
concrete in resisting both tension and compression stresses.
Comparatively, steel s ten times stronger than concrete in resisting
compression load and hundred times stronger in tensile stresses.
The design of concrete assumes that concrete and steel
reinforcement acts together in resisting load and likewise to be in
the state of simultaneous deformation, otherwise, the steel bars
might slip from the concrete in the absence of sufficient bond due
to excessive load
In order to provide a higher degree of sufficient bond between
the two materials, steel reinforcing bars with a surface deformation
in various designs are introduced.
Ny
iS
M4
2
Types of Deformed Bars
FIGURE 3-1
75|
|
|
SIMPLIFIED CONSTRUCTION ESTIMATE
TABLE 3-1 STANDARD WEIGHT OF PLAIN OR DEFORMED
ROUND STEEL BARS IN KILOGRAMS
Diam. | 5.0m. | 60m.| 75m] 9.0m.| 105m./ 120m) 135m.
8mm | 198 | 237 | 296 | 356 | 415 | 474] 5233
10mm | 308 | 370 | 462 | 554 | 647] 739] 832
12mm | 446 | 533 | 666 | 7.99 | 9232 | 1068 | 11.99
13mm | 621 | 625 | 783 | 938 | 1094 | 1250 | 1407
16mm | 790 | 9.47 | 11.84 | 14.21 | 1658 | 18.95 | 21.32
20 mm | 1233 | 14.80 | 1850 | 22.19 | 28.89 | 2959 | 33.29
25mm | 19.27 | 23.12 | 28.90 | 34.68 | 40.46 | 46.24} 52.02
28 mm | 24.17 | 29.00 | 36.25 | 43.50 | 50.75 | 58.00 | 65.25
30 mm | 27.75 | 33.29 | 41.62 | 49.94 | 58.26 | 6659 | 74.91
32 mm | 31.57 | 37.88 | 47.35 | 56.82 | 66.29 | 75.76 | 85.23
36.mm | 39.96 | 47.95 | 59.93 | 71.92 .| 83.91 | 95.89 | 107.68
TABLE 3-2 DEFORMATION REQUIREMENTS
Nominal | Max. Average Height | Tolerance Max. Value
Diameter | Spacing of jugs | Minimum | Maximum ‘Summation
_ __ of lugs gap
os 55
08 78
1.0 94
12 10.2
14 126
20 157
24 196
28 220
30 | 236
32 254
36 275METAL REINFORCEMENT
TABLE 3-2A MECHANICAL PROPERTIES.
Yield | Fensiie Elongation | Bending | Diameter
Strength | Strength] Specimen | in 200 mim} Angle’ | of Pin
Class Grade} MPa ‘MPa mm.” percent Degree | d=nominal
mm | mm min, dia. at
specimen
Hot Rolled} 230 230 390 D<25 18 180 3d
Non Wel- O>25 16 . 4d
dable def-| 275 | 275 480 D<28 10 180 4d
‘Steel Bar D>25 8 5d
415 | 415 620 O<25 8 180 5d
D>25 7 6d
Hot Rolled] 230 | 230 390 D<25 20 180 ad
Weldable D>25 18 4d
Def. or 275 275 480 o<25 16 180 Ad
Plain bar D<25 14 54
415 | 415 550 D<25 14 180 Sd
D>25 12 6d
3-2 IDENTIFICATION OF STEEL BARS
Steer reinforcing bars are provided with distinctive markings
Which identify the name of the manufacturer with its initial and the
bar size number including the type of steel bars such as:
N = For Billet
A= For Axle
Rail Sign = For Rail Steel
7|
SIMPLIFIED CONSTRUCTION ESTIMATE
Main Ribs — Main Ribs
Initial of
Manufacturer
eat Sie) Bar Size
~ Steel Type
Grade 40
Grade 50 TI two Line - Grade 75
‘One Line - Grade 60 ~
Stee! Bars Marking System
FIGURE 3-2
3-3 BAR SPLICE, HOOK AND BEND
In estimating the quantity of the steel reinforcing bars, one has
to consider the additional length for the hook, the bend and the
splice whose length varies depending upon the limitation as
provided for by the National Building Code.
‘Types of Reinforcement Minimum Splice length
1. Tension Bars = 25 x Bar Size + 150 mm.
2. Compression Bars _ = 20 x Bar Size + 150 mm.
ILLUSTRATION 3-1
Determine the length ot the splice joint fora 16 mm. steel bars
under the following conditions:
78METAL REINFORCEMENT
a) Tensile reinforcement of a beam
b) Compressive reinforcement of a column
SOLUTION 3-1
a) Classification of the reinforcement is under tension. Thus,
Multiply:
25 x 16mm-+ 150mm, = 550mm.
b) For reinforcement under compression
Multiply:
20 x 16mm + 150mm = 470mm
“T
4d
i h=od 24
2d
' WE
Hook Bend
Hook Length = L+h_ for hook
Mild Steel Minimum Hook and Bend Allowance.
tT 4d
n=tid{ (Aa 6s n= ssa] | fod!
i 4 3d
7 =" @
[an Pes | }-+-1 —_}
Hook Bend
Hook Length = L +n for Bend
High Yield Bars Minimum Hook and Bend Allowance
FIGURE 3-3
79SIMPLIFIED CONSTRUCTION ESTIMATE
L = 2A+3B 4224
(] ~
L = 2(A+B)+20¢
Total Length = A+B+C+D
i
NK Total Length = A+B-12¢-g
N A
B ~
| r
Length = A+2B+C+D-2r- 4
<|
FIGURE 3-4 |
80METAL REINFORCEMENT
niber
= A =] A
b--————— A+
Total Length = A Total Length = A+h
Allir
t a
A
To eel
Total Length = A+2h
‘@ be: J
A A
|
Total Length = A+h TotalLength = A+2h
7
C
Total Length=A+B-1/2r-d
FIGURE 3-5
81SIMPLIFIED CONSTRUCTION ESTIMATE
Comments:
1. To those who have not been exposed to detail drafting work
nor actual field construction of reinforced concrete will find
it difficult to make a detailed estimate of the various
reinforcement required.
The difficulties lies not on the ability of the estimator to
compute but his inability to familiarize with the different
types and parts of the reinforcement that comprises the
footings, columns, beams, slab etc.
N
The various parts of reinforcement that an estimator should
be familiar with are:
Concrete Hollow Block Reinforcement is the simplest
type of vertical and horizontal reinforcement in between
cells and layers of the blocks respectively.
Footing Reinforcements comprises the following:
1. Footing slab reinforcement for small and medium
size.
2. Beam reinforcement for large foundations
3. Dowels
Post and Column Reinforcement:
1. Main vertical reinforcement
2. Lateral ties
a. Outer ties
b. Inner ties
82METAL REINFORCEMENT
c. Straight ties
3. Spiral ties
Beam and Girder Reinforcement
1. Main reinforcement
a. Straight bars
b. Bend bars
2. Stirrups
a. Open stirrups
b. Closed stirrups
3. Cut Bars
a. Over and across. the support
b. Between supports.
c. Dowels
Floor Slab Reinforcement
1. Main Reinforcement
a. Straight main reinforcing bars
b. Main alternate reinforcing bend bars
2. Temperature Bars
3. Cut additional alternate bars over support (beam)
4. Dowels.
Not until after familiarizing with these different types of
reinforcement could one make a sound and reliable estimate.
Estimating steel bar reinforcements could be done with the
following procedures:
83SIMPLIFIED CONSTRUCTION ESTIMATE
1. The main reinforcement for post, columns, beams, girders
and the like, is determined by the “Direct Counting
Method" That is, by counting the number of main
reinforcement in one post, column or beam as the case
maybe then multiplied by the total number of the same
category in the plan. The additional length for hook, bend
and splices for lapping should not be overlooked as it is
always the case in ordering length.
2. For other structural member such as lateral ties, stirrups,
spirals, dowels, cut bars and the like should be treated
Separately, one at a time. The length of their cut must.
include the mandatory additional length for hook and bend.
TABLE 3-3 AREAS OF GROUPS OF REINFORCING BARS
Bar
Dia, Number of Bars ( mm)?
m4 203 4 «5 6 7 8 8
6) 28 87 85 113 141 170 198 26 254 283
8 | 80 101 151 201 251 302 352 402 452503
10) 79 157 236 314 393 471 550 628 707785
12) 113 226 339 452 565 679792 905 1017 1131
16 | 201 402 603 804 1005 1206 1407 1608 1809 2011
20) 314 628 942 1257 1571 i885 2199 2513 2827 3142
25 | 491 982 1473 1963 2454 2945 3436 3827-4418 4909
32 | 804 1608 2412 3216 4021 4825 5629 6433 7237 8042
40 /1256 2513 3769 5026 6283 7539 8796 1005 1131 1257
3. After knowing the length of the lateral ties, stirrups, and
other smilar parts, select the steel bars to be ordered from
the various commercial length of from 5.00 meters to 13.50
84METAL REINFORCEMENT
meters long avoiding extra cuts which might be classified
as junk unless they could be of service or used on other
structural members.
4. Tie wire for reinforcement joints and intersections is a big
item of large construction work considering its cost. Cutting
of each tie wire should be done to the minimum required
length based from the diameter of the bars to be tied with.
3-4 REINFORCEMENT FOR CONCRETE
HOLLOW BLOCKS
Steel bars as reinforcement is a requirement in all types of
concrete and masonry structures of which concrete hollow blocks
is one. The National Building Code has promulgated guidelines on
how and what kind of reinforcement is appropriate for this type of
work depending upon the purpose itis to serve,
The size and spacing requirements for concrete hollow block
reinforcement must be indicated on the plan or specifications. The
number of steel bars for concrete: hollow block work could be
determined in three ways:
1, By Direct Counting Method
2. By the Unit Block Method
3. By the Area Method
Under the Direct Counting Method the vertical and
horizontal reinforcements are directly counted in the plan. The
length is also determined from the the plan or elevation although,
the hook, bend and lapping splices are imaginarily added to its
85SIMPLIFIED CONSTRUCTION ESTIMATE
length because it is very very rare to see a plan with a large scale
detailed drawing showing this particular requirements of reinforcing
Steel bars. Thus, estimators must be familiar with the hook, bend
and splicing requirements to be able to work on effectively even if
the plan is not accompanied with such details.
The Area‘and Unit Block Method Is the simplest method of
Computing the steel bar reinforcement for CHB with the aid of Table
3-4. The values presented in this table includes the allowances
tequired for standard bend, hook and splices.
ILLUSTRATION 3-2
From Figure 3-6, determine the number of 10 m.(4") concrete
hollow blocks including the 10 mm vertical and horizontal
teinforcing bars required if it is spaced at 80 cm. on center and one
horizontal bars at every after three layers respectively.
CHB, ap CHE Vertical Rent @ 80 em. oc,
Horizontal Rein,
at every 3 layers
2.60m
Natural Ground
40 cm
= Footing
4,00 m
FIGURE 3-6
86METAL REINFORCEMENT
Ist SOLUTION (By the Square Meter or Area Method)
1. Solve for the area of the fence
A = length x height
.00 x 3.00
A = 12sq.. m.
2. For vertical reinforcement spaced at 80 cm. on center;
Refer to Table 3-4, By the square meter or area method,
Multiply:
12 x 1.60 = 19.2 meters
e
Convert this value to the commercial length of steel bars
fanging from 5.00 to 13.50 meters long. Select the most
economical length avoiding extra cut.
Select: 4 pcs. 10 mm. x 5.00 m. long
= 20 meters
4. Horizontal bars at every after 3 layers. From Table 3-4,
Multiply:
12 x 2.15 = 25.80 meters.
Select: 4 pes. at 5.00 m. and
1 pe. at 6.00 m. long
5. Order:
8pcs.10mm x 5.00 m. Steel bars
1 pcs. 10 mm. x 6.00 m. Steel bars
87SIMPLIFIED CONSTRUCTION ESTIMATE
TABLE 3-4 LENGTH OF STEEL BAR REINFORCEMENT FOR
CONCRETE HOLLOW BLOCK WORK
Vertical Reinforcement Horizontal Reinforcement
Spacing | Length of Bars in Meter | Spacing| Length of Bars in Meter
cm, | PerBlock Per Sq.M.| Layers | Per Block Per Sq. M.
40 0.235 2.93 2 0.264 3.30 ~
60 0.171 2.13 3 0.172 2.15 -
80 0.128 1.60 4 0.138 1720. +
2nd SOLUTION (By the Unit Block Method)
1. Solve for the area of the fence
A= 4x 3.00
A= 12sq.m.
2. Determine the number of CHB
12 x 12.5 = 150 pes.
3. Referring to Table 3-4
a} Vertical Reinforcement per block spaced at .80 m. o.c.
Multiply:
150 x 0.128 = 19.2 meters
Select: 4 pcs. 10 mm. x 5.00 m. long
88METAL REINFORCEMENT
b} Horizontal bars at every after 3 layers
Referring to Table 3-4,
Multiply:
150 x 0.172 = 25.8m.
¢} Convert to commercial length
Select:
4 pcs. 10mm x 5.00 m. long and
1pc. 10mm x 6.00 m. long
4. Order:
8 pcs. 10 mm x 5.00 m. and
1 pcs. 10mm x 6.00 m. Steel bars
3-5 TIE WIRE FOR STEEL REINFORCEMENT
Tie wire refers to gauge No. 16 galvanized iron wire popularly
called G.I. tie wire. Tie wire is used to secure the steel bars in its
designed position before accepting fresh concrete
Ordering tie wire is not by feet or meter length but in kilograms
or roll. One rollis equivalent to 40 to 45 kilograms or approximately
2,285 meters or 53 meters per kilogram.
The length of each tie wire depends upon the size of the bars
to be tied on. However, tie wire is cut into length ranging from 20
to 40 centimeters for small and medium size steel bars.
This is one item of construction materials which is always
included in the bill of materials but never computed. The quantity
89SIMPLIFIED CONSTRUCTION ESTIMATE
is determined through a more or less calculation. In short, it is a
quantity with uncertainty of its accuracy. The only thing that is
certain is either it is over estimated or under estimated which is as
bad as the other
The problem is how to determine the number of kilograms
required which when cut into pieces as ties will be sufficient enough
to provide adequate ties to all joints as required by the Code.
Tie wire for CHB Reinforcement,
The common size of steel reinforcement specified for concrete
hollow block work is either 10 mm, 12 mm, 13 mm or 16 mm
depending upon the plan and specifications. For these particular
Size of reinforcement, a 25 cm. or 30 cm. long tie wire folded at the
center will be satisfactory.
TABLE 3-5 KILOGRAMS OF NO. 16 TIE WIRE FOR CHB
REINFORCEMENT.
Vertical Horizontal Kilogram per 100 CHB
‘Spacing Layer Spacing [~~ 25cm ties | 30cm ties
~ {
40 2 0042 0051
40 3 0031 .0038
40 4 .0028 0033
60 2 0028 0034
60 3 0021 0025
60 4 0018 0022
80 2 0021 | 0025
80 3 0016 0019
80 4 0014 | 0017
!
90METAL REINFORCEMENT
ILLUSTRATION 3-3
Continuing the solution of illustration 3-2 and from the
following data obtained, determine the quantity of tie wire required
in kilograms.
Vertical Reinforcement spacing = 80 om.
Horizontal Reinforcement spacing at every 3 layers
Area of the wall = 12sq.m.
SOLUTION 3-3
1. Determine the number of CHB
12 x 12.5 = 150 pes.
2. Referring to Table 3-5, using a 25 cm. long tie wire,
Multiply:
150 x .0016 = .24 kg. No. 16 G.I. tie wire
More of this tie wire example will be presented in the
succeeding examples of steel reinforcement.
3-6 INDEPENDENT FOOTING REINFORCEME!
Independent footing is an Individual or Isolated footing. The
steel bar reinforcement for this type of structure is determined
through the following methods
1. Know the actual dimensions of the footing as to its length
and width.
a1SIMPLIFIED CONSTRUCTION ESTIMATE
2. Remember that the minimum underground protective
covering of concrete to the steel reinforcement is 7.5 cm.
3. If the plan does not call for a hook or bend of the footing
reinforcement, the length of the bar is equal to the length or
width of the footing minus the protective covering at both
ends.
Footing Slab
+44—_ 2
75cm 750m 7.5m 75cm
Length of Bar = L +2 (75cm)
FIGURE 3-7 FIGURE3-8
4. Ifthe plan calls for a hook or bend of the reinforcement, the
bar-cut should include the allowances for hook and bend as
presented in Figure 3-4 and 3-5.
5. Know the spacing distance of the steel bars both ways to
determine the exact number required. As much as
possible, select the appropriate steel bar length which is
divisible by the cut length to avoid unwanted extra cuts.
Various problems in computing for the steel! bar reinforcement
will be encountered because of varied measurements and
designs. Problems however, usually arise on reinforcing members
which requires cutting and bending. Others could be determined
by the Direct Counting Method specially those which does not
require hook, and bend.
92METAL REINFORCEMENT
ILLUSTRATION 3-4
From Figure 3-9, determine the number of 12 mm. steel bars
required if there are 6 footings with a general dimensions of 1.50
x 1.50 meters.
FIGURE 3-9
SCLUTION 3-4
1. The net length of one reinforcing cut bar is,
1.50- (.075 +.075) =1.35
2. Find the total number of cut bars in one footing.
By direct counting
13 x 2 = 26 pcs.
93SIMPLIFIED CONSTRUCTION ESTIMATE
Get the total number of bars for the 6 footings.
26 x 6 = 156 pes. at 1.35 m. long
4. Select the steel bars whose length is economically cut into
1.35 m, long. Say 6.00 meters.
600m. = 4.44 pes.
1.35 m
The fractional value of .44 is inevitable, but should not be
included in the computation because it is less than one cut bar
length. Use the whole value of 4.0 thus,
5. Divide the result of step 3 by 4.0
156 = 39 pes. of 12 mm. x 6.00 m.
40
The common error committed in estimating the number of steel!
bars is presented below.
Using the same data we have :
1. The net length of one cut reinforcing bar is 1.35 m. long,
2. Total number of bars in one footing is *
13 x 2 = 26 pes.
3. Total number of cut bars for 6 footings
26 x 6 = 156 pes.
94METAL REINFORCEMENT
4. The total length of these cut bars in meter is:
156 x 1.35 = 210.6 m.
5. Converting this length to commercial steel bar length
say 6.00 m.
210.6 m. = 35 pes. steel bars
6.00 m.
Analysis:
Comparing the results of the two estimating procedures, the
answers has-a difference of 4 pieces steel bars at 6.00 meters
fong. This is the result by including the fractional amount of .44 as
divisor of the reinforcing bar length.
The second procedure could be correct if the quotient in
dividing the length of one commercial steel bar by the length of
one cut bar yields a whole value, on the contrary, if the result has
a fractional amount, the second procedure will not give a correct
answer.
The following illustration is an example where the
second procedure applies.
ILLUSTRATION 3-5
From Figure 3-10, determine the number of 12 mm steel bars
including the tie wire in kilograms if there are 20 pcs. independent
square footing with a general dimensions of 1.15 x 1.15 meters.
95SIMPLIFIED CONSTRUCTION ESTIMATE
12 mm Steel Bars
115m,
L=1.20m.
[38m
FIGURE 3-10
SOLUTION 3-5
1, Determine the net length of one reinforcing cut-bar
1.00m. + 20m. = 1.20m.
2. Total cut-bars in one footing
6 x2 = 12pcs.
3. Total cut-bars for 20 footings
12 x 20 = 240 pes
4. Total length of all the bars
240 x 1.20 = 288 meters
96METAL REINFORCEMENT
5. Divide the above result by the length of one steel bar say
6.00 meters.
288 = 48 pes.
6.00
Order: 48 pes. 12mm x 6.00 m. long steel bars
Solving the same problem by the Ist procedure, we
have:
1. Net length of one reinforcing cut bar = 1.20m
2. Total bars in one footing
6 x 2 = 12 pes.
3. Total for 20 footings
12 x 20 = 240 pes.
4. Divide the commercial length of one steel bar by
the length of one cut bar;
This simply means that 5 pes. at 1.20 meter long reinforcing
bar could be taken from a 6.00 meters long steel bar, thus,
5. Divide the total cut bars for 20 footings by 5
97SIMPLIFIED CONSTRUCTION ESTIMATE
240 = 48 pieces
5
The question now is when to use the first procedure and when
to adopt the second procedure. In determining alone what
Procedure to adopts an additional burden, to avoid such confusion,
the following rules will help in making the right choice.
1. Determine the net length of one reinforcing cut bar
2. Divide 6.00 m. or any chosen commercial length of stec!
bar by the result of step 1.
3. If the result is a whole number (exact value) use the
second procedure.
4. If the result has a fractional value, adopt the first procedure.
Considering illustration 3-5, Tie Wire could be
determined through the following steps:
1. Find the number of steel bar intersections in one footing
6 x 6 = 36ties
2. Total Ties for 20 footings
20 x 36 = 720ties
3. Using 25 em. length per tie wire
Multiply:
98”
METAL REINFORCEMENT
720 x .25m. = 180 meters
4. One kilo of No. 16 G.l. wire is approximately 53 meters
long. Divide
180 = 3 4 kilos
53
3-7 POST AND COLUMN REINFORCEME
The reinforcement of posts and columns to be considered in
the estimates are:
1. The Main or Vertical Reinforcement
2. The Lateral Ties or
3. The Spiral Ties for Circular Column
The quantity ana length of the main reinforcement is
determined by the ” Direct Counting Method ". giving ‘special
attention to the additional length for:
2
. Lap joints of end splices.
b. Allowance for bending and or hook.
. Additional length for the beam depth and floor thickness if
the height indicated in the building plan is from floor to
ceiling.
Distance from floor to footing.
Provisions for splices of! succeeding floors
2
eo
99SIMPLIFIED CONSTRUCTION ESTIMATE
Add Length
'
Lap Joint
Bend
FIGURE 3-11
3-8 BEAMS AND GIRDERS REINFORCEMENT
The "Direct Counting Method" is the best method in
determining the main teinforcement for beams and girders.
Provided that, in determining the length of steel bars, the following
Physical conditions of the beam in relation with their ‘support must
be considered.
1. Verify from the plan if the Span of the column where the
beamis resting indicates the following conditions:
a) Center to Center of the column
b) Outer to center of the column
©) Outer to Outer of the column
100METAL REINFORCEMENT
Each physical condition of the beam must be given special
attention in determining the length of steel bars
2. Verify the splicing position of the reinforcement if it is
adjusted to the commercial length of steel bars. Remember
that "The Lesser the splice the lesser is the cost”
3. Identify the bars with bend and hook, for adjustment of their
order length.
Column
Center to Center ‘Center to Outer Side
~ ed
: Beam ‘Beam
Column
-— ad
Inside to Inside Outer to Outer side
‘Span of Beam
FIGURE 3-12
101SIMPLIFIED CONSTRUCTION ESTIMATE.
3-9 LATERAL TIES
Tied column has reinforcement consisting of vertical bars
held in a position by lateral reinforcement called Lateral Ties.
The ACI Code so provides that: "All non-prestressed bars
Sor tied column shall be enclosed by lateral ties of at least No. 3.
in size for longitudinal bars No. 10 or smaller and at least No. 4
in size for No. 11 to 18 and bundled longitudinal bars."
The Code provisions simply mean that;
a.) If the’ main longitudinal reinforcement of a tied column is
No. 10 bar or smaller in size, the Lateral Ties should not be
‘smalier than No. 3 steel bar in size.
b) Ifthe main reinforcement of tied column is No. 11 to No.
18 and bundled bars, Lateral Ties should not be less than
No. 4 steel bar.
Steel Bars
__Number Designation
C©ovoOnaewN
|
118 28
144
102METAL REINFORCEMENT
SUInIIEEE PERI nEIORIDOInan EERE
44 138 35
12 | 1412 38
13 | t 58 41
44 | tos | 44
15 1718 47
16 | 2.0 50
17 | 218 | 53
18 | 214 | 56
nnn RR
The ACI Code further provides that, spacing of the lateral
ties shall not exceed the following:
1.16 x the longitudinal bar diameter
2. 48 x lateral tie bar diameter or
3. The least dimension of the column
ILLUSTRATION 3-6
Determine the spacing of the lateral ties for a tied column as
shown in Figure 3-13.
SOLUTION 3-6
ter of the main longitudinal bars is 20 mm
403SIMPLIFIED CONSTRUCTION ESTIMATE
2. Diameter of the lateral ties is 10 mm.
3. Multiply:
16 x 20 = 320mm.
48 x 10 = 480 mm.
Shortest side of the column = 300 mm.
4. Adopt the least value of 300 mm or 30 cm. spacing
{—— 20mm
10 mm Lateral Ties +
Column Reinforcement!
—W
FIGURE 3-13
ILLUSTRATION 3-7
A building has a series of 26 square columns having a cross
sectional dimensions of 30 x 30 cm. 7.00 m. long with 8 pieces
20 mm vertical reinforcing bars for each column. Make an order
of 10 mm steel bars required for making the lateral ties
104METAL REINFORCEMENT
a 30cm.
Column + i
Reinforcement | || 7
IL 30 em ‘Col. Reint,
10mm f |
Lateral Ties
10 mm Lateral Ties
30cm.
L
rT
FIGURE 3-14
SOLUTION 3-7
1. Determine the spacing of the lateral ties.
16 x 20 mm. = 320 mm. or 32 cm,
48 x 10 mm. = 480 mm. or 48 cm.
The shortest side of the column is = 30cm.
2. Adopt the 30 cm. spacing
3. Determine the number of lateral ties in one column
7.00 m. ht. = 23.3 pes.
30
105SIMPLIFIED CONSTRUCTION ESTIMATE
4. The 23 pes. is the distance between the lateral ties, what
we need is the number of ties in one column, so, we add
one to be exact.
23 + 1 = 24pcs.
5. Solve for the total ties of the 26 columns.
26 x 24 = 624 pos.
6. Find the length of one lateral tie.
By inspection the tie is 120 om. long or 1.20 m.
7. Determine the number of 1.20 m. cut froma
6.00 m. commercial length steel bar
6.00 = Specs.
1.20
8. Divide the result of 5 by result of 7
624 = 124.8say 125 pcs.
5
9. Order: 125 pcs. of 10 mmx 6.00 m. steel bars.
ILLUSTRATION 3-8
From Figure 3-15 prepare an order of 10 mm. steel bars for
making the lateral ties
106METAL REINFORCEMENT
| 30m —.|
Col. Reint. i
30cm
Lateral Ties [tT
SO Inner Ties
a
L
FIGURE 3-15
SOLUTION 3-8
1. This problem is an improvement of illustration 3-7 Where
the outer ties have been found to be 125 pcs. 10 mm. x 6.00 m.
What is to be determined here is the inner ties.
2. By inspection the length of the inner tie is 83 cm.
3. Determine how many 83 cm. could be cut ina 6.00 m. steel
bar.
600 = 7.23 pcs.
83
107SIMPLIFIED CONSTRUCTION ESTIMATE .
4. Disregard the fractional value of .23 accept 7 pes. and
Divide:
624'pes. by 7 pos. (See 5 of illustration 3-7)
624 = 89 pcs. of 10mm. x 6.00 m.
7
5. Total: 125 + 89 = 214 pes. of 10 mmx 6.00 steel bars
ILLUSTRATION 3-9
From Figure 3-16 prepare an order of 10 mm steel bars for
making the lateral ties including the tie wire required.
er u
| Outer Ties
40m {— Straight Ties ~
| Inner Ties
7
fe 25cm 2; 25cm |
4 LL ob
FIGURE 3-16
108METAL REINFORCEMENT
Given Data:
Number of Columns = 16 pes.
Size 25 x 40cm
Clear Height 4.60 m.
Ties Spacing = 25 cm.
SOLUTION 3-9
1. By inspection, there are 3 types of ties:
a) Outer ties
b) Inner ties
©) Straight Ties
= 120 cm. long
85 cm. long
50 om. long
2. Determine how many 120 cm., 85 cm. and 50 cm. long
could be made out
Outer ties:
Inner ties:
Straight ties:
from one 6.00 m. steel bar.
600 = Specs.
720
600 = 7 pcs.
“BS
600 = 12 pcs.
50
3. Determine the number of ties in one column
4.60 m: ht. = 1
8.4 say 19 pes
-25 m. spacing
109SIMPLIFIED CONSTRUCTION ESTIMATE
4, Total ties for 16 columns
19 x 16 = 304 pcs.
5. Divide 304 by each type of tie (in step 2)
304 = 60.8 say 61 pcs.
5
304 = 43.4 say 44 pos.
7
304 = 25.3 say 26 pes
12 :
6. Order: 131 pes. of 10 mm x 6.00 m. steel bars.
The values found in step 5 was rounded to the next whole
number having the sum of 131 pes. steel bars.
7. Solving for the tie wire:
a) Number of Joints per lateral tie by direct counting = 12.
b) Number of ties in a column
12 x 19 = 228 pos.
©) Total tie wire for the 16 columns
228 x 16 = 3,648 pcs.
d) Multiply by the length of each tie wire,say 30 cm.
110METAL REINFORCEMENT
‘TABLE - 3-6 NUMBER OF LATERAL TIES IN ONE STEEL BAR AND.
QUANTITY PER METER LENGTH OF COLUMN
Spacing of] Number of | Length of NUMBER OF CUT IN ONE
Lateral | Lateral Ties| Ties with STEEL BAR LENGTH
Tiescm. | PerM.Ht.| Hook & Bend | 50m] 60m. 75m] 90m] 120m.
15 6.70 60 x | 10 | x | 15 | 20
| 70 7) x [x |x | 17
20 5.15 80 6} x |x | 11] 15
85 x | 7] x | x | 14
25 4.13 90 x | x | 8 | 10 | 13
95 5] x [x] x x
30 3.43 100 5] 6] x | 9 | 12
105 x} x | 7] x x
35 3.00 110 x} x |x |} 8 x
115 x 5 x x x
40 2.64 120 4 5 x x 10
| 126 4] x | 6] x x
45 236 | 130 x} x |x] x 9
| 136 x} xix |x | x
50 2.14 140 x} 4[x«]x x
145 x] 4]5] 6 x
55 1.96 150 x 4 5 6 8
160 3 x x x x
60 1.81 170 x x x | 5 7
180 x} x | 4] 5 x
190 x 3 x x 6
200 x 3 x x 6
X - Not advisable length for economical reasons.
111SIMPLIFIED CONSTRUCTION ESTIMATE
3,648 x 30m. = 1,094.4m
€). Divide by 53 m. length of tie wire per kilogram
1,094.4 = 20.6
53
say 21 kilograms of No. 16 G.I wire
Table 3-6 was prepared to simplify further the estimate for
column fateral ties and stirrups for beams and girders. It will be
noted that there are x- entry in the Table which simply mean that
such length of steel bars is not recommended for economical
reasons. The main objective of this Table is to guide the estimator
in selecting reinforcing bar whose commercial length when divided
by the length of each lateral tie will avoid extra cut of unwanted
size. To use the table, consider the following example
ILLUSTRATION 3-10
A building has 12 columns with a cross sectional dimensions
of 30 cm. x 40 cm. each with a clear height of 7.00 meters. Prepare
an order of 10 mm steel bars for the lateral ties spaced at 20 cm.
SOLUTION 3-10
1. By inspection there are two types of lateral ties
a) outer ties = 125 cm. long with hook
b) inside ties = 80 cm. long with hook
112METAL REINFORCEMENT
Col. Reinf,
10 mm
Lateral Ties 20cm
A 20 mm col. Reinf.
FIGURE 3-17
2. Find the total length of the 12 columns
12 x 7.00 m. = 84.00 meters
3. Referring to Table 3-6 under spacing at 20 cm.
Multiply:
84 x 5.15 = 432 pes.
4. Referring to Table 3-6, fer a 125 cm. outer ties
Divide:
113SIMPLIFIED CONSTRUCTION ESTIMATE
= 72pes. 10mm x 7.50 m. bars
432 = 108 pcs. 10mm x 5.00 m. bars
4
5. From Table 3-6 for the 80 cm. Inside ties
Divide:
432 = 72 pcs. 10mm. x 5.00 m. bars
6
6. Order:
72 pes. 10mm. x 7.50 m. steel bars
72 pcs. 10mm x 5.00 m. steel bars
Solving for the Tie Wire, we have;
1. Total number of lateral ties
2. Total number of vertical reinforcement
3. Multiply:
432 x 8 = 3,456
4. If the length of each tie is 40 cm.
Multiply:
3,456 x 40m. = 1,382.4 meters
114METAL REINFORCEMENT
5. Divide by 53 meters ( the length of tie wire in one kilo)
1,382.4 = 26 kilograms
53
3-10 STIRRUPS FOR BEAM AND GIRDER
Svtirrup is the structural reinforcing member that holds or binds
together the main reinforcement of a beam or girder to a designed
position,
The two types of stirrups commonly used are:
1. Open Stirrups
2. Closed stirrups
Open Stirrups Closed Stirrups
FIGURE 3-18
115SIMPLIFIED CONSTRUCTION ESTIMATE
The methods in estimating the number of stirrups required is
the same as that of the lateral ties as explained in Article 3-9 with
the aid of Table 3-6. However, the spacing of the stirrups could
not be determined by the linear meter method because the spacing
of stirrups become closer as it approaches the beam support. The
number of stirrups is best determined by direct counting per span
by categories according to the design as indicated in the detailed
drawings.
ILLUSTRATION 3-11
A concrete beam with a cross-sectional dimension of 25 x 40
cm. requires 10 mm. open stirrups spaced as shown in Figure
3-19. Prepare an order of 10 mm. steel bars forstirrups of 8 beams
with the same category.
Beam
aI t
i | Bend Bars Main Reinforcement
i |
! I Column
H
4
10 mm stirrups
FIGURE 3-19
116METAL REINFORCEMENT
SOLUTION 3-11
1. By direct counting, there are 24 stirrups at 98 cm, say
1.00 m. long
2. Total number of stirrups
24 x 8 beams = 192 pes.
3. Referring to Table 3-6 for a 1.00 m. long stirrups using a
5.00 m. fong steel bars.
Divide:
492 = 38.4 pes. 10mm. x 5.00 m.
5
or using a 6.00 m. long steel bars.
Divide:
192 = 32.0 pcs. 10 mm x 6.00 m.
6
4. Order: 32 pcs. of 10mm x 6.00 m. steel bars
Comment:
.
15.00 m. steel bar is chosen, the order will be 39 pes. not 38.4
because we cannot order .4 steel bar. After cutting the stirrups
there will be an excess of .6 of 5.00 meter steel bar which is
equivalent to 3.00 meters long. Thus, in order to be exact, a 6.00
meter steel bar should be chosen.
117SIMPLIFIED CONSTRUCTION ESTIMATE.
3-11 SPIRAL AND COLUMN TIES
The spiral reinforcement consist of evenly spaced continuous
spirals held firmly in place by at least three vertical bar spacers
under the following considerations:
1. That, the center to center spacing of this spiral. should not
exceed 6th part of the diameter core.
2. That, the clear spacing between the spirals should not
exceed 7.5 om. nor less than 5.0 cm. or,
3. The clear spacing between the spirals be less than one and
one half (1 12) times the biggest size of the coarse
aggregate (gravel).
ILLUSTRATION 3-12
A spiral column with a cross sectional diameter of 50 cm.
requires 10 mm spiral reinforcement as shown in Figure 3-20. If
there are 14 columns at 7.00 meters high. find the number of 10
mm steel bars needed for a 5.00 cm. pitch spirals.
SOLUTION 3-12
A. Spiral Reinforcement
1. Find the total length of the 14 columns
7 x 14 = 98 meters
118METAL REINFORCEMENT
2. From Table 3-7 for a 50 cm. col
pitch.
Multiply:
lumn diameter 5.00 cm.
98 x 3.223 = 315.8 say 316 pcs.
3. Order: 316 pcs. 10 mm x 9.00 m. steel bars
| Som Pitch h
Spiral Column
FIGURE 3-20
1. Find the number of vertical bars per column =
12
2. Refer to Table 3-7. Alon,
5 cm. pitch, the number
Multiply:
1g 50 cm column diameter,
of turn per meter height is 21
12 x 21 = 252 ties per meter height,
119SIMPLIFIED CONSTRUCTION ESTIMATE
3. Total tie wire for 14 column bar intersections at 7.00 m. ht.
252 x 7.00m. x 14 = 24,696 pcs
4. Total length of the wire at .30 m. long Per tie wire
24,696 x 30 = 7,409 m.
5. Convert to kilogram at 53 m. long per kg.
Divide:
7409 = 139.8say 140 kgs.
53
6. Order: 140 kilograms of No. 16 G.I. wire
TABLE 3-7 NUMBER OF SPIRAL REINFORCING BARS PER METER
HEIGHT*
Col. Dia.| Pitch No. or Turn Number of Steel Bars froma
em, cm. | per Meter Ht. 6.00m. | 9.00m. | 12.00m.
5.00 21.0 2.604 1.706 1.269
30.0 | 6.25 17.0 2.108 1.381 1.027
7.50 14.3 1.778 1.165 0.866
5.00 21.0 2.894 1.896 1.410
325 | 6.25 17.0 2.342 1.535 1.141
7.50 14.3 1.975 1.294 0.962
5.00 21.0 | 3.183 2.085 | 1.550
36.0 | 6.25 17.0 2577 1.688 1.255
7.50 14.3 2.172 1.423 1.058
120METAL REINFORCEMENT
| 5.00 210 3472 | 2275 | 1.692
37.5 | 6.25 17.0 2811 1.842 | 1.393
7.50 143 | 2.370 1524 | 4.154
- 7 | |
5.00 21.0 | 3762 | 2465 | 1.833
40.0 | 6.25 17.0 3.045 | 1995 | 1.484
7.50 143 2.567 1682 | 1.251
5.00 21.0 4.051 2654 | 1.974
425 | 6.25 17.0 3.281 2149 | 1,598
7.50 143 2.765 vez | 1.347
- _ - —_ —
5.00 | 21.0 4.340 2844 | 2.115
45.0 | 625 | 170 3.513 2302 | 1712
750 | 143 2.962 | 1940 | 1.443
5.00 | 21.0 4.630 3033 | 2.256
475 | 6.25 17.0 3.748 2455 | 1.826
7.50 143 3.159 | 2070 | 1.539
| 5.00 21.0 4919 3.223 | 2.397
50.0 | 6.25 17.0 3.982
7.50 143 3.367
5.00 21.0 5.498 3602 | 2678
55.0 | 6.25 17.0 4.451 2916 | 2168
7.50 14.3 3752 | 2458 | 1.828
5.00 21.0 6.077 | 3.981 2.960
60.0 | 6.25 17.0 4919
7.50 143 | 4sge |
5.00 21.6 7.234 4.740 | 3.524
70.0 | 6.25 17.0 5.856 3.837 | 2853
7.60 143 4936 | 3.234 | 2405SIMPLIFIED CONSTRUCTION ESTIMATE
5.00 21.0 "8391 | 6.498
80.0 | 6.25 170 6793 | 44st |
143 5.726 | 3752 | 2790
50 | ato 9542 | 6256 | 4652
900 | 625 | 170 | 7.730 5.064 | 3.766
17.50 | 143 | 6366 | 4171 | ator
5.00 | 21.0 10.706 7014 | 5.216
100 | 6.25 17.0 | 8007 8678 | 4.222
7.50 143 | 7197 | ae7e | 3.477
oe a ee es ae
* Values given includes the end-| ap or splice allowance.
3-12 ONE WAY REINFORCED CONCRETE
SLAB
The one way reinforcement of cencrete slab is adopted
when the concrete beams or girders that supports the floor slab
is almost or rectangular in shape. Solution can either be by direct
counting or by the area method.
ILLUSTRATION 3-13
From Figure 3-21, determine the number of steel bars for a
one way reinforcement slab including the tie wires required
SOLUTION 3-13
1. Given Data:
Spacing of Main Reinforcement = 150mm. (15.cm,)
122METAL REINFORCEMENT
Temperature Bars Spacing = 250mm. (25 cm.)
Size of the Reinforcement = 12 mm. diameter
Type of reinforcement = One way
i
tt
‘Straight far i
—
}
One Way Slab Reinforcement
FIGURE 3-21
2. Determine the number of Main Reinforcements.
4.70 + 1 = 32.33 pes. at 5.00 m long steel bars
15
Note: In dividing the span by the bar spacing, what is found
is the number of spacing. Add one (1) to get the number of steel
bars.
3. Determine the length of the alternate cut bars to be installed
in between the main reinforcement.
123SIMPLIFIED CONSTRUCTION ESTIMATE
1.075 + 175 (hook) = 1.25 meters
4. Using a 5.00 m. steel bars,divide:
5.00 = 4 pes. (number of cut bars taken from one
1.25 steel bar)
5. Divide: Step 2 by step 4
32.33 = 8 pcs, at 5.00 m. steel bar
4
6. Total Main Reinforcing Bars
32.33 + 8 = 40.33 pes.
7. Solve for the Temperature bars at 2.15 m. span
215 +1=96 say10pcs, ~
5
8. Temperature bars at 1.075 span
1.075 +1= 5.3 pos. ~
25
9. Multiply by 2 layers at 2 sides
5.3.x 4 = 21.2 pcs.
10. Add result of 6 hnd 9
96 + 21.2 = 308po.%
12411. Summary total of 6 and 10
40.33 + 30.8
METAL REINFORCEMENT
= 71.1 pes. 12mm. x 5.00 m. steel bars.
Order: 72 pes. 12 mm x 5.00 m. steel bars.
TABLE 3-8 QUANTITY OF STEEL BARS AND TIE WIRES IN A
ONE-WAY REINFORCED CONCRETE SLAB
Bar Number of Steel Bars per Square Meter | Length of Tie
Spacing Wire / sq. m.
om. | 5.0m. 6.0m 750m. 9.0m. 120m. 25m. 30cm.
10.0 | 4.493 3667 2856 2.320 1.834 | 242 201
125 | 3911 3.186 2483 2015 1593 | 197 236
15.0 | 3524 2866 2234 1,812 1.433 | 163 195 ]
175 | 3247 2637 2056 1.667 1.319 | 141 169
20.0 | 3.030, 2465 1192 1558 1.233 | 126 .152
225 | 2878 2332 1.819 1.473 1.166 | 111 133
25.0 | 2749 2225 1.737 1.405 1.113 | 101.121
27.5 | 2643 2138 1.669 1.350 1.069 | .091 109
30.0 | 2554 2065 1.612 1.304 1.033 | 086 103
2nd SOLUTION ( By the Area Method )
1. Solve for the area of the floor
4.70 x 4.30 = 20.21 sq. m.
125SIMPLIFIED CONSTRUCTION ESTIMATE
2. Referring to Table 3-8 using a 5.00 m. bars at 18 cm. -
spacing.
Multiply:
20.21 x 3.24 = 71.2 pes
3. Order: 72 pes. 12 mm deformed steel bars.
Solving for the tie wires at 25 cm. o.c.
1, Referring to Table 3-8
Multiply:
20.21 x 163 = 3.29 kgs.
2. Order: 4 kgs. No. 16 G.I. wire
3-13. TWO WAY REINFORCED CONCRETE
SLAB
A two way reinforced concrete slab is adopted when the beam
or girder that supports the concrete floor slab is almost or square
in shape or position.
ILLUSTRATION 3-14
From Figure 3-22, determine the number of 13 mm steel bars
and tie wire required.
126METAL REINFORCEMENT
Bend Bars
720m
‘Straight Bars
—_[Bend Bars |
Coo ‘Temp. Bars
+—————7:20 n. -
' Two Way Slab Reinforcement
FIGURE 3-22
SOLUTION 3-14
1. Solve for the main reinforcement
3.60 + 1 = 37 pes.
“10
2. There are.two way - run of reinforcement
37 x 2 = 74 pes. steel bars
127SIMPLIFIED CONSTRUCTION ESTIMATE
3. For cut bars at 1.87 m. tong, 4 pcs. can be obtained in a
7.50 m. commercial steel bar
Divide:
74 = 185 pes. steel bars
4
4. Temperature bars at 1.80 m. span ‘
1.80 + 1 = B.2 pcs.
25
5. Multiply by 4 sides at 2 layers
8.2 x 8 = 65.66 pcs.
6. Summary total of step 2,3 and 5
74 + 18.5 + 65.6 = 158 Pcs.
2nd SOLUTION ( By the area Method )
1. Area of the floor slab:
7.20 x 7.20 = 51.84 sq.m.
2. Referring to Table 3-9, for a 7.50 m. steel bars at 10cm
spacing; Multiply:
51.84 x 3.050 = 158 Pcs.
126METAL REINFORCEMENT
3. Order:
158 pcs. 13mm x 7.50 m. steel bars
Solve for No. 16 G.. tie wire cut at 30 cm.
1. Referring to Table 3-9;
Multiply:
51.84 x .437 = 22.65 say 23 kilos.
TABLE 3-9 QUANTITY OF STEEL BARS AND TIE WIRES
ON A TWO WAY REINFORCED CONCRETE SLAB
Bar Number of Steel Bars per Squaré Meter | Length of Tie
Spacing = — Wire / sq.m
om, 50m 60m 75m 90m 120m) 25em-30em
10.0 4.953 3995 3.050 3.047 2000 | 364 437
12.5 4.409 3549 2703 2.734 1.775 | 279 .335
15.0 4.047 3.252 2471 2524 1.626 238 = .286
17.5 3.788 «693.039 2306 2.377 1.520 .208 = .250
20.0 3.594 2880 2182 2266 1440 | 185 .222
22.5 3.443 2.756 2.085 2179 1378 | 168 .202
25.0 3.322 2656 2.008 2109 1328 | 156 .187
275 3.223 2675 1945 2053 1.268-| 146 175
30.0 3.141 2507 1.892 2005 1.254 | 138 .165
3-14 CONCRETE PIPE REINFORCEMENT
From Figure 3-21, determine the quantity of steel bar
reinforcement using 10 mm diameter and number 16 Tie Wire.
129SIMPLIFIED CONSTRUCTION ESTIMATE
Concrete Pipe
Reinf. Ring
FIGURE 3-23
SOLUTION
1. Solve for the circumference of the circle’ at midpoint of the
concrete thickness "t".
c=
C = 3.1416 x (90 + .10)
3.1416 x 1.00m.
= 3.1416 m.
2. Total length of one ring plus 15 om. splice
3.1416 + 15 = 329m.
3. Find the total number of ring at .20 om. o.c. spacing.
1.00 m. ht.
20 cm.
130METAL REINFORCEMENT
"
5 + 1 to get the total number of ring.
6 pcs.
4. Temp, bars at 25 m.0.¢
3.1416 = 12.56 say 13 pcs. at 100 long
25
Tie Wire
1. The total number of ring multiplied by the number of
temperature bars.
6 x 13 = 78 pes. at.30 m. long per tie wire
2. Total length: 78 x .30 = 23.40m
3. Divide by 53.00 meters to find the weight in kg.
23.40m. = .44 say 50 kg. No. 16 Tie wire
53.00 m.
134CHAPTER 8
HARDWARE
8-1 BOLTS
Bott is a pin or rod with a head at one end threaded at the
other end to receive a nut.
‘The different kinds of bolts used in building construction
are:
1. Machine Bolt - Has a head at one end and a short thread
at the other end.
2. Countersunk Bolt - Has a beveled head fitting into a
countersunk hole.
3. Key Head Bolt - Has a head shaped end fitted to a groove
that will not turn when the nut is screwed into the other end.
4. Stud Bolt - A headless bolt threaded at both ends.
Size and Length of Bolts
267SIMPLIFIED CONSTRUCTION ESTIMATE
The length of bot is the sum of the thickness of both pieces
being connected plus 12 mm.. With respect to the size or diameter
of bolt, depends upon the thickness of the object to be bolted.
{ a) Lumber up to 5 cm. thick, use... 6 mm (1/4") diameter.
b) 7.5 cm. (3") thick lumber use . . 10 mm (3/8") diameter.
©) 10 cm. (4") thick lumber use. . 12 mm (1/2") diameter.
4) Drillhole is 1.5 mm (1/16") larger than bott diameter unless
snug fit is necessary.
e) Use washers under head and nut of machine bolt. _
f) For carriage bolt use washer under nut only.
9) Use toggle bolt for attaching fixture to plaster wall,
hie h) Use expansion bolt for fastening to masonry.
{ i) For outdoor exposure, use brass or cadmium plated finish.
TABLE 8-1 U.S. STANDARD THREAD OF BOLTS
Length | Diameter of Bolts _
in| 12 | se | 34 | 78 1 | awe [144
mm 12 16 20 | 22 25 28 3
10.0 | 144 | 245 | 3.64 | 5.24 | 7.23 | 9.78 | 12.60
125 | 169 | 2.85 | 4.21 6.01 8.24 | 14.06 | 14.18
15.0 | 194 | 3.24 4.78 6.78 9.26 | 12.33 | 15.76
175 | 219 | 3.64 | 5.35 7.55 | 10.27 | 13.61 | 17.35
20.0 | 245 | 4.03 | 5.92 832 | 11.29 | 14.89 | 18.93
225 | 270 | 4.43 6.49 9.09 | 12.30 | 16.17 | 20.51
25.0 | 2.95 | 4.82 7.06 | 986 | 13.31 | 17.44 | 22.09
27.5 | 3.20 | 5.22 7.63 10.63 | 14.33 | 18.72 | 23.67
30.0 | 346 561 8.20 11.40 | 15.34 | 20.00 | 25.26
325 | 3.71 | 6.01 | 877 | 12.17 | 16.36 | 21.27 | 26.84
if 35.0 | 396 | 6.40 | 9.34 | 1294 | 17.37 | 22.55HARDWARE
Machine Bolts
FIGURE 8-1
ae arsenal
Bevel Head Countersunk Head
Ce) oy
Turned Oval Head Bastard Head
Carriage Bolts
FIGURE 8-2
ty i Head
Stud Bolt
FIGURE 8-3
269SIMPLIFIED CONSTRUCTION ESTIMATE
Railroad Track Bott Welded Eye Bott
fa
Plain and Shouldered Step Bolt
Forged EyeBolt
Expansion Bolt
Various Types of Bolt
FIGURE 8-4
270HARDWARE
Estimating Procedure in Determining Length of the
Bolt
Post
WL. Post Strap
—— Bolts
Footing
FIGURE 8-5
WOODEN POST ANCHORED BY POST STRAP
The Length of the Boit is equal to the width of the post plus
the two thickness of the post strap plus 20 mm allowance for the
thread and nut.
L=w+13mm + 20mm.
POST AND SINGLE BEAM
The Length of Bolt is equal to the width of the post plus the
thickness of the beam.
Lowest
|
|
FIGURE 8-6 |
'
|
271SIMPLIFIED CONSTRUCTION ESTIMATE,
TABLE 8-2 WEIGHT OF BOLTS WITH SQUARE HEADS AND
HEXAGONAL NUTS PER 10 BOLTS.
T
Diameter 1/4 | 8/16) 3/8 | 7/16} 1/2) 9/16] 5/8) 3/4 718] 1
of Bolts 6 | 7 | 9 | 10 | 12 | 14 | 16| 19 | 22 | 25
No. of Thread] 20] 18 [46 | 44 [43 ) 42 | 41] 10 ,
perinch _ _t
Diameterof [5 | 6 [8 | 9 | 17] 12 | 13] 18
Top Dri 43} 4 | 8 | 23 | 27 | 45 }47 | 32
4 | 4 |i6 | 64 | 64 | 64 | 32 | 64
2» Bolt
fp Beam
20mm dap
FIGURE 8-7
POST WITH TWO BEAMS OF THE SAME THICKNESS
Length of the Bolt is equal to the width of the post plus 2
thickness of the beam minus 20 mm dap.( There’ are two dap
opposite the column sides but only one is subtracted because the
other 20 mm dap is reserved for the thread that will receive the
nut.)
L=w+ 2t- 20mm
272HARDWARE
Beam
Bott
Bolt Washers
FIGURE 8-8
POST AND TWO BEAMS OF DIFFERENT THICKNESS
Length of bolt is equal to the width of the post plus ty + tz
minus 20 mm,
L—. wood Block
| machine Boits
FIGURE 8-9
BOLTS ON TRUSSES
Length of bolt is equal tothe thickness of the membersin layer
plus 20 mm
3 x 50mm + 20mm = 170mm. or 17 cm
273
|
|i SIMPLIFIED CONSTRUCTION ESTIMATE
Exampie: 3 x 50mm = 150mm + 20 mm
= 170 mm.
TABLE 8-3 POST ROUGH HARDWARE
Size of Post] W.! Post] No.] Bok WI. Splice | No. | Bolt
om Strap (mm) mm | Strap (mm) mm
10 x 10 6x45x600 | 2 | 12'| 6x37x600 4] 12
13 x 13
18 x 15
18 x 18
20 x 20 6x50x600 | 2 | 16 6x 50x 600 4 16
23 x 23
25 x 25
28 x 28 6x62x600 | 2 | 20 6x 62x 900 4 20
8-2 SCREW
In carpentry work, screw is sometimes used instead of nails
due to the following advantages:
1. Greater holding power
2. Neat in appearance
3. Less chance of injuring the materials
4. Ease of removal in case of repair
How to Chodse Screw
le 1. Select one thatis tong enough wherein one halfto two thirds
i 274HARDWARE
of its length will enter the base in which threads are
embedded.
2, The length of the screw should be 1/8" or 3mm less than
the combined thickness of the boards being joined.
3. Use fine thread screw for hard wood and coarse for soft
wood.
How to Use the Screw
Always drill lead hole for the screw
2. Hole in top board should be slightly larger than the shank,
in second board slightly smaller than the threaded portion.
In soft wood, bore to depth half the length of the thread.
4. In hard wood, bore nearly as deep as the length of the
screw.
5. For lag screw, drill hole two-thirds its length then drive in
with hammer, and finally tighten with wrench.
»
How to buy screw
1. Screws are classified by gauge (thickness) and length.Each
gauge has a variety of different lengths which maybe
obtained up to 12 cm. (5 inches)
2. When ordering screw, specify head shape (e.g., round
head), finish (brass), gauge (number 5) and length (2" to 5
cm).
2
Square-headed fag screws come in diameters of 6 mm. to
25 mm (1/4 to 1inch) with its length from 4 cm. to 30 cm
(1 1/2" to 12 inches.)
275SIMPLIFIED CONSTRUCTION ESTIMATE
Wood Screw - Is a screw nail with handed coarse thread to
give a grip.
Materials Used
{fron 3.Brass_ ‘5. Bronze
2.Steel 4. Copper 6. Aluminum
Shape of the Head
1. Flat 8. Headless
2. Round 9. Slotted (wood screw)
3. Fillister 10. Square (lag screw)
4. Oval 41. Hexagonal
5. Winged 12. Clove
6. Bung 13. Grooved
7. Punched
Shape of the Point
1.Standard
2. Full length
3. Coarse
Duty
1, Wood (light duty)
2. Lag (heavy duty)
Finish
1. Bright 6. Bronzed
2. Blued 7. Coppered
3. Nickel Plated 8. Japanned
4. Silver Plated 9. Lacquered
5. Brass 10, Galvanized
276HARDWARE
TABLE 8-4 STANDARD WOOD SCREW AND NUMBER PER
KILOGRAMS
RR
1 —— i
inches [4/2 [1 |192] 2 J|212| 3 Jar 4 lara s| 5
mm {12 | 25 | 37 [50 [62 | 75 | a7 =r t
Number /6.211] 3,443} 2,329 | 1,779] 1,414 |1,186| 1,126] 910] 739 [ess [aie
oe |
mx
Ordinary Lag Screw
thy
Coach Lag Screw
i
|
F—~ Effective Length of Screw
~~
Standard Wood Screw Point
FIGURE 8-10
277SUV PLIFIED CONSTRUCTION
ESTIMATE
Flat Head Round Head
Oval Head Counter Sunk Fillister Head
i ti, Felloe seas Closed Head
xe]
Hexagonal Round Bung Head
EE J
Grooved Headless
i
| Pinched Head Square Bung Head
Winged Winged Winged Head
Drive
\ Various Types of Wood Screw
h FIGURE 8-11
278HARDWARE
The Three Shapes of Screw Point are:
1. Gimlet point —- used on wood and coach screws.
2. Diamond point - is used when more driving is done before
turning as in drive and lag screw.
3. Conical point - same as diamond point.
Gimlet_ Diamond Cone
Types of Wood Screw as to the Point
FIGURE 8-11
8-3 NAILS
The first handmade nails were used in the United States which
lasted up'to the end of the Colonial Period. In France, light aaits
for carpenters were made by hand and hammer aut of steel wire
as early as the days of Napoleon 1. In the United States, the wire
nail was first introduced by William Herser of Now York in 1851
Twenty five years later in 1876, Father Goebel introduced the
manufacture of wire nails and at the last part of the 18th century,
twenty three patents for nail making machine were approved in the
United States which was later introduced in England,
Kinds of Nail as to:
279k
SIMPLIFIED CONSTRUCTION ESTIMATE
1. Cross-Sectional Shape
a) Cut (rectangular)
b) Wire (circular)
2. Size
a) Tacks c) Brads e) Spike
b) Sprigs —d) Nails
3. Materials
a) Steel b) Brass c) Copper
4. h
a) Plain c) Galvanized
b) Coated d) Blued
5. Service
a)Common _) Finishing
b) Flooring d) Roofing e) Boat, etc.
Types of Nail Points
; U q V
Round Blunt Diamond Long Diamond Needle
Chisel Point Front Side ‘Cut Nail
Sheared Bevel
FIGURE 8-12
2802d to 60d
2d to 40d
2d to 400
2d to 204.
3/16" to 3"
2d to 204
6" to 12"
HARDWARE
2d
3d
4d
Sd
6d
Td
8d
10d
12d
16d
Length of Nails ( Actual Size )
FIGURE 8-13
For General Construction
For Light Construction Household Use.
For Interior Trim
For Cabinetwork Furnitures
For Light Work Mouldings
Flooring Construction
For Heavy Construction
281
Common Nail
Box
Casing
Finishing Nail
Wire Brad
Cut
SpikeSIMPLIFIED CONSTRUCTION ESTIMATE.
kx 2d to 60d.
_——— 2d to 404.
to 04
> _ 2dto204.
——— ate" to"
TSE Ad to 204
Common Nail
Box
Casing
Finishing Nail
Wire Brad’
Cut
ny ——
rah eo 12 spike
Types of Nails and: Their Uses
FIGURE 8-14
Flat Large Flat. ‘Large Flat
Common "98 Reinforced
Round Oval Round
Countersunk Countersunk
Non leak Gone Cuned Cut Nail
0
Wire Spike Oval
—
Offset Hook
Brad Diamond
Barge Spike
Types of Nail Heads
FIGURE 8-15
282HARDWARE
A) Tacks
Are small, sharp pointed nails with tapering sides and a thin flat
head. Tacks are nails chiefly usedin fastening carpets and flashing
of any thin materials.
FIGURE 3-16
TABLE 8-5 NUMBER OF WIRE TACKS PER KILOGRAM
st ii son aot
Inches Length (mm) | Number per Kilogram
18 3 35,200
36 5 23,465 |
114 6 17,600
56 8 14,080 ii
3/8 10 11,732 dl
76 12 8,800
one 14 5,865 |
5/8 16 4,400 !
1116 7 10,120 i
34 19 2,930 |
13/16 20.5 i 2.514
718 22 1,200 |
1516 24 1,953 |
1 25 1,760 |
116 27 | 1,599
118 28 1,465
283SIMPLIFIED CONSTRUCTION ESTIMATE
B) Sprigs
Are small headless nails sometimes called barbed dowel pins.
The regular size of sprigs ranges from 12 mm. to 5.0 cm. gauge
No. 8 wire or 4 mm. diameter.
C) Brads
Are small slender nails with small deep heads. The common
variety is made in sizes from 2.5 cm. (2d) to 15 cm. (6d) in length
while the flooring brads- from 5 cm. to 10 cm. length.
TABLE 8-6 FLOOR BRADS TECHNICAL DATA
Size | Length | Gauge Head | Approx. | Gauge | No. of Nails
mm Gauge | No/kg.| No. per kg,
6d 50 1 6 322 12 14,500
7d | 3201 44 6 277 | 12°} 12,500
ed | 37 | 10 | 5 200 | 14 9,000
9d 44 10 5 173 11 7,800
10d 75 9 4 131 10 5,900
12d 81 8 3 95 9 4,300
16d | 87 7 2 76 8 3,450
20d 100 6 1 87 7 2,600
D) Nails
Is a popular name for all kinds of nail except those extreme
sizes such as Tacks and Spikes. The most generally used are
called Common Nails of sizes from 2.5 cm. to 15 cm,
284HARDWARE
TABLE 8-7 COMMON WIRE NAILS TECHNICAL DATA
Size | Gauge
| __ Approximate Number
No. Per Kilogram | Per Keg
—— + ————
2d) 15 1831 | @2,400
Bd 14 1,177 | 53,000
4d 125° | 666 | 30,000
Sd | 125 580 26,100
66) 115 | 382 17,200
74 15 | 344 | 15,500
ad | 10.25 208 =| 9.400
9d} 10.25 | 188 | «8,500
wd | 9 | 138 6,250
tad) 9 | 124 5,600
16d | 8 | 93 | 4,200
20d) 6 58 2,625
4od | 4 | 45 | 2,040
50d | 3 | 34 | 1,540
6od | 2 6 150 20 | 910
Flat Head Diamone Point
Oval Head Chisel Point
FIGURE 8-17
E) Spikes
An ordinary spike is a stout piece of metal from 7.5 om. to 30
cm. in length, much thicker in proportion than a common nail.
285SIMPLIFIED CONSTRUCTION ESTIMATE
Spike is much used in attaching railroad tails, construction of
docks, piers and other work that uses large timber.
There are Two Kinds of Spikes, namely:
a) Flat Head, diamond point
b) Oval Head, chisel point
F) Boat Spikes
Are small kind of nail driven mostly in hard timber with a clear
cut sharp chisel point.
TABLE 8-8 COMMON BRADS TECHNICAL DATA.
OO
- Size Length Approximate Number
{ | Inches mm Per Kilogram Per Keg
2d + | 2 1,904 85,700
3d 14 | 34 1,206 54,300
{ 4d 1412 37 662 29,800
| Sd 13/4 44 566 25,500
6d 2 50 307 17,900
7d 214 | 56 340 15,300
i 8d 22 | 6 224 10,100
i 9d 23/4 69 197 8,900
40d 3 7 146 6,600
i 12d 334 | at 137 6,200
- 16d 312 | 88 108 4,900
| 20d 4 | 100 68 3,100
i i sod | aie } 112 53 2,400
| it 40d 5 | 125 40 1,800
i 50d S12 | 137 28 1,300
{ ( 286HARDWARE
Size Approx. No.
“Inches [| mm per Kilogram
10d 3 75 | 90
124 304 81 83
16d 302 88 66
20d 4 100 | 50
30d 412 112 37
40d 5 125 28
50d 512 137} 22
60d 6 150 19
175 mm 7 175 15
200 mm 8 200 9
225 mm 9 225 8
250 mm 10 250 7
300 mm 12 300 6
Other Important Facts and Uses of Nails
1. Use a nail that is three times as long as the thickness of the board
2. Nails with sharp point holds better than blunt ones but tend to split
wood,
3. Flatten the point with hammer before driving into an easily split
wood
Use thinner nails for hardwood than for soft wood.
For weather resistance, use copper, aluminum or galvanized nails
Zinc or cement coatings increase resistance to withdrawal
Barbed nails hold best in green wood
Sizes of nails are indicated by "penny" abbreviated as “d"
Example: 20 penny nail is known as 20 d nail
@rygaen
287SIMPLIFIED CONSTRUCTION ESTIMATE
TABLES8-10 USES AND APPROXIMATE QUANTITY OF NAILS
Materials Unit Per Approx. kg. | Size Kind of
j Required Nails
|
Floof joist and |
bridging at 30.0.c. | sq.m 47 20d} CWN
T&GFlooring |
1x4 | sqm 15 6d | Flooring brad
1x6 sq.m. 09 | 6d | Flooring brad
Siding Wood Board | |
on studs at 60 o.c.
1x6 | sqm 08 6d | Casing brads
1x8 sq.m. 06 6d | Casing brads.
Studs:
at 40 0.c. sq.m 08 8d cWN
at 60 0.c. sq.m. 05 ad cWN
- Scaffolding Meter ht 73 20d cCWN
| ofpost |
Plywood Wall | Per sheet
and Ceiling | at.150.con .055 | 2d | Finishing nails
| 40x 60 joist
Rafters, Purlins = Persq. m. 20 | 200 cw
and Cleats | purlins at 70 0.c
Base Board | Meterlength 03 6d | cWN
Fascia Board Meterlength 048 | 8d cWN
fen] Ceiling Joist | |
i: at 40 x 60 0.c, Sq.m 05 8d | CW
288
eeeHARDWARE
ILLUSTRATION 8-1
A wall partition 16.00 meters long by 3.00 meters high specify
the use 1" x 8" stone cut wood board on studs spaced at .60 m.
0.¢. Determine the nails Fequired for the studs and the wood board.
SOLUTION
A) Nails for studs
1. Find the area of the wall
A= 20.00 x 3.00 m.
= 60sqa.m.
2. Referting to Table 8-11 along stud at .60 m. 0.c.
Multiply:
60 x .05 = 3.0 kilos 8d CW Nail
B) Nails for 1" x 8" Wood Board
1. Area = 20.00 x 3.00 m.
A= 60sq.m.
2. Referring to Table 8-11 along 1" x 8" board
Multiply:
60 x .06= 3. 6 say 4 kilos 6d CW Nail
289
|
i
i|SIMPLIFIED CONSTRUCTION ESTIMATE
Cement Coated Nails Measured Here
Bright Flat Headed Nails Measured Here.
Concrete Nails
FIGURE 8-18
TABLE 8-11 QUANTITY OF CEMENT COATED NAILS PER
KILOGRAM
Length Penny Gauge No. of Nails/ Kg.
" 2d 15 1863
144" 3d 14 1195
142" 4d 12472 651
13/4" Sd 12112 559
2 6d 1112 367
214" 7d 11142 330
21/2" ed 10414 222
23/4" od 1014 202
3 10d 9 145
314" 12d 9 149
312" 16d 8 103
a 20d 6 64
412" 30d 5 48
s 40d 4 37
512" 50d 3 31
e 60d 2 24
te
290