0% found this document useful (0 votes)
44 views3 pages

Material Request 7-Oct-18

The document contains three material requisition forms from Electro Mechanics LLC requesting safety and medical supplies for various construction projects. The forms request items like safety shoes, laminated sheets, first aid supplies, warning tape, fire extinguishers, and protective clothing to be delivered to project sites in Al Amerat and Barka. The requisitions must be checked and approved before the materials are delivered.

Uploaded by

Rizwan Kazi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views3 pages

Material Request 7-Oct-18

The document contains three material requisition forms from Electro Mechanics LLC requesting safety and medical supplies for various construction projects. The forms request items like safety shoes, laminated sheets, first aid supplies, warning tape, fire extinguishers, and protective clothing to be delivered to project sites in Al Amerat and Barka. The requisitions must be checked and approved before the materials are delivered.

Uploaded by

Rizwan Kazi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

ELECTRO MECHANICS LLC

MATERIAL REQUISITION
Requisition No: EM-HSE-05 MJ √ EJ √ Project Name / No. Construction of Lulu at Al-amerat, EJ-1710; MJ-1707 Date : 8-Oct-18

Required Remarks /
SI.NO DESCRIPTION MAKE/ MODEL .NO MAS No. Quantity Unit
Before Action
Last issue:
1 Safety Shoe- High ankle- Size: 43. Delta plus- SAGA 3 SRC Pair 1 10-Oct-18
Apr-2016
2 A3 Lamination Sheet Box 1 9-Oct-18

3 A4 Lamination Sheet Box 1 9-Oct-18

4 First aid Items

a Plaster (Water proof) Box 4

b Dettol- 100 ml Bottle 3

c Panadol Box 4

d Cool Pack No 1 9-Oct-18

e Pain relief spray No 2

f Antiseptic Cream No 2

g Alcohol Pad Box 1

5 Cello Tape- 4 inch roll 2

6 Warning Tape- RED/ WHITE roll 10

To Be Delivered At: Al Sarooj Office. Contact Person: Mohammed Al Zadjali- 95599647

Requested by: Checked by: Approved by:

Mr. Mohammed Al Zadjali Mr. Abdul Rasheed- HSE Manager Mr. Edy Slim

EM-QMS-F028; Rev.1
ELECTRO MECHANICS LLC
MATERIAL REQUISITION
Requisition No: EM-HSE-MR-01 MJ √ EJ √ Project Name / No. Construction of Lulu at Al-amerat, EJ-1710; MJ-1707 Date : 22-Mar-18

Required Remarks /
SI.NO DESCRIPTION MAKE/ MODEL .NO MAS No. Quantity Unit
Before Action
Need to transfer
1 Portable fire extinguishers 5 No's
from Barka site
Available at Ghala
2 Full body harness- Double Hook 30 No's
store.
Need to transfer
3 Notice boards 2 No's
from Barka site
Need to transfer
4 Drip Tray 4 No's
from Barka site
Need to transfer
5 Skip bins 4 No's
from Barka site
Need to transfer
6 Fabricated tables/ Chair (2 Table, 4 Chairs) 2 Set
from Barka site

To Be Delivered At: Lulu Al-amerat Project Contact Person: Mr. Mohammed Al Zadjali- 9559947

Requested by: Checked by: Approved by:

Mohammed Al Zadjali- HSE Officer Abdul Rasheed- HSE Manager

EM-QMS-F028; Rev.1
ELECTRO MECHANICS LLC
MATERIAL REQUISITION
Requisition No: MJ EJ √ Project Name / No. Date : 7-Oct-18

Required Remarks /
SI.NO DESCRIPTION MAKE/ MODEL .NO MAS No. Quantity Unit
Before Action

1 Fire retardant Coverall Nomex- Dupond No 2 7-Oct-18

2 Safety Shoe- High ankle Delta plus- SAGA 3 SRC Pair 1 7-Oct-18

(For PDO Site Visit- Mr. Lloyd- Electrical Project Manager)

To Be Delivered At: Al Sarooj Office. Contact Person: Abdul Rasheed- 94249226

Requested by: Checked by: Approved by:

Mr. Llyod- Project manager Abdul Rasheed- HSE Manager