LCC Pump Maintenance Guide
LCC Pump Maintenance Guide
07/2012 LCC
Pump Type:
Pump Serial Number:
Date:
Purchaser:
Purchaser’s Order Number:
GIW Work Order Number:
Shipped To:
A KSB Company
Contents
Section Page Section Page
1 General 4 7 Maintenance 21
7.1 Supervision of Operation 21
2 Safety 5 7.2 Drainage / Disposal 21
2.1 Safety Markings 5 7.3 Lubrication and Lubricant Change 21
2.2 Personnel Qualification and Training 5 7.3.1 Underwater Operation 22
2.3 Non-compliance with Safety Instructions 5 7.4 Procedures for Maximum Parts Life 22
2.4 Safety Awareness 5 7.5 Operational Problems and Solutions 22
2.5 Safety Instructions for Operators 5
2.6 Safety Instructions for Maintenance, Inspection & 8 Mechanical End 24
Installation 6 8.1 Mechanical End Overview 24
2.7 Unauthorized Modification and Manufacture of 8.2 Mechanical End Disassembly 24
Spare Parts 6 8.3 Mechanical End Assembly 25
2.8 Unauthorized Modes of Operation 6 8.3.1 Mounting the Bearings 25
2.9 Assembly & Disassembly Safety 6 8.3.2 Back to Back Thrust Bearing Installation 26
8.3.3 Face to Face Thrust Bearing Installation 27
3 Transport and Storage 8 8.3.4 Installing End Covers and Seals 28
3.1 Transport & Handling Safety 8 8.4 Bearing Assembly Mounting 29
3.2 Storage Requirements 9
3.2.1 Storage of New Pumps – Pumps under Warranty 9 9 Shaft Seal 30
3.2.2 Removing from Storage 9 9.1 Mechanical Seal 30
3.3 Recommended Lifting 10 9.1.1 Mechanical Seal Assembly and Disassembly 30
9.2 Stuffing Box 30
4. Description 11 9.2.1 Stuffing Box Packing 31
4.1 Technical Specification 11 9.2.2 Stuffing Box Assembly 31
4.2 Designation 11 9.2.3 Stuffing Box Maintenance 31
4.3 Design Details 11 9.3 Expeller Seal 33
4.4 Noise Characteristics 11 9.3.1 Expeller Assembly 34
4.5 Accessories 11 9.3.2 Expeller Disassembly 34
4.6 Dimensions and Weights 11 9.3.3 Expeller Running Clearance 35
4.7 Forces and Moments at Nozzles 12
10 Wet End 36
5 Installation at Site 13 10.1 Wet End Overview 36
5.1 Safety Regulations 13 10.1.1 Pump Casing 36
5.2 Foundation 13 10.1.2 Impeller Form 36
5.3 Installing the Baseplate and Pump 13 10.2 Wet End Disassembly 36
5.3.1 Aligning the Pump / Drive Train 13 10.2.1 Impeller Removal 36
5.3.2 Place of Installation 14 10.2.2 Impeller Break-Loose Jig 36
5.4 Connecting the Piping 14 10.2.3 Impeller Lifting Jig 37
5.4.1 Auxiliary Connections 14 10.2.4 Casing Removal 37
5.5 Safety Guards 14 10.2.5 Elastomer-Liner Removal 37
5.6 Oil Temperature Monitoring (RTD) 14 10.3 Wet End Assembly 37
5.7 Final Check 14 10.3.1 Mounting the Shaft Sleeve 37
5.8 Connection to Power Supply 15 10.3.2 Mounting the Casing 37
6 Commissioning, Startup and Shutdown 16 10.3.3 Elastomer Lined Wet End 37
6.1 Commissioning / Return to Service 16 10.3.4 Installing the Impeller 38
6.1.1 Bearing Lubrication 16 10.3.5 Suction Plate & Liner (LCC-H only) 38
6.1.2 Shaft Seal Commissioning 17 10.4 Setting the Nose Gap 38
6.1.3 Checking the Direction of Rotation 18 11 Tooling 40
6.1.4 Cleaning the Plant Piping 18 11.1 Torque Requirements 40
6.1.5 Suction Strainer 18 11.2 Spare Parts Stock 40
6.2 Startup 18
6.2.1 Priming the Pump 19 12 Troubleshooting 41
6.3 Shutdown 19
6.3.1 Measures to be taken for Prolonged Shutdown 19 13 Supplements 42
6.4 Operating Limits 19 13.1 Duo Cone Seals 42
6.4.1 Temperature Limits 19 NOTES 44
6.4.2 Switching Frequency 20
6.4.3 Density of the Medium Handled 20 General Drawing with List of Components 45
6.5 Underwater Pump Operation 20
2
Index
Section Page Section Page
3
LCC
1 General
This manual contains important information for reliable, proper and efficient operation. Compliance with the
Caution
operating instructions is of vital importance to ensure reliability and long service life of the pump, and to avoid
any risks.
These operating instructions do not take into account local regulations; the operator must ensure that such regulations are
strictly observed by all, including the personnel called in for installation.
This pump / unit must not be operated beyond the limit values specified in the technical documentation for the
medium handled, capacity, speed, density, pressure, temperature and motor rating. Make sure that operation is in
accordance with the instructions given in this manual or in the contract documentation.
The nameplate indicates the type series / size, main operating data and serial number. Please quote this information in all
queries, repeat orders and particularly when ordering spare parts.
If you need any additional information or instructions exceeding the scope of this manual or in case of damage, please contact
your GIW / KSB representative.
4
LCC
2 Safety
These operating instructions contain fundamental information that must be complied with during installation, operation and
maintenance. Therefore this operating manual must be read and understood both by the installing personnel and the
responsible trained personnel / operators prior to installation and commissioning, and it must always be kept close to the
operating location of the machine / unit for easy access.
Not only must the general safety instructions given in this chapter of “Safety” be complied with, but also the safety instructions
outlined under specific headings.
The electrical danger warning sign is the safety sign in accordance with DIN 4844-W8.
Caution The word caution is to introduce safety instructions whose non-observance may lead to damage to the
machine and its functions.
Personnel responsibilities, competence and supervision must be clearly defined by the operator. If the personnel in question
are not already in possession of the requisite know-how, appropriate training and instruction must be provided. If required, the
operator may commission the manufacturer / supplier to provide such training. In addition, the operator is responsible for
ensuring that the contents of the operating instructions are fully understood by the responsible personnel.
5
LCC
2.6 Safety Instructions for Maintenance, Inspection & Installation
The operator is responsible for ensuring that all maintenance, inspection and installation work is performed by authorized
and qualified personnel who are thoroughly familiar with the manual.
Work on the machine must be carried out only during standstill. The shutdown procedure described in the manual for
taking the machine out of service must be adhered to without fail.
Pumps or pump units handling media injurious to health must be decontaminated.
Immediately following completion of the work, all safety / protective devices must be re-installed and / or re-activated.
Please observe all instructions set out in the Section 6 “Commissioning” before returning the machine to service.
Dismantling and reassembly must always be carried out in accordance with the rules of sound engineering practice and
the relevant sectional drawings. Any work on the motor, gear reducer, mechanical seal or other non-pump equipment shall
be governed by the specifications and regulations of the respective supplier.
Before assembly thoroughly clean all dismantled part mating surfaces and check them for signs of wear. Damaged or
worn components are to be replaced by original equipment spare parts. Make sure that the seal faces are clean and the o-
rings and gaskets are properly fitted. It is recommended that new seal elements (o-rings and gaskets) be used whenever
the pump is reassembled. Make sure that new gaskets have the same thickness as the old ones.
Avoid the use of mounting aids as much as possible. Should a mounting aid be required, use a commercially available
contact adhesive. The adhesive should only be applied at selected points (three to four spots) and in thin layers. Do not
use cyanoacryiate adhesives (quick-setting adhesives). If in certain cases mounting aids or anti-adhesives other than
those described are required, please contact the sealing material manufacturer.
The operator is responsible for ensuring that all maintenance inspection and installation work is carried out by authorized,
duly qualified staff who are thoroughly familiar with these operating instructions.
A regular maintenance schedule will help avoid expensive repairs and contribute to trouble-free, reliable operation of the
pump with a minimum of maintenance expenditure.
Repair and maintenance work to the pump must only be carried out by specially trained personnel, using original
equipment spare parts.
Proper lifting, rigging and safety practices must be observed at all times.
Do not attempt to lift heavy components by hand as this may result in personal injury and damage to equipment.
Work on the unit must only be carried out with the electrical connections disconnected and locked out. Make sure that
the pump set cannot be switched on accidentally.
Pumps handling liquids posing health hazards must be decontaminated. When draining the medium ensure there is
no risk to persons or the environment. All relevant laws must be adhered to.
Before dismantling or reassembly, secure the pump so as to make sure it cannot be switched on accidentally. The
shut-off elements in the suction and discharge nozzles must be closed. The pump must have cooled down to ambient
temperature, drained, and its pressure must be released.
Before dismantling or reassembly of vertical pumps, remove the motor and pull the assembly out of the sump.
Do not apply heat to the impeller hub or nose due to the sealed cavity at the impeller nose.
DANGER OF EXPLOSION!
Upon completion of the work, all safety-related and protective equipment must be properly refitted and/or reactivated
before starting the pump set.
6
LCC
Always ensure that lifting equipment does not bind the swivel hoist ring. Binding can cause the ring to fail.
When lifting a plate that contains two swivel hoist rings, do not allow the angle between the lines of tension from the
rings to exceed 120°. This could cause the hoist rings to fail.
120° MAX
Do NOT bind lifting equipment Do NOT exceed 120° between lines of tension
7
LCC
3 Transport and Storage
3.1 Transport & Handling Safety
Proper rigging, lifting and safety practices must be observed at all times.
If the pump / unit slips out of the suspension arrangement, it may cause personal injury and damage to property.
Follow proper lifting practice and safety rules at all times, including:
Verification of the lift weight and load rating of the lift equipment.
Suitability and stability of the attachment points.
Be aware of the location of the center of gravity, which is usually NOT located at the physical center of the unit. In general,
the following guidelines will apply, although common sense and testing of the lift before movement should be used to
verify:
Bare shaft pump (without motor): Near the shaft seal area.
Pump with overhead mounted motor: Between the pump and motor, slightly behind (towards the drive end) of the
shaft seal.
Vertical pump: between the pump and bearing assembly, but closer to the bearing assembly.
Space the lifting points evenly about the center of gravity and as far apart as practical. This will result in the most stable
lift. Note that certain lift points on the pedestal may be intended for use in handling the pedestal alone and are not
necessarily optimum balance points for the entire pump unit.
See Section 3.3 for suggested lifting methods. Actual safe lifting method will vary with pump configuration and type of
lifting equipment.
Ensure secure attachments and test the lifting method for stability before moving pump.
Ensure that the unit remains in the horizontal position during lifting and cannot slip out of the suspension arrangement.
Ensure that the pump is firmly strapped down during shipment. Pump should be protected from direct contact with the
elements. Motors and gear reducers may require immediate cover (consult manufacturer). After arrival on site, consult
GIW Pump Storage recommendations for further storage instructions.
In corrosive environments be sure to remove all lifting devices from the pump and store in a non-corrosive environment
until needed.
DO NOT: Lift with less than four (4) attachment points.
DO NOT: Use eyebolt or shackle locations on the bearing assembly, motor or pump plates. These are intended for lifting
those items alone and must not be used when lifting the entire pump.
DO NOT: Place excessive side loads on cast lifting eyes. The side loading angle on any lifting eye should not exceed 30
degrees.
8
LCC
3.2 Storage Requirements
Upon Receipt
Once received, pumps need to be stored indoors and out of the weather until ready for installation. In construction
environments where indoor storage is not available, st-ore the pump on blocks or pallets, build a frame around it and cover it
with tarpaulin. Ensure the tarpaulin does not touch the pump, since this can lead to condensation. Leave the bottom open for
ventilation. Frame must be able to withstand snow and wind and must be anchored. Frame must also be built in a manner to
last the entire time pump is in storage. Shelter must be continuously maintained in a stable and leak free condition. If the pump
is fitted with a mechanical seal, be sure to consult the seal manufacturer’s maintenance manual for any additional storage
instructions.
3 Months
For storage exceeding 3 months up to 12 months, extra precautions are required.
The wetted pump parts should be drained and isolated from reaction vessel gasses.
The drive train should be manually rotated approximately 5 turns each month.
Check the rust inhibitor coatings on bare metal surfaces and renew exposed areas.
Check the painted surfaces for any signs of corrosion or breaks in the coatings and touch-up as needed.
Verify all threaded holes are protected with grease and plugged.
Fill the bearing assembly with GIW Storage Oil to the center of the sight glass. This oil contains a Vapor Phase Corrosion
Inhibitor (VPCI) additive that will coat the internal bearing surfaces and protect them from corrosion for up to 12 months.
No rotation is needed. For this product to be effective, the bearing assembly must remain sealed in the factory assembled
condition. In particular, the oil fill plug must be securely replaced and no breather or other vent added to the bearing
housing.
Pumps with Inpro® seals must be coated externally with white grease or petroleum jelly to seal the gap between the rotor
and stator. Units equipped with a vent kit must have the vents either removed and plugged, or blocked to prevent air
exchange. Sealing the bearing assembly is especially important when a VPCI product is used.
Oil should be replaced if shutdown duration exceeds 12 months.
Auxiliary systems should be regularly tested according to manufacturer’s recommendations.
If pump is exposed to the weather at any time, frame requirements still stand.
Properly stored elastomer parts will retain their properties for about two years for gum rubber, or five years for neoprene or
urethane. The parts should be periodically inspected for the presence of a soft chalky layer, easily rubbed off, which would
indicate deterioration. Darkening or discoloration of elastomer parts over time is a natural occurrence and does not by itself
indicate any loss of properties.
9
LCC
3.3 Recommended Lifting
Caution Actual safe lifting method will vary with pump configuration and type of lifting equipment.
10
LCC
4. Description
4.1 Technical Specification
The LCC pump range is an international product and has been designed, in most respects, to the METRIC system of units
using metric components. All fasteners are metric and will require metric tooling. All seals are metric including oil seals, O-
rings and stuffing box packing.
Two important exceptions:
1) The suction and discharge flange bolting patterns are to the American (ANSI) standard, however, flange adapting spools
are available.
2) The drive end bearing is an inch based taper roller bearing.
Centrifugal pump for handling coarse or fine particles from solids-laden waste water to aggressive slurries of an abrasive or
corrosive nature. Applications include process pumping and tailings disposal for mining, dredging and other industrial
operations.
4.2 Designation
LCC-M 300-710.5M C M1 Options
Pump Type O Open Shroud Impeller
Hydraulic Type AF Oil Lubricated Face to Face
Discharge Nozzle (mm) AB Oil Lubricated Back to Back
Nominal Impeller Diameter (mm) UF Underwater Oil Lubricated Face to Face
Mechanical Size UB Underwater Oil Lubricated Back to Back
Seal Type GF Grease Lubricated Face to Face
Options GB Grease Lubricated Back to Back
Material Code T Turn Down Impeller
C Elastomer Impeller
Hydraulic Type
M Metal Material Code
R Rubber M1 Metal
H Heavy Construction MC2 Metal / Chemical
R1 Rubber
Mechanical (Frame) Size
1 2 3 4 5 Nominal Flange and Impeller Diameters in mm (inches)
35 mm 50 mm 70 mm 100 mm 125 mm Designation Discharge Suction Impeller
LCC 50 - 230 50 ( 2”) 80 ( 3” ) 225 ( 8.86” )
Seal Type LCC 80 - 300 80 ( 3” ) 100 ( 4” ) 310 ( 12.22”)
K KE LCC 100 - 400 100 ( 4” ) 150 ( 6” ) 395 ( 15.55”)
B Throat Bushing LCC 150 - 500 150 ( 6” ) 200 ( 8” ) 500 ( 19.69” )
M Mechanical Seal LCC 200 - 610 200 ( 8” ) 250 ( 10”) 610 ( 24” )
E Expeller LCC 250 - 660 250 (10”) 300 ( 12”) 660 ( 26” )
LCC 300 - 710 300 ( 12”) 350 ( 14”) 710 ( 27.95”)
For additional information concerning the LCC family of pumps, contact your GIW / KSB representative.
The addition of coarse solids, froth or cavitating conditions can significantly increase the noise levels in both the
pump and piping. If accurate noise levels are required for these conditions, field-testing will be required.
Sound pressure levels from motor and gear reducer must be added to the above in accordance with standard acoustic
formulas, taking into account the distance between units. For belt driven units, add an additional 2 dB.
4.5 Accessories
Couplings, pulleys, belts, motor mounts and/or base plates may be provided. Refer to the bill-of-materials, data sheets and/or
drawings for further information.
11
LCC
4.7 Forces and Moments at Nozzles
Below are the allowable combined branch loads applicable for all GIW slurry pumps. Fzd
Methods based on ANSI/HI 12.1-12.6-2011 Slurry Pump Standard. Loads generally
exceed HI/ANSI 9.6.2-2008 table 9.6.2.1.4a and API 610-2004, Table 4. Higher Mzd
Mxd
allowable loads may be possible depending on individual pump configuration and
operating conditions. Contact your GIW Application Engineer for more information. Fxd Myd
Fzs Fyd
NOTE: Discharge branch coordinate system always moves with the branch angle.
(Fz is always along the direction of flow). Mzs
Mxs
Fxs Mys
Fys
12 300 3420 15230 2740 12180 5070 22560 5210 7070 5210 7070 7900 10710
14 350 3890 17300 3110 13830 5540 24640 5710 7740 5710 7740 8650 11730
16 400 4440 19760 3550 15790 6090 27100 6200 8410 6200 8410 9400 12750
18 450 5110 22750 4090 18190 6760 30090 6690 9070 6690 9070 10140 13750
20 500 5900 26240 4720 20990 7550 33580 7170 9730 7170 9730 10870 14740
22 550 6680 29730 5350 23790 8330 37070 7650 10380 7650 10380 11600 15720
24 600 7350 32720 5890 26190 9000 40060 8120 11020 8120 11020 12310 16700
26 650 7900 35170 6330 28150 9550 42510 8590 11650 8590 11650 13020 17660
30 750 8780 39090 7030 31260 10430 46430 9510 12900 9510 12900 14410 19540
36 900 9860 43890 7890 35090 11510 51230 10850 14710 10850 14710 16440 22290
38 950 10150 45170 8120 36150 11820 52580 11280 15300 11280 15300 17100 23190
3 75 3410 15180 1760 7840 1410 6270 4390 5960 2900 3930 2900 3930
4 100 3580 15930 1930 8590 1550 6890 4790 6500 3160 4290 3160 4290
6 150 3920 17450 2270 10110 1820 8090 5580 7570 3680 4990 3680 4990
8 200 4280 19040 2630 11700 2100 9340 6360 8620 4200 5690 4200 5690
10 250 4660 20730 3010 13390 2410 10710 7130 9670 4700 6380 4700 6380
12 300 5070 22560 3420 15230 2740 12180 7900 10710 5210 7070 5210 7070
14 350 5540 24640 3890 17300 3110 13830 8650 11730 5710 7740 5710 7740
SUCTION PIPE
16 400 6090 27100 4440 19760 3550 15790 9400 12750 6200 8410 6200 8410
18 450 6860 30090 5110 22750 4090 18190 10140 13750 6690 9070 6690 9070
20 500 7550 33580 5900 26240 4720 20990 10870 14740 7170 9730 7170 9730
22 550 8330 37070 6680 29730 5350 23790 11600 15720 7650 10380 7650 10380
24 600 9000 40060 7350 32720 5890 26190 12310 16700 8120 11020 8120 11020
26 650 9550 42510 7900 35170 6330 28150 13020 17660 8590 11650 8590 11650
28 700 10020 44590 8370 37250 6700 29800 13720 18600 9050 12280 9050 12280
30 750 10430 46430 8780 39090 7030 31260 14410 19540 9510 12900 9510 12900
34 850 11170 49710 9520 42370 7620 33890 15770 21390 10410 14110 10410 14110
36 900 11510 51230 9860 43890 7890 35090 16440 22290 10850 14710 10850 14710
38 950 11820 52580 10150 45170 8120 36150 17100 23190 11280 15300 11280 15300
12
LCC
5 Installation at Site
5.1 Safety Regulations
Electrical equipment operated in hazardous locations must comply with the applicable explosion protection
regulations. This is indicated on the motor rating plate. If the equipment is installed in hazardous locations, the
applicable local explosion protection regulations and the regulations of the test certificate supplied with the equipment
and issued by the responsible approval authorities must be observed and complied with. The test certificate must be
kept close to the location of operation for easy access.
5.2 Foundation
All structural work required must have been prepared in accordance with the dimensions stated in the dimension table /
installation plan.
The concrete foundation shall have sufficient strength for the pump and be completely cured before installation. The mounting
surface must be flat and level. Anchor bolts must be located according to the installation plan. This can be done when the
concrete is poured, or by drilling holes in existing foundations and grouting the bolts in place.
Appropriate personal protective equipment should be worn when handling concrete and grouting materials.
After placing the baseplate on the foundation, it must be leveled by shimming. Shims should be fitted between the baseplate
and the foundation itself; they should always be inserted to the left and right of the foundation bolts and in close proximity to
these bolts. For a bolt-to-bolt clearance of more than 800mm (30 in.), additional shims should be inserted halfway between the
adjoining holes. All shims must lie perfectly flush.
Insert the foundation bolts and set them into the foundation using concrete. When the mortar has set, tighten the foundation
bolts evenly and firmly and grout the baseplate using low shrinkage grout.
Foundation bolts
Caution Improper alignment of the unit can cause damage to both the coupling and the unit itself!
Use of the mounting bolts to close gaps between motor feet and the mounting plate (in place of shimming) is not
recommended and may result in twisting of the motor frame, “soft foot” mounting and excessive vibration.
Care must be taken when removing drive components to avoid personal injury or damage to the equipment.
Avoid contact with hot surfaces such as couplings, which may heat up during normal operation and cause injury.
Proper alignment must be taken into consideration when using an overhead motor mount accessory. Motor feet must be
firmly supported at each mounting bolt location before the bolts are tightened. Shims should be used to fill any gaps and
ensure solid mounting and vibration prevention.
For optimum performance, the pump should be mounted directly to the baseplate without shims. The rest of the drive train
is then aligned to the pump. For this reason, GIW baseplate designs generally allow space for shimming under the gear
reducer and motor, but not under the pump itself. The only exception occurs in cases where regular removal and
replacement of the entire pump is stipulated during the equipment design stage. In these cases, special instructions for
alignment and shimming of the pump may be given on the pump assembly and/or general arrangement drawings.
13
LCC
Coupling check and realignment must be done even if pump and motor are supplied completely assembled and aligned on
a common base plate. The correct distance between the coupling halves as specified in the installation plan must be
observed.
The pump set is correctly aligned if a straightedge placed axially on both coupling halves is the same distance from each
shaft at all points around the circumference. In addition, the distance between the two coupling halves must remain the
same all around the circumference. Use a feeler gauge, a wedge gauge or a dial micrometer to verify.
The radial and axial deviation (tolerance) between the two coupling halves should not exceed 0.1 mm (0.004 inch).
For V-belt installations, the pulleys are correctly aligned if a straightedge placed vertically shows a deviation of no more
than 1.0 mm (0.04 in.). Both pulleys must be parallel.
Straight edge
a b
a b
Take the necessary precautions to avoid burns to personnel and adjacent equipment.
Thermal expansions of the pipelines must be compensated by appropriate measures so as not to impose any extra loads
on the pump exceeding the permissible pipeline forces and moments.
An excessive, impermissible increase in the pipeline forces may cause leaks on the pump where the medium handled can
escape into the atmosphere.
The flange covers on the pump suction and discharge nozzles must be removed prior to installation in the piping.
Caution These connections are required for proper functioning of the pump and are therefore of vital importance!
The dimensions and locations of the auxiliary connections (cooling, heating, sealing liquid, flushing liquid, etc.) are
indicated on the installation plan or piping layout.
14
LCC
5.8 Connection to Power Supply
A trained electrician must make the connection to the power supply. Check available main voltage against the data
on the motor rating plate and select the appropriate start-up method. The use of a motor protection device is strongly
recommended.
An emergency shut off switch should be installed to prevent damage to the personnel and environment in the event
of hazardous pump operation.
15
LCC
6 Commissioning, Startup and Shutdown
Compliance with the following requirements is of paramount importance. Damage resulting from non-
Caution
compliance shall not be covered by the scope of warranty. This manual applies to single stage pumps.
Procedures for multistage pumps should be obtained from the GIW/KSB sales office.
This manual applies to single stage pumps. Procedures for multistage pumps should be obtained from GIW/KSB sales office.
Caution Before starting up the pump make sure that the following requirements are checked and fulfilled.
1. If the pump has been in long term storage (more than 3 months), proper storage procedures were followed, including
instructions for removing the pumps from storage (see contract documents and/or contact your GIW representative).
Failure to follow proper storage procedures will void your warranty.
See Section 3.2 “Storage Requirements”.
2. The impeller nose clearance has been properly set.
See Section 10.4 “Setting Impeller Nose Gap” for details.
3. Pump drive train final alignment is complete.
See Section 5.3.1 “Alignment” for details.
4. Final torquing of all bolts has been completed.
See Section 11.1 “General Torque” for details.
5. All electrical and power supply connections are in order, including fuses and overload protection devices.
See Section 5.1 “Safety Regulations” for details.
6. All required auxiliary connections, such as shaft seal water, oil coolers, etc. are made, tested and ready to function.
See Section 5.4.1 “Auxillary Connection” for details.
7. All safety guards and equipment are in place.
See Section 5.5 “Safety Guards” for details.
8. Any required instrumentation has been properly installed.
See Section 5.6 “Oil Temperature Monitoring” for details on RTD installation.
9. Bearing assembly lubrication is completed.
See Section 6.1.1 “Bearing Lubrication” for details.
10. Shaft seal is ready for operation
See Section 6.1.2 “Shaft Seal Commissioning” for details.
11. Drive train direction of rotation at the pump is correct.
See Section 6.1.3 “Checking the Direction of Rotation” for details.
12. The pump set is primed.
See Section 6.2.1. “Priming the Pump”
13. The desired operating conditions do not exceed those allowed by the pump.
See Section 6.4 “Operating Limits” for details.
16
LCC
Approximate Grease Capacity
Bearing *Shaft Speed Spherical Taper
Assembly RPM Roller Bearing Roller Bearing
mL (oz) mL (oz)
35mm 2300 15 (0.5) 20 (0.7)
50mm 1800 20 (0.7) 40 (1.4)
70mm 1400 30 (1.0) 90 (3.0)
100mm 1000 90 (3.0) 190 (6.4)
125mm 750 140 (4.7) 280 (9.5)
*Monitor commission temperature if exceeded
Oil-lubricated bearings
Pump bearing units are shipped with preservative and empty of oil. Before starting the pump, fill them to the
Caution
center of the oil level sight gauge using the GIW Blue 150 synthetic bearing oil supplied with the unit.
Otherwise, use an equivalent synthetic or a high quality ISO220 mineral oil suitable for use with heavy
industrial equipment, anti-friction bearings and oil circulating systems. Such oil typically has high temperature
stability, resistance to oxidation and foaming, and inhibits rust, corrosion, and the formation of deposits. Oils
with EP additives are not recommended.
If locally obtained oil is desired, use an equivalent synthetic or a high quality ISO220 or 320 mineral oil suitable for use with
heavy industrial equipment, anti-friction bearings and oil circulating systems. Such oil typically has high temperature stability,
resistance to oxidation and foaming, and inhibits rust, corrosion, and the formation of deposits. Oils with EP additives are not
generally recommended. Detailed bearing oil specifications and GIW Blue replacement oil are available from GIW.
Oil operating temperatures for GIW bearing assemblies will depend on pump size, speed and ambient conditions. Under
typical conditions, they will run from 50 °C – 85 °C (125 °F – 185°F). For oil temperatures above 85 °C (185 °F) or for severe
load conditions, a high quality synthetic lubricant (such as GIW Blue) should be used. At higher speeds, or in hotter ambient
conditions, temperatures can rise to 100 °C (210 °F). Slightly higher temperatures may be seen for a brief period during the
breaking in of new bearings. The unit should be shut down immediately if temperatures rise to 120 °C (250 °F).
If the pump is equipped with a deaeration chamber (HVF), the mechanical seal must be of the double faced type with barrier
fluid. This will prevent dry running and seal face destruction.
Mechanical seals require safety checks prior to start-up such as removing seal assembly fixtures, checking
Caution
axial alignment, checking torques etc. Refer to the mechanical seal operating manual for all required safety
checks.
17
LCC
Prior to commissioning, the gland packing supplied with the pump must be adjusted. Preformed packing rings sets from GIW /
KSB are recommended. For alternate brands, refer to packing manufacturer’s instructions regarding installation and use.
For gland flush supply, use suitable non-aggressive clean water not liable to form deposits and not containing suspended
solids. Hardness should average 5 with a pH>8. It should be conditioned and neutral with regards to mechanical corrosion.
An Inlet Temperature of 10 °C – 30 °C (50 °F – 85 °F) should produce a maximum Outlet Temperature 45 °C (115 °F) when
the gland is properly adjusted.
If a Variable Frequency Drive (VFD) or other controller is used, it is recommended to permanently disable REVERSE and
BRAKE function during controller set up.
If motive power is applied to the pump, and it is run in the wrong direction of rotation, even momentarily, the
Caution
impeller may unscrew causing extensive damage to the entire unit. This is especially important during initial
start up as the impeller may not be fully torqued onto the pump shaft.
6.2 Startup
Before starting the pump verify that the shut-off element in the suction line is fully open.
The pump may be started up against a closed discharge shut-off element. Once the pump has reached full rotational
speed, open the discharge valve slowly and adjusted to the duty point.
When starting up against an open discharge-side shut-off element, take the resulting increase in input power requirements
into account.
Start-up, shutdown, filling and draining procedures must be designed to prevent any possibility of negative torque
being experienced on the pump shaft. Negative torque can cause the impeller to unscrew, leading to severe damage
throughout the rotating assembly and drive train. In particular, the following practices must be avoided:
1. Any flow through the idle pump, in any direction, in excess of 5% of the normal operating flow rate before the
impeller has been tightened by running under normal loads. This includes flow due to filling or draining of the
system and/or flow caused by the equalization of different levels between the sump and discharge line after the
opening of any valves in the piping.
2. Any attempt to restrict the flow after shutdown, by either manual or automatic systems, until the pump comes to
a complete standstill.
3. Any braking or re-energizing of the drive train after shutdown, until the system has reached a complete static
condition.
Prolonged operation at zero or low flow, typically due to closed valve or unintended pipeline blockage, is not
prohibited. Danger of steam generation and explosion.
Start-up and shutdown procedures must be designed to prevent any possibility of water hammer. Water hammer can
place excessive loads on the piping, resulting in damage to the pump flanges. The pressure waves generated by
water hammer can also cause damage to the pressure containing components of the pump, the mechanical end
and/or the mechanical seal.
During the initial commissioning, once the pump and bearing assembly stabilize at normal operating
Caution
temperature, or in the event of system leaks, stop the unit and re-tighten all bolts. Check the coupling
alignment and re-align if necessary.
18
LCC
6.2.1 Priming the Pump
Before start-up, the pump, suction line and (if applicable) the tank must be vented and primed with the liquid to be pumped.
Any valve in the suction line must be fully open. Open all auxiliary connections (flushing, sealing, cooling liquid, etc.) and check
the through flow.
Dry-running will result in increased wear on the gland packing and shaft protecting sleeve or failure of the
Caution
mechanical seal and must be avoided!
6.3 Shutdown
Under no circumstances should the pipe system be equipped with a check valve or other device that can rapidly
decelerate the flow rate.
Switch off the drive, making sure that the unit runs smoothly down to a complete stop. Variable Frequency Drive (VFD)
and other controllers must not use any braking function to slow the pump. Diesel power trains should disengage the clutch
and allow the pump to coast to a stop.
Close any auxiliary connections. Pressurized bearing lubrication systems must remain running until all rotation has
stopped. If the any part of the system uses a cooling liquid supply, turn that off only after the pump has cooled down.
Where liquid filled shaft seals are used, consult seal maintenance manual for specific shutdown procedures.
Where temperatures may drop below freezing, the pump and system must be drained or otherwise protected against
freezing.
If the pump is equiped with an deaeration chamber (HVF) the following steps may be taken to reduce the amount of fluid
in the vent pipe and hose:
1. Reduce suction pressure to 10kPa / 1.5 psig by lowering the sump level
2. Close the vent valve to stop slurry from re-entering the vent hose
Caution Pipe system design and pump operation should prevent damage to the pump during a scheduled or
emergency shutdown.
In the event of shutdown where a significant static discharge head exists in the system, the impeller can begin
Caution
to run back-wards as the flow reverses in the pipeline. This creates a positive torque on the shaft so the
impeller connection will not unscrew. Until the flow stops, do not close any main line valves. A change in fluid
velocity can create a negative torque on the impeller and unscrew it from the shaft. This can damage wet end
pump parts as well as bearings, seals and other components
Any make up water or outside water supply for the system must be installed so that the GIW pump will never
Caution
be exposed to a pressure in excess of its maximum allowable operating pressure.
Damage resulting from disregarding this warning will not be covered by the manufacturer’s warranty.
Bearing temperatures must be observed. Excessive bearing temperature could indicate misalignment or other technical
problem.
19
LCC
6.4.2 Switching Frequency
To prevent high temperature increases in the motor and excessive loads on the pump, coupling, motor, seals and bearings,
the switching frequency should not exceed the following number of start-ups per hour.
Due to the angular position of ladder mounted pumps in most dredge operations, the UCBA must be completely filled with oil to
provide lubrication to the rear thrust bearing when the cutter head is lowered. This requires the use of tank mounted above the
deck to detect leaks and accommodate internal pressure changes. A pressurized recirculating system can be used, but the
simplest method is an expansion tank suitable for operation within the marine environment. This must be designed to prevent
dirt, water or other contaminants from entering the oil system while providing a vent to atmosphere.
This tank keeps a positive pressure on the bearing side of the Duo-Cone seals to counteract the water pressure as the pump is
submerged. The tank should be mounted high enough to maintain a pressure of about 7 psi (0.5 bar) above what is created by
the maximum water depth. Note that the specific gravity of oil is only about 85% of water and must be taken into account when
calculating the mounting height of the tank.
The tank should have an oil level indicator to allow the operator to see if the level changes. After the oil temperature stabilizes,
the level should remain constant and any significant change would indicate a leaking seal. This early warning can prevent oil
from leaking into the surrounding water and avoid bearing failure.
Dredge pumps are designed to run with the UCBA and Duo-Cone seals fully submerged. This enables the surrounding water
to dissipate heat generated by the bearings and seal faces. If the pump will be operated above the water line for extended
periods, the bearings can create extra heat in the oil and the seal faces may overheat. Provisions should be made to provide a
supply of cooling water to each Duo-Cone seal and a water spray onto the UCBA itself. If the pump will run continuously above
water, other sealing systems are recommended, or oil circulating and seal cooling systems will be required.
Care should be taken to operate the pump within the speed limitations specified by GIW on the pump drawing for the particular
seal size installed. If a seal is replaced, it must be installed with the correct gap (specified by GIW for each seal size) between
the seal holders, as this distance provides the correct seal face pressure for proper operation.
Failure to operate the seals within the above parameters may result in premature seal failure or oil leakage through the Duo-
Cone seals. Any change in the operating conditions should be discussed with your GIW / KSB representative to establish if the
new conditions are suitable for the equipment.
20
LCC
7 Maintenance
Refer to Section 2.9 “Assembly & Disassembly Safety” prior to working on the pump
Caution If the flexible coupling elements begin to show signs of wear, they should be replaced.
Neglect of maintenance procedures and monitoring can result in failure and leakage of the shaft seal, bearing seals,
and wear components.
Operational procedures which may cause system water hammer must be avoided.
Sudden and catastrophic failure of pump casing and plates may result.
When running the pump against a closed discharge-side shut-off element for a short period, the permissible pressure and
temperature values must not be exceeded.
Verify the oil level is correct.
The gland packing (if the pump is fitted with one) should drip slightly during operation. The gland should only be gently
tightened.
Any stand-by pumps installed should be switched on and off again once a week to keep them operational. Attention
should be paid to the correct functioning of the auxiliary connections.
For pumps equipped with a deaeration chamber (HVF):
o Under normal operating conditions where suction pressure is slightly greater than atmospheric pressure (by
about 10 kPag / 1.5 psig), the vent pipe will mainly expel air. However, during system upsets where suction
pressure is increased, a mixture of air and slurry may rise up into the vent pipe. In the case of viscous liquids, a
liquid filled vent pipe may slow the action of the venting system, so it is preferred to keep suction pressure low
(below 50 kPag / 7.25 psig) whenever possible.
o System upsets which reduce the suction pressure below 10 kPag / 1.5 psig should also be avoided, as they may
cause the vent pipe to ingest air into the pump and the pump to lose prime. In most cases, this will correct itself
as the sump level and suction pressure rise and the venting system again expels the excess air. It is not
recommended, however, to allow the pump to cycle in this way between positive and negative suction pressure,
since this may lead to unstable system operation, reduced efficiency and poor wear performance. If necessary,
adjust pump speed and sump levels to maintain a normal suction pressure around 10 kPag / 1.5 psig.
If the media handled by the pumps leaves residues which might lead to corrosion when coming into contact with atmospheric
humidity, or which might ignite when coming into contact with oxygen, the unit must be flushed thoroughly and neutralized.
The flushing liquid used and any liquid residues in the pump must be properly collected and disposed of without posing any
risk to persons or the environment.
Oil Changes
Refer to Section 6.1.1 “Bearing Lubrication” for bearing oil change instructions, specifications & capacities.
The first oil change should be carried out after 300 operating hours, then every 3000 hours thereafter or when it appears
or is suspected of being dirty or contaminated.
Drain the existing oil by removing the drain plug on the bottom of the housing.
Reinstall the drain plug and fill with fresh oil until the oil level reaches the center of the oil sight gauge.
Grease Changes
Refer to Section 6.1.1 “Bearing Lubrication” for bearing grease change instructions, specifications & capacities.
Grease lubricated bearings should be replenished after the initial 50 hours of operation, then every 1,500 hours thereafter
by an injection roughly equal to one half of the amount originally used to pack the bearings.
21
LCC
After 20,000 operating hours or 2.5 years the bearings should be checked, then cleaned and relubricated if required.
For more information on Underwater Bearing Assemblies see Section 6.5 “Underwater Pump Operation”
Suction Liner
The suction liner should be rotated 180° at approximately half life if localized wear occurs. If localized wear is severe,
repair as recommended by GIW / KSB before rotation.
A new gasket / o-ring should always be used with a new suction liner or new pump casing.
Impeller
The impeller to suction liner clearance should be adjusted forward several times during its life cycle for maximum impeller
and suction liner life. See Section 10.4 “Setting the Nose Gap”.
In general, an impeller does not require replacement until it fails to produce sufficient head for the application. Impellers
are sometimes changed too soon based on appearance. Vibration caused by an impeller wearing out of balance is rare
but possible. If this occurs, the impeller may be statically balanced by hand grinding on back shroud.
The impeller should never be repaired by welding.
Pump Casing
If wear is localized with a deep gouge, repair or replace as recommended by GIW / KSB. Excessive wear problems are
usually indications that the pump is not operating at the flow and head conditions originally specified for the design.
Expeller Maintenance
Proper adjustment of the impeller nose clearance as covered in the Section 10.4 “Setting the Nose Gap” should result in
proper expeller clearances in the new condition and no further adjustments should be necessary. In some cases adjusting
the impeller after excessive suction liner wear may result in the expeller rubbing against the expeller plate. In other cases
it is desired to optimize expeller performance rather than optimize the impeller clearance. Refer to Section 9.3.3 “Expeller
Running Clearance” for instructions.
Optimizing the expeller clearances is recommended only in cases where expeller performance is
Caution
marginal and a small increment in performance is required to seal against the pump pressure. Setting of
clearances for optimal expeller performance may result in excessive impeller clearance and accelerated
wear. If necessary, this may be remedied by providing a custom fitted machined spacer with gaskets
between the impeller and expeller.
Sump Design
A minimum sump capacity of one minute at the expected flow conditions should be provided. Sump design should prevent
any uneven flow of the solids to the suction. Often, a flat bottom sump is best since it will allow the solids to assume a
natural slope of repose. The sump should be observed during operation to ensure that solids are not building up and
sloughing off.
Sump design should prevent the formation of a vortex, or other means of introducing air into the pump. Where a
submerged suction is available, the depth of water level above the pump suction is more important than the cross-
sectional area of the sump. Frothing of the sump should be eliminated by the installation of baffles, a submerged inlet pipe
or other methods to prevent air becoming entrained in the slurry. If unavoidable, frothing must be accounted for in the
system design and operation.
If the sump runs dry, the system will surge causing accelerated pump wear. Pump speed or impeller diameter should be
decreased or make up water increased. If the flow variations are too great, a variable speed motor may be required.
During the initial stages of operation, motor load on the pump should be checked. If there is an excess amount of power being
drawn by the pump, it may be caused by the system head (TDH) being lower than predicted thus resulting in higher flow rates
and power consumption. This sometimes happens when a safety factor is applied to the head during the design of the system.
Cavitation may also occur under these high flow conditions. The pump speed should be slowed down to reduce flow, or the
total discharge head against the pump should be increased (resulting in reduced flow and power consumption).
If actual supply flow rates are lower than predicted, the sump may run dry causing the system to surge and accelerating pump
wear. Pump speed or impeller diameter should be decreased or make up water increased to keep the sump at the highest
stable level possible. If the flow variations are too great, a variable speed motor may be required. This problem is especially
common in applications with a high proportion of static head, such as mill discharge and cyclone feed. It can be further
aggravated by operation well below the best efficiency flow rate of the pump where the pump head curve is relatively flat.
Under these conditions, minor fluctuations in the system resistance caused by normal variations in solids concentration or size
can result in surging flow rates.
Whenever possible, avoid prolonged operation at flows well below the optimum flow rate. This causes recirculation of slurry
within the pump and encourages localized wear.
In the event problems are encountered, contact your GIW / KSB representative. The pump serial number, in addition to the
following, should be furnished to assist in evaluation of the problem:
A. Pump serial number (from the nameplate on the pedestal), customer location, and the approximate startup date.
B. Pumped fluid SG (specific gravity), slurry information including SG and particle size, and liquid temperature.
C. The approximate flow rate desired and the actual minimum and maximum flow rate of the system if known.
D. The system static head (the difference in elevation between the water level on the suction side of the pump and the
point of discharge)
E. The length and size of suction and discharge lines, including a description of the general arrangement including fit-
tings, bends and valves
F. If the discharge point is not to atmosphere, what is the pressure, (e.g. cyclone backpressure).
G. If suction is taken from a sump, provide the general arrangement including size dimensions and minimum and maxi-
mum sump levels referenced to the suction centerline of the pump.
H. The available driver horsepower, speed of motor and pump or description of the ratio device between the pump and
motor.
I. The impeller diameter if different from that supplied with the pump.
The above items of data are especially important when a pump has been transferred from the duty for which it was selected to
some other application.
In many instances, it will be found that unusual wear in the pump, or low efficiencies, are caused by a mismatch between the
pump and the system application and can be corrected once the operating conditions are known.
Contact your GIW / KSB representative for further specific recommendations regarding system design. A useful reference and
textbook has also been published by GIW titled: “Slurry Transport Using Centrifugal Pumps,” by Wilson, Addie & Clift.
23
LCC
8 Mechanical End
8.1 Mechanical End Overview
The bearing assembly is a cartridge design mounted on a concentric pedestal with an adjustment mechanism for setting
the impeller axial clearance.
Standard lubrication is grease. Oil lube is also available. See Section 6.1.1 “Bearing Lubrication” for lubrication quality and
quantity.
Basic bearing parts are listed below for reference. Note that the suffix can vary depending on configuration and vendor.
Replacement bearings are available from GIW/KSB.
Bearings Installed
Double Row Taper Roller - Back to Back Double Row Taper Roller - Face to Face
Bearing Spherical
Assembly Part number Bench Part Number Bench
Roller
(Timken) End-Play (SKF) End-Play
E Type Cone / Cup / Spacer * mm (inch) mm (inch)
53177
35 mm 22209E 53376D 0.15 (0.006) 31309 J2/QCL7CDF 0.10 (0.004)
X2S53176
72225C
50 mm 22212E 72488D 0.15 (0.006) 31312 J2/QDF 0.12 (0.005)
X1S72225
9285
70 mm 22217E 9220D 0.18 (0.007) 31316 J1/QLC7CDF 0.14 (0.006)
X4S9285
HM926740
100 mm 22224E HM926710CD 0.25 (0.010) 31322 XJ2/DF 0.16 (0.006)
HM92674XA
HH932145
125 mm 22230E HH932110 0.20 (0.008) 31328 XJ2/DF 0.19 (0.008)
H932145XA **
* Koyo is also an approved supplier for the Back to Back Taper roller bearing.
** Assembled from two single row bearings.
Refer to Section 2.9 “Assembly & Disassembly Safety” prior to working on the pump.
24
LCC
Drain the oil (if applicable) by removing the drain plug on the bottom of the housing.
Remove the flingers (if any) and bearing housing end covers. Care should be taken with the Inpro oil seals, which should
not be removed from the end covers unless they have been damaged and are in need of replacement. Inspect the seals,
gaskets, and o-rings, and discard any that appear worn or broken.
The locknut and lock washer that clamp the drive side bearing should also be removed. One tab of the lock washer will be
bent into a recess on the lock ring and must be bent back to allow the lock nut to be unscrewed.
The shaft and bearings (which are pressed onto the shaft) may then be removed as a unit from the drive end of the
housing. Horizontal disassembly is acceptable when proper support is given to the shaft to prevent its contacting and
marring any of the finished surfaces of the shaft or bearing housing bore. Care should be taken to avoid damaging the
grease retaining ring (part 63-7, grease lubricated) or spacer ring (part 45-4, oil lubricated) that will come out on the shaft
between the two bearings.
The bearings are hot when installed on the shaft, and fit tight. It is difficult to remove them from the shaft undamaged, and
they should be removed only if a bearing needs to be replaced. Bearings are normally removed by heating, which should
be done quickly to prevent heating of the shaft as well. Flame cutting of the outer race and careful grinding of the inner
race may occasionally be required. Care must be taken, however, to avoid damaging the shaft, especially in the oil seal
area.
Refer to Section 2.9 “Assembly & Disassembly Safety” prior to working on the pump
Caution Before assembly, thoroughly clean all shaft, housing bore, and end cover surfaces with a suitable solvent to
remove old grease and any water, dust or grit. Clean all dismantled components and check them for signs of
wear. Damaged or worn components are to be replaced by original equipment spare parts. Make sure that the
seal faces are clean and the O-rings and gaskets are properly fitted.
Heat radial bearing to 120 °C (250 °F) by a suitable bearing heater, oil bath, or other even heating device prior to
mounting. Flame heating is not recommended.
Install radial bearing onto shaft
Press fit bearing ensuring that it is seated fully against the abutting shaft shoulder.
Caution Use the bearing assembly drawing to determine if the bearing assembly uses the face to face or back to back
taper bearing arrangement.
Back to Back Taper Roller Bearing Face to Face Taper Roller Bearing
25
LCC
Taper Bearing Locknut Assembly Torque
Locknut Assembly Torque
Bearing Assembly
N-m ft-lbs
35 mm 100 75
50 mm 135 100
70 mm 200 150
100 mm 375 275
125 mm 680 500
Cup
Outboard Inboard
Side Side
Cone / Roller
Spacer
The grease retaining ring (63-7, for grease lubrication) or spacer ring (45-4, for oil lubrication) must be placed
Caution
on the shaft between the bearings, and in the proper orientation, before both bearings are mounted. Once the
bearings are mounted, they cannot be removed without risk of damage. The grease ring is essential in
protecting the taper bearing from loss of lubrication in the event of high loadings. Failure to install the ring may
result in significantly reduced bearing life.
Heat inboard cone to 120 °C (250 °F) and install. Ensure that the larger OD of the bearing is towards the center of the
shaft.
Install spacer and bearing cup
Caution Over-tightening can damage the lock washer and allow the locknut to back off during operation.
Do not back off the locknut any amount after tightening in an attempt to set the bearing clearances.
Caution
The taper bearing has an internal spacer, which automatically sets the internal bearing clearances.
After tightening, bend down one tab of the lock washer into one of the mating grooves on the locknut. If none of the tabs
are aligned with a groove, locate the nearest one, and further tighten the locknut until the tab can be bent down.
26
LCC
Failure to bend down one of the lock washer tabs may allow the locknut to back-off and lead to premature bearing failure.
Ensure that the bearing outer diameters and housing bores are clean. Coat shaft between the bearings with GIW Blue
Synthetic Bearing Lubricant.
Lift shaft vertically and place into housing from drive end. It will be necessary to align the grease ring 63-7 or spacer 45-4
as it enters the housing since it has about 6mm (0.25”) of clearance with the shaft.
The bearings should slide easily and fully into the bearing housing without excessive force that would indicate
Caution
possible dust or grit between the bearings and the housing, and result in a thrust preloading on the impeller
end spherical roller bearing. Preloading of the bearing will cause it to carry thrust loadings, which would
normally be carried by the taper roller bearing and can result in overheating and premature failure of the
spherical roller bearing.
Spacer
Outboard
Inboard
Side
Side
Cup
Cone / Roller
Face to Face Thrust Bearing Arrangment
After both cones are installed and before the taper roller bearing has cooled on the shaft, use the lock nut without lock
washer to fully seat the bearing against the shaft shoulder. (The lock washer must be left out during this step to prevent
damage)
After the bearings have cooled, remove the locknut and reinstall with lock washer against the taper roller bearing,
tightening the nut according to the torque given in Section 8.3.1 “Mounting the Bearings”.
Caution Over-tightening can damage the lock washer and allow the locknut to back off during operation.
Do not back off the locknut any amount after tightening in an attempt to set the bearing clearances.
Caution
The taper bearing has an internal spacer, which automatically sets the internal bearing clearances.
After tightening, bend down one tab of the lock washer into one of the mating grooves on the locknut. If none of the tabs
are aligned with a groove, locate the nearest one, and further tighten the locknut until the tab can be bent down.
27
LCC
Failure to bend down one of the lock washer tabs may allow the locknut to back-off and lead to premature bearing failure.
Ensure that the bearing outer diameters and housing bores are clean. Coat shaft between the bearings with GIW Blue
Synthetic Bearing Lubricant then lift shaft vertically and place into housing from drive end.
Insert the spacer and cup for the outboard bearing using a rubber mallet.
The bearings should slide easily and fully into the bearing housing without excessive force that would indicate
Caution
possible dust or grit between the bearings and the housing, and result in a thrust preloading on the impeller
end spherical roller bearing. Preloading of the bearing will cause it to carry thrust loadings, which would
normally be carried by the taper roller bearing and can result in overheating and premature failure of the
spherical roller bearing.
Bearing Assembly inserted into Housing Drive End Use a rubber mallet to ease insertion
Bottom
Install with lubrication return trough at 6 o’clock position VBX Inpro Seal
Slide end covers with gaskets and Inpro seals over the shaft at each end, again making certain that the contaminant
expulsion port and lubrication return trough are located at the bottom. Use O-Ring lubricant, Parker O-Lube or Parker
Super-O-Lube to lubricate the inner diameter o-rings against the shaft. Take special care when running the seal over the
shaft keyway to avoid cutting the o-ring. If necessary, lightly file the keyway edges to avoid this problem.
28
LCC
After bolting the end covers in place, rotate the shaft by hand. There should be no frictional contact between the rotating
and stationary parts of the Inpro seal. Any rubbing or axial movement in the seal may indicate misalignment. If this is the
case, tap lightly into alignment. Note that the drive side end cover clamps against the outer race of the taper roller bearing
and may not fit flush against the housing. No shimming is necessary. A gap of up to 1 mm (0.04”) is acceptable and within
the tolerance of the parts. Any larger gap may indicate that the taper roller bearing is not fully seated into the housing.
Install grease fittings or oil plugs.
Failure to install the bearing housing hold down bolts at this time may result in tipping of the bearing assembly and
possibly personal injury when the impeller is screwed on to the shaft.
29
LCC
9 Shaft Seal
9.1 Mechanical Seal
Mechanical seals are precision devices which require special care for their proper operation. The instruction manual for the
seal should be consulted for special storage, start-up, and maintenance requirements.
Mechanical seals require safety checks prior to start-up such as removing seal assembly fixtures, checking
Caution
axial alignment, checking torques etc. Refer to the mechanical seal operating manual for all required safety
checks.
Always refer to the mechanical seal maintenance manual for further instructions.
The Forward Flush design is the simplest and easiest to operate. It consists of a lantern ring backed with multiple
packing rings and is used where gland water supply is plentiful and addition of water to the process flow is not problematic.
The KE design is used where minimum water usage is desired. One or two rings of packing are located between the
lantern ring and the wear plate to restrict seal water flow into the pump cavity, while the packing rings behind the lantern
ring seal to atmosphere. It is the most sensitive design to variable operating conditions and abrasive wear, and requires
more careful maintenance.
The Throat Bushing design combines the lantern ring with a longer, tight tolerance collar and provides a compromise
between the Forward Flush and KE designs in difficult applications where water reduction is needed. It produces a
throttling effect that restricts seal water flow in the pump while maintaining pressure and flow at the packing rings. This
reduces the amount of water that enters the process flow while providing an easy-to-maintain stuffing box assembly.
The Throat Bushing design is also available in a variation incorporating the SpiralTrac® technology. This allows for flowrates to
be reduced by 50% or more while still maintaining acceptable packing life and sleeve wear.
30
LCC
The packing type must be compatible with your pumping application. This includes pressure, temperature, pH and solids
content. Seal water quality can also affect packing selection. Refer to your Bill of Materials for the packing type supplied with
your pump or contact your GIW representative if a change in packing type is needed.
Clearance is provided between the stuffing box rabbet fit and the pedestal to allow centering of the stuffing box to the shaft
sleeve. During installation, the packing space should be equalized to within 0.25 mm (.010”) at all locations before fully
tightening the stuffing box flange bolts.
In some cases, a separate stuffing box wear plate may be provided. This should be fastened into place with a fresh gasket.
Caution Failure to center the stuffing box may result in greatly reduced service life for the packing and shaft sleeve.
31
LCC
The sealing water pressure required to maintain satisfactory stuffing box operation will vary with pump operating pressure,
slurry properties, condition of the packing, and the type of stuffing box. A supply pressure of 10 psi (0.7 bar) over the
discharge pressure of the pump should be available. In most cases, adjustments to supply pressures can be made with a
manual valve and gauge near the stuffing box.
32
LCC
9.3 Expeller Seal
Expeller seals are used in pump applications where limited or
no gland flush water is readily available or where it is not
compatible with the process fluid. A second rotating impeller
contained in a separate casing creates a lower pressure at
the stuffing box seal area. This allows the shaft sleeve to be
grease lubricated and run with only enough packing
compression to seal the pump.
Unlike mechanical seals, expellers must be carefully selected Metal Seal Ring
for each application and specific operating conditions.
Expellers require additional driver horsepower, which must
be accounted for during motor selection. Changes to head,
flow, pump speed, process solids or sump level after the
pump has been installed can affect the functionality of an
expeller sealing system.
Solids – Slurries that could deposit scale on pump surfaces Typical Expeller Arrangement
should be avoided.
Flow rate – Stay between 0.5 and 1.3 times the Best Efficiency Point (QBEP).
Flushing – Solids in the process flow can precipitate out when the pump stops and build up in the expeller chamber. Over
time, this reduces efficiency and accelerates wear. The system should always be purged with clear water for at least 15
minutes prior to stopping the pump. Starting the system on clear water will help the expeller displace solids. For applications
where precipitate buildup in the expeller chamber is unavoidable, intermittent gland water flush may be necessary.
When the stuffing box does not have flush water, the packing must be lubricated with grease or oil. Graphite packing such as
Tuf-Pak 400 is recommended. Manual or automatic grease dispensers are available depending on the application. Twisting the
cap in on the manual units will add a small amount of grease to the packing. These are refilled by removing the cap and
packing the cup with lubricant. Automatic greasers use a spring driven piston to maintain a steady supply of grease. These are
refilled by connecting a grease gun to the fitting on the side of the unit. Note that extremes in temperature can alter the amount
of lubricant supplied to the packing and must be accounted for. Springs are available for the automatic greaser with three
different tension levels to control the flow of grease.
New expeller pumps are equipped with a diverter ring pressed into the hub area of the pump casing. This acts as a baffle to
help reduce the amount of solids entering the seal chamber. The diverter can be ordered as a service part and retrofit into
earlier units. For diverter installation see supplement 11.4.
It is important to operate the expeller pump within the speed limitations and operating conditions specified in the original design
parameters. Wide variations in flow rate and solids can allow particles to accumulate in the expeller chamber, which may result
in a plugging or premature component failure. Any change in the operating conditions should be discussed with your GIW /
KSB representative to establish if the new conditions are suitable for the equipment.
33
LCC
9.3.1 Expeller Assembly
For 2x3 and 3x4 LCC-M Pumps
Before mounting the expeller (23-15) a 0.5 mm (0.020 inch) aramid gasket (400.31) is placed between the shaft sleeve
and the expeller to prevent galling and ensure ease of removal. The gasket should be installed dry, without grease.
Mount the expeller casing (10-7) to the pedestal using two spare bolts (not provided) at 180 degrees to each other to hold
it temporarily in place.
After mounting the expeller, which is a close sliding fit to the shaft, adjust the bearing assembly towards the drive end until
the expeller just begins to rub on the expeller casing. Then move it back towards the pump end approx. 1.0 mm (0.4 inch).
This is a preliminary adjustment. Final adjustment will be made after wet end assembly is complete.
Mount the expeller plate (16-4) at the same time the shell or casing is mounted by inserting the studs into the shell or
casing and allowing the expeller plate to rest on and be supported by the studs.
If attempt is made to mount the expeller plate without the support of the shell or casing studs, it will not be
properly supported and may fall without warning.
If attempt is made to mount the expeller plate without the support of the shell or casing studs, it will not be
properly supported and may fall without warning.
If not removed in the above manner, the expeller plate may fall without warning after the shell is removed.
If not secured in the above manner, the expeller casing may fall without warning after the expeller is removed.
The expeller (23-15) may now be removed from the shaft. The fit of this part is similar to that of a shaft sleeve (a close
sliding fit). If necessary, the expeller casing may be unfastened from the pedestal, supported as needed and used to apply
pressure to the expeller in order to force it from the shaft. This pressure must be applied at several points around the
expeller casing to prevent uneven loading and potential breakage of the hard iron parts.
34
LCC
9.3.3 Expeller Running Clearance
The following procedure is recommended for optimizing expeller performance or for setting the clearances in pumps containing
any worn parts:
1. With the suction plate/liner removed, adjust the bearing assembly toward the pump end until the back surface of the
expeller just begins to rub the expeller plate.
2. Mount a dial gauge to indicate cartridge bearing assembly axial movement and zero the dial gauge at this location.
3. Now adjust the bearing assembly toward the drive (or motor) end until the expeller vanes just begin to rub on the expeller
casing, or the impeller begins to rub on the hub side of the pump shell, whichever comes first.
4. Adjust the bearing assembly toward the pump end again approximately 1.0 mm (0.04 in.) to provide a minimal expeller
running clearance. If optimization of expeller performance is desired, lock the adjustment at this location
5. Reassemble the suction plate and check the impeller to liner clearance. If not optimizing expeller clearances set the
impeller clearance as detailed in the section “Axial Adjustment of the Bearing Housing”. Do not allow the dial gauge to
come closer than 1.0 mm (0.04 in.) to the original zero setting or expeller rubbing may occur. If necessary, consider the
use of a spacer as mentioned in step 4.
35
LCC
10 Wet End
10.1 Wet End Overview
10.1.1 Pump Casing
Three standard configurations are available:
1 Hard Metal. Single-wall casing, impeller and suction liner of high-chrome white iron. Suitable for high-discharge head, all
particle sizes up to maximum sphere passage and mildly corrosive slurries. Custom materials available for highly corrosive
slurries.
2 Elastomer Lined. Radially split construction with ductile iron outer casing and molded-elastomer inner liners. Impeller of
high chrome white iron or polyurethane. For moderate discharge head, fine to medium particles and highly corrosive slurries.
3 Extra Heavy Hard Metal. Similar to hard metal version, but with heavier sections and hydraulics suited to the most severe
slurry duties. Two-stage pressure capability. Available in sizes LCC 150 - 500 and above.
All casings carry 125 pound, ANSI flange bolting patterns. Adapters for conversion to DIN flanges are available.
Refer to Section 2.9 “Assembly & Disassembly Safety” prior to working on the pump
Do not apply heat to the impeller hub or nose due to the sealed cavity at the impeller nose.
DANGER OF EXPLOSION!
Rotate the impeller until the tip of one blade is facing the pump discharge.
Insert the jig through the eye of the impeller and attach to trailing edge of blade facing
discharge.
Rotate the shaft in the direction opposite to normal, using the pump pulley or a spanner
wrench.
For ease of impeller removal, the shaft threads should be heavily coated with anti-seize
compound during re-assembly. Two aramid paper gaskets should be used between the
shaft sleeve and the impeller.
Impeller Break Loose Jig
36
LCC
10.2.3 Impeller Lifting Jig
For impeller removal or installation, grasp the impeller at the suction eye. The impeller can be leveled by turning the
adjusting bolt which bears against the impeller nose. This is especially useful during re-installation.
For impeller removal ensure that the lifting line is tight prior to thread disengagement.
Do not remove, lift, move or re-install impeller without properly using a recommended impeller lifting jig.
Refer to Section 2.9 “Assembly & Disassembly Safety” prior to working on the pump
37
LCC
Do not use petroleum-based products to lubricate the liners since they can cause degradation of the
Caution
elastomer.
Before assembling the casing halves together, check the fit of the liners in the casing to ensure that they are seated
correctly, especially in the suction, hub, and discharge flange areas. Clearance allowing for limited readjustment of parts
has been provided in the holes through which the liner studs protrude.
When bolting the casings together, ensure that the liners remain well aligned with each other on their outer perimeter,
especially in the discharge area. Some bulge may occur at the seam on the discharge flange. This may be removed, and
the sealing surface restored to flatness by lightly buffing with a coarse grade sand paper or grinding stone. If desired,
rubber gaskets may be applied at both the suction and discharge flanges, although this is typically not necessary.
Some bulging may also occur inside the casing between liners. This is normal and does not affect performance.
Before adjustment may proceed, the pump wet end must be completely assembled.
o Stuffing Boxes may be packed before or after the adjustment procedure.
o Mechanical seal axial set must be left until after the adjustment is complete.
38
LCC
Ensuring that all of the bearing housing hold down bolts are slightly loosened
Run the bearing assembly towards the impeller end by means of the adjusting screw until the impeller first begins to rub
the suction liner. It is helpful to slowly rotate the impeller during this procedure.
Reverse the adjusting screw until the clearance between the impeller and the suction liner is brought to the recommended
values shown in below.
Once the clearance is correct, tighten the bearing housing hold down bolts according to the requirements of Section 8.4
“Bearing Assembly Mounting” and recheck clearance.
Once the clearance is correct, lightly tighten the bolts of the four bearing housing clamps by hand, making sure that proper
contact is maintained at all four locations. Next fully tighten the bolts according to the requirements of Section 8.4 “Bearing
Assembly Mounting” and recheck clearance.
Finally, firmly lock the adjusting screw and nut together against the bearing housing tab.
The final movement of the bearing housing during adjustment should always be away from the impeller end, as
Caution
described above. This ensures that the threads of the adjusting screw will contain no backlash against the
forward directed thrust loading that the pump will generate during operation. It is especially important that this
convention be followed when a mechanical seal is being used, or when a preservative has been applied to the
bearing housing and pedestal mounting saddles.
Proper tightening of the bearing housing clamps and adjusting nut is essential to prevent movement of the
Caution
rotating assembly during operation. Failure to do so can result in severe vibration and damage to all pump
components.
39
LCC
11 Tooling
11.1 Torque Requirements
Some parts of the pump may require special torque requirements
For bearing housing hold down bolt torque refer to Section 8.4 “Bearing Assembly Mounting”.
If the pump is equipped with an impeller release ring refer to 10.3 “Wet End Assembly” for torque requirements.
If the pump is equipped with a mechanical seal is used refer to the Mechanical Seal Manual for torque requirements.
Fastener torque must be accurately measured to achieve the proper clamping force. The use of a Hydraulic Torque
Wrench is recommended as these tools can be calibrated to produce the necessary accuracy.
No special torque requirements exist for the remaining nuts and bolts unless specifically called for on the assembly
drawing. Bolts and nuts for which torque is not specified should be tightened enough to ensure a firm mating between
parts in accordance with good maintenance practice. Where possible, the use of an air driven impact wrench is
recommended for bolts over one inch (25 mm) in diameter.
Bolts must be lubricated to ensure maintenance. Anti seize compound is preferred, but well oiled is also acceptable.
The following are recommended lists of parts (whenever applicable) to have on hand for normal maintenance and inspection.
The quantities of parts kept in store will depend upon the severity of the slurry duty and the number of units operating.
Maintenance practices may also favor keeping fully built sub-assemblies or complete pumps on hand in some cases. Previous
experience in similar duties often provides the best experience. If in doubt, contact your GIW / KSB representative for specific
recommendations.
Commissioning Spares
Gaskets for all equipment
Wet End fasteners
Shaft Sleeve w/ gaskets & o-rings
Impeller Release Ring assembly
Impeller Release Ring hardware
Mechanical Seal w/ adapter & fasteners
Bearing Assembly
Bearings
Bearing Assembly Gasket Kit
Bearing Lubricant
Shaft Seal
Shaft Sleeve
Shaft Seal Water Ring
Stuffing Box Packing
Additional mechanical Seal
Seal Plate or Optional Throttle Seal
40
LCC
12 Troubleshooting
Remedy
Leakage at the pump
Cause
Motor is overloaded
WARNING: Pump must not be run with blocked If piping cannot be unblocked immediately, pump must be
piping. Danger of explosion due to heating of shut down without delay.
liquid and overpressure of pump.
System head is higher than expected. Check for unexpected clogging, collapsed line or partially
closed valve.
Check system calculations. Adjustment may be needed to
system design and/or pump operating conditions.*
Low flow operation. Increase flowrate. In general, operation below 30% of best
efficiency flowrate is not recommended.
System head is lower than expected, leading to Adjustment may be needed to system design and/or pump
excessive flowrate. operating conditions.*
Pump and piping are not completely vented or primed. Vent and / or prime.
Excess air entrained in liquid. Improve sump design and venting to prevent air from
reaching pump. Consider a froth pump design if air cannot
be avoided.
Partial clogging of impeller. Remove blockage. Be aware that blockage may drain back
into sump after shutdown.
Resonance vibrations in the piping. Check pipeline connections and pump mounting.
If required, reduce the distances between, or otherwise
modify pipe supports.
Insufficient suction head (NPSH available ) Check sump level. Raise if necessary.
Fully open any valves in the suction line.
Check suction line friction loss calculations. Alter design if
necessary.*
Density or viscosity of the fluid pumped is higher than Adjustment may be needed to system design and/or pump
expected. operating conditions.*
Speed is too high. Reduce the speed.
Worn parts. Check for worn parts. Replace as needed.
Loose bolts, seals or gaskets. Tighten the bolts and/or fit new seals and gaskets if needed.
Incorrect packing material or adjustment or… Correct adjustment. Replace parts as needed.
Incorrect seal water pressure (too high or low). (See GIW Tech Article on this subject.)
The unit is misaligned. Check the coupling. Re-align if required.
Bearing failure. Replace bearings. Check lubricant for contamination.
Inspect and repair bearing seals as needed.
Contact a GIW service center for factory rebuild services.
Insufficient or excessive quantity of lubricant or Correct according to maintenance manual
unsuitable lubricant. recommendations.
Insulating or hot ambient conditions Remove insulation and/or dirt from bearing assembly.
Improve ventilation around pump.
Operating voltage is too low. Increase the voltage.
* Contact your GIW/KSB representative for further advice.
41
LCC
13 Supplements
Supplements provide additional information for optional equipment. These options may not be available for your pump.
See your Bill of Materials for options that were included with your pump.
Seal rings, rubber torics and housings must be completely clean and free of
any oil or dirt. Use a lint free cloth with a solvent that evaporates quickly and
leaves no residue. It must be compatible with rubber toric rings. Isopropyl
Alcohol or other mild cleaner will work. Follow all safety guidelines for use
according to the solvent Material Safety Data Sheet. Check the rubber toric
for surface defects and inspect the entire metal seal face for dirt or marks. Do
not place the polished seal ring face on any surface
Gently stretch the toric over the metal seal rings until it seats in the radius.
Verify that the toric is not twisted by inspecting the mold flash line on the
outside diameter. Eliminate any irregularity by gently pulling a section of the
toric radially off the ring and letting it snap back. Twisted torics will cause
nonuniform face load, resulting in leakage and bearing contamination.
Place the housing end cover and seal holder on a flat, clean surface. Verify that the grooves are clean
and free from burrs or sharp edges. Using the correct Seal Installation Tool, locate the machined ridge
in the tool over the toric and clamp together. Align the parts squarely with the groove and carefully
snap the seal assembly into place using a rapid, even push. Isopropyl alcohol can be used as a
lubricant. Allow time for the assembly lube to evaporate.
42
LCC
Apply a very thin film of pure Molybdenum Disulfide lubricant or light oil to the seal faces just prior to
final assembly. This will lubricate the seals during initial start up. Do not to get any lube on the rubber
toric rings. Be sure there is no debris on either of the seal faces, since even a small piece of lint can
hold the seal faces apart and cause leakage or damage to the sealing surfaces.
Final assembly is detailed on the Bearing Housing Assembly drawing. Bolt the end covers in
place and install the two (2) studs and nuts for the installation tool. Verify that there are no
burrs or sharp edges on the shaft that could damage the o-ring. Coat the long set screws with
anti-seize and thread them into the tapped holes until the points are 1/8” (3mm) from the inside
bore. Install the o-ring in the Seal Holder. Coat the ID of the holder with RTV silicone sealant,
including the o-ring and set screw holes. Place a small bead of silicone around the shaft
diameter to help the o-ring slide. Use extra care at the shaft keyway. Place the gap spacer over
the shaft and carefully slide the holder until it contacts the spacer. Lower the installation tool
over the shaft and tighten the nuts ¼ to ½ turn past hand tight against the tool.
The gap spacer should not move and the holder should contact it evenly on all sides. Tighten the set screws in a crisscross
pattern. Remove the installation tool and gap spacer, and then retorque the set screws. Coat the lock screws with anti-seize
and tighten them in the tapped holes. Fill the tapped holes flush to the top with silicone to protect the set screws. This will make
removal easier for future maintenance. Rotate the shaft by hand and check for smooth operation. Verify that the holders are
square to the end cover. The metal seal rings may appear cocked slightly relative to the holders. This is not a problem, the
rings will run true when the pump starts.
After the assembly is complete, remove one of the pipe plugs from the bearing housing. Install an air line fitting and slowly
pressurize the unit with dry shop air to 10-15 psi or 1 bar. Check all joints and the Duo-Cone seals for leaks by spraying with a
soapy water solution. Do NOT exceed 15 psi, as this could cause the torics to extrude from the seal grooves. If this occurs,
disassemble the unit and reinstall the toric. Release the air pressure, replace the pipe plug and prepare the unit for shipping or
installation on the pump pedestal.
Units being returned to service must be completely filled with oil. Remove the top filler plug and add oil. If the unit will remain
empty during pump installation, be sure it is clearly indicated to ADD OIL prior to start up on both the pump and the control
panel. After the day tank is connected, fill the hoses and tank. Allow time for the oil to displace the air in the lines. Mark the oil
level in the tank for reference. Note that a single hose system or colder temperatures will require time to bleed all the air from
the system. The level should equalize after the pump has been operating for an hour or two. At this point, fill the tank to the
correct operating level.
Underwater Bearing
Shaft Size Assembly Oil Quantity
liters (quarts)
35 mm 1.5 (1.5)
50 mm 4.0 (4.0)
70 mm 9.0 (9.5)
100 mm 18 (19)
125 mm 35 (36)
4–7/16” 18 (19)
5–7/16” 41 (43)
6–7/16” 73 (77)
7–3/16” 88 (93)
9” 131 (138)
10–1/4” 170 (180)
11–1/2” 284 (300)
Approximate Values
43
LCC
NOTES
44
LCC
General Drawing with List of Components
Pump assembly, bill of material and other drawings or special instructions relevant to each order will be attached to the back of
this manual.
45