Hyderabad Metro Rail Project A Case Stud

The document discusses the Hyderabad Metro Rail Project including its metro network consisting of 3 corridors, financial aspects with a total cost of Rs. 14,320 Cr. and contributions from central, state and L&T governments. The structure includes foundations laid through open or pile methods, piers constructed using formwork and transit mixers, bearings to resist rotatory loads, and pre-cast concrete segments strung together using launching gantries.

Uploaded by

venu4u498
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
91 views20 pages

Hyderabad Metro Rail Project A Case Stud

The document discusses the Hyderabad Metro Rail Project including its metro network consisting of 3 corridors, financial aspects with a total cost of Rs. 14,320 Cr. and contributions from central, state and L&T governments. The structure includes foundations laid through open or pile methods, piers constructed using formwork and transit mixers, bearings to resist rotatory loads, and pre-cast concrete segments strung together using launching gantries.

Uploaded by

venu4u498
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

Hyderabad Metro Rail Project

- A case study
Topics
• Metro Network
• Financial Aspects
• Sub-structure
- Foundation
• Super structure
- Piers, Bearings, Pre-Cast Segments
• Station Concept
• Rolling Stock
• Automatic Train Operation (ATO)
• Summary
Metro Network

CORRIDOR I - RED
CORRIDOR II - GREEN
MIYAPUR CORRIDOR III - BLUE

SHILPARAMAM JBS

NAGOLE

L B NAGAR
FALAKNUMA
Financial Aspects

• Initially allotted to MAYTAS, but, was cancelled


due to delay in Financial closure.
• Allotted to L&T in PPP mode, DBFOT basis.

Total cost of Project Rs.14,320 Cr.


Central GOVT 10% of Total cost

L&T Metro Rail Hyderabad limited Remaining Total cost

State GOVT (Telangana) Ready to bear the extra cost

State GOVT (Andhra Pradesh) 0%


Structure - Overview
Foundation

• Soil Investigation
• Shifting of Services and Amenities
• Foundation
• Open foundation
• Pile foundation

Concrete/
Rock Breaker

Vibrator
Compactor
Pile driving equipment
Piers

• Inner surface of Formwork coated with Mould


Releasing Agent ; to prevent adhesion of Boom Placer
Concrete to the Formwork.

Shuttering
Transit Mixer

Security
Barricade
Piers (Contd.)

Total distance covered 72 KM


Piers
Total no. of piers 2748
Piers in corridor – I 1109
Piers in corridor – II 588
Piers in corridor – III 1051
Piers completed till now 1635

Piers
Bearings

• Bearings are used for resisting the rotatory loads


Pre-Fabrication

• Piers hold the viaduct, this is done by stringing and sticking the Segments together.

Segments

Gantry and Travel for Lifting and


Loading Segments in the Yard
Pre-Cast Segments

• In gen, 10 Segments between 2 Piers, each Segment about 40 Tons.


• Placing Viaduct Segments with the help of Launching Gantry.

Slings for holding Launching Gantry


Viaduct Segments
Traveler Viaduct Segments
For Lifting under-slung during
And Shifting Sticking and
Segments Stitching process

VIADUCT
P
I VIADUCT
E
R
Pre-Cast Segments (Contd.)

Sticking the Pre-Cast Segments

Application of
Epoxy on surface
of Segment
Pre-Cast Segments (Contd.)
Stringing of Pre-Cast Segments

Duct in Stringing
Pre-Cast Cable
Segment
Station Concept

• The Stations, being windows to the Metro Service, are tastefully designed
reflecting local culture.

Interior view of station Uppal station


Station Concept (Contd.)
• Stations are covered by an overlapping
roofing system, open at sides, covering
the platform
• Staircases & Escalators designed based
on
• Architectural Elements
• Functional Aspects.

Station Design
Rolling Stock

• LTHMR has given Rolling Stock contract to


Hyundai Rotem Company (South Korea).
• Total 57 Three-Car Train Sets.

Measurement of car 21.7 X 2.9 X 3.8 (meters)


Material of car Stainless steel
Gauge length 1435 mm
Max. Design Speed 90 Km/h
Signal System ATO/ATP
Capacity (per train set) 126 seats
Power supply 25 KV AC
Rolling Stock
Automatic Train Operation (ATO)

• LTHMR has given the Communication Based Train Control (CBTC) system
to  The Thales Company .
• Thales will Design, Build, Deliver and Manage the installation of the fully
automated CBTC.

Interior view Train


controls
Summary

• Faster :
- Journey Time  Reduced

• Greater traffic capacity equivalent to:


• 7 lanes of Bus Traffic (or)
• 24 lanes of Car Traffic

• Low Energy Consumption per Passenger Km:


• 20% only  in comparison to Road-based Systems.

• Eco-Friendly :
• Air Pollution  Nil
• Sound Pollution  Negligible
Development never ENDS