Inter. Acc. (Assigment) - 1
Inter. Acc. (Assigment) - 1
Assignment
Intermediate Accounting
Instructions
Problem #2
During 2012, Nilsen Company started a construction job with a contract price of $1,600,000. The job was
completed in 2014. The following information is available.
Required
(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of completion
method is used.
(b) Prepare all necessary journal entries for 2013.
(c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract
method is used.